SlideShare a Scribd company logo
1 of 48
SITE INVESTIGATION
NATURE OF SITE
INVESTIGATION
At any site, the ground conditions need to be assessed to enable safe and
cost-effective design, construction and operation of civil engineering projects.
This will generally include sub-surface ground investigation (GI), which
needs to be focused on the particular project needs and unknowns.
The requirements for GI will be very different for a tunnel compared to the
design of foundations for a high-rise building or for stability assessment of a
cut slope.
There needs to be a preliminary review of the nature of the project, the
constraints for construction and the uncertainties about the engineering
geological conditions at the site.
The British Code of Practice for Site Investigation, BS 5930 (BSI, 1999),
sets out the objectives broadly as follows:
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 2
NATURE OF SITE
INVESTIGATION
1. Suitability: to assess the general suitability of a site and its environs for the
proposed works.
2. Design: to enable an adequate and economic design, including for temporary
works.
3. Construction: To plan the best method of construction and, for some projects, to
identify sources of suitable materials such as concrete aggregate and fill and to
locate sites for disposal of waste.
4. Effect of changes: to consider ground and environmental changes on the works
(e.g. intense rainfall and earthquakes) and to assess the impact of the works on
adjacent properties and on the environment.
5. Choice of site: where appropriate, to identify alternative sites or to allow
optimal planning of the works.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 3
OVERALL SCOPE OF SITE
INVESTIGATION
1) Hazards and constraints during construction and in the
longer term:
2) Previous site use – obstructions, contamination
3) Any history of mining or other underlying or adjacent projects
(e.g. tunnels or pipelines)
4) Sensitive receivers – such as neighbours that might be affected
by noise, dust, vibration and changes in water levels
5) Regulatory restrictions
6) Natural hazards, including flooding, wind, earthquakes,
subsidence and landslides
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 4
OVERALL SCOPE OF SITE
INVESTIGATION
2) Assess and record site characteristics:
 Access constraints for investigation and construction
 Need for traffic control, access for plant and waste disposal
 Access to services
 Site condition survey (partly as a record for any future dispute)
3) Geological profile at site:
 Distribution and nature of soil and rock underlying the site, to
an adequate degree, to allow safe and cost-effective design
 Usually this will require a sub-surface ground investigation
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 5
OVERALL SCOPE OF SITE
INVESTIGATION
4) Physical properties of soil and rock units and design parameters:
 Key parameters:
– mass strength (to avoid failure)
– deformability (to ensure movements are tolerable)
– permeability (flow to and from site, response to rainfall and
loading/unloading)
 Other factors:
– chemical stability (e.g. reactivity in concrete, potential for dissolution)
– potential for piping and collapse
– abrasivity (sometimes a major consideration for construction)
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 6
OVERALL SCOPE OF SITE
INVESTIGATION
5) Changes with time:
 install instruments to check physical nature of the
site – e.g. groundwater response to rainfall
– install instruments to monitor settlement and
effect on adjacent structures during construction
– consider the potential for deterioration and need
for maintenance
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 7
STAGES IN SITE
INVESTIGATION
Stage 1: Desk study at project conception stage:
– Identification of key geological and environmental hazards at optional sites based
on broad desk study and possibly site visits.
– Consider site constraints, engineering considerations and economic factors.
Stage 2: Detailed desk study and reconnaissance survey
– Collect and review all documents relevant to the preferred site, including
topographic and geological maps, aerial and terrestrial photographs and any previous
investigation reports. Review site history including previous building works and
mining. Look for hazards such as landslides.
– Site mapping, possibly with advance contract allowing safe access, vegetation
clearance and trial pits or trenches.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 8
STAGES IN SITE
INVESTIGATION
Stage 3: Preliminary ground investigation linked to basic engineering
design
– Consider use of geophysical techniques to investigate large areas and volumes.
– Preliminary boreholes designed to prove geological model (rather than design parameters).
– Instrumentation as appropriate (e.g. to establish groundwater conditions and seismicity).
Stage 4: Detailed ground investigation
– Further investigation to prepare detailed ground model and allow detailed design.
– In situ and laboratory testing to establish parameters.
– Detailed instrumentation and monitoring.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 9
STAGES IN SITE
INVESTIGATION
Stage 5: Construction
– Review of ground models during construction (including logging of
excavations).
– Testing to confirm design parameters.
– Instrumentation to monitor behaviour and check performance against
predictions.
– Revision to design as necessary.
Stage 6: Maintenance
– Ongoing review – e.g. of settlement, slope distortion, groundwater changes and
other environmental impacts, possibly linked to a risk management system.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 10
EXTENT OF GROUND
INVESTIGATION
Important questions are, how much ground investigation is required and
how should it be done?
There are no hard and fast rules, even though some authors try to provide
guidance on the basis of site area or volume for particular types of operation.
In reality, it depends upon the complexity of the geology at the site, how
much is already known about the area, the nature of the project and cost.
For sites with simple geology, the plan might be for boreholes at 10m to
30m spacing, for discrete structures like a building.
For a linear structure like a road or railway project, the spacing might be
anywhere between 30 and 300m spacing, depending on perceived variability
(Clayton et al., 1995).
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 11
For example,
Figure shows the
route of a planned
tunnel in Hong
Kong, with
potential hazards
identified, together
with a rationale for
their mitigation
and additional GI.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 12
Where
steeply
dipping
geological
structures such
as faults are
anticipated,
inclined
boreholes may
be required.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 13
EXTENT OF GROUND
INVESTIGATIONAs a general rule, at any site, at least one borehole should be put down to prove
ground conditions to a depth far greater than the depth of ground to be stressed
significantly by the works. Generally, for foundations, at least one borehole should be
taken to at least 1.5 times the breadth (B) of the foundation
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 14
EXTENT OF GROUND
INVESTIGATION
Poulos (2005) discusses the consequences of
‘geological imperfections’ on pile design and
performance.
Boreholes are often terminated once
rock has been proved to at least 5m, but
this may be inadequate to prove bedrock
in weathered terrain (Hencher &
McNicholl, 1995).
Whether or not one has reached in situ
bedrock might be established by geological
interpretation of consistent rock fabric or
structure across a site, but elsewhere it may be
more difficult, in which case it is best to take
one or more boreholes even deeper if
important to the design. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 15
PROCEDURES FOR SITE
INVESTIGATION
Desk Study: Sources of information
For any site, it is important to conduct a thorough document search.
This should include topographic and geological maps. Hazard maps are
sometimes available. These include broad seismic zoning maps for countries
linked to seismic design codes. In some countries, there are also local seismic
micro-zoning maps showing locations of active faults and hazards such as
liquefaction susceptibility.
Air Photograph interpretation
Air photographs can be extremely useful for examining sites. Pairs of
overlapping photographs can be examined in 3D using stereographic viewers,
and skilled operators can provide many insights into the geology and
geomorphological conditions. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 16
