This document summarizes research on the performance of four saturated riparian buffers in Iowa over sixteen site years from 2018-2021. The key findings are:
1) The buffers consistently removed nitrate from subsurface agricultural drainage, with an average removal rate of 1.88 g/m2/day and removing 45% of the total nitrate load on average.
2) Buffers with larger widths relative to their drainage areas had higher nitrate removal fractions.
3) Despite high bypass flows, the site treating the most flow (BC-2) removed the highest total nitrate mass.
4) Sixteen new site years of data showed continued consistent nitrate removal by these buffers.
1. Performance of Saturated
Riparian Buffers in Iowa Across
Sixteen Site Years
Gabe Johnson
Iowa State University
Co-Authors: Tom Isenhart and Dan Jaynes
International Drainage Symposium | August 31, 2022
Water Quality and Drainage – Saturated Buffers and Hybrid Projects
NRCS/SWCS photo by Lynn Betts
3. Background • Extensive subsurface drainage in U.S. Midwest
• Nitrate-nitrogen (NO3-N) transported directly
from field to stream
• Eutrophication, hypoxia, drinking water
contamination
3
Drainage benefits:
Field access
Soil warming
Yield increases
Drainage drawbacks:
Nutrients transported
directly to streams
Bypass natural areas for
nitrate removal
• e.g., stream buffers,
natural wetlands
4. Edge of Field
Practices
Capture and treat drainage water before discharging into stream
4
Iowa Learning Farms
Wetlands Denitrifying Bioreactors Saturated Buffers
5. Saturated Buffers
Divert subsurface drainage from
crop fields through a vegetated
stream buffer
Removal of nitrate nitrogen
(NO3-N) via denitrification and
plant uptake
5
6. Objectives
• Analyze nitrate removal performance of four saturated buffers from
2018-2021
• Compare results with prior studies and earlier years of data at these
sites
• Prior Work: Jaynes and
Isenhart, 2019
6
7. Study Sites BC-1 BC-2
IA-1 SH
BC-1 IA-1 BC-2 SH
Installation
Date
Oct.
2010
June
2013
Oct.
2015
May
2016
Drainage
Area (ha)
(estimated)
5.9 4.7 40.5 3.4
Buffer Width
(m)
21 24 22 19
Distribution
Pipe Length
(m)
335 308 168 266
Jaynes and Isenhart, 2019: Data from installation through 2017 7
8. Methods
• Flow monitored in control structures using v-notch weirs and
pressure transducers
• Approximately bi-weekly sampling for nitrate
• Control structure
• Monitoring wells
• Creek
• Nitrate mass loads determined by multiplying concentrations by
flow volumes
• Nitrate load removed determined from difference in
concentration of field tile and wells nearest stream
8
14. Nitrate Removal Summary
Site
NO3 removal
rate
NO3 removal per
drainage area
Fraction of total
NO3 load removed
Number of Site
Years
g m-1 d-1 kg ha-1 %
BC-1 1.73 11.4 42 11
IA-1 1.41 14.0 81 8
BC-2 3.84 4.52 19 6
SH 0.74 14.2 35 6
Average 1.88 11.2 45 Total
Standard
Deviation
1.66 8.30 26 31
14
All site years from 2011 to 2021
Data from 2011 to 2017 from Jaynes and Isenhart, 2019
15. Conclusions
• 16 new site years of data showed
continued consistent nitrate removal
• Fraction of total NO3 load removal
highest in sites with large buffer
lengths relative to drainage areas
• Despite high bypass flows, total NO3
mass removal highest in site treating
most flow (BC-2)
15
16. Future Work
• Statistically significant differences in
site performance?
• Summary metrics – is kg/ha (mass
load per drainage area) adequate?
• Add additional site-years and
analyze long term trends
• Improved design guidelines to
optimize performance
16
17. Acknowledgements
USDA-ARS National Lab for Agriculture and the Environment
Kent Heikens
Natalia Rogovska
Dan Jaynes, retired
USDA NRCS Conservation Innovation Grant NR213A750013G038
Questions?
Contact: gjohnson@iastate.edu
17
19. Load removed vs % of total load removed
19
y = -0.0757x + 12.032
R² = 0.0067
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00
45.00
0 5 10 15 20 25 30 35
NO
3
-N
Load
Removal
per
drainge
area
(kg/ha)
Fraction of Total NO3-N Load Removed (%)
Editor's Notes
4 study sites that have been previously monitored
Hamilton and Boone counties, IA
BC1 18 Wells
IA 1 16 wells
BC2 9 wells
SH 6 wells
BC2 is outlier with much larger drainage area relative to buffer length
IA-1 has small drainage area relative to buffer length
Coland soils at most sites, some more well drained clarion soils at SH
FLOW TO BUFFER
2018 and 2019 wetter than average
2020 and 2021 drier than average
2018 had higher summer rains, lower spring rains
2019 had higher spring rains and lower summer rains
Both 2018 and 2019 had higher fall rains than spring rains
2020: higher spring rains than summer and fall
2021: higher summer rains, then fall, then spring
2018 had higher summer rains, lower spring rains
2019 had higher spring rains and lower summer rains
Both 2018 and 2019 had higher fall rains than spring rains
2020: higher spring rains than summer and fall
2021: higher summer rains, then fall, then spring
Timing, intensity, duration of precip events meant than even in wet years there could still be relatively similar removal based on flow diverted
Consistent performance at sites with similar ratio of drainage area to buffer length (BC-1, IA-1, SH)
Higher removal rate per length of buffer at BC-2 due to high loads diverted to buffer, even though on average it removed a lower fraction of the total load
Design considerations: ensuring adequate buffer length for the expected flow volumes (drainage area)
We’re working on updating our estimates of drainage area
How can we improve design to optimize performance?
Design considerations: ensuring adequate buffer length for the expected flow volumes (drainage area)
We’re working on updating our estimates of drainage area
How can we improve design to optimize performance?
Design considerations: ensuring adequate buffer length for the expected flow volumes (drainage area)
We’re working on updating our estimates of drainage area
How can we improve design to optimize performance?