SlideShare a Scribd company logo
1 of 8
Download to read offline
1
Arc Flash Hazard,
When Over-Estimating Under-Estimates a Problem
Del John Ventruella, PE
Abstract: When one undertakes an arc flash
study, one must develop a model based on the
power system of interest. The model requires
estimates of conductor lengths. To insure that
the arc flash study that one is performing does
not underestimate the magnitudes of the short
circuit currents present within the power
system, and to allow for limitations in the
procedure by which one develops the model,
typically visual inspection, one must carefully
estimate the lengths of conductors.
This requires that one avoid over-estimates of
conductor lengths or risk computing short circuit
currents that are below the magnitudes of short
circuit and arc flash currents that are actually
present at the ends of conductors, where circuit
breaker panels or substations are located. If
one over-estimates the short circuit current, the
time delay of the circuit breakers affected will
tend to be reduced based on the typical time
current curve characteristic of circuit breakers.
If the response time of a circuit breaker is
reduced in terms of the time current curve plots
due to higher short circuit current level
estimates being produced, and if these short
circuit current level estimates are in error, the
actual energy released could be much greater
because the circuit breaker will trip in response
to the actual short circuit current magnitude,
which will be lower than that which is calculated
using shorter conductor lengths, and will
typically involve a trip characteristic that
involves a longer time delay (perhaps a long
time trip rather than a short time trip, or a short
time trip rather than an instantaneous trip).
This could dramatically increase the Personnel
Protective Equipment level that is required
compared to the level predicted in a study.
Introduction
The selection of Personnel Protective
Equipment is based on the magnitude of the
energy released.
Power is energy per unit time, so energy is:
E = R(I2
)t.
This is computed as:
(Rlower) Isc-lower
2
tsc-lower > (Rhigher) Isc-higher
2
tsc-higher,
If the variation between Isc-higher and Isc-lower is
small enough while the magnitude of tsc-lower is
sufficiently greater than tsc-higher due to a much
greater circuit breaker response time associated
with the lower fault current, the energy
released for the lower short circuit current
could be much greater if the circuit breaker
requires considerably more time to respond to
the lower arc flash current level (perhaps a long
time trip response rather than an instantaneous
or short time trip response). This assumes that
Rlower and Rhigher are roughly equal for
approximately the same short circuit or arc
flash level.
Arc Flash current levels at low Voltage tend to
be proportional to the fault current level.
Experience demonstrates that arc flash currents
are diminished by some twenty percent1
relative to the three-phase fault level.
If the time required for a trip response
associated with the lower arc flash current
affects a greater time delay, perhaps several
seconds due to a long time trip unit reacting for
a lower level current, which is much longer than
the short time or instantaneous delay of the
higher short circuit current estimate, the total
2
energy released for the lower level arc flash
current will actually be substantially greater
than that computed for the higher current.
If the short circuit current estimated due to
shorter than actual conductor length places the
trip response time to the right of a trip device
characteristic segment that is vertical, and if the
short circuit current (arc flash current) is
actually to the left of the trip device
characteristic, the time difference in the
response of the trip device could be so great as
to dramatically increase the Personnel
Protective Equipment (PPE) level that is
required. Note that PPE levels are based on the
computed short circuit current and time delay
and the minimum arc flash current level
calculated to be present.
If the arc flash current level computed based on
the conductor length is too great, based on too
short an estimate of conductor length, the time
required for the circuit breaker response could
be much less than that which occurs in reality,
and the PPE required to provide adequate
protection to personnel in reality could similarly
increase dramatically in comparison. In effect,
personnel could be left inadequately protected
from arc flash hazard due to estimates of
conductor length that are too short. Even with
a suitable engineering study, this fact could
never be described within its pages if the
engineer is not aware of this danger, or if the
engineer’s work environment does not grant
the time to consider this possibility while
performing the study.
Analysis
The concept being presented is illustrated in
Figure 1.0.
Figure 1.0 – Time Current Curve Illustration of
Circuit Breaker with Long Time and
Instantaneous Trip Devices and Two Arc Flash
Currents with Response Times, Each Separated
by a Few Hundred Amperes (Roughly the
Thickness of the Circuit Breaker’s Time Current
Curve).
If the length of a cable is underestimated, the
calculated arc flash may appear to force a
response to the fault level on the right (see
Figure 1.0). In reality, a more realistic estimate
of the cable length may make it respond to the
arc flash current level on the left (also Figure
1.0), involving a much longer response time
(perhaps several seconds instead of roughly one
tenth second).
In Figure 1.0, the energy released for the 15 kA
current is:
I2
tR = 15 kA 2
(0.10 sec.)R = 22,500,000 A2
R sec.
The energy released for the 14.7 kA current is:
I2
tR = 14.6 kA 2
(7.0 sec.)R = 1,512,630,000 A2
R
sec.
If the arc flash current in reality is only (roughly)
300 Amperes (the thickness of the circuit
breaker trip characteristic) lower than the
computed value, the energy released will
actually be greater for 14.7 kA of arc flash
current than for 15 kA of arc flash current. It is
thus clear that if the arc flash current is
3
estimated to be over-valued, in a manner
consistent with the estimation of short circuit
