SlideShare a Scribd company logo
Inspection Report
              DAR’s
       AGRARIAN REFORM
INFRASTRUCTURE SUPPORT PROJECT
         (ARISP) Phase III




            May 28, 2012
(ARISP) Phase III
The Agrarian Reform Infrastructure     The project components are:
   Support Project (ARISP) Phase
   III is a foreign-assisted project   •   construction of irrigation
   of DAR                                  systems
• Designed to provide basic            •   farm-to-market roads,
   support services to help develop        bridges
   Agrarian Reform Communities         •   rural water supply systems
   (ARCs).                             •   post harvest facilities
• It is funded from a concessional     •   Institutional development
   loan from the Government of             including Agricultural
   Japan with counterpart                  Extension and Livelihood
   financing from the DAR, Local
   Government Units and the            •   Project Administration
   beneficiaries.
ARISP III Status, 1st Quarter 2012
                                                              Status
         Project            Location        Proj. Cost Php
                                                             EO March
Daguioman CIS          Daguioman, Abra       14,623,400.00    100%
Dalingoan PWS          Bakun, Benguet         2,094,916.00    100%
Namagtey-Tungey FMR    Bakun, Benguet         28,449382.00    84.72%
Amgam CIS              Bakun, Benguet         9,086,923.00    41.66%
Sta. Maria-Allig CIS   Flora, Apayao          6,166,170.00    2.16%
Monamon Norte CIS      Bauko, Mt. Prov.      26,964,120.00     NYS
Pitpitan-Tamog-o FMR   Bauko, Mt. Prov.      20,000,000.00     NYS
Sadangan Upland CIP    Sadanga, Mt. Prov.    26,683,350.00     NYS
CAR:Total                                   134,068261.00     33.37%
Basic Project Information
       Project          Location      Proj. Cost Php     Status
ARISP III-          Bakun, Benguet   Php 28,449,382.00   89.23 %
                                     (Loan with GOP      As of
Improvement of                                           May 28,
                                     and LGU
Namagtey-Tungey FMR                  counterpart)        2012


                                     Loan Proceed:
                                     Php 26,056,287

                                     GOP:
                                     Php 2,393,095
Project Description
The project includes the following
work items:
Roadway and drainage
  excavation;
Embankment;
Aggregate sub-based course;
PCCP 15cm. thick with
  provision of 36" diameter;
RCPCs;
Catch basin, concrete curb and
  gutter.
Inspection Findings/Recommendations
                   Occurrence of everyday rains
                   delayed implementation of project.
                   DPWH to consider the request for a
                   second extension and closely monitor
                   the quality of ongoing works

                   Contractor to make a catch up
                   plan/strategy to complete the project as
                   soon as possible.
Inspection Findings/Recommendations




Large volume of runoff water carries off
base course and gutters laid.
           Road scouring/scaling due to
           large volume of water run-off
Contractor to continue remedial/counter
measures to protect and prevent further
damage to all completed and all ongoing
activities.
Inspection Findings/Recommendations
Project area is prone to landslides/ erosion
    Contractor to maintain and always keep
    the road open: Clean & remove debris

    LGU to allocate:
    •Additional funding for added work like
    slope protection structures & drainage.
    •Budget for O&M to sustain the
    maintenance program for the project.
Inspection Findings/Recommendations




                  Curb and gutter not provided making
                  water catchment useless
                  Uncompleted water catchment
                  For the project consultant to reconsider
                  constructing side and curb gutter in both
                  sides of the road considering project area
                  is prone to erosion/ landslides and further
                  prevent damage to all completed and all
                  ongoing activities.
Briefing/Exit Conference with:
Mayor Marcelo B. Contada
Vice Mayor Paulino F. Dalmones
SP Members
MPDC Bakun
DAR
DPWH




