SlideShare a Scribd company logo
Amortized Computational Complexity
Abstract : A powerful technique in the complexity analysis of various algorithms is amortization
or averaging over time. Amortized running time is a realistic measure of complexity of a
sequence of operations . It will not provide you with the exact computational time . Instead , it
lets you calculate a tight upper bound and lower bound of algorithms . Based on the result
obtained, varieties of algorithms can be compared for performance analysis . This white-paper
describes several methods of evaluating amortized complexity .
Introduction : In many uses of data structures , a sequence of operations , rather than a single
operation, is performed . So, the final goal is to evaluate the amortized time complexity of that
sequence . The only requirement is that the sum of the amortized complexity of all elements in
a sequence is greater than the sum of the actual complexities of the elements . So, we can
conclude :
Sum(amortized(i)) >= Sum(actual(i)) ........... (1.1)
Relative to actual cost and amortized cost of an operation in a sequence of n operations , we
define a potential function as below :
P(i) = amortized(i) - actual (i) - P(i-1) ...........(1.2)
Taking sum of the equation , we obtain :
P(n) = Sum(amortized(i)) - Sum(actual(i)) ..........(1.3)
From (1.1) & (1.3) , we conclude :
P(n) >= 0 ........(1.4)
To make the idea of amortization and motivation behind it more concrete , let us consider the
example of evaluating the amortized complexity of an algorithm , which displays number of toys
available in binary format . To update every digit of the display the algorithm takes d unit of
time . Assuming that the number of current toys is N and initial no. of toys is 0, we need to
evaluate the amortized complexity of the algorithm used to display the number of toys . There
are three popular methods to arrive at the amortized complexity of the operations, namely , (1)
aggregate method , (2) accounting method and (3) potential method .
Aggregate Method : In the aggregate method ,we determine the
UpperBoundOnSumOfActualCosts(N) for the sum of the actual costs of the n operations.The
amortized cost is amounted to UpperBoundOnSumOfActualCosts(N) /N .
Let N be the number of toys manufactured ; the number of digits used to display the number of
toys is n or 'Base-2 logN' . The least significant bit of the display has been changed N times ; the
second least significant bit changes once for every 2 toys ; the third least significant bit changes
once for every 4 times and so on...
So, the aggregate number of digits that have been changed is bounded by N (1+1/2+1/4+...)d or
d2N. So, the amortized cost is amounted to 2dN/N = 2d.
Accounting Method : To proceed using accounting method , we must first assign an amortized
cost and then prove that this assignment satisfies eq - (1.1). Generally we start by assigning an
amortized cost obtained by a good guess . Once we have shown this , we obtain an upper bound
on the cost of any operation sequence by computing Sum(f(i)*amortized(i)) , where f(i) be the
frequency of the operation and amortized(i) the amortized cost of the operation .
Suppose , we assign a guessed amortized cost of 2d for each display change . Then the potential
function
P(n) = Sum(amortized(i)) - Sum(actual(i))
= 2dN - d(1+1/2+1/4+.......)
> 0;
So, the accounting method proved that the amortized cost of the display can be reduced to 2d.
Potential Method : In this approach , we postulate a function for the analysis and use the
function to satisfy eq - (1) .
Consider the example given in the introduction section . When the first toy is available , we can
use the amortized cost 2d to pay for the update , in which d amount is spent and remaining d
amount is retained as a credit to the first least significant bit. Following the update of the second
toy , the amount spent is 2d*2 in which 3d is spent to update two least significant digits and the
second least significant bit now has credit d and the first least significant bit has credit 0 .
Proceeding in this way , we can sum up credit on each digit of the display always equal (2d-d)v ,
where 2d be the amortized cost , d the actual cost and v the value of the digit. So, we should
use the potential function
P(N) = (2d-d)*Sum(v(i)) , where v(i) = face value of the i-th digit
Let q be the number of 1’s at the rightmost places and the j th display and it has been changed
from jth to (j+1) th no.So, when the display changes from j th to j+1 th value, where j = 1111011
the potential change incurred
P(N) - P(N-1)= d(1-q*1) ;
So the amortized cost for the display change = actual cost + P(N) - P(N-1)= (q+1)d + d(1-2*1) = 2d
.
Conclusion : A worst case analysis ,in which we sum the worst-case time of individual
operations, may be unduly pessimistic ; it ignores correlated effect on data structures. On the
other hand, average case analysis can be inaccurate , as the probabilistic assumptions needed to
carry out the analysis may be false . In such a scenario, amortized analysis , in which we average
the running time over per operation , yield an answer that is both realistic and robust .