current and too short conductor length
estimates, the actual energy released and the
arc flash personnel protective equipment (PPE)
level could be considerably greater than that
predicted by the arc flash study, based on a
higher short circuit estimate (and a lower circuit
breaker response time), would predict.
The single-line diagram for the power system to
be examined to prove this concept follows in
Figure 2.0.
Figure 2.0 – Sample Single-line Drawing with
Buses One, Two, and Three Shown
The system consists of a utility source, a
transformer that steps the Voltage down from
12.47 kV to 480 V. and a single cable extending
the system. This model, as realized in Table 1.0,
with an approximate 500 foot long conductor,
might represent an older system in which two
or three conductors have been “daisy chained”
to produce the single, 500 foot long conductor
that is modeled. An available short circuit MVA
(SCMVA) of 100 is used in this model, and may
represent utility loads in urban areas where the
magnitude of the three-phase short circuit
current is intentionally reduced by controls
imposed by the utility.
Short Circuit Calculations for Model of Figure 1.0
Utility PU Impedance
100000000 12470 1.555009 Ohms
VA VOLTS 1 pu Z
Transformer PU
Impedance
2500000 5.75% 2.3 pu Z
0.0052992 2.3
Ohms pu
4
Cable PU Impedance
Cable Ohms
0.118 Per 1000 ft
Cable Imp. % of 500 Ft.
pu Cable
Imp. Cable Length
0.0590 100.0% 25.61 100% (500 Ft.))
0.0575 97.5% 24.97 97.5% (475 Ft.)
0.0561 95.0% 24.33 95% (450 Ft.)
0.0546 92.5% 23.69 92.5% (425 Ft.)
0.0531 90.0% 23.05 90% (400 Ft.)
Short Circuit Currents
Total Pu
Impedance Current (A) Bus
Currents at Buses In
System
Utility 1.00 4630 1
Trans. Sec. 3.30 36450 2
Cable End 28.91 4161 3 100% of 500 Ft. Cable
(Based on 28.27 4255 3 97.5% of 500 Ft. Cable
500 Ft. 27.63 4354 3 95% of 500 Ft. Cable
Total Cable 26.99 4457 3 92.5% of 500 Ft. Cable
Length) 26.35 4565 3 90% of 500 Ft. Cable
Table 1.0 – Short Circuit Calculations (Includes Multiple Calculations of Current Based on Various Cable
Lengths at Bus Three)
The short circuit currents at each bus are clearly
marked in Table 1.0 (relative to Figure 2.0). The
values for Bus Three are shown for various
estimated lengths of the conductor, from 100%
of the conductor length to 90% of its length.
With circuit breaker characteristics typically a
few hundred Amperes in horizontal thickness, it
is clear that errors in estimating cable lengths,
and particularly so-called “conservative”
estimates of length (producing higher short
circuit current magnitudes) can produce results
that leave the arc flash current estimate to the
right of the time current curve short time or
instantaneous response characteristic, while
the actual fault level may exist to the left of the
time current curve, in the long time range
(given some 400 Amperes of variation between
100% accuracy at 500 feet and 90% accuracy at
450 feet). If the true, lower arc flash current
level were computed it could add seconds to
the response time, while leaving the arc flash
current essentially in the same range as it was,
producing a need for much more elaborate PPE
(or eliminating the possibility of PPE) than
would exist if the short time or instantaneous
trip were to respond to an arc flash.
5
Short Circuit Currents for Various Sources, Transformers, and Cables
(480 V) (480 V)
Current at Bus Current at Bus Difference in
12470
V Transformer Cable Length 480 V at End of Cable (A) at End of Cable (A) Current
SCMVA kVA (Feet) Cable Size (100% of Length) (90% of Length) (Amperes)
100 2500 500 #8 822 911 89
2.3 0.3295 143
pu value Ohms pu Z
100 500 500 500 MCM 5299 5548 249
11.5 0.0235 10
pu value Ohms pu Z
500 2500 500 #8 827 917 90
11.5 0.3295 715
pu value Ohms pu Z
500 500 500 500 MCM 5493 5761 268
57.5 0.0235 51
pu value Ohms pu Z
Note: Cable is #8, or 0.659 Ohms per 1000 Ft. OR
Cable is 500 MCM, or 0.047 Ohms per 1000 Ft.
Transformer is 5.75% impedance.
Table 2.0 – Variations in Current due to Estimation Based on Cable Size and Available SCMVA at Source
Causes
What might cause circuit breakers to be set in a
manner that would produce results that would
push the time current curve characteristic so far
to the right in the time current curve plot? One
might imagine a few easily, the most obvious of
which would be conditions under which many
circuit breakers exist in series in older buildings,
so that there is a need to make the most of the
area of the time current curve when
coordinating circuit breakers. From the
perspective of the person developing the
settings, the results of the arc flash study and
coordination study may appear to produce a
perfectly legitimate result in terms of circuit
breaker settings, if the possibility of failure to
properly estimate cable lengths and
overestimates of short circuit current are not
considered.
Table 2.0 illustrates the variation in short circuit
current that would result due to variations in
conductor length and available SCMVA (short
circuit MVA). The short circuit current variation
could be as great as approximately 250
Amperes for a ten percent error in judgement
of cable length for a 500 MCM cable. Based on
this, for transformers that are rated at 480 Volt
and no larger than 2500 kVA, and with an
available SCMVA of 500 MVA or less, and a
single cable or string of daisy chained cables of
500 feet in length with 500 MCM rating, the
maximum error would be roughly 250 Amperes.
6
Given the results of Table 2.0, one could, by
making certain that the highest valued vertical
transition to the next slowest trip element of
the circuit breaker’s protective device is at least
200% of 250 Amperes to the left of the
computed minimum arc flash current level, or
500 Amperes to the left of the protective trip
device element’s intended trip for arc flash, to
insure that one need not concern oneself with
the risk of error due to estimation of cable
lengths. (See Figure 3.0.) Of course, to be
precise the specific system configuration must
be considered in each instance (as in Table 2.0)
and compared to the circuit breaker’s time
current curve plot, which is a rather time
consuming task.
Figure 3.0 – Illustration of Application of Results
of Table 2.0