                   Ms. Adela Comila, MARO-Bakun
                   briefing the RIT

More Related Content

What's hot

Contractor Awareness Training Above Ground Facilities Part 1 2016
Contractor Awareness Training Above Ground Facilities Part 1 2016Contractor Awareness Training Above Ground Facilities Part 1 2016
Contractor Awareness Training Above Ground Facilities Part 1 2016
Fairfax County
 
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021
Fairfax County
 
Transportation Milton, presentation by joseph lai - ministry of transporation
Transportation Milton, presentation by  joseph lai - ministry of transporationTransportation Milton, presentation by  joseph lai - ministry of transporation
Transportation Milton, presentation by joseph lai - ministry of transporation
Milton Chamber of Commerce
 
Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Scotts Run Tributary at Windy Hill Road: Stream Stabilization ProjectScotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Fairfax County
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
Fairfax County
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
Fairfax County
 
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Fairfax County
 
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021
Fairfax County
 
Stringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionStringfellow Park and Ride Expansion
Stringfellow Park and Ride Expansion
Fairfax County
 
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Fairfax County
 
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Fairfax County
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014
Fairfax County
 
Retrofit Facility DP0625 West Potomac High School
Retrofit Facility DP0625 West Potomac High SchoolRetrofit Facility DP0625 West Potomac High School
Retrofit Facility DP0625 West Potomac High School
Fairfax County
 
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectDead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Fairfax County
 
Potosi Sidewalk Plan
Potosi Sidewalk PlanPotosi Sidewalk Plan
Potosi Sidewalk Plan
Brody Johnson
 
Pohick Creek Tributary at Greentree Village Park Stream Restoration
Pohick Creek Tributary at Greentree Village Park Stream RestorationPohick Creek Tributary at Greentree Village Park Stream Restoration
Pohick Creek Tributary at Greentree Village Park Stream Restoration
Fairfax County
 
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Fairfax County
 
Sutton Oaks Pond Improvements
Sutton Oaks Pond ImprovementsSutton Oaks Pond Improvements
Sutton Oaks Pond Improvements
Fairfax County
 
Draft Chesapeake Bay TMDL Action Plan Public Meeting
Draft Chesapeake Bay TMDL Action Plan Public MeetingDraft Chesapeake Bay TMDL Action Plan Public Meeting
Draft Chesapeake Bay TMDL Action Plan Public Meeting
Fairfax County
 
Towlston Meadows Restoration Project
Towlston Meadows Restoration ProjectTowlston Meadows Restoration Project
Towlston Meadows Restoration Project
Fairfax County
 

What's hot (20)

Contractor Awareness Training Above Ground Facilities Part 1 2016
Contractor Awareness Training Above Ground Facilities Part 1 2016Contractor Awareness Training Above Ground Facilities Part 1 2016
Contractor Awareness Training Above Ground Facilities Part 1 2016
 
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021
 
Transportation Milton, presentation by joseph lai - ministry of transporation
Transportation Milton, presentation by  joseph lai - ministry of transporationTransportation Milton, presentation by  joseph lai - ministry of transporation
Transportation Milton, presentation by joseph lai - ministry of transporation
 
Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Scotts Run Tributary at Windy Hill Road: Stream Stabilization ProjectScotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
 
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)
 
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021
 
Stringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionStringfellow Park and Ride Expansion
Stringfellow Park and Ride Expansion
 
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
 
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014
 
Retrofit Facility DP0625 West Potomac High School
Retrofit Facility DP0625 West Potomac High SchoolRetrofit Facility DP0625 West Potomac High School
Retrofit Facility DP0625 West Potomac High School
 
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectDead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
 
Potosi Sidewalk Plan
Potosi Sidewalk PlanPotosi Sidewalk Plan
Potosi Sidewalk Plan
 
Pohick Creek Tributary at Greentree Village Park Stream Restoration
Pohick Creek Tributary at Greentree Village Park Stream RestorationPohick Creek Tributary at Greentree Village Park Stream Restoration
Pohick Creek Tributary at Greentree Village Park Stream Restoration
 