PLANNING A GROUND
INVESTIGATION
The three verbal equations of Knill (1976) are.
1.The first part is to consider geological factors: material and
mass strengths and other properties.
2.The second is to assess the influence of environmental factors
such as in situ stress, water and earthquakes.
3.The final consideration is how these factors affect, and are
affected by the construction works.
A very similar process has been proposed for addressing risk by
Pöschl & Kleberger (2004), particularly for tunnels.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 17
PLANNING A GROUND
INVESTIGATION
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 18
MATERIAL SCALE
The material scale is that of the intact soil and rock making up the site.
It is also the scale of laboratory testing, which is usually the source of engineering parameters
for design.
Hazards might include adverse chemical attack on foundations or ground anchors,
liquefaction during an earthquakeor swelling or low shear strength due to the
presence of smectite clays.
Inherent site hazards associated with geology include harmful minerals such as asbestos.
Gas hazards are especially important considerations for tunnelling and mining but are also an
issue for completed structures, as illustrated by the Abbeystead disaster of 1984 when methane
that migrated from coal-bearing strata accumulated and exploded killing 16 people (Health and
Safety Executive, 1985). These are all material-scale factors linked to the geological nature of
the rocks at a site.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 19
EQUATION 1: GEOLOGY
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 20
MASS SCALE
One of the main geological hazards to engineering projects at the mass
scale is faults.
Faults can be associated with zones of fractured and weathered material, high permeability and
earthquakes.
Alternatively, faults can be tight, cemented and actually act as barriers to flow, as natural dams
rather than zones of high permeability.
Faults should always be looked for and their influence considered.
There are many cases of unwary constructers building on or across faults, with severe
consequences, sometimes leading to delays to projects or a need for redesign.
Consequence is sometimes difficult to predict but should be considered and investigated.
Other examples of mass factors that would significantly affect projects include boulders in
otherwise weak soil, which might preclude the use of driven piles or would comprise a hazard on a
steep slope.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 21
MASS SCALE
Mass-scale factors include the distribution of different materials in different
weathering zones or structural regimes, as successive strata or as intrusions.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 22
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 23
EQUATION 3: CONSTRUCTION
RELATED FACTORS
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 24
GEOPHYSICAL METHODS
Self study
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 26
SUBSURFACE EXPLORATION
The scale of the mapping will depend on the engineering
requirement, the complexity of the geology, and the staff and time
available.
Rock and soil types should be mapped according to their
lithology and, if possible, presumed physical behaviour, that is, in
terms of their engineering classification, rather than age.
Geomorphological conditions, hydrogeological conditions,
landslips, subsidences, borehole and field-test information all can
be recorded on geotechnical maps.
Particular attention should be given to the nature of the
superficial deposits and, where present, made-over ground.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 27
SUBSURFACE EXPLORATION
There are no given rules regarding the location of boreholes or drillholes, or the depth
to which they should be sunk.
This depends upon the geological conditions and the type of project concerned.
The information provided by the desk study, the preliminary reconnaissance and
from any trial trenches should provide a basis for the initial planning and layout of
the borehole or drillhole programme.
Holes should be located so as to detect the geological sequence and structure.
Obviously, the more complex this is, the greater the number of holes needed.
In some instances, it may be as well to start with a widely spaced network of holes.
As information is obtained, further holes can be put down if and where necessary.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 28
SUBSURFACE EXPLORATION
The results from a borehole or drillhole should be documented on a log.
Apart from the basic information such as number, location, elevation, date, client,
contractor and engineer responsible, the fundamental requirement of a borehole log is to
show how the sequence of strata changes with depth.
Individual soil or rock types are presented in symbolic form on a log.
The material recovered must be described adequately, and in the case of rocks
frequently include an assessment of the degree of weathering, fracture index and relative
strength.
The type of boring or drilling equipment should be recorded, the rate of progress made
being a significant factor.
The water level in the hole and any water loss, when it is used as a flush during rotary
drilling, should be noted, as these reflect the mass permeability of the ground.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 29
SUBSURFACE EXPLORATION
The simplest method whereby data relating to
subsurface conditions in soils can be obtained is by hand
augering.
Soil samples that are obtained by augering are badly
disturbed and invariably some amount of mixing of soil
types occurs.
Critical changes in ground conditions therefore are
unlikely to be located accurately. Even in very soft soils it
may be very difficult to penetrate more than 7 m with
hand augers.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 30
SUBSURFACE EXPLORATION
Basic soil sampling kit animation
Hand augers for heterogeneous soils
Horizontal Directional Drilling _ Boring (HDD)- How the Drill Bit is Steered -
YouTube
Rotary drilling, percussion drilling, cable tool drilling, coredrilling, diamond bits,
casing will not be dealt in here.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 31
CORE LOGGING
Poor or inappropriate core logging can lead to major civil engineering
claims.
Accordingly, accurate core logging is one of the most important activities
for the engineering geologist.
Cores taken as part of a site investigation for an engineering project should
be logged by an engineering geologist rather than a geologist for the style,
content and emphasis of the descriptions will depend on the recognition of
the importance of the geological factors revealed in the cores to the particular
engineering project.
If the logging of a specific geology feature, such as structural geology,
fossil content, etc., is required, a geologist spe cialised in the required feature
should rather do this additionally.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 32
BASIC REQUIREMENTS OF GOOD
CORE LOGGING
The contractor and consultant must ensure that the cores
are placed in good, well-labelled core boxes and are
stored so that their condition as recovered from the bore-
hole is maintained.
They should not be allowed to dry out, be eroded by
rain, frozen, etc.
A well-lit large table in a clean, dry, covered store
should be provided as a logging area.
Help should be available to move core boxes.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 33
THE PROCESS OF CORE
LOGGINGIdeally, all the cores should be logged in one exercise and the logger must
be fully aware of and understand the nature of the engineering work so that
the log gives the information necessary for the design of that work.
Cores may be logged as they come out of the borehole for their description
may influence the further development of the investigation but this
provisional log should not be the final log.
 For the final log the logger must look at all the soils and rocks and decide
provisionally what they should be called and in what detail they should be
described.
A published system of description should be used and its selection justified.
The way in which the cores are described will depend upon the geology,
the engineering work, and the nature of the problem that the geology poses
for that work.
Photos of the core boxes against a scale should be made for later reference.R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 34
THE PROCESS OF CORE
LOGGINGThe cores should be sorted out so that they fit
together as well as possible to allow Total Core
