Resource Loading the Scheduling Tool Create the “Resource Sheet” Apply the correct resources to activities Load the required resources Viewing resources
Create the Resource Sheet 1. 2. 3. Determine Resource Breakdown Structure Similar to Organizational Breakdown Structure (ie. Org Chart) except different functions may be further defined into skill groups/levels (eg.  Engineer into Junior/Senior/Staff Engineer;  Test Engineer into System Test Engineer/Component Test Engineer) Unique nomenclature assigned Determine resource availability  From Charter and/or “Resource Contracts” (see Kicking off the Team) Rate information derived from HR/cost accounting system Pay rate, overtime rate, overhead rate Typical workday (eg. 7.5h, 8h, 12h) may be entered here or in standard work calendar
Applying Resources to Schedule Using “Resource Work” view Window/Split Right click in bottom pane and select “Resource Work Slower but allows full flexibility to enter resources and rates ,[object Object]
Double click on activity
Choose “Resource Tab”
Resource Application Rules
Activities only; no resources against WBS
All resources required to do an activity should be booked into the same activity ,[object Object]

More Related Content

Viewers also liked

3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization
harwoodr
 
3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating
harwoodr
 
3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing
harwoodr
 
3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan
harwoodr
 
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
harwoodr
 
3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network
harwoodr
 
Brand Reputation & Conversation
Brand Reputation & ConversationBrand Reputation & Conversation
Brand Reputation & Conversation
DuvalGuillaume
 
3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development
harwoodr
 
3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget
harwoodr
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
harwoodr
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
harwoodr
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
harwoodr
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
NASAPMC
 
James.smith
James.smithJames.smith
James.smith
NASAPMC
 
New product development costing. Carles Debart
New product development costing. Carles DebartNew product development costing. Carles Debart
New product development costing. Carles Debart
Carles Debart
 
A.Sanchez_Part1_Planning and Scheduling Construction Projects_The Planning Pr...
A.Sanchez_Part1_Planning and Scheduling Construction Projects_The Planning Pr...A.Sanchez_Part1_Planning and Scheduling Construction Projects_The Planning Pr...
A.Sanchez_Part1_Planning and Scheduling Construction Projects_The Planning Pr...
Alberto Sanchez
 
A.sanchez part1 planning and scheduling construction projects_the planning pr...
A.sanchez part1 planning and scheduling construction projects_the planning pr...A.sanchez part1 planning and scheduling construction projects_the planning pr...
A.sanchez part1 planning and scheduling construction projects_the planning pr...
Alberto Sanchez
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
Sadhanandavel Ramdoss
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Ciprian Rusen
 

Viewers also liked (20)

3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization
 
3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating
 
3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing
 
3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan
 
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
 
3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network
 
Brand Reputation & Conversation
Brand Reputation & ConversationBrand Reputation & Conversation
Brand Reputation & Conversation
 
3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development
 
3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
 
James.smith
James.smithJames.smith
James.smith
 
New product development costing. Carles Debart
New product development costing. Carles DebartNew product development costing. Carles Debart
New product development costing. Carles Debart
 
A.Sanchez_Part1_Planning and Scheduling Construction Projects_The Planning Pr...
A.Sanchez_Part1_Planning and Scheduling Construction Projects_The Planning Pr...A.Sanchez_Part1_Planning and Scheduling Construction Projects_The Planning Pr...
A.Sanchez_Part1_Planning and Scheduling Construction Projects_The Planning Pr...
 
A.sanchez part1 planning and scheduling construction projects_the planning pr...
A.sanchez part1 planning and scheduling construction projects_the planning pr...A.sanchez part1 planning and scheduling construction projects_the planning pr...
A.sanchez part1 planning and scheduling construction projects_the planning pr...
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 

Similar to 3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule

MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docxMS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
rosemarybdodson23141
 
Ms Project
Ms ProjectMs Project
Ms Project
Noman Aftab
 
MProjectTutorial.pdf
MProjectTutorial.pdfMProjectTutorial.pdf
MProjectTutorial.pdf
dhansingh21
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
Santosh Dwivedi
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
Abrianto Nugraha
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - Tutorial
VR M
 
Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.
TURKI , PMP
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
Ronald Oroya
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
Kushal Patel
 
DesignPeopleSystem
DesignPeopleSystemDesignPeopleSystem
DesignPeopleSystem
ahmad bassiouny
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
Jason Koo
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
성철 박
 
Open the Project Libre file with activity durations and predeces.docx
Open the Project Libre file with activity durations and predeces.docxOpen the Project Libre file with activity durations and predeces.docx
Open the Project Libre file with activity durations and predeces.docx
amit657720
 