The horizontal “gap” that must be maintained
and is illustrated in Figure 3.0 becomes even
worse as “estimates” of cumulative or daisy-
chained cable lengths become worse, as shown
in Table 3.0 for a 20% error.
7
Short Circuit Currents for Various Sources, Transformers, and Cables
(480 V) (480 V)
Current at Bus Current at Bus
Difference
in
12470
V Transformer Cable Length 480 V at End of Cable (A)
at End of Cable
(A) Current
SCMVA kVA (Feet)
Cable
Size (100% of Length) (80% of Length) (Amperes)
500 500 500 500 MCM 5493 6057 564
57.5 0.0235 51
pu value Ohms pu Z
Note: Cable is #8, or 0.659 Ohms per 1000 Ft. OR
Cable is 500 MCM, or 0.047 Ohms per 1000 Ft.
Transformer is 5.75% impedance.
400 Feet of length estimated
Table 3.0 – Illustration of Growth of Magnitude of Error in Arc Flash Current Due to Error in Estimate of
Length of Cable (20%) (If a margin of 200% were deemed reasonable, this would require an 1100 A
“gap” between the minimum arc flash current and the rightmost portion of the vertical characteristic
transitioning to the next slowest trip response by the circuit breaker providing protection on the source
side.)
The Cure
There is a simple cure for this problem of under-
estimating cable lengths (save for computations
of the sort performed in Table 2.0 under an
assumed “certainty” in the maximum error
inherent in the estimation of the cable/wire
length). There exist today circuit breakers with
“maintenance” switch3
settings that are
designed to respond very quickly in a very
sensitive manner to arc flash current once the
“maintenance” switch on the circuit breaker has
been activated. (This is a solution
recommended in the National Electrical Code,
Article 240.87, Arc Energy Reduction.4
) These
devices typically respond in an instantaneous
manner to very low level faults in the event that
the maintenance switch is triggered. The
maintenance switch thus is placed in the “on”
position whenever work is being performed on
the load side of the circuit breaker.
There may be other solutions, such as turning
the instantaneous trip to a very low setting
whenever work is being performed on the load
side of circuit breakers, but this must be
considered in the course of an arc flash study to
allow for the starting of motors or other inrush
loads that may normally occur while energized
work is being performed.
Conclusion
Errors in the measurement of cable lengths can
produce inaccurate Arc Flash Studies and circuit
breaker settings that can appear to conform to
lower level PPE requirements (due to very
short, circuit breaker response times) while in
fact producing unrealistically high short circuit
trip intervals. As a result of much longer
response times to lower short circuit currents
by circuit breakers in reality, much greater PPE
requirements can result in general.
8
If studies are performed by third parties, it may
be impossible, given the “assembly line”
mentality of many service providers, for such
errors to be caught, and where not identified,
they can produce grave dangers to personnel
and passers-by (particularly if PPE may not, in
reality, be possible to specify for a given
location and circuit breaker setting). It is, after
all, clear that long table allowing for estimates
in cable lengths are absent from most arc flash
studies. The only other potential solution,
substantially improving the estimate of
conductor lengths during data collection, is
probably unrealistic, although it might be
conceivable if estimation within 10% of the
cable length is perceived as possible, and
computing the potential error in short circuit
current as a result is undertaken (as in Table
2.0) in the course of the study.
It is virtually inevitable that slight errors in
estimates of conductor lengths will be made.
Such approaches to estimating cable lengths
actually assure adequately rated circuit
breakers in short circuit studies. Such errors
can have the opposite effect in arc flash studies.
Arc flash studies can be useful, but only if errors
in conductor length do not produce PPE levels
that underestimate arc flash durations. The use
of circuit breakers equipped with
“maintenance” switches (or potentially by
having an alternate, much lower setting for
each circuit breaker where work is to be
performed on the load side) are possible
solutions to this serious and potentially
unrecognized problem in Arc Flash studies.
Time consuming calculations (of the type
undertaken in Table 2.0 and Figure 3.0) are less
likely to occur to estimate the extent of the
offset from vertical transitions (between trip
types) in circuit breaker time current curves
based on short circuit current levels, and would
only be of value if the error in the length of the
cable estimates could be assured.
Bibliography
1. Fault Arc Resistance (magnitude), 3-Phase
Short-Circuit Current (Isc) at any Point Within a
LV Installation, http://www.electrical-
installation.org/enwiki/3-phase_short-
circuit_current_(Isc)_at_any_point_within_a_LV
_installation .
2. Energy Expressed In Terms of Current,
https://en.wikipedia.org/wiki/Joule_heating .
3. Arc Flash Reduction Maintenance System,
http://www.eaton.com/Eaton/ProductsServices
/Electrical/ProductsandServices/CircuitProtectio
n/ArcflashReductionMaintenanceSystem/index.
htm .
4. Electrical Maintenance Switch, NEC, Article
240.87, Arc Energy Reduction.
5. Anixter Technical Handbook (English Edition),
Page 92, Cable Impedance, 1/0 cable.
Biography
Del John Ventruella is licensed as a Professional
Engineer in the District of Columbia. He
completed the Bachelors of Science degree in
Electrical Engineering from The Rose-Hulman
Institute of Technology in Terre, Haute, Indiana
and immediately went to work for a multi-
national firm offering power systems
engineering studies to heavy industry, hospitals,
and airports. In time he came to assume
responsibility for his own territory, and began
completion of the Masters of Science degree in
electrical engineering at The University of
Alabama at Birmingham. He specialized in
power systems, but also completed coursework
in robotics and control systems. He has
authored papers for the IEEE, and presented
them at local meetings and international
conferences.