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
 
Sutton Oaks Pond Improvements
Sutton Oaks Pond ImprovementsSutton Oaks Pond Improvements
Sutton Oaks Pond Improvements
 
Draft Chesapeake Bay TMDL Action Plan Public Meeting
Draft Chesapeake Bay TMDL Action Plan Public MeetingDraft Chesapeake Bay TMDL Action Plan Public Meeting
Draft Chesapeake Bay TMDL Action Plan Public Meeting
 
Towlston Meadows Restoration Project
Towlston Meadows Restoration ProjectTowlston Meadows Restoration Project
Towlston Meadows Restoration Project
 

Similar to ARISP III Inspection Report

Dar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_fDar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_f
Rdc Cordillera
 
CV_Jagannath Hosmani
CV_Jagannath HosmaniCV_Jagannath Hosmani
CV_Jagannath Hosmani
Jagannath Hosmani
 
Water Management Financing in the Caribbean - Part 2
Water Management Financing in the Caribbean - Part 2Water Management Financing in the Caribbean - Part 2
Water Management Financing in the Caribbean - Part 2
Global Water Partnership-Caribbean (GWP-C)
 
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
APA Florida
 
CV_Jagannath Hosmani_10May2016
CV_Jagannath Hosmani_10May2016CV_Jagannath Hosmani_10May2016
CV_Jagannath Hosmani_10May2016
Jagannath Hosmani
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
City of College Station
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
City of College Station
 
Da charmp 2 2nd qtr_f
Da charmp 2 2nd qtr_fDa charmp 2 2nd qtr_f
Da charmp 2 2nd qtr_f
Rdc Cordillera
 
Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement Report
Festo Wasukira
 
LESCO- EIA report
LESCO- EIA reportLESCO- EIA report
LESCO- EIA report
Ash Hassan
 
1. River Basin Planning - some key developments - Colin Byrne, DHPLG
1. River Basin Planning - some key developments - Colin Byrne, DHPLG1. River Basin Planning - some key developments - Colin Byrne, DHPLG
1. River Basin Planning - some key developments - Colin Byrne, DHPLG
Environmental Protection Agency, Ireland
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
Riaz Zalil
 
1 and 2 SRK WUL workshop introduction objectives and eWULAAS
1 and 2 SRK WUL workshop introduction objectives and eWULAAS1 and 2 SRK WUL workshop introduction objectives and eWULAAS
1 and 2 SRK WUL workshop introduction objectives and eWULAAS
srkconsulting
 
Critical Study on Kochi Barrage
Critical Study on Kochi BarrageCritical Study on Kochi Barrage
Critical Study on Kochi Barrage
IRJET Journal
 
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
The Piedmont Environmental Council
 
Training report 1
Training report 1Training report 1
Training report 1
Sandun Thilina
 
Performance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxPerformance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptx
sheikhInayat5
 
AHBeosumbarPrTechEngCV2013Vol2
AHBeosumbarPrTechEngCV2013Vol2AHBeosumbarPrTechEngCV2013Vol2
AHBeosumbarPrTechEngCV2013Vol2
Ashwin Beosumbar
 
2nd qtr rpmes 2013
2nd qtr rpmes 20132nd qtr rpmes 2013
2nd qtr rpmes 2013
Rdc Cordillera
 
Bunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model townBunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model town
Smart Villages
 

Similar to ARISP III Inspection Report (20)

Dar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_fDar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_f
 
CV_Jagannath Hosmani
CV_Jagannath HosmaniCV_Jagannath Hosmani
CV_Jagannath Hosmani
 
Water Management Financing in the Caribbean - Part 2
Water Management Financing in the Caribbean - Part 2Water Management Financing in the Caribbean - Part 2
Water Management Financing in the Caribbean - Part 2
 