Recovery (TCR) and, if required, Solid Core
Recovery (SCR) and Rock Quality
Designation (RQD) to be measured.
TCR is the length of core recovered divided
by the length of hole drilled (the core run)
expressed as a percentage.
SCR is the total length of solid core cylinders as a
percentage of the core run.
Care has to be taken in defining what is meant by
‘solid’ (Norbury et al. 1986).
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 35
THE PROCESS OF CORE
LOGGINGRQD is the total length of core sticks longer than 4 inches (now commonly converted to
100 mm) expressed as a percentage of the core run.
According to Deere (1968) “ ‘The Rock Quality Designation’ (RQD) is based on a
modified core recovery procedure which, in turn, is based indirectly on the number of
fractures and the amount of softening or alteration in the rock mass as observed in the
rock cores in a borehole. ”
Fractures induced by handling or the drilling process should not be counted (the pieces
broken by such fractures should be fitted together and their total length measured) and the
pieces counted should be ‘hard and sound’.
If all the sticks of core measured are less than 100 mm long, RQD is zero and if there
are no breaks in the core RQD is 100%.
This raises the possibility that if all sticks were 99 mm long, RQD would be 0% and if
all were 101 mm long RQD would be 100%.
Clearly measuring mechanical discontinuity spacing against a fixed baseline has some
disadvantages. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 36
THE PROCESS OF CORE
LOGGINGSome rock materials are composed of thinly interlaminated sandy and clayey bands.
They may come out of the core barrel as solid sticks of rock but on drying out separate
into thin discs, splitting along the clayey layers.
RQD measured on the dried out cores would be very much lower than on those just
recovered from the borehole.
The logger is then faced with the difficult choice between including or ignoring the
drying-out breaks.
Inclusion gives a quality assessment of the rock material; exclusion gives an RQD
related only to genetically, tectonically, or geomorphologically induced discontinuities.
Such discing may also be a consequence of stress relief.
Whether or not included in RQD measurements such dicing would merit description and
discussion in the report.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 37
RECORDING
The logging process falls mostly into two parts; first describing the materials and second,
describing the discontinuities.
It is often a good idea to do the discontinuity measurements (stick length, joint and
bedding dip etc.) first.
It is better to measure the depth and dip of every mechanical discontinuity so that
thereafter any calculations (RQD, frequency etc.) can be made.
If using a rock mass classification system somewhere in the project remember to gain the
data to fill in the ratings.
This may involve noting joint roughness, infilling etc., and also means that the rock mass
classification system must be chosen before beginning logging.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 38
RECORDING
Features in the cores resulting from drilling, have to be identified.
Thus, ends of core runs tend to be more broken while core springs may produce scratch
marks simulating bedding.
These should be noted on the record. Because the core spring is situated above the cutting
face of the drilling bit extraction of the core may leave a core stub at the bottom of the
borehole.
If this is recovered in the next run then the core recovery for that run could exceed 100%.
If a stub is left at the bottom of the hole and the next core run completely fills the core
barrel then cores may be crushed.
If samples are extracted then something should be put in their place (ideally a block of
wood cut to length and labelled) and noted.
Core boxes should have a logging record pinned to the inside of the lid on which t he
logger notes who and when the cores were logged and also records any samples taken.R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 39
RECORDING
In the initial stages of logging, errors of the driller in placing the cores in the box may be
encountered.
It is useful to be familiar with top and bottom criteria to identify cores that may have
been put in upside down.
Before logging rock it is useful to wash the cores and look at them wet, for wet cores
show more than dry ones.
In soils a little drying often helps reveal delicate sedimentary structures such as
lamination.
Cores may have to be broken to determine the rock type. If this is done note the locations
of breaks made.
If possible, at the end of the logging of a number of boreholes, all logs should be
examined again to check consistency of description.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 40
SAMPLING IN SOILS
As far as soils are concerned, samples may be divided into two types,
disturbed and undisturbed.
In a disturbed sample, the material must be representative of the mass from
which it has been taken. Any type of soil sample should contain the same
ingredients as the mass from which it is extracted and in proper proportion,
including the moisture content.
Disturbed samples can be obtained by hand, by auger or from the shell of a
boring rig. Samples of fine soils should be approximately 0.5 kg in weight.
The samples are sealed in jars.
A larger sample is necessary if the particle size distribution of coarse soil is
required, and this may be retained in a tough plastic sack. Care must be
exercised when obtaining such samples to avoid loss of fines.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 41
SAMPLING IN SOILS
An undisturbed sample can be regarded as one that is removed from its
natural condition without disturbing its structure, density, porosity,
moisture content and stress condition.
These samples are taken primarily for all shear and consolidation tests,
which generally are essential for the design and analysis of foundations.
Although it must be admitted that no sample is ever totally undisturbed,
every attempt must be made to preserve the original condition of such
samples.
Unfortunately, mechanical disturbances produced when a sampler is
driven into the ground distort the soil structure.
Furthermore, a change of stress condition occurs when a borehole is
excavated. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 42
SAMPLING IN SOILS
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 43
IN-SITU TESTING OF SOIL
There are two categories of penetrometer tests, the dynamic and the static. Both
methods measure the resistance to penetration of a conical point offered by the soil at
any particular depth.
Penetration of the cone creates a complex shear failure and thus provides an indirect
measure of the in situ shear strength of the soil.
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 44
IN-SITU TESTING OF SOIL
The most widely used dynamic method is the standard
penetration test.
The SPT is probably the most commonly used in situ test,
whereby the number of blows to hammer a sample tube into
the ground is recorded.
The split spoon sampler used for the SPT is a steel tube with
a tapered cutting shoe.
It is lowered down the borehole, attached to connecting
rods, and then driven into the ground by a standard weight,
which drops a standard height, as illustrated in Figure.
The number of blows for each penetration of 75mm is
recorded; blows for the first 150mm are recorded but
essentially ignored (considered disturbed); the blows for the
final 300mm are added together as the N-value.
Standard Penetration Test (SPT)
Demonstration – YouTube
Standard-Penetration-Test, Demo –
YouTube
Geoprobe® 7822DT Geotechnical
Auto Drop Hammer Collecting Split
Spoon Samples - YouTube
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 45
IN-SITU TESTING OF SOIL
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 46
IN-SITU TESTING OF SOIL
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 47
IN-SITU TESTING OF SOIL
The static cone penetrometer is a conical tool (like an SPT)
that is pushed rather than driven into the ground, usually from
a heavy lorry.
The end force on the cone tip, and drag on the sides of the
tool, are measured independently and can be interpreted in
terms of strength and deformability.
Clay, being cohesive, grips the side proportionally more
than sand or gravel, so the ratio between end resistance and
the side friction can be used to interpret the type of soil as
well as strength.
Cone Penetrometer Testing –
YouTube
Cone penetration test movie -
YouTube
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 48
IN-SITU TESTING OF SOIL
R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 49