More Related Content

What's hot

Mitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoMitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoGilberto Mejía
 
EM_II_Project_London_Julia
EM_II_Project_London_JuliaEM_II_Project_London_Julia
EM_II_Project_London_JuliaJulia London
 
Emtp rv ic-part1
Emtp rv ic-part1Emtp rv ic-part1
Emtp rv ic-part1Julian Reis
 
Parametros diodos
Parametros diodosParametros diodos
Parametros diodosKarenCo12
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersThorne & Derrick International
 
The sheath voltage_limiter
The sheath voltage_limiterThe sheath voltage_limiter
The sheath voltage_limiterGilberto Mejía
 
1999 si pi_dws_training_course
1999 si pi_dws_training_course1999 si pi_dws_training_course
1999 si pi_dws_training_coursePiero Belforte
 
Day 3: Power Supply Quality in Buildings
Day 3: Power Supply Quality in Buildings Day 3: Power Supply Quality in Buildings
Day 3: Power Supply Quality in Buildings RCREEE
 
Antennas and Wave Propagation
Antennas and Wave Propagation Antennas and Wave Propagation
Antennas and Wave Propagation VenkataRatnam14
 
Antenna arrays
Antenna arraysAntenna arrays
Antenna arraysAJAL A J
 
Transmission line analysis
Transmission line analysisTransmission line analysis
Transmission line analysisAnurag Anupam
 
Antenna basics from-r&s
Antenna basics from-r&sAntenna basics from-r&s
Antenna basics from-r&sSaurabh Verma
 

What's hot (20)

Mitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoMitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacino
 
Ce31533536
Ce31533536Ce31533536
Ce31533536
 
SWR
SWRSWR
SWR
 
EM_II_Project_London_Julia
EM_II_Project_London_JuliaEM_II_Project_London_Julia
EM_II_Project_London_Julia
 
Emtp rv ic-part1
Emtp rv ic-part1Emtp rv ic-part1
Emtp rv ic-part1
 
Parametros diodos
Parametros diodosParametros diodos
Parametros diodos
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
 
Rf antenna basics
Rf antenna basicsRf antenna basics
Rf antenna basics
 
The sheath voltage_limiter
The sheath voltage_limiterThe sheath voltage_limiter
The sheath voltage_limiter
 
Tan Delta on MV Cables (Megger)
Tan Delta on MV Cables (Megger)Tan Delta on MV Cables (Megger)
Tan Delta on MV Cables (Megger)
 
1999 si pi_dws_training_course
1999 si pi_dws_training_course1999 si pi_dws_training_course
1999 si pi_dws_training_course
 
Protection of Transmission lines
Protection of Transmission linesProtection of Transmission lines
Protection of Transmission lines
 
Chap2 s11b
Chap2 s11bChap2 s11b
Chap2 s11b
 
Day 3: Power Supply Quality in Buildings
Day 3: Power Supply Quality in Buildings Day 3: Power Supply Quality in Buildings
Day 3: Power Supply Quality in Buildings
 
Antennas and Wave Propagation
Antennas and Wave Propagation Antennas and Wave Propagation
Antennas and Wave Propagation
 
Ijsea04021004
Ijsea04021004Ijsea04021004
Ijsea04021004
 
Antenna arrays
Antenna arraysAntenna arrays
Antenna arrays
 
Antenna basics
Antenna basicsAntenna basics
Antenna basics
 
Transmission line analysis
Transmission line analysisTransmission line analysis
Transmission line analysis
 
Antenna basics from-r&s
Antenna basics from-r&sAntenna basics from-r&s
Antenna basics from-r&s
 

Viewers also liked

Tamer Mohammed kamal
Tamer Mohammed kamalTamer Mohammed kamal
Tamer Mohammed kamaltamer kamal
 
AI Moral Field Based Control Copyright (C) 2014 by Del John Ventruella All Ri...
AI Moral Field Based Control Copyright (C) 2014 by Del John Ventruella All Ri...AI Moral Field Based Control Copyright (C) 2014 by Del John Ventruella All Ri...
AI Moral Field Based Control Copyright (C) 2014 by Del John Ventruella All Ri...Del Ventruella
 
ブログメディアにおけるData APIの活用について
ブログメディアにおけるData APIの活用についてブログメディアにおけるData APIの活用について
ブログメディアにおけるData APIの活用についてHatsuhito UENO
 
Einstein and Galileo Masters of Relativity History's Pawns REVISED FINAL PAPE...
Einstein and Galileo Masters of Relativity History's Pawns REVISED FINAL PAPE...Einstein and Galileo Masters of Relativity History's Pawns REVISED FINAL PAPE...
Einstein and Galileo Masters of Relativity History's Pawns REVISED FINAL PAPE...Del Ventruella
 
برنامج حسابات و مخازن ( Easy store) تحكم فى كافه الأقسام
برنامج حسابات و مخازن  ( Easy store) تحكم فى كافه الأقسامبرنامج حسابات و مخازن  ( Easy store) تحكم فى كافه الأقسام
برنامج حسابات و مخازن ( Easy store) تحكم فى كافه الأقسامPioneers Solutions
 
canine kidney failure article
canine kidney failure articlecanine kidney failure article
canine kidney failure articleDel Ventruella
 
برنامج حسابات و مخازن ( E asy store)
برنامج حسابات و مخازن ( E asy store)برنامج حسابات و مخازن ( E asy store)
برنامج حسابات و مخازن ( E asy store)Pioneers Solutions
 
AWSアカウントに関する不正使用を整理してみた
AWSアカウントに関する不正使用を整理してみたAWSアカウントに関する不正使用を整理してみた
AWSアカウントに関する不正使用を整理してみたNaoto Katsumi
 