More Related Content

What's hot

Amortized analysis
Amortized analysisAmortized analysis
Amortized analysis
ajmalcs
 
13 Amortized Analysis
13 Amortized Analysis13 Amortized Analysis
13 Amortized Analysis
Andres Mendez-Vazquez
 
Aoa amortized analysis
Aoa amortized analysisAoa amortized analysis
Aoa amortized analysis
Salabat Khan
 
Amortized Analysis
Amortized Analysis Amortized Analysis
Amortized Analysis
sathish sak
 
Adauctions
AdauctionsAdauctions
Adauctions
超 刘
 
BIometrics- plotting DET and EER curve using Matlab
BIometrics- plotting DET and EER curve using MatlabBIometrics- plotting DET and EER curve using Matlab
BIometrics- plotting DET and EER curve using MatlabShiv Koppad
 
Solving a “Transportation Planning” Problem through the Programming Language “C”
Solving a “Transportation Planning” Problem through the Programming Language “C”Solving a “Transportation Planning” Problem through the Programming Language “C”
Solving a “Transportation Planning” Problem through the Programming Language “C”
Shahadat Hossain Shakil
 
Hw5 2017-spring
Hw5 2017-springHw5 2017-spring
Hw5 2017-spring
奕安 陳
 
Synchronous Loadable Up and Down Counter
Synchronous Loadable Up and Down Counter Synchronous Loadable Up and Down Counter
Synchronous Loadable Up and Down Counter
Digital System Design
 
Amortized analysis
Amortized analysisAmortized analysis
Amortized analysis
mohit tripathi
 
Dynamic Program Problems
Dynamic Program ProblemsDynamic Program Problems
Dynamic Program ProblemsRanjit Sasmal
 
Chapter10 noha2012
Chapter10 noha2012Chapter10 noha2012
Chapter10 noha2012
TopanArdiansyahPutra
 
A star
A starA star
A star
minhaz uddin
 
Nrtl activity coefficient for mixture1
Nrtl activity coefficient for mixture1Nrtl activity coefficient for mixture1
Nrtl activity coefficient for mixture1
ESSID Abou Hligha
 
Ch08
Ch08Ch08
Ch08
waiwai28
 

What's hot (17)

Amortized analysis
Amortized analysisAmortized analysis
Amortized analysis
 
13 Amortized Analysis
13 Amortized Analysis13 Amortized Analysis
13 Amortized Analysis
 
Amortized
AmortizedAmortized
Amortized
 
Aoa amortized analysis
Aoa amortized analysisAoa amortized analysis
Aoa amortized analysis
 
Amortized Analysis
Amortized Analysis Amortized Analysis
Amortized Analysis
 
Adauctions
AdauctionsAdauctions
Adauctions
 
BIometrics- plotting DET and EER curve using Matlab
BIometrics- plotting DET and EER curve using MatlabBIometrics- plotting DET and EER curve using Matlab
BIometrics- plotting DET and EER curve using Matlab
 
Test
TestTest
Test
 
Solving a “Transportation Planning” Problem through the Programming Language “C”
Solving a “Transportation Planning” Problem through the Programming Language “C”Solving a “Transportation Planning” Problem through the Programming Language “C”
Solving a “Transportation Planning” Problem through the Programming Language “C”
 
Hw5 2017-spring
Hw5 2017-springHw5 2017-spring
Hw5 2017-spring
 
Synchronous Loadable Up and Down Counter
Synchronous Loadable Up and Down Counter Synchronous Loadable Up and Down Counter
Synchronous Loadable Up and Down Counter
 
Amortized analysis
Amortized analysisAmortized analysis
Amortized analysis
 
Dynamic Program Problems
Dynamic Program ProblemsDynamic Program Problems
Dynamic Program Problems
 
Chapter10 noha2012
Chapter10 noha2012Chapter10 noha2012
Chapter10 noha2012
 
A star
A starA star
A star
 
Nrtl activity coefficient for mixture1
Nrtl activity coefficient for mixture1Nrtl activity coefficient for mixture1
Nrtl activity coefficient for mixture1
 