More Related Content

What's hot

Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing Pirpasha Ujede
 
SOIL EXPLORATION
SOIL EXPLORATIONSOIL EXPLORATION
SOIL EXPLORATIONserinsara
 
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Make Mannan
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadampradip dangar
 
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702Dr. BASWESHWAR JIRWANKAR
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Muhammad Irfan
 
Geotechnical Engineering-I [Lec #29: Soil Exploration - II]
Geotechnical Engineering-I [Lec #29: Soil Exploration - II]Geotechnical Engineering-I [Lec #29: Soil Exploration - II]
Geotechnical Engineering-I [Lec #29: Soil Exploration - II]Muhammad Irfan
 
Geotechnical Engineering-I [Lec #28: Soil Exploration]
Geotechnical Engineering-I [Lec #28: Soil Exploration]Geotechnical Engineering-I [Lec #28: Soil Exploration]
Geotechnical Engineering-I [Lec #28: Soil Exploration]Muhammad Irfan
 
Trial pit n borehole
Trial pit n boreholeTrial pit n borehole
Trial pit n boreholeFiQahh AmiNn
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rockkamariya keyur
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnellingProf. A.Balasubramanian
 

What's hot (20)

Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing
 
Soil penetration tests
Soil penetration testsSoil penetration tests
Soil penetration tests
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
 
SOIL EXPLORATION
SOIL EXPLORATIONSOIL EXPLORATION
SOIL EXPLORATION
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
Rock reinforcement and rock support
Rock reinforcement and rock supportRock reinforcement and rock support
Rock reinforcement and rock support
 
CBR Test
CBR TestCBR Test
CBR Test
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
 
Geotechnical investigation
Geotechnical investigationGeotechnical investigation
Geotechnical investigation
 
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]
 
Geotechnical Engineering-I [Lec #29: Soil Exploration - II]
Geotechnical Engineering-I [Lec #29: Soil Exploration - II]Geotechnical Engineering-I [Lec #29: Soil Exploration - II]
Geotechnical Engineering-I [Lec #29: Soil Exploration - II]
 
Geotechnical Engineering-I [Lec #28: Soil Exploration]
Geotechnical Engineering-I [Lec #28: Soil Exploration]Geotechnical Engineering-I [Lec #28: Soil Exploration]
Geotechnical Engineering-I [Lec #28: Soil Exploration]
 
Trial pit n borehole
Trial pit n boreholeTrial pit n borehole
Trial pit n borehole
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnelling
 
Grouting
GroutingGrouting
Grouting
 

Similar to 6 site investigation

INTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxINTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxCarolTumaneng
 
Geotechnical studies_EG-Projects_17-01_2022.pptx
Geotechnical studies_EG-Projects_17-01_2022.pptxGeotechnical studies_EG-Projects_17-01_2022.pptx
Geotechnical studies_EG-Projects_17-01_2022.pptxKumarShubham771183
 
Introduction to Site Investigation Methods
Introduction to Site Investigation MethodsIntroduction to Site Investigation Methods
Introduction to Site Investigation MethodsMohdBilal430488
 
The role of site investigation
The role of site investigationThe role of site investigation
The role of site investigationAngelo Indelicato
 
Module- 3 Subsurface Investigation.pptx
Module- 3 Subsurface Investigation.pptxModule- 3 Subsurface Investigation.pptx
Module- 3 Subsurface Investigation.pptxSilasChaudhari
 
Soil exploration lecture.
Soil exploration lecture.Soil exploration lecture.
Soil exploration lecture.Damii Abire
 
F0373040048
F0373040048F0373040048
F0373040048theijes
 
Soil investigation by AURANGZEB
Soil investigation by AURANGZEBSoil investigation by AURANGZEB
Soil investigation by AURANGZEBAURANGZEB442
 
THE EFFECT OF GEOTECHNICAL PROPERTIES ON THE BEARING CAPACITY OF SELECTED SOI...
THE EFFECT OF GEOTECHNICAL PROPERTIES ON THE BEARING CAPACITY OF SELECTED SOI...THE EFFECT OF GEOTECHNICAL PROPERTIES ON THE BEARING CAPACITY OF SELECTED SOI...
THE EFFECT OF GEOTECHNICAL PROPERTIES ON THE BEARING CAPACITY OF SELECTED SOI...IAEME Publication
 
CHAP - 1 SOIL INVESTIGATION.ppt civil engineering
CHAP - 1 SOIL INVESTIGATION.ppt civil engineeringCHAP - 1 SOIL INVESTIGATION.ppt civil engineering
CHAP - 1 SOIL INVESTIGATION.ppt civil engineeringteseraaddis1
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel ProjectsKeith Kong
 
Engineering Site investigation
 Engineering Site investigation Engineering Site investigation
Engineering Site investigationVasu Goel
 
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...Christian Olele
 
1892 soil investigation for foundations
1892 soil investigation for foundations1892 soil investigation for foundations
1892 soil investigation for foundationsChandra Mouli
 
Site subsurface Investigation
Site subsurface InvestigationSite subsurface Investigation
Site subsurface InvestigationAkram Suleiman
 
Soil exploration by abhishek sharma
Soil exploration by abhishek sharmaSoil exploration by abhishek sharma
Soil exploration by abhishek sharmaABHISHEK SHARMA
 

Similar to 6 site investigation (20)

INTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxINTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptx
 
Unit1 hbn
Unit1 hbnUnit1 hbn
Unit1 hbn
 
Geotechnical studies_EG-Projects_17-01_2022.pptx
Geotechnical studies_EG-Projects_17-01_2022.pptxGeotechnical studies_EG-Projects_17-01_2022.pptx
Geotechnical studies_EG-Projects_17-01_2022.pptx
 
Introduction to Site Investigation Methods
Introduction to Site Investigation MethodsIntroduction to Site Investigation Methods
Introduction to Site Investigation Methods
 
The role of site investigation
The role of site investigationThe role of site investigation
The role of site investigation
 
Module- 3 Subsurface Investigation.pptx
Module- 3 Subsurface Investigation.pptxModule- 3 Subsurface Investigation.pptx
Module- 3 Subsurface Investigation.pptx
 
Soil exploration lecture.
Soil exploration lecture.Soil exploration lecture.
Soil exploration lecture.
 
F0373040048
F0373040048F0373040048
F0373040048
 
Soil investigation by AURANGZEB
Soil investigation by AURANGZEBSoil investigation by AURANGZEB
Soil investigation by AURANGZEB
 
lecture2 site investigation
lecture2   site investigationlecture2   site investigation
lecture2 site investigation
 
THE EFFECT OF GEOTECHNICAL PROPERTIES ON THE BEARING CAPACITY OF SELECTED SOI...
THE EFFECT OF GEOTECHNICAL PROPERTIES ON THE BEARING CAPACITY OF SELECTED SOI...THE EFFECT OF GEOTECHNICAL PROPERTIES ON THE BEARING CAPACITY OF SELECTED SOI...
THE EFFECT OF GEOTECHNICAL PROPERTIES ON THE BEARING CAPACITY OF SELECTED SOI...
 