The Road less Traveled in Africa by Abraham J. Meintjes
The Road less Traveled in Africa by Abraham J. MeintjesThe Road less Traveled in Africa by Abraham J. Meintjes
The Road less Traveled in Africa by Abraham J. MeintjesAbraham J. (Johan) Meintjes
 
برنامج محاسبة Easy store( إدارة المخازن)
برنامج محاسبة Easy store(  إدارة المخازن)برنامج محاسبة Easy store(  إدارة المخازن)
برنامج محاسبة Easy store( إدارة المخازن)Pioneers Solutions
 

Viewers also liked (16)

Tamer Mohammed kamal
Tamer Mohammed kamalTamer Mohammed kamal
Tamer Mohammed kamal
 
AI Moral Field Based Control Copyright (C) 2014 by Del John Ventruella All Ri...
AI Moral Field Based Control Copyright (C) 2014 by Del John Ventruella All Ri...AI Moral Field Based Control Copyright (C) 2014 by Del John Ventruella All Ri...
AI Moral Field Based Control Copyright (C) 2014 by Del John Ventruella All Ri...
 
ブログメディアにおけるData APIの活用について
ブログメディアにおけるData APIの活用についてブログメディアにおけるData APIの活用について
ブログメディアにおけるData APIの活用について
 
Einstein and Galileo Masters of Relativity History's Pawns REVISED FINAL PAPE...
Einstein and Galileo Masters of Relativity History's Pawns REVISED FINAL PAPE...Einstein and Galileo Masters of Relativity History's Pawns REVISED FINAL PAPE...
Einstein and Galileo Masters of Relativity History's Pawns REVISED FINAL PAPE...
 
Galileo galilei
Galileo galileiGalileo galilei
Galileo galilei
 
برنامج حسابات و مخازن ( Easy store) تحكم فى كافه الأقسام
برنامج حسابات و مخازن  ( Easy store) تحكم فى كافه الأقسامبرنامج حسابات و مخازن  ( Easy store) تحكم فى كافه الأقسام
برنامج حسابات و مخازن ( Easy store) تحكم فى كافه الأقسام
 
canine kidney failure article
canine kidney failure articlecanine kidney failure article
canine kidney failure article
 
برنامج حسابات و مخازن ( E asy store)
برنامج حسابات و مخازن ( E asy store)برنامج حسابات و مخازن ( E asy store)
برنامج حسابات و مخازن ( E asy store)
 
AWSアカウントに関する不正使用を整理してみた
AWSアカウントに関する不正使用を整理してみたAWSアカウントに関する不正使用を整理してみた
AWSアカウントに関する不正使用を整理してみた
 
Johnny's incredible Congo River Journey
Johnny's incredible Congo River JourneyJohnny's incredible Congo River Journey
Johnny's incredible Congo River Journey
 
Congo river mission ctn feb 10
Congo river mission ctn feb 10Congo river mission ctn feb 10
Congo river mission ctn feb 10
 
The unreached vs 2016 years of theology
The unreached vs 2016 years of theologyThe unreached vs 2016 years of theology
The unreached vs 2016 years of theology
 
The Road less Traveled in Africa by Abraham J. Meintjes
The Road less Traveled in Africa by Abraham J. MeintjesThe Road less Traveled in Africa by Abraham J. Meintjes
The Road less Traveled in Africa by Abraham J. Meintjes
 
Congo River Mission - Riverboat Construction
Congo River Mission - Riverboat ConstructionCongo River Mission - Riverboat Construction
Congo River Mission - Riverboat Construction
 
Congo River Mission
Congo River MissionCongo River Mission
Congo River Mission
 
برنامج محاسبة Easy store( إدارة المخازن)
برنامج محاسبة Easy store(  إدارة المخازن)برنامج محاسبة Easy store(  إدارة المخازن)
برنامج محاسبة Easy store( إدارة المخازن)
 

Similar to Arc flash hazard paper on estimates

Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in briefMuthar Hussain
 
ENEL301 report _Joseph Haystead_1132999
ENEL301 report _Joseph Haystead_1132999ENEL301 report _Joseph Haystead_1132999
ENEL301 report _Joseph Haystead_1132999Joseph Haystead
 
Interaction of the secondary arc
Interaction of the secondary arcInteraction of the secondary arc
Interaction of the secondary arcUNAC
 
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...paperpublications3
 
RCBU-2-Arc-Flash-Protection_Key_Considerations_for_Selection
RCBU-2-Arc-Flash-Protection_Key_Considerations_for_SelectionRCBU-2-Arc-Flash-Protection_Key_Considerations_for_Selection
RCBU-2-Arc-Flash-Protection_Key_Considerations_for_SelectionKieron King
 
6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_webLaurence Michael, PE
 
Modeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonModeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonGilberto Mejía
 
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Premier Publishers
 
Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...IJERA Editor
 
Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...IJERA Editor
 
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution SystemsIRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution SystemsIRJET Journal
 
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution SystemsIRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution SystemsIRJET Journal
 
How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?Fang Sam
 
Short-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.pptShort-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.pptJatmylHarnero1
 
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITSNOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITSVLSICS Design
 
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITSNOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITSVLSICS Design
 
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATORDESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATORVLSICS Design
 

Similar to Arc flash hazard paper on estimates (20)

Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 
Pe3426652670
Pe3426652670Pe3426652670
Pe3426652670
 
ENEL301 report _Joseph Haystead_1132999
ENEL301 report _Joseph Haystead_1132999ENEL301 report _Joseph Haystead_1132999
ENEL301 report _Joseph Haystead_1132999
 
Interaction of the secondary arc
Interaction of the secondary arcInteraction of the secondary arc
Interaction of the secondary arc
 
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
 
Arrester
ArresterArrester
Arrester
 
RCBU-2-Arc-Flash-Protection_Key_Considerations_for_Selection
RCBU-2-Arc-Flash-Protection_Key_Considerations_for_SelectionRCBU-2-Arc-Flash-Protection_Key_Considerations_for_Selection
RCBU-2-Arc-Flash-Protection_Key_Considerations_for_Selection
 
6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web
 
Modeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonModeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenon
 
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
 
Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...
 
Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...
 
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution SystemsIRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
 
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution SystemsIRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
IRJET- ARC Fault and Flash Signal Analysis in DC Distribution Systems
 
K046016266
K046016266K046016266
K046016266
 
How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?
 
Short-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.pptShort-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.ppt
 
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITSNOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
 
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITSNOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
NOVEL SLEEP TRANSISTOR TECHNIQUES FOR LOW LEAKAGE POWER PERIPHERAL CIRCUITS
 
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATORDESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
 

Recently uploaded

NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 

Recently uploaded (20)

NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 

Arc flash hazard paper on estimates

  • 1. 1 Arc Flash Hazard, When Over-Estimating Under-Estimates a Problem Del John Ventruella, PE Abstract: When one undertakes an arc flash study, one must develop a model based on the power system of interest. The model requires estimates of conductor lengths. To insure that the arc flash study that one is performing does not underestimate the magnitudes of the short circuit currents present within the power system, and to allow for limitations in the procedure by which one develops the model, typically visual inspection, one must carefully estimate the lengths of conductors. This requires that one avoid over-estimates of conductor lengths or risk computing short circuit currents that are below the magnitudes of short circuit and arc flash currents that are actually present at the ends of conductors, where circuit breaker panels or substations are located. If one over-estimates the short circuit current, the time delay of the circuit breakers affected will tend to be reduced based on the typical time current curve characteristic of circuit breakers. If the response time of a circuit breaker is reduced in terms of the time current curve plots due to higher short circuit current level estimates being produced, and if these short circuit current level estimates are in error, the actual energy released could be much greater because the circuit breaker will trip in response to the actual short circuit current magnitude, which will be lower than that which is calculated using shorter conductor lengths, and will typically involve a trip characteristic that involves a longer time delay (perhaps a long time trip rather than a short time trip, or a short time trip rather than an instantaneous trip). This could dramatically increase the Personnel Protective Equipment level that is required compared to the level predicted in a study. Introduction The selection of Personnel Protective Equipment is based on the magnitude of the energy released. Power is energy per unit time, so energy is: E = R(I2 )t. This is computed as: (Rlower) Isc-lower 2 tsc-lower > (Rhigher) Isc-higher 2 tsc-higher, If the variation between Isc-higher and Isc-lower is small enough while the magnitude of tsc-lower is sufficiently greater than tsc-higher due to a much greater circuit breaker response time associated with the lower fault current, the energy released for the lower short circuit current could be much greater if the circuit breaker requires considerably more time to respond to the lower arc flash current level (perhaps a long time trip response rather than an instantaneous or short time trip response). This assumes that Rlower and Rhigher are roughly equal for approximately the same short circuit or arc flash level. Arc Flash current levels at low Voltage tend to be proportional to the fault current level. Experience demonstrates that arc flash currents are diminished by some twenty percent1 relative to the three-phase fault level. If the time required for a trip response associated with the lower arc flash current affects a greater time delay, perhaps several seconds due to a long time trip unit reacting for a lower level current, which is much longer than the short time or instantaneous delay of the higher short circuit current estimate, the total
  • 2. 2 energy released for the lower level arc flash current will actually be substantially greater than that computed for the higher current. If the short circuit current estimated due to shorter than actual conductor length places the trip response time to the right of a trip device characteristic segment that is vertical, and if the short circuit current (arc flash current) is actually to the left of the trip device characteristic, the time difference in the response of the trip device could be so great as to dramatically increase the Personnel Protective Equipment (PPE) level that is required. Note that PPE levels are based on the computed short circuit current and time delay and the minimum arc flash current level calculated to be present. If the arc flash current level computed based on the conductor length is too great, based on too short an estimate of conductor length, the time required for the circuit breaker response could be much less than that which occurs in reality, and the PPE required to provide adequate protection to personnel in reality could similarly increase dramatically in comparison. In effect, personnel could be left inadequately protected from arc flash hazard due to estimates of conductor length that are too short. Even with a suitable engineering study, this fact could never be described within its pages if the engineer is not aware of this danger, or if the engineer’s work environment does not grant the time to consider this possibility while performing the study. Analysis The concept being presented is illustrated in Figure 1.0. Figure 1.0 – Time Current Curve Illustration of Circuit Breaker with Long Time and Instantaneous Trip Devices and Two Arc Flash Currents with Response Times, Each Separated by a Few Hundred Amperes (Roughly the Thickness of the Circuit Breaker’s Time Current Curve). If the length of a cable is underestimated, the calculated arc flash may appear to force a response to the fault level on the right (see Figure 1.0). In reality, a more realistic estimate of the cable length may make it respond to the arc flash current level on the left (also Figure 1.0), involving a much longer response time (perhaps several seconds instead of roughly one tenth second). In Figure 1.0, the energy released for the 15 kA current is: I2 tR = 15 kA 2 (0.10 sec.)R = 22,500,000 A2 R sec. The energy released for the 14.7 kA current is: I2 tR = 14.6 kA 2 (7.0 sec.)R = 1,512,630,000 A2 R sec. If the arc flash current in reality is only (roughly) 300 Amperes (the thickness of the circuit breaker trip characteristic) lower than the computed value, the energy released will actually be greater for 14.7 kA of arc flash current than for 15 kA of arc flash current. It is thus clear that if the arc flash current is
