Basic Information for MS Project
 What tasks must be done to meet the objectives?
 What tangible results (deliverables) must be produced
and when?
 How does each task depend on the other tasks?
 How long does each task take?
 Who’s going to do the work?
 What materials are needed in the work?
Installation
 https://products.office.com/en-us/Project/project-pro-for-
office-365
 Register, download, and install the Microsoft Project Pro
for Office 365
Getting Started
 Project should give you the option to open a new blank
project when you open it.
 Or select: File tab -> New -> Blank Project.
 Choose: Project -> Project Information -> Start Date, and
adjust appropriately
After starting Project a blank template will appear.
New Project Screen
Basic Project Information
• From the “Project” menu select “Project Information”
and enter the anticipated project start date.
Default Project Settings
• From the “File” menu select “Options”.
Working Time Settings
• From the “Project” menu select “Change Working Time”.
Enter the major tasks
• Type in the major tasks in the “Task Name” box.
• Each row is a separate task
What tasks must be done to meet the objectives?
 After several have been entered you can group them with a
summary task
 Drag over tasks (row numbers) of a group and under the Tasks tab,
select Insert-> Summary.
 Name summary task, click drop-down triangle arrow to show or hide
What tangible results (deliverables) must be
produced and when?
 Just like inserting a Summary task, you can insert a
Milestone from the same location (Tasks -> Insert ->
Milestone).
 Milestones take zero time (by definition) and are
appropriate for marking the completion of a deliverable
or phase
 A milestone can be a subtask of a summary (if you want
it to be hide-able) or at the same indent level as the
summary task (if you want it to show)
 Add as many milestones as you want – they don’t cost
any time and are just markers.
How long does each task take?
 In the Gantt View, type in durations for each task
 Can leave question mark for an unsure duration
 Use abbreviations (m) minutes, (h) hours , (d) days, (w)
weeks or (mo) months, or days is default
 Can change defaults under File -> Options
 “Task mode” is “Manually scheduled” by default. Can
turn on “Auto-scheduled.”
 Right-click a column, insert column -> task mode
 In auto-scheduled mode, summary task durations will fill-in
automatically
 Or can be adjusted to show slack, switching it to manual
How does each task depend on the other tasks?
 Select a group of consecutively listed tasks, then hit the
Link (chain icon) under Tasks
 Project now links these tasks so that each one cannot start until
after the previous one finishes
 Or, select one task, Ctrl-Click one that must start after it
finishes, then hit the Link button
 Or, drag from the first to the second in the Gantt Chart
view
 Or, manually type numbers into the predecessors
column, separated by commas
 Click the link between tasks, change the task
dependency
 Or double click the task, change the predecessors
settings
Who’s going to do the work? What materials are
needed in the work?
 Select Resource -> View -> Resource Sheet
 or, View -> Resource views -> Resource Sheet
 or, learn the shortcut button, bottom right
List the names of workers (resources)
Assign resources to the tasks
 Return to Gantt Chart view (under Tasks or View tab)
 or, shortcut, or right click far left and check View bar
 For each task row, click on the cell in Resource Names
column
 Select a resource from the checklist to assign it to the
task
Over allocated Resource
 Jack is involved in both build and test
Basic Project Statistics
 Select Project-> Project Information -> Statistics…
Set Baseline to compare your schedule
 Select Project-> Set Baseline -> Set Baseline …
Tracking your project
 Select View-> Task Views -> Tracking Gantt Chart
 Select View-> Data -> Table -> Tracking
Details of the tasks
Generate Project Reports
More Tips
 Ctrl+Z (undo, repeatedly if necessary) if something
unexpected happens, or close without saving and return
to a saved version.
 Check out templates available online:
 E.g. Go to File -> New -> Select a Template -> Create
 Browse, and get ideas about the wide range of applications
Use MS Project in your project
You can use MS Project to:
 Draw Gantt Chart In the section of project planning.
 Tract your project schedule with Tracking Gantt.
 Summarize your project information with the statistics
and report functions of MS Project
References
Some of the contents are adapted from
 http://users.business.uconn.edu/bday/PMTutorial1.ppt
 https://support.office.com/en-us/article/Project-2013-
videos-and-tutorials-af7d1e17-5fa7-421f-a452-
9bbe2cd7b082
 https://www.youtube.com/watch?v=sPwURRG9_Gs
 https://www.youtube.com/watch?v=ZIrshh-0s3I

More Related Content

Similar to MProjectTutorial.pdf

Devry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project newDevry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project new
uopassignment
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
Santosh Dwivedi
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
Ong-Art Sanpinit
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
Ong-Art Sanpinit
 
Project management software
Project management softwareProject management software
Project management software
Puan Zamri Yaacob
 
CSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxCSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docx
mydrynan
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentation
Khem Singh
 
Copper Training
Copper TrainingCopper Training
Copper Training
Lisa Faulkner
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
Farrukh Raja
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
Khem Singh
 
Project NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxProject NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docx
wkyra78
 
Ms Project
Ms ProjectMs Project
Ms Project
Noman Aftab
 
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docxMS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
rosemarybdodson23141
 