Ch08
Ch08Ch08
Ch08
 

Viewers also liked

Общество Мертвых Потоков
Общество Мертвых ПотоковОбщество Мертвых Потоков
Общество Мертвых Потоков
Alexey Fyodorov
 
Agricultural investment briefing
Agricultural investment briefingAgricultural investment briefing
Agricultural investment briefingTony Palanca
 
Spieler Press Release_al_2_3_16
Spieler Press Release_al_2_3_16Spieler Press Release_al_2_3_16
Spieler Press Release_al_2_3_16Geri Spieler
 
JLL Columbus Office Outlook: Q3 2016
JLL Columbus Office Outlook: Q3 2016JLL Columbus Office Outlook: Q3 2016
JLL Columbus Office Outlook: Q3 2016
Peter McStravick
 
Issue 7 NTEU Chapter_164_newsletter
Issue 7 NTEU Chapter_164_newsletterIssue 7 NTEU Chapter_164_newsletter
Issue 7 NTEU Chapter_164_newsletter
NTEU Chapter 164
 
Moving to g1 gc by Kirk Pepperdine.
Moving to g1 gc by Kirk Pepperdine.Moving to g1 gc by Kirk Pepperdine.
Moving to g1 gc by Kirk Pepperdine.
J On The Beach
 
Doing math with python.ch04
Doing math with python.ch04Doing math with python.ch04
Doing math with python.ch04
Seok-joon Yun
 
Versiooniuuenduse automatiseerimine kasutades skriptimiskeelt Bash
Versiooniuuenduse automatiseerimine kasutades skriptimiskeelt BashVersiooniuuenduse automatiseerimine kasutades skriptimiskeelt Bash
Versiooniuuenduse automatiseerimine kasutades skriptimiskeelt Bash
Irina Ivanova
 
Certificado de participação no Hackathon Globo 2016 - Cesar A. Nogueira
Certificado de participação no Hackathon Globo 2016 - Cesar A. NogueiraCertificado de participação no Hackathon Globo 2016 - Cesar A. Nogueira
Certificado de participação no Hackathon Globo 2016 - Cesar A. Nogueira
Cesar Augusto Nogueira
 
Waldorf Education
Waldorf Education Waldorf Education
Waldorf Education
Nenevie Villando
 
Hadoop HDFS Detailed Introduction
Hadoop HDFS Detailed IntroductionHadoop HDFS Detailed Introduction
Hadoop HDFS Detailed Introduction
Hanborq Inc.
 
Project Performance Dashboard
Project Performance DashboardProject Performance Dashboard
Project Performance Dashboard
Chris Vizzuett
 
Personal Mission and Vision Statements
Personal Mission and Vision StatementsPersonal Mission and Vision Statements
Personal Mission and Vision Statements
Aurelien Domont, MBA
 

Viewers also liked (13)

Общество Мертвых Потоков
Общество Мертвых ПотоковОбщество Мертвых Потоков
Общество Мертвых Потоков
 
Agricultural investment briefing
Agricultural investment briefingAgricultural investment briefing
Agricultural investment briefing
 
Spieler Press Release_al_2_3_16
Spieler Press Release_al_2_3_16Spieler Press Release_al_2_3_16
Spieler Press Release_al_2_3_16
 
JLL Columbus Office Outlook: Q3 2016
JLL Columbus Office Outlook: Q3 2016JLL Columbus Office Outlook: Q3 2016
JLL Columbus Office Outlook: Q3 2016
 
Issue 7 NTEU Chapter_164_newsletter
Issue 7 NTEU Chapter_164_newsletterIssue 7 NTEU Chapter_164_newsletter
Issue 7 NTEU Chapter_164_newsletter
 
Moving to g1 gc by Kirk Pepperdine.
Moving to g1 gc by Kirk Pepperdine.Moving to g1 gc by Kirk Pepperdine.
Moving to g1 gc by Kirk Pepperdine.
 