CHAP - 1 SOIL INVESTIGATION.ppt civil engineering
CHAP - 1 SOIL INVESTIGATION.ppt civil engineeringCHAP - 1 SOIL INVESTIGATION.ppt civil engineering
CHAP - 1 SOIL INVESTIGATION.ppt civil engineering
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel Projects
 
Geological Site Investigation Methods
Geological Site Investigation MethodsGeological Site Investigation Methods
Geological Site Investigation Methods
 
Engineering Site investigation
 Engineering Site investigation Engineering Site investigation
Engineering Site investigation
 
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
 
1892 soil investigation for foundations
1892 soil investigation for foundations1892 soil investigation for foundations
1892 soil investigation for foundations
 
Site subsurface Investigation
Site subsurface InvestigationSite subsurface Investigation
Site subsurface Investigation
 
Soil exploration by abhishek sharma
Soil exploration by abhishek sharmaSoil exploration by abhishek sharma
Soil exploration by abhishek sharma
 
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
 

More from Raghav Gadgil

7 slopes and slope stability
7 slopes and slope stability7 slopes and slope stability
7 slopes and slope stabilityRaghav Gadgil
 
3 geological materials for construction
3 geological materials for construction3 geological materials for construction
3 geological materials for constructionRaghav Gadgil
 
4 foundation geology
4 foundation geology4 foundation geology
4 foundation geologyRaghav Gadgil
 
Ch 19 continental alkaline lecture
Ch 19 continental alkaline lectureCh 19 continental alkaline lecture
Ch 19 continental alkaline lectureRaghav Gadgil
 
Ch 11 diversification
Ch 11 diversificationCh 11 diversification
Ch 11 diversificationRaghav Gadgil
 
Ch 10 magma generation
Ch 10 magma generationCh 10 magma generation
Ch 10 magma generationRaghav Gadgil
 
Ch 03 igneous textures
Ch 03 igneous texturesCh 03 igneous textures
Ch 03 igneous texturesRaghav Gadgil
 
Ch 04 field relationships
Ch 04 field relationshipsCh 04 field relationships
Ch 04 field relationshipsRaghav Gadgil
 
Ch 02 igneous classification
Ch 02 igneous classificationCh 02 igneous classification
Ch 02 igneous classificationRaghav Gadgil
 

More from Raghav Gadgil (13)

7 slopes and slope stability
7 slopes and slope stability7 slopes and slope stability
7 slopes and slope stability
 
3 geological materials for construction
3 geological materials for construction3 geological materials for construction
3 geological materials for construction
 
4 foundation geology
4 foundation geology4 foundation geology
4 foundation geology
 
5 rock properties
5 rock properties5 rock properties
5 rock properties
 
2 tunnels
2 tunnels2 tunnels
2 tunnels
 
1 dams
1 dams1 dams
1 dams
 
Ch 19 continental alkaline lecture
Ch 19 continental alkaline lectureCh 19 continental alkaline lecture
Ch 19 continental alkaline lecture
 
Ch 11 diversification
Ch 11 diversificationCh 11 diversification
Ch 11 diversification
 
Ch 10 magma generation
Ch 10 magma generationCh 10 magma generation
Ch 10 magma generation
 
Ch 03 igneous textures
Ch 03 igneous texturesCh 03 igneous textures
Ch 03 igneous textures
 
Ch 04 field relationships
Ch 04 field relationshipsCh 04 field relationships
Ch 04 field relationships
 
Ch 02 igneous classification
Ch 02 igneous classificationCh 02 igneous classification
Ch 02 igneous classification
 
Ch 01 intro
Ch 01 introCh 01 intro
Ch 01 intro
 

Recently uploaded

Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 

Recently uploaded (20)

Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 

6 site investigation

  • 2. NATURE OF SITE INVESTIGATION At any site, the ground conditions need to be assessed to enable safe and cost-effective design, construction and operation of civil engineering projects. This will generally include sub-surface ground investigation (GI), which needs to be focused on the particular project needs and unknowns. The requirements for GI will be very different for a tunnel compared to the design of foundations for a high-rise building or for stability assessment of a cut slope. There needs to be a preliminary review of the nature of the project, the constraints for construction and the uncertainties about the engineering geological conditions at the site. The British Code of Practice for Site Investigation, BS 5930 (BSI, 1999), sets out the objectives broadly as follows: R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 2
  • 3. NATURE OF SITE INVESTIGATION 1. Suitability: to assess the general suitability of a site and its environs for the proposed works. 2. Design: to enable an adequate and economic design, including for temporary works. 3. Construction: To plan the best method of construction and, for some projects, to identify sources of suitable materials such as concrete aggregate and fill and to locate sites for disposal of waste. 4. Effect of changes: to consider ground and environmental changes on the works (e.g. intense rainfall and earthquakes) and to assess the impact of the works on adjacent properties and on the environment. 5. Choice of site: where appropriate, to identify alternative sites or to allow optimal planning of the works. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 3
  • 4. OVERALL SCOPE OF SITE INVESTIGATION 1) Hazards and constraints during construction and in the longer term: 2) Previous site use – obstructions, contamination 3) Any history of mining or other underlying or adjacent projects (e.g. tunnels or pipelines) 4) Sensitive receivers – such as neighbours that might be affected by noise, dust, vibration and changes in water levels 5) Regulatory restrictions 6) Natural hazards, including flooding, wind, earthquakes, subsidence and landslides R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 4
  • 5. OVERALL SCOPE OF SITE INVESTIGATION 2) Assess and record site characteristics:  Access constraints for investigation and construction  Need for traffic control, access for plant and waste disposal  Access to services  Site condition survey (partly as a record for any future dispute) 3) Geological profile at site:  Distribution and nature of soil and rock underlying the site, to an adequate degree, to allow safe and cost-effective design  Usually this will require a sub-surface ground investigation R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 5
  • 6. OVERALL SCOPE OF SITE INVESTIGATION 4) Physical properties of soil and rock units and design parameters:  Key parameters: – mass strength (to avoid failure) – deformability (to ensure movements are tolerable) – permeability (flow to and from site, response to rainfall and loading/unloading)  Other factors: – chemical stability (e.g. reactivity in concrete, potential for dissolution) – potential for piping and collapse – abrasivity (sometimes a major consideration for construction) R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 6
  • 7. OVERALL SCOPE OF SITE INVESTIGATION 5) Changes with time:  install instruments to check physical nature of the site – e.g. groundwater response to rainfall – install instruments to monitor settlement and effect on adjacent structures during construction – consider the potential for deterioration and need for maintenance R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 7
  • 8. STAGES IN SITE INVESTIGATION Stage 1: Desk study at project conception stage: – Identification of key geological and environmental hazards at optional sites based on broad desk study and possibly site visits. – Consider site constraints, engineering considerations and economic factors. Stage 2: Detailed desk study and reconnaissance survey – Collect and review all documents relevant to the preferred site, including topographic and geological maps, aerial and terrestrial photographs and any previous investigation reports. Review site history including previous building works and mining. Look for hazards such as landslides. – Site mapping, possibly with advance contract allowing safe access, vegetation clearance and trial pits or trenches. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 8
  • 9. STAGES IN SITE INVESTIGATION Stage 3: Preliminary ground investigation linked to basic engineering design – Consider use of geophysical techniques to investigate large areas and volumes. – Preliminary boreholes designed to prove geological model (rather than design parameters). – Instrumentation as appropriate (e.g. to establish groundwater conditions and seismicity). Stage 4: Detailed ground investigation – Further investigation to prepare detailed ground model and allow detailed design. – In situ and laboratory testing to establish parameters. – Detailed instrumentation and monitoring. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 9
  • 10. STAGES IN SITE INVESTIGATION Stage 5: Construction – Review of ground models during construction (including logging of excavations). – Testing to confirm design parameters. – Instrumentation to monitor behaviour and check performance against predictions. – Revision to design as necessary. Stage 6: Maintenance – Ongoing review – e.g. of settlement, slope distortion, groundwater changes and other environmental impacts, possibly linked to a risk management system. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 10
  • 11. EXTENT OF GROUND INVESTIGATION Important questions are, how much ground investigation is required and how should it be done? There are no hard and fast rules, even though some authors try to provide guidance on the basis of site area or volume for particular types of operation. In reality, it depends upon the complexity of the geology at the site, how much is already known about the area, the nature of the project and cost. For sites with simple geology, the plan might be for boreholes at 10m to 30m spacing, for discrete structures like a building. For a linear structure like a road or railway project, the spacing might be anywhere between 30 and 300m spacing, depending on perceived variability (Clayton et al., 1995). R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 11
  • 12. For example, Figure shows the route of a planned tunnel in Hong Kong, with potential hazards identified, together with a rationale for their mitigation and additional GI. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 12
  • 13. Where steeply dipping geological structures such as faults are anticipated, inclined boreholes may be required. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 13
  • 14. EXTENT OF GROUND INVESTIGATIONAs a general rule, at any site, at least one borehole should be put down to prove ground conditions to a depth far greater than the depth of ground to be stressed significantly by the works. Generally, for foundations, at least one borehole should be taken to at least 1.5 times the breadth (B) of the foundation R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 14
  • 15. EXTENT OF GROUND INVESTIGATION Poulos (2005) discusses the consequences of ‘geological imperfections’ on pile design and performance. Boreholes are often terminated once rock has been proved to at least 5m, but this may be inadequate to prove bedrock in weathered terrain (Hencher & McNicholl, 1995). Whether or not one has reached in situ bedrock might be established by geological interpretation of consistent rock fabric or structure across a site, but elsewhere it may be more difficult, in which case it is best to take one or more boreholes even deeper if important to the design. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 15
  • 16. PROCEDURES FOR SITE INVESTIGATION Desk Study: Sources of information For any site, it is important to conduct a thorough document search. This should include topographic and geological maps. Hazard maps are sometimes available. These include broad seismic zoning maps for countries linked to seismic design codes. In some countries, there are also local seismic micro-zoning maps showing locations of active faults and hazards such as liquefaction susceptibility. Air Photograph interpretation Air photographs can be extremely useful for examining sites. Pairs of overlapping photographs can be examined in 3D using stereographic viewers, and skilled operators can provide many insights into the geology and geomorphological conditions. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 16
  • 17. PLANNING A GROUND INVESTIGATION The three verbal equations of Knill (1976) are. 1.The first part is to consider geological factors: material and mass strengths and other properties. 2.The second is to assess the influence of environmental factors such as in situ stress, water and earthquakes. 3.The final consideration is how these factors affect, and are affected by the construction works. A very similar process has been proposed for addressing risk by Pöschl & Kleberger (2004), particularly for tunnels. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 17
  • 18. PLANNING A GROUND INVESTIGATION R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 18
  • 19. MATERIAL SCALE The material scale is that of the intact soil and rock making up the site. It is also the scale of laboratory testing, which is usually the source of engineering parameters for design. Hazards might include adverse chemical attack on foundations or ground anchors, liquefaction during an earthquakeor swelling or low shear strength due to the presence of smectite clays. Inherent site hazards associated with geology include harmful minerals such as asbestos. Gas hazards are especially important considerations for tunnelling and mining but are also an issue for completed structures, as illustrated by the Abbeystead disaster of 1984 when methane that migrated from coal-bearing strata accumulated and exploded killing 16 people (Health and Safety Executive, 1985). These are all material-scale factors linked to the geological nature of the rocks at a site. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 19
  • 20. EQUATION 1: GEOLOGY R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 20
  • 21. MASS SCALE One of the main geological hazards to engineering projects at the mass scale is faults. Faults can be associated with zones of fractured and weathered material, high permeability and earthquakes. Alternatively, faults can be tight, cemented and actually act as barriers to flow, as natural dams rather than zones of high permeability. Faults should always be looked for and their influence considered. There are many cases of unwary constructers building on or across faults, with severe consequences, sometimes leading to delays to projects or a need for redesign. Consequence is sometimes difficult to predict but should be considered and investigated. Other examples of mass factors that would significantly affect projects include boulders in otherwise weak soil, which might preclude the use of driven piles or would comprise a hazard on a steep slope. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 21
  • 22. MASS SCALE Mass-scale factors include the distribution of different materials in different weathering zones or structural regimes, as successive strata or as intrusions. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 22
  • 23. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 23
  • 24. EQUATION 3: CONSTRUCTION RELATED FACTORS R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 24
  • 25. GEOPHYSICAL METHODS Self study R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 26
  • 26. SUBSURFACE EXPLORATION The scale of the mapping will depend on the engineering requirement, the complexity of the geology, and the staff and time available. Rock and soil types should be mapped according to their lithology and, if possible, presumed physical behaviour, that is, in terms of their engineering classification, rather than age. Geomorphological conditions, hydrogeological conditions, landslips, subsidences, borehole and field-test information all can be recorded on geotechnical maps. Particular attention should be given to the nature of the superficial deposits and, where present, made-over ground. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 27
  • 27. SUBSURFACE EXPLORATION There are no given rules regarding the location of boreholes or drillholes, or the depth to which they should be sunk. This depends upon the geological conditions and the type of project concerned. The information provided by the desk study, the preliminary reconnaissance and from any trial trenches should provide a basis for the initial planning and layout of the borehole or drillhole programme. Holes should be located so as to detect the geological sequence and structure. Obviously, the more complex this is, the greater the number of holes needed. In some instances, it may be as well to start with a widely spaced network of holes. As information is obtained, further holes can be put down if and where necessary. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 28