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
 
CV_Jagannath Hosmani_10May2016
CV_Jagannath Hosmani_10May2016CV_Jagannath Hosmani_10May2016
CV_Jagannath Hosmani_10May2016
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Da charmp 2 2nd qtr_f
Da charmp 2 2nd qtr_fDa charmp 2 2nd qtr_f
Da charmp 2 2nd qtr_f
 
Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement Report
 
LESCO- EIA report
LESCO- EIA reportLESCO- EIA report
LESCO- EIA report
 
1. River Basin Planning - some key developments - Colin Byrne, DHPLG
1. River Basin Planning - some key developments - Colin Byrne, DHPLG1. River Basin Planning - some key developments - Colin Byrne, DHPLG
1. River Basin Planning - some key developments - Colin Byrne, DHPLG
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
 
1 and 2 SRK WUL workshop introduction objectives and eWULAAS
1 and 2 SRK WUL workshop introduction objectives and eWULAAS1 and 2 SRK WUL workshop introduction objectives and eWULAAS
1 and 2 SRK WUL workshop introduction objectives and eWULAAS
 
Critical Study on Kochi Barrage
Critical Study on Kochi BarrageCritical Study on Kochi Barrage
Critical Study on Kochi Barrage
 
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
 
Training report 1
Training report 1Training report 1
Training report 1
 
Performance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxPerformance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptx
 
AHBeosumbarPrTechEngCV2013Vol2
AHBeosumbarPrTechEngCV2013Vol2AHBeosumbarPrTechEngCV2013Vol2
AHBeosumbarPrTechEngCV2013Vol2
 
2nd qtr rpmes 2013
2nd qtr rpmes 20132nd qtr rpmes 2013
2nd qtr rpmes 2013
 
Bunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model townBunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model town
 

More from Rdc Cordillera

1st qtr rpmes 2013
1st qtr rpmes 20131st qtr rpmes 2013
1st qtr rpmes 2013
Rdc Cordillera
 
2012 yearend report
2012 yearend report2012 yearend report
2012 yearend report
Rdc Cordillera
 
3rd qtr rpmes report
3rd qtr rpmes report3rd qtr rpmes report
3rd qtr rpmes report
Rdc Cordillera
 
2nd qtr rpmes report
2nd qtr rpmes report2nd qtr rpmes report
2nd qtr rpmes report
Rdc Cordillera
 
2nd qtr rpmes report
2nd qtr rpmes report2nd qtr rpmes report
2nd qtr rpmes report
Rdc Cordillera
 
1st qtr rpmes report
1st qtr rpmes report1st qtr rpmes report
1st qtr rpmes report
Rdc Cordillera
 
Search for cordillera champions
Search for cordillera championsSearch for cordillera champions
Search for cordillera champions
Rdc Cordillera
 
Nomination form
Nomination formNomination form
Nomination form
Rdc Cordillera
 
Vacaciesjan2012 1
Vacaciesjan2012 1Vacaciesjan2012 1
Vacaciesjan2012 1
Rdc Cordillera
 
2nd qtr rpmes 2012
2nd qtr rpmes 20122nd qtr rpmes 2012
2nd qtr rpmes 2012
Rdc Cordillera
 
2nd qtr rpmes 2012
2nd qtr rpmes 20122nd qtr rpmes 2012
2nd qtr rpmes 2012
Rdc Cordillera
 
Dpwh kabugao
Dpwh kabugaoDpwh kabugao
Dpwh kabugao
Rdc Cordillera
 
Dep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_fDep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_f
Rdc Cordillera
 
Doh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_fDoh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_f
Rdc Cordillera
 
Dpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_fDpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_f
Rdc Cordillera
 
Dpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_fDpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_f
Rdc Cordillera
 
Dswd 4 ps_2nd qtr_f
Dswd 4 ps_2nd qtr_fDswd 4 ps_2nd qtr_f
Dswd 4 ps_2nd qtr_f
Rdc Cordillera
 