Doing math with python.ch04
Doing math with python.ch04Doing math with python.ch04
Doing math with python.ch04
 
Versiooniuuenduse automatiseerimine kasutades skriptimiskeelt Bash
Versiooniuuenduse automatiseerimine kasutades skriptimiskeelt BashVersiooniuuenduse automatiseerimine kasutades skriptimiskeelt Bash
Versiooniuuenduse automatiseerimine kasutades skriptimiskeelt Bash
 
Certificado de participação no Hackathon Globo 2016 - Cesar A. Nogueira
Certificado de participação no Hackathon Globo 2016 - Cesar A. NogueiraCertificado de participação no Hackathon Globo 2016 - Cesar A. Nogueira
Certificado de participação no Hackathon Globo 2016 - Cesar A. Nogueira
 
Waldorf Education
Waldorf Education Waldorf Education
Waldorf Education
 
Hadoop HDFS Detailed Introduction
Hadoop HDFS Detailed IntroductionHadoop HDFS Detailed Introduction
Hadoop HDFS Detailed Introduction
 
Project Performance Dashboard
Project Performance DashboardProject Performance Dashboard
Project Performance Dashboard
 
Personal Mission and Vision Statements
Personal Mission and Vision StatementsPersonal Mission and Vision Statements
Personal Mission and Vision Statements
 

Similar to Amortized complexity

Amortized complexity
Amortized complexityAmortized complexity
Amortized complexity
paramita30
 
DOC-20230417-WA0013.-7-27.pptx
DOC-20230417-WA0013.-7-27.pptxDOC-20230417-WA0013.-7-27.pptx
DOC-20230417-WA0013.-7-27.pptx
03Shrishti
 
5.2 Least Squares Linear Regression.pptx
5.2  Least Squares Linear Regression.pptx5.2  Least Squares Linear Regression.pptx
5.2 Least Squares Linear Regression.pptx
MaiEllahham1
 
Bellmon Ford Algorithm
Bellmon Ford AlgorithmBellmon Ford Algorithm
Bellmon Ford Algorithm
69RishabhPandey
 
Asymptotic Notation
Asymptotic NotationAsymptotic Notation
Asymptotic Notation
Lovely Professional University
 
Cs6402 daa-2 marks set 1
Cs6402 daa-2 marks set 1Cs6402 daa-2 marks set 1
Cs6402 daa-2 marks set 1
Vai Jayanthi
 
Basic Computer Engineering Unit II as per RGPV Syllabus
Basic Computer Engineering Unit II as per RGPV SyllabusBasic Computer Engineering Unit II as per RGPV Syllabus
Basic Computer Engineering Unit II as per RGPV Syllabus
NANDINI SHARMA
 
economic load dispatch and unit commitment power_system_operation.pdf
economic load dispatch and unit commitment power_system_operation.pdfeconomic load dispatch and unit commitment power_system_operation.pdf
economic load dispatch and unit commitment power_system_operation.pdf
ArnabChakraborty499766
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Asymptotic Analysis in Data Structure using C
Asymptotic Analysis in Data Structure using CAsymptotic Analysis in Data Structure using C
Asymptotic Analysis in Data Structure using C
Meghaj Mallick
 
Unit i basic concepts of algorithms
Unit i basic concepts of algorithmsUnit i basic concepts of algorithms
Unit i basic concepts of algorithms
sangeetha s
 
DESIGN AND ALGORITHM.pptx BCA BANGALORECITY UNIVERSITY
DESIGN AND ALGORITHM.pptx BCA BANGALORECITY UNIVERSITYDESIGN AND ALGORITHM.pptx BCA BANGALORECITY UNIVERSITY
DESIGN AND ALGORITHM.pptx BCA BANGALORECITY UNIVERSITY
AneetaGrace1
 
Lec03 04-time complexity
Lec03 04-time complexityLec03 04-time complexity
Lec03 04-time complexityAbbas Ali
 
Dynamic programming1
Dynamic programming1Dynamic programming1
Dynamic programming1
debolina13
 
algo_vc_lecture8.ppt
algo_vc_lecture8.pptalgo_vc_lecture8.ppt
algo_vc_lecture8.ppt
Nehagupta259541
 
DSA Complexity.pptx What is Complexity Analysis? What is the need for Compl...
DSA Complexity.pptx   What is Complexity Analysis? What is the need for Compl...DSA Complexity.pptx   What is Complexity Analysis? What is the need for Compl...
DSA Complexity.pptx What is Complexity Analysis? What is the need for Compl...
2022cspaawan12556
 