Lesson 13 primavera.pptx..........................
Lesson 13 primavera.pptx..........................Lesson 13 primavera.pptx..........................
Lesson 13 primavera.pptx..........................
EngrMuhammadJavidNaw
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resoures
Mayank Kothawade
 
EAM
EAMEAM
Yom Institute Presentation project management course
Yom Institute Presentation project management courseYom Institute Presentation project management course
Yom Institute Presentation project management course
Abebaw31
 
Work study
Work studyWork study
MONEY SUPPLY, BANK RESERVES, and FEDERAL RESERVE STIMULUS (Data Se.docx
MONEY SUPPLY, BANK RESERVES, and FEDERAL RESERVE STIMULUS (Data Se.docxMONEY SUPPLY, BANK RESERVES, and FEDERAL RESERVE STIMULUS (Data Se.docx
MONEY SUPPLY, BANK RESERVES, and FEDERAL RESERVE STIMULUS (Data Se.docx
moirarandell
 
EAM Overview
EAM OverviewEAM Overview

Similar to 3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule (20)

MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docxMS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
 
Ms Project
Ms ProjectMs Project
Ms Project
 
MProjectTutorial.pdf
MProjectTutorial.pdfMProjectTutorial.pdf
MProjectTutorial.pdf
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - Tutorial
 
Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
DesignPeopleSystem
DesignPeopleSystemDesignPeopleSystem
DesignPeopleSystem
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
Open the Project Libre file with activity durations and predeces.docx
Open the Project Libre file with activity durations and predeces.docxOpen the Project Libre file with activity durations and predeces.docx
Open the Project Libre file with activity durations and predeces.docx
 
Lesson 13 primavera.pptx..........................
Lesson 13 primavera.pptx..........................Lesson 13 primavera.pptx..........................
Lesson 13 primavera.pptx..........................
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resoures
 
EAM
EAMEAM
EAM
 
Yom Institute Presentation project management course
Yom Institute Presentation project management courseYom Institute Presentation project management course
Yom Institute Presentation project management course
 
Work study
Work studyWork study
Work study
 
MONEY SUPPLY, BANK RESERVES, and FEDERAL RESERVE STIMULUS (Data Se.docx
MONEY SUPPLY, BANK RESERVES, and FEDERAL RESERVE STIMULUS (Data Se.docxMONEY SUPPLY, BANK RESERVES, and FEDERAL RESERVE STIMULUS (Data Se.docx
MONEY SUPPLY, BANK RESERVES, and FEDERAL RESERVE STIMULUS (Data Se.docx
 
EAM Overview
EAM OverviewEAM Overview
EAM Overview
 

Recently uploaded

20240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 202420240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 2024
Matthew Sinclair
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
Alpen-Adria-Universität
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
KAMESHS29
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
James Anderson
 
Large Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial ApplicationsLarge Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial Applications
Rohit Gautam
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
Kari Kakkonen
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 
20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website
Pixlogix Infotech
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
Daiki Mogmet Ito
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
Adtran
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Zilliz
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems S.M.S.A.
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
Neo4j
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
Edge AI and Vision Alliance
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
danishmna97
 

Recently uploaded (20)

20240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 202420240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 2024
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
 
Large Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial ApplicationsLarge Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial Applications
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 
20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
 

3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule

  • 1. Resource Loading the Scheduling Tool Create the “Resource Sheet” Apply the correct resources to activities Load the required resources Viewing resources
  • 2. Create the Resource Sheet 1. 2. 3. Determine Resource Breakdown Structure Similar to Organizational Breakdown Structure (ie. Org Chart) except different functions may be further defined into skill groups/levels (eg. Engineer into Junior/Senior/Staff Engineer; Test Engineer into System Test Engineer/Component Test Engineer) Unique nomenclature assigned Determine resource availability From Charter and/or “Resource Contracts” (see Kicking off the Team) Rate information derived from HR/cost accounting system Pay rate, overtime rate, overhead rate Typical workday (eg. 7.5h, 8h, 12h) may be entered here or in standard work calendar
  • 3.
  • 4. Double click on activity
  • 7. Activities only; no resources against WBS
  • 8.
  • 9. Viewing Activity Resources Task Info Box – check what resources assigned while doing other work “Resource Work” view – most useful for initial entry and systematic review “Resource Name” column – rarely used, for display or transfer to Excel
  • 10. Viewing Project Resources Resource Usage View Task Usage View Resource Graph View
  • 11. WORKED EXAMPLE: Table Construction Project Resource load the schedule for the Table Construction Project using “Table Construction – Sequencing Complete.mpp” Additional Info: See Org Chart, Project Charter and Responsibilities Allocation Matrix on next slide
  • 12. WORKED EXAMPLE: Table Construction Project Project Charter excerpt: “…project will require one full time carpenter, will share a painter currently working on Projects A and B, and will require minimal support (approx 10%) from QA…”