Summary of priority sectoral program projects
Summary of priority sectoral program projectsSummary of priority sectoral program projects
Summary of priority sectoral program projects
Rdc Cordillera
 
Denr ngp 2nd qtr_f
Denr ngp 2nd qtr_fDenr ngp 2nd qtr_f
Denr ngp 2nd qtr_f
Rdc Cordillera
 
2nd qtr major program projects
2nd qtr major program projects2nd qtr major program projects
2nd qtr major program projects
Rdc Cordillera
 

More from Rdc Cordillera (20)

1st qtr rpmes 2013
1st qtr rpmes 20131st qtr rpmes 2013
1st qtr rpmes 2013
 
2012 yearend report
2012 yearend report2012 yearend report
2012 yearend report
 
3rd qtr rpmes report
3rd qtr rpmes report3rd qtr rpmes report
3rd qtr rpmes report
 
2nd qtr rpmes report
2nd qtr rpmes report2nd qtr rpmes report
2nd qtr rpmes report
 
2nd qtr rpmes report
2nd qtr rpmes report2nd qtr rpmes report
2nd qtr rpmes report
 
1st qtr rpmes report
1st qtr rpmes report1st qtr rpmes report
1st qtr rpmes report
 
Search for cordillera champions
Search for cordillera championsSearch for cordillera champions
Search for cordillera champions
 
Nomination form
Nomination formNomination form
Nomination form
 
Vacaciesjan2012 1
Vacaciesjan2012 1Vacaciesjan2012 1
Vacaciesjan2012 1
 
2nd qtr rpmes 2012
2nd qtr rpmes 20122nd qtr rpmes 2012
2nd qtr rpmes 2012
 
2nd qtr rpmes 2012
2nd qtr rpmes 20122nd qtr rpmes 2012
2nd qtr rpmes 2012
 
Dpwh kabugao
Dpwh kabugaoDpwh kabugao
Dpwh kabugao
 
Dep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_fDep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_f
 
Doh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_fDoh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_f
 
Dpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_fDpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_f
 
Dpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_fDpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_f
 
Dswd 4 ps_2nd qtr_f
Dswd 4 ps_2nd qtr_fDswd 4 ps_2nd qtr_f
Dswd 4 ps_2nd qtr_f
 
Summary of priority sectoral program projects
Summary of priority sectoral program projectsSummary of priority sectoral program projects
Summary of priority sectoral program projects
 
Denr ngp 2nd qtr_f
Denr ngp 2nd qtr_fDenr ngp 2nd qtr_f
Denr ngp 2nd qtr_f
 
2nd qtr major program projects
2nd qtr major program projects2nd qtr major program projects
2nd qtr major program projects
 

Recently uploaded

Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
46adnanshahzad
 
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfThe 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
thesiliconleaders
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
marketing317746
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Operational Excellence Consulting
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
jeffkluth1
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
JeremyPeirce1
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
Chandresh Chudasama
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
Alexandra Fulford
 
Building Your Employer Brand with Social Media
Building Your Employer Brand with Social MediaBuilding Your Employer Brand with Social Media
Building Your Employer Brand with Social Media
LuanWise
 
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
bosssp10
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
Norma Mushkat Gaffin
 
Best practices for project execution and delivery
Best practices for project execution and deliveryBest practices for project execution and delivery
Best practices for project execution and delivery
CLIVE MINCHIN
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
my Pandit
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
ssuser567e2d
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Holger Mueller
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
Adnet Communications
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 
2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
aragme
 
Easily Verify Compliance and Security with Binance KYC
Easily Verify Compliance and Security with Binance KYCEasily Verify Compliance and Security with Binance KYC
Easily Verify Compliance and Security with Binance KYC
Any kyc Account
 

Recently uploaded (20)

Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
 
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfThe 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
 