  • 3. 3 estimated to be over-valued, in a manner consistent with the estimation of short circuit current and too short conductor length estimates, the actual energy released and the arc flash personnel protective equipment (PPE) level could be considerably greater than that predicted by the arc flash study, based on a higher short circuit estimate (and a lower circuit breaker response time), would predict. The single-line diagram for the power system to be examined to prove this concept follows in Figure 2.0. Figure 2.0 – Sample Single-line Drawing with Buses One, Two, and Three Shown The system consists of a utility source, a transformer that steps the Voltage down from 12.47 kV to 480 V. and a single cable extending the system. This model, as realized in Table 1.0, with an approximate 500 foot long conductor, might represent an older system in which two or three conductors have been “daisy chained” to produce the single, 500 foot long conductor that is modeled. An available short circuit MVA (SCMVA) of 100 is used in this model, and may represent utility loads in urban areas where the magnitude of the three-phase short circuit current is intentionally reduced by controls imposed by the utility. Short Circuit Calculations for Model of Figure 1.0 Utility PU Impedance 100000000 12470 1.555009 Ohms VA VOLTS 1 pu Z Transformer PU Impedance 2500000 5.75% 2.3 pu Z 0.0052992 2.3 Ohms pu
  • 4. 4 Cable PU Impedance Cable Ohms 0.118 Per 1000 ft Cable Imp. % of 500 Ft. pu Cable Imp. Cable Length 0.0590 100.0% 25.61 100% (500 Ft.)) 0.0575 97.5% 24.97 97.5% (475 Ft.) 0.0561 95.0% 24.33 95% (450 Ft.) 0.0546 92.5% 23.69 92.5% (425 Ft.) 0.0531 90.0% 23.05 90% (400 Ft.) Short Circuit Currents Total Pu Impedance Current (A) Bus Currents at Buses In System Utility 1.00 4630 1 Trans. Sec. 3.30 36450 2 Cable End 28.91 4161 3 100% of 500 Ft. Cable (Based on 28.27 4255 3 97.5% of 500 Ft. Cable 500 Ft. 27.63 4354 3 95% of 500 Ft. Cable Total Cable 26.99 4457 3 92.5% of 500 Ft. Cable Length) 26.35 4565 3 90% of 500 Ft. Cable Table 1.0 – Short Circuit Calculations (Includes Multiple Calculations of Current Based on Various Cable Lengths at Bus Three) The short circuit currents at each bus are clearly marked in Table 1.0 (relative to Figure 2.0). The values for Bus Three are shown for various estimated lengths of the conductor, from 100% of the conductor length to 90% of its length. With circuit breaker characteristics typically a few hundred Amperes in horizontal thickness, it is clear that errors in estimating cable lengths, and particularly so-called “conservative” estimates of length (producing higher short circuit current magnitudes) can produce results that leave the arc flash current estimate to the right of the time current curve short time or instantaneous response characteristic, while the actual fault level may exist to the left of the time current curve, in the long time range (given some 400 Amperes of variation between 100% accuracy at 500 feet and 90% accuracy at 450 feet). If the true, lower arc flash current level were computed it could add seconds to the response time, while leaving the arc flash current essentially in the same range as it was, producing a need for much more elaborate PPE (or eliminating the possibility of PPE) than would exist if the short time or instantaneous trip were to respond to an arc flash.
  • 5. 5 Short Circuit Currents for Various Sources, Transformers, and Cables (480 V) (480 V) Current at Bus Current at Bus Difference in 12470 V Transformer Cable Length 480 V at End of Cable (A) at End of Cable (A) Current SCMVA kVA (Feet) Cable Size (100% of Length) (90% of Length) (Amperes) 100 2500 500 #8 822 911 89 2.3 0.3295 143 pu value Ohms pu Z 100 500 500 500 MCM 5299 5548 249 11.5 0.0235 10 pu value Ohms pu Z 500 2500 500 #8 827 917 90 11.5 0.3295 715 pu value Ohms pu Z 500 500 500 500 MCM 5493 5761 268 57.5 0.0235 51 pu value Ohms pu Z Note: Cable is #8, or 0.659 Ohms per 1000 Ft. OR Cable is 500 MCM, or 0.047 Ohms per 1000 Ft. Transformer is 5.75% impedance. Table 2.0 – Variations in Current due to Estimation Based on Cable Size and Available SCMVA at Source Causes What might cause circuit breakers to be set in a manner that would produce results that would push the time current curve characteristic so far to the right in the time current curve plot? One might imagine a few easily, the most obvious of which would be conditions under which many circuit breakers exist in series in older buildings, so that there is a need to make the most of the area of the time current curve when coordinating circuit breakers. From the perspective of the person developing the settings, the results of the arc flash study and coordination study may appear to produce a perfectly legitimate result in terms of circuit breaker settings, if the possibility of failure to properly estimate cable lengths and overestimates of short circuit current are not considered. Table 2.0 illustrates the variation in short circuit current that would result due to variations in conductor length and available SCMVA (short circuit MVA). The short circuit current variation could be as great as approximately 250 Amperes for a ten percent error in judgement of cable length for a 500 MCM cable. Based on this, for transformers that are rated at 480 Volt and no larger than 2500 kVA, and with an available SCMVA of 500 MVA or less, and a single cable or string of daisy chained cables of 500 feet in length with 500 MCM rating, the maximum error would be roughly 250 Amperes.