Big Oh.ppt
Big Oh.pptBig Oh.ppt
Big Oh.ppt
Senthil Vit
 
TIME EXECUTION OF DIFFERENT SORTED ALGORITHMS
TIME EXECUTION   OF  DIFFERENT SORTED ALGORITHMSTIME EXECUTION   OF  DIFFERENT SORTED ALGORITHMS
TIME EXECUTION OF DIFFERENT SORTED ALGORITHMS
Tanya Makkar
 
WVKULAK13_submission_14
WVKULAK13_submission_14WVKULAK13_submission_14
WVKULAK13_submission_14Max De Koninck
 

Similar to Amortized complexity (20)

Amortized complexity
Amortized complexityAmortized complexity
Amortized complexity
 
DOC-20230417-WA0013.-7-27.pptx
DOC-20230417-WA0013.-7-27.pptxDOC-20230417-WA0013.-7-27.pptx
DOC-20230417-WA0013.-7-27.pptx
 
5.2 Least Squares Linear Regression.pptx
5.2  Least Squares Linear Regression.pptx5.2  Least Squares Linear Regression.pptx
5.2 Least Squares Linear Regression.pptx
 
Bellmon Ford Algorithm
Bellmon Ford AlgorithmBellmon Ford Algorithm
Bellmon Ford Algorithm
 
Asymptotic Notation
Asymptotic NotationAsymptotic Notation
Asymptotic Notation
 
Cs6402 daa-2 marks set 1
Cs6402 daa-2 marks set 1Cs6402 daa-2 marks set 1
Cs6402 daa-2 marks set 1
 
Basic Computer Engineering Unit II as per RGPV Syllabus
Basic Computer Engineering Unit II as per RGPV SyllabusBasic Computer Engineering Unit II as per RGPV Syllabus
Basic Computer Engineering Unit II as per RGPV Syllabus
 
economic load dispatch and unit commitment power_system_operation.pdf
economic load dispatch and unit commitment power_system_operation.pdfeconomic load dispatch and unit commitment power_system_operation.pdf
economic load dispatch and unit commitment power_system_operation.pdf
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Asymptotic Analysis in Data Structure using C
Asymptotic Analysis in Data Structure using CAsymptotic Analysis in Data Structure using C
Asymptotic Analysis in Data Structure using C
 
Unit i basic concepts of algorithms
Unit i basic concepts of algorithmsUnit i basic concepts of algorithms
Unit i basic concepts of algorithms
 
DESIGN AND ALGORITHM.pptx BCA BANGALORECITY UNIVERSITY
DESIGN AND ALGORITHM.pptx BCA BANGALORECITY UNIVERSITYDESIGN AND ALGORITHM.pptx BCA BANGALORECITY UNIVERSITY
DESIGN AND ALGORITHM.pptx BCA BANGALORECITY UNIVERSITY
 
Lec03 04-time complexity
Lec03 04-time complexityLec03 04-time complexity
Lec03 04-time complexity
 
Dynamic programming1
Dynamic programming1Dynamic programming1
Dynamic programming1
 
algo_vc_lecture8.ppt
algo_vc_lecture8.pptalgo_vc_lecture8.ppt
algo_vc_lecture8.ppt
 
DSA Complexity.pptx What is Complexity Analysis? What is the need for Compl...
DSA Complexity.pptx   What is Complexity Analysis? What is the need for Compl...DSA Complexity.pptx   What is Complexity Analysis? What is the need for Compl...
DSA Complexity.pptx What is Complexity Analysis? What is the need for Compl...
 
Big Oh.ppt
Big Oh.pptBig Oh.ppt
Big Oh.ppt
 
TIME EXECUTION OF DIFFERENT SORTED ALGORITHMS
TIME EXECUTION   OF  DIFFERENT SORTED ALGORITHMSTIME EXECUTION   OF  DIFFERENT SORTED ALGORITHMS
TIME EXECUTION OF DIFFERENT SORTED ALGORITHMS
 
Slide2
Slide2Slide2
Slide2
 
WVKULAK13_submission_14
WVKULAK13_submission_14WVKULAK13_submission_14
WVKULAK13_submission_14
 

Recently uploaded

Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 

Recently uploaded (20)

Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 

Amortized complexity

  • 1. Amortized Computational Complexity Abstract : A powerful technique in the complexity analysis of various algorithms is amortization or averaging over time. Amortized running time is a realistic measure of complexity of a sequence of operations . It will not provide you with the exact computational time . Instead , it lets you calculate a tight upper bound and lower bound of algorithms . Based on the result obtained, varieties of algorithms can be compared for performance analysis . This white-paper describes several methods of evaluating amortized complexity . Introduction : In many uses of data structures , a sequence of operations , rather than a single operation, is performed . So, the final goal is to evaluate the amortized time complexity of that sequence . The only requirement is that the sum of the amortized complexity of all elements in a sequence is greater than the sum of the actual complexities of the elements . So, we can conclude : Sum(amortized(i)) >= Sum(actual(i)) ........... (1.1) Relative to actual cost and amortized cost of an operation in a sequence of n operations , we define a potential function as below : P(i) = amortized(i) - actual (i) - P(i-1) ...........(1.2) Taking sum of the equation , we obtain : P(n) = Sum(amortized(i)) - Sum(actual(i)) ..........(1.3) From (1.1) & (1.3) , we conclude : P(n) >= 0 ........(1.4) To make the idea of amortization and motivation behind it more concrete , let us consider the example of evaluating the amortized complexity of an algorithm , which displays number of toys available in binary format . To update every digit of the display the algorithm takes d unit of time . Assuming that the number of current toys is N and initial no. of toys is 0, we need to evaluate the amortized complexity of the algorithm used to display the number of toys . There are three popular methods to arrive at the amortized complexity of the operations, namely , (1) aggregate method , (2) accounting method and (3) potential method .
  • 2. Aggregate Method : In the aggregate method ,we determine the UpperBoundOnSumOfActualCosts(N) for the sum of the actual costs of the n operations.The amortized cost is amounted to UpperBoundOnSumOfActualCosts(N) /N . Let N be the number of toys manufactured ; the number of digits used to display the number of toys is n or 'Base-2 logN' . The least significant bit of the display has been changed N times ; the second least significant bit changes once for every 2 toys ; the third least significant bit changes once for every 4 times and so on... So, the aggregate number of digits that have been changed is bounded by N (1+1/2+1/4+...)d or d2N. So, the amortized cost is amounted to 2dN/N = 2d. Accounting Method : To proceed using accounting method , we must first assign an amortized cost and then prove that this assignment satisfies eq - (1.1). Generally we start by assigning an amortized cost obtained by a good guess . Once we have shown this , we obtain an upper bound on the cost of any operation sequence by computing Sum(f(i)*amortized(i)) , where f(i) be the frequency of the operation and amortized(i) the amortized cost of the operation . Suppose , we assign a guessed amortized cost of 2d for each display change . Then the potential function P(n) = Sum(amortized(i)) - Sum(actual(i)) = 2dN - d(1+1/2+1/4+.......) > 0; So, the accounting method proved that the amortized cost of the display can be reduced to 2d.
  • 3. Potential Method : In this approach , we postulate a function for the analysis and use the function to satisfy eq - (1) . Consider the example given in the introduction section . When the first toy is available , we can use the amortized cost 2d to pay for the update , in which d amount is spent and remaining d amount is retained as a credit to the first least significant bit. Following the update of the second toy , the amount spent is 2d*2 in which 3d is spent to update two least significant digits and the second least significant bit now has credit d and the first least significant bit has credit 0 . Proceeding in this way , we can sum up credit on each digit of the display always equal (2d-d)v , where 2d be the amortized cost , d the actual cost and v the value of the digit. So, we should use the potential function P(N) = (2d-d)*Sum(v(i)) , where v(i) = face value of the i-th digit Let q be the number of 1’s at the rightmost places and the j th display and it has been changed from jth to (j+1) th no.So, when the display changes from j th to j+1 th value, where j = 1111011 the potential change incurred P(N) - P(N-1)= d(1-q*1) ; So the amortized cost for the display change = actual cost + P(N) - P(N-1)= (q+1)d + d(1-2*1) = 2d .
  • 4. Conclusion : A worst case analysis ,in which we sum the worst-case time of individual operations, may be unduly pessimistic ; it ignores correlated effect on data structures. On the other hand, average case analysis can be inaccurate , as the probabilistic assumptions needed to carry out the analysis may be false . In such a scenario, amortized analysis , in which we average the running time over per operation , yield an answer that is both realistic and robust .