Building Your Employer Brand with Social Media
Building Your Employer Brand with Social MediaBuilding Your Employer Brand with Social Media
Building Your Employer Brand with Social Media
 
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
 
Best practices for project execution and delivery
Best practices for project execution and deliveryBest practices for project execution and delivery
Best practices for project execution and delivery
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 
2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
 
Easily Verify Compliance and Security with Binance KYC
Easily Verify Compliance and Security with Binance KYCEasily Verify Compliance and Security with Binance KYC
Easily Verify Compliance and Security with Binance KYC
 

ARISP III Inspection Report

  • 1. Inspection Report DAR’s AGRARIAN REFORM INFRASTRUCTURE SUPPORT PROJECT (ARISP) Phase III May 28, 2012
  • 2. (ARISP) Phase III The Agrarian Reform Infrastructure The project components are: Support Project (ARISP) Phase III is a foreign-assisted project • construction of irrigation of DAR systems • Designed to provide basic • farm-to-market roads, support services to help develop bridges Agrarian Reform Communities • rural water supply systems (ARCs). • post harvest facilities • It is funded from a concessional • Institutional development loan from the Government of including Agricultural Japan with counterpart Extension and Livelihood financing from the DAR, Local Government Units and the • Project Administration beneficiaries.
  • 3. ARISP III Status, 1st Quarter 2012 Status Project Location Proj. Cost Php EO March Daguioman CIS Daguioman, Abra 14,623,400.00 100% Dalingoan PWS Bakun, Benguet 2,094,916.00 100% Namagtey-Tungey FMR Bakun, Benguet 28,449382.00 84.72% Amgam CIS Bakun, Benguet 9,086,923.00 41.66% Sta. Maria-Allig CIS Flora, Apayao 6,166,170.00 2.16% Monamon Norte CIS Bauko, Mt. Prov. 26,964,120.00 NYS Pitpitan-Tamog-o FMR Bauko, Mt. Prov. 20,000,000.00 NYS Sadangan Upland CIP Sadanga, Mt. Prov. 26,683,350.00 NYS CAR:Total 134,068261.00 33.37%
  • 4. Basic Project Information Project Location Proj. Cost Php Status ARISP III- Bakun, Benguet Php 28,449,382.00 89.23 % (Loan with GOP As of Improvement of May 28, and LGU Namagtey-Tungey FMR counterpart) 2012 Loan Proceed: Php 26,056,287 GOP: Php 2,393,095
  • 5. Project Description The project includes the following work items: Roadway and drainage excavation; Embankment; Aggregate sub-based course; PCCP 15cm. thick with provision of 36" diameter; RCPCs; Catch basin, concrete curb and gutter.
  • 6. Inspection Findings/Recommendations Occurrence of everyday rains delayed implementation of project. DPWH to consider the request for a second extension and closely monitor the quality of ongoing works Contractor to make a catch up plan/strategy to complete the project as soon as possible.
  • 7. Inspection Findings/Recommendations Large volume of runoff water carries off base course and gutters laid. Road scouring/scaling due to large volume of water run-off Contractor to continue remedial/counter measures to protect and prevent further damage to all completed and all ongoing activities.
  • 8. Inspection Findings/Recommendations Project area is prone to landslides/ erosion Contractor to maintain and always keep the road open: Clean & remove debris LGU to allocate: •Additional funding for added work like slope protection structures & drainage. •Budget for O&M to sustain the maintenance program for the project.
  • 9. Inspection Findings/Recommendations Curb and gutter not provided making water catchment useless Uncompleted water catchment For the project consultant to reconsider constructing side and curb gutter in both sides of the road considering project area is prone to erosion/ landslides and further prevent damage to all completed and all ongoing activities.
  • 10. Briefing/Exit Conference with: Mayor Marcelo B. Contada Vice Mayor Paulino F. Dalmones SP Members MPDC Bakun DAR DPWH Ms. Adela Comila, MARO-Bakun briefing the RIT