  • 28. SUBSURFACE EXPLORATION The results from a borehole or drillhole should be documented on a log. Apart from the basic information such as number, location, elevation, date, client, contractor and engineer responsible, the fundamental requirement of a borehole log is to show how the sequence of strata changes with depth. Individual soil or rock types are presented in symbolic form on a log. The material recovered must be described adequately, and in the case of rocks frequently include an assessment of the degree of weathering, fracture index and relative strength. The type of boring or drilling equipment should be recorded, the rate of progress made being a significant factor. The water level in the hole and any water loss, when it is used as a flush during rotary drilling, should be noted, as these reflect the mass permeability of the ground. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 29
  • 29. SUBSURFACE EXPLORATION The simplest method whereby data relating to subsurface conditions in soils can be obtained is by hand augering. Soil samples that are obtained by augering are badly disturbed and invariably some amount of mixing of soil types occurs. Critical changes in ground conditions therefore are unlikely to be located accurately. Even in very soft soils it may be very difficult to penetrate more than 7 m with hand augers. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 30
  • 30. SUBSURFACE EXPLORATION Basic soil sampling kit animation Hand augers for heterogeneous soils Horizontal Directional Drilling _ Boring (HDD)- How the Drill Bit is Steered - YouTube Rotary drilling, percussion drilling, cable tool drilling, coredrilling, diamond bits, casing will not be dealt in here. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 31
  • 31. CORE LOGGING Poor or inappropriate core logging can lead to major civil engineering claims. Accordingly, accurate core logging is one of the most important activities for the engineering geologist. Cores taken as part of a site investigation for an engineering project should be logged by an engineering geologist rather than a geologist for the style, content and emphasis of the descriptions will depend on the recognition of the importance of the geological factors revealed in the cores to the particular engineering project. If the logging of a specific geology feature, such as structural geology, fossil content, etc., is required, a geologist spe cialised in the required feature should rather do this additionally. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 32
  • 32. BASIC REQUIREMENTS OF GOOD CORE LOGGING The contractor and consultant must ensure that the cores are placed in good, well-labelled core boxes and are stored so that their condition as recovered from the bore- hole is maintained. They should not be allowed to dry out, be eroded by rain, frozen, etc. A well-lit large table in a clean, dry, covered store should be provided as a logging area. Help should be available to move core boxes. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 33
  • 33. THE PROCESS OF CORE LOGGINGIdeally, all the cores should be logged in one exercise and the logger must be fully aware of and understand the nature of the engineering work so that the log gives the information necessary for the design of that work. Cores may be logged as they come out of the borehole for their description may influence the further development of the investigation but this provisional log should not be the final log.  For the final log the logger must look at all the soils and rocks and decide provisionally what they should be called and in what detail they should be described. A published system of description should be used and its selection justified. The way in which the cores are described will depend upon the geology, the engineering work, and the nature of the problem that the geology poses for that work. Photos of the core boxes against a scale should be made for later reference.R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 34
  • 34. THE PROCESS OF CORE LOGGINGThe cores should be sorted out so that they fit together as well as possible to allow Total Core Recovery (TCR) and, if required, Solid Core Recovery (SCR) and Rock Quality Designation (RQD) to be measured. TCR is the length of core recovered divided by the length of hole drilled (the core run) expressed as a percentage. SCR is the total length of solid core cylinders as a percentage of the core run. Care has to be taken in defining what is meant by ‘solid’ (Norbury et al. 1986). R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 35
  • 35. THE PROCESS OF CORE LOGGINGRQD is the total length of core sticks longer than 4 inches (now commonly converted to 100 mm) expressed as a percentage of the core run. According to Deere (1968) “ ‘The Rock Quality Designation’ (RQD) is based on a modified core recovery procedure which, in turn, is based indirectly on the number of fractures and the amount of softening or alteration in the rock mass as observed in the rock cores in a borehole. ” Fractures induced by handling or the drilling process should not be counted (the pieces broken by such fractures should be fitted together and their total length measured) and the pieces counted should be ‘hard and sound’. If all the sticks of core measured are less than 100 mm long, RQD is zero and if there are no breaks in the core RQD is 100%. This raises the possibility that if all sticks were 99 mm long, RQD would be 0% and if all were 101 mm long RQD would be 100%. Clearly measuring mechanical discontinuity spacing against a fixed baseline has some disadvantages. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 36
  • 36. THE PROCESS OF CORE LOGGINGSome rock materials are composed of thinly interlaminated sandy and clayey bands. They may come out of the core barrel as solid sticks of rock but on drying out separate into thin discs, splitting along the clayey layers. RQD measured on the dried out cores would be very much lower than on those just recovered from the borehole. The logger is then faced with the difficult choice between including or ignoring the drying-out breaks. Inclusion gives a quality assessment of the rock material; exclusion gives an RQD related only to genetically, tectonically, or geomorphologically induced discontinuities. Such discing may also be a consequence of stress relief. Whether or not included in RQD measurements such dicing would merit description and discussion in the report. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 37
  • 37. RECORDING The logging process falls mostly into two parts; first describing the materials and second, describing the discontinuities. It is often a good idea to do the discontinuity measurements (stick length, joint and bedding dip etc.) first. It is better to measure the depth and dip of every mechanical discontinuity so that thereafter any calculations (RQD, frequency etc.) can be made. If using a rock mass classification system somewhere in the project remember to gain the data to fill in the ratings. This may involve noting joint roughness, infilling etc., and also means that the rock mass classification system must be chosen before beginning logging. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 38
  • 38. RECORDING Features in the cores resulting from drilling, have to be identified. Thus, ends of core runs tend to be more broken while core springs may produce scratch marks simulating bedding. These should be noted on the record. Because the core spring is situated above the cutting face of the drilling bit extraction of the core may leave a core stub at the bottom of the borehole. If this is recovered in the next run then the core recovery for that run could exceed 100%. If a stub is left at the bottom of the hole and the next core run completely fills the core barrel then cores may be crushed. If samples are extracted then something should be put in their place (ideally a block of wood cut to length and labelled) and noted. Core boxes should have a logging record pinned to the inside of the lid on which t he logger notes who and when the cores were logged and also records any samples taken.R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 39
  • 39. RECORDING In the initial stages of logging, errors of the driller in placing the cores in the box may be encountered. It is useful to be familiar with top and bottom criteria to identify cores that may have been put in upside down. Before logging rock it is useful to wash the cores and look at them wet, for wet cores show more than dry ones. In soils a little drying often helps reveal delicate sedimentary structures such as lamination. Cores may have to be broken to determine the rock type. If this is done note the locations of breaks made. If possible, at the end of the logging of a number of boreholes, all logs should be examined again to check consistency of description. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 40
  • 40. SAMPLING IN SOILS As far as soils are concerned, samples may be divided into two types, disturbed and undisturbed. In a disturbed sample, the material must be representative of the mass from which it has been taken. Any type of soil sample should contain the same ingredients as the mass from which it is extracted and in proper proportion, including the moisture content. Disturbed samples can be obtained by hand, by auger or from the shell of a boring rig. Samples of fine soils should be approximately 0.5 kg in weight. The samples are sealed in jars. A larger sample is necessary if the particle size distribution of coarse soil is required, and this may be retained in a tough plastic sack. Care must be exercised when obtaining such samples to avoid loss of fines. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 41
  • 41. SAMPLING IN SOILS An undisturbed sample can be regarded as one that is removed from its natural condition without disturbing its structure, density, porosity, moisture content and stress condition. These samples are taken primarily for all shear and consolidation tests, which generally are essential for the design and analysis of foundations. Although it must be admitted that no sample is ever totally undisturbed, every attempt must be made to preserve the original condition of such samples. Unfortunately, mechanical disturbances produced when a sampler is driven into the ground distort the soil structure. Furthermore, a change of stress condition occurs when a borehole is excavated. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 42
  • 42. SAMPLING IN SOILS R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 43
  • 43. IN-SITU TESTING OF SOIL There are two categories of penetrometer tests, the dynamic and the static. Both methods measure the resistance to penetration of a conical point offered by the soil at any particular depth. Penetration of the cone creates a complex shear failure and thus provides an indirect measure of the in situ shear strength of the soil. R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 44
  • 44. IN-SITU TESTING OF SOIL The most widely used dynamic method is the standard penetration test. The SPT is probably the most commonly used in situ test, whereby the number of blows to hammer a sample tube into the ground is recorded. The split spoon sampler used for the SPT is a steel tube with a tapered cutting shoe. It is lowered down the borehole, attached to connecting rods, and then driven into the ground by a standard weight, which drops a standard height, as illustrated in Figure. The number of blows for each penetration of 75mm is recorded; blows for the first 150mm are recorded but essentially ignored (considered disturbed); the blows for the final 300mm are added together as the N-value. Standard Penetration Test (SPT) Demonstration – YouTube Standard-Penetration-Test, Demo – YouTube Geoprobe® 7822DT Geotechnical Auto Drop Hammer Collecting Split Spoon Samples - YouTube R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 45
  • 45. IN-SITU TESTING OF SOIL R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 46
  • 46. IN-SITU TESTING OF SOIL R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 47
  • 47. IN-SITU TESTING OF SOIL The static cone penetrometer is a conical tool (like an SPT) that is pushed rather than driven into the ground, usually from a heavy lorry. The end force on the cone tip, and drag on the sides of the tool, are measured independently and can be interpreted in terms of strength and deformability. Clay, being cohesive, grips the side proportionally more than sand or gravel, so the ratio between end resistance and the side friction can be used to interpret the type of soil as well as strength. Cone Penetrometer Testing – YouTube Cone penetration test movie - YouTube R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 48
  • 48. IN-SITU TESTING OF SOIL R. R. GADGIL, DEPT. OF EARTH SCIENCE, GOA UNIVERSITY 49