  • 6. 6 Given the results of Table 2.0, one could, by making certain that the highest valued vertical transition to the next slowest trip element of the circuit breaker’s protective device is at least 200% of 250 Amperes to the left of the computed minimum arc flash current level, or 500 Amperes to the left of the protective trip device element’s intended trip for arc flash, to insure that one need not concern oneself with the risk of error due to estimation of cable lengths. (See Figure 3.0.) Of course, to be precise the specific system configuration must be considered in each instance (as in Table 2.0) and compared to the circuit breaker’s time current curve plot, which is a rather time consuming task. Figure 3.0 – Illustration of Application of Results of Table 2.0 The horizontal “gap” that must be maintained and is illustrated in Figure 3.0 becomes even worse as “estimates” of cumulative or daisy- chained cable lengths become worse, as shown in Table 3.0 for a 20% error.
  • 7. 7 Short Circuit Currents for Various Sources, Transformers, and Cables (480 V) (480 V) Current at Bus Current at Bus Difference in 12470 V Transformer Cable Length 480 V at End of Cable (A) at End of Cable (A) Current SCMVA kVA (Feet) Cable Size (100% of Length) (80% of Length) (Amperes) 500 500 500 500 MCM 5493 6057 564 57.5 0.0235 51 pu value Ohms pu Z Note: Cable is #8, or 0.659 Ohms per 1000 Ft. OR Cable is 500 MCM, or 0.047 Ohms per 1000 Ft. Transformer is 5.75% impedance. 400 Feet of length estimated Table 3.0 – Illustration of Growth of Magnitude of Error in Arc Flash Current Due to Error in Estimate of Length of Cable (20%) (If a margin of 200% were deemed reasonable, this would require an 1100 A “gap” between the minimum arc flash current and the rightmost portion of the vertical characteristic transitioning to the next slowest trip response by the circuit breaker providing protection on the source side.) The Cure There is a simple cure for this problem of under- estimating cable lengths (save for computations of the sort performed in Table 2.0 under an assumed “certainty” in the maximum error inherent in the estimation of the cable/wire length). There exist today circuit breakers with “maintenance” switch3 settings that are designed to respond very quickly in a very sensitive manner to arc flash current once the “maintenance” switch on the circuit breaker has been activated. (This is a solution recommended in the National Electrical Code, Article 240.87, Arc Energy Reduction.4 ) These devices typically respond in an instantaneous manner to very low level faults in the event that the maintenance switch is triggered. The maintenance switch thus is placed in the “on” position whenever work is being performed on the load side of the circuit breaker. There may be other solutions, such as turning the instantaneous trip to a very low setting whenever work is being performed on the load side of circuit breakers, but this must be considered in the course of an arc flash study to allow for the starting of motors or other inrush loads that may normally occur while energized work is being performed. Conclusion Errors in the measurement of cable lengths can produce inaccurate Arc Flash Studies and circuit breaker settings that can appear to conform to lower level PPE requirements (due to very short, circuit breaker response times) while in fact producing unrealistically high short circuit trip intervals. As a result of much longer response times to lower short circuit currents by circuit breakers in reality, much greater PPE requirements can result in general.
  • 8. 8 If studies are performed by third parties, it may be impossible, given the “assembly line” mentality of many service providers, for such errors to be caught, and where not identified, they can produce grave dangers to personnel and passers-by (particularly if PPE may not, in reality, be possible to specify for a given location and circuit breaker setting). It is, after all, clear that long table allowing for estimates in cable lengths are absent from most arc flash studies. The only other potential solution, substantially improving the estimate of conductor lengths during data collection, is probably unrealistic, although it might be conceivable if estimation within 10% of the cable length is perceived as possible, and computing the potential error in short circuit current as a result is undertaken (as in Table 2.0) in the course of the study. It is virtually inevitable that slight errors in estimates of conductor lengths will be made. Such approaches to estimating cable lengths actually assure adequately rated circuit breakers in short circuit studies. Such errors can have the opposite effect in arc flash studies. Arc flash studies can be useful, but only if errors in conductor length do not produce PPE levels that underestimate arc flash durations. The use of circuit breakers equipped with “maintenance” switches (or potentially by having an alternate, much lower setting for each circuit breaker where work is to be performed on the load side) are possible solutions to this serious and potentially unrecognized problem in Arc Flash studies. Time consuming calculations (of the type undertaken in Table 2.0 and Figure 3.0) are less likely to occur to estimate the extent of the offset from vertical transitions (between trip types) in circuit breaker time current curves based on short circuit current levels, and would only be of value if the error in the length of the cable estimates could be assured. Bibliography 1. Fault Arc Resistance (magnitude), 3-Phase Short-Circuit Current (Isc) at any Point Within a LV Installation, http://www.electrical- installation.org/enwiki/3-phase_short- circuit_current_(Isc)_at_any_point_within_a_LV _installation . 2. Energy Expressed In Terms of Current, https://en.wikipedia.org/wiki/Joule_heating . 3. Arc Flash Reduction Maintenance System, http://www.eaton.com/Eaton/ProductsServices /Electrical/ProductsandServices/CircuitProtectio n/ArcflashReductionMaintenanceSystem/index. htm . 4. Electrical Maintenance Switch, NEC, Article 240.87, Arc Energy Reduction. 5. Anixter Technical Handbook (English Edition), Page 92, Cable Impedance, 1/0 cable. Biography Del John Ventruella is licensed as a Professional Engineer in the District of Columbia. He completed the Bachelors of Science degree in Electrical Engineering from The Rose-Hulman Institute of Technology in Terre, Haute, Indiana and immediately went to work for a multi- national firm offering power systems engineering studies to heavy industry, hospitals, and airports. In time he came to assume responsibility for his own territory, and began completion of the Masters of Science degree in electrical engineering at The University of Alabama at Birmingham. He specialized in power systems, but also completed coursework in robotics and control systems. He has authored papers for the IEEE, and presented them at local meetings and international conferences.