Editor's Notes

  1. Practical Engineering Geology by Steve Hencher pg115
  2. Practical Engineering Geology by Steve Hencher pg115
  3. Practical Engineering Geology by Steve Hencher pg115
  4. Practical Engineering Geology by Steve Hencher pg115
  5. Practical Engineering Geology by Steve Hencher pg115
  6. Practical Engineering Geology by Steve Hencher pg115
  7. Practical Engineering Geology by Steve Hencher pg115
  8. Practical Engineering Geology by Steve Hencher pg115
  9. Practical Engineering Geology by Steve Hencher pg115
  10. Practical Engineering Geology by Steve Hencher pg115
  11. Practical Engineering Geology by Steve Hencher pg115
  12. Practical Engineering Geology by Steve Hencher pg124
  13. Practical Engineering Geology by Steve Hencher pg124
  14. Practical Engineering Geology by Steve Hencher pg125
  15. Practical Engineering Geology by Steve Hencher pg129
  16. Practical Engineering Geology by Steve Hencher pg129
  17. Practical Engineering Geology by Steve Hencher pg130
  18. Practical Engineering Geology by Steve Hencher pg130
  19. Practical Engineering Geology by Steve Hencher pg131
  20. Practical Engineering Geology by Steve Hencher pg131
  21. Practical Engineering Geology by Steve Hencher pg135
  22. Practical Engineering Geology by Steve Hencher pg135
  23. Practical Engineering Geology by Steve Hencher pg140
  24. Practical Engineering Geology by Steve Hencher pg140
  25. Engineering Geology by Bell pg318
  26. Engineering Geology by Bell pg318
  27. Engineering Geology by Bell pg318
  28. Engineering Geology by Bell pg318
  29. Engineering Geology by Bell pg318
  30. Engineering Geology Principles and Practice pg84
  31. Engineering Geology Principles and Practice pg84
  32. Engineering Geology Principles and Practice pg84
  33. Engineering Geology Principles and Practice pg84
  34. Engineering Geology Principles and Practice pg84
  35. Engineering Geology Principles and Practice pg85
  36. Engineering Geology Principles and Practice pg86
  37. Engineering Geology Principles and Practice pg86-87
  38. Engineering Geology Principles and Practice pg86-87
  39. Engineering Geology by Bell pg318 Red text from Krynine and Judd Engineering Geology pg227
  40. Engineering Geology by Bell pg318 Red text from Krynine and Judd Engineering Geology pg227
  41. Engineering Geology by Bell pg318 Red text from Krynine and Judd Engineering Geology pg227
  42. Engineering Geology by Bell pg334
  43. Practical Engineering Geology by Hencher pg162 The SPT data can be interpreted in terms of shear strength and deformability (Chapter 5) and for making predictions of settlement directly (Chapter 6).
  44. Practical Engineering Geology by Hencher pg162 The SPT data can be interpreted in terms of shear strength and deformability (Chapter 5) and for making predictions of settlement directly (Chapter 6).
  45. Practical Engineering Geology by Hencher pg162 The SPT data can be interpreted in terms of shear strength and deformability (Chapter 5) and for making predictions of settlement directly (Chapter 6).
  46. Practical Engineering Geology by Hencher pg162 The SPT data can be interpreted in terms of shear strength and deformability (Chapter 5) and for making predictions of settlement directly (Chapter 6).
  47. Practical Engineering Geology by Hencher pg162 The SPT data can be interpreted in terms of shear strength and deformability (Chapter 5) and for making predictions of settlement directly (Chapter 6).