Odoo project management_casestudy
Odoo project management_casestudyOdoo project management_casestudy
Odoo project management_casestudy
Rishi Pujara
 
ms-project-presentation.pptx
ms-project-presentation.pptxms-project-presentation.pptx
ms-project-presentation.pptx
SunilHotkar2
 
dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptx
SunilHotkar2
 
]project-open[ Budget Planning and Tracking
]project-open[ Budget Planning and Tracking]project-open[ Budget Planning and Tracking
]project-open[ Budget Planning and Tracking
Klaus Hofeditz
 
Project Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team MembersProject Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team Members
Toney Sisk
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
Jason Koo
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
성철 박
 

Similar to MProjectTutorial.pdf (20)

Devry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project newDevry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project new
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Project management software
Project management softwareProject management software
Project management software
 
CSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxCSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docx
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentation
 
Copper Training
Copper TrainingCopper Training
Copper Training
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Project NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxProject NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docx
 
Ms Project
Ms ProjectMs Project
Ms Project
 
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docxMS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
 
Odoo project management_casestudy
Odoo project management_casestudyOdoo project management_casestudy
Odoo project management_casestudy
 
ms-project-presentation.pptx
ms-project-presentation.pptxms-project-presentation.pptx
ms-project-presentation.pptx
 
dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptx
 
]project-open[ Budget Planning and Tracking
]project-open[ Budget Planning and Tracking]project-open[ Budget Planning and Tracking
]project-open[ Budget Planning and Tracking
 
Project Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team MembersProject Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team Members
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 

Recently uploaded

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
riddhimaagrawal986
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
IJECEIAES
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 

Recently uploaded (20)

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 

MProjectTutorial.pdf

  • 1. Microsoft Project Tutorial Xiao Li Department of Informatics University of Zurich
  • 2. Basic Information for MS Project  What tasks must be done to meet the objectives?  What tangible results (deliverables) must be produced and when?  How does each task depend on the other tasks?  How long does each task take?  Who’s going to do the work?  What materials are needed in the work?
  • 4. Getting Started  Project should give you the option to open a new blank project when you open it.  Or select: File tab -> New -> Blank Project.  Choose: Project -> Project Information -> Start Date, and adjust appropriately
  • 5. After starting Project a blank template will appear. New Project Screen
  • 6. Basic Project Information • From the “Project” menu select “Project Information” and enter the anticipated project start date.
  • 7. Default Project Settings • From the “File” menu select “Options”.
  • 8. Working Time Settings • From the “Project” menu select “Change Working Time”.
  • 9. Enter the major tasks • Type in the major tasks in the “Task Name” box. • Each row is a separate task
  • 10. What tasks must be done to meet the objectives?  After several have been entered you can group them with a summary task  Drag over tasks (row numbers) of a group and under the Tasks tab, select Insert-> Summary.  Name summary task, click drop-down triangle arrow to show or hide
  • 11. What tangible results (deliverables) must be produced and when?  Just like inserting a Summary task, you can insert a Milestone from the same location (Tasks -> Insert -> Milestone).  Milestones take zero time (by definition) and are appropriate for marking the completion of a deliverable or phase  A milestone can be a subtask of a summary (if you want it to be hide-able) or at the same indent level as the summary task (if you want it to show)  Add as many milestones as you want – they don’t cost any time and are just markers.
  • 12.
  • 13. How long does each task take?  In the Gantt View, type in durations for each task  Can leave question mark for an unsure duration  Use abbreviations (m) minutes, (h) hours , (d) days, (w) weeks or (mo) months, or days is default  Can change defaults under File -> Options  “Task mode” is “Manually scheduled” by default. Can turn on “Auto-scheduled.”  Right-click a column, insert column -> task mode  In auto-scheduled mode, summary task durations will fill-in automatically  Or can be adjusted to show slack, switching it to manual
  • 14. How does each task depend on the other tasks?  Select a group of consecutively listed tasks, then hit the Link (chain icon) under Tasks  Project now links these tasks so that each one cannot start until after the previous one finishes  Or, select one task, Ctrl-Click one that must start after it finishes, then hit the Link button  Or, drag from the first to the second in the Gantt Chart view  Or, manually type numbers into the predecessors column, separated by commas  Click the link between tasks, change the task dependency  Or double click the task, change the predecessors settings
  • 15.
  • 16. Who’s going to do the work? What materials are needed in the work?  Select Resource -> View -> Resource Sheet  or, View -> Resource views -> Resource Sheet  or, learn the shortcut button, bottom right List the names of workers (resources)
  • 17. Assign resources to the tasks  Return to Gantt Chart view (under Tasks or View tab)  or, shortcut, or right click far left and check View bar  For each task row, click on the cell in Resource Names column  Select a resource from the checklist to assign it to the task
  • 18.
  • 19. Over allocated Resource  Jack is involved in both build and test
  • 20. Basic Project Statistics  Select Project-> Project Information -> Statistics…
  • 21. Set Baseline to compare your schedule  Select Project-> Set Baseline -> Set Baseline …
  • 22. Tracking your project  Select View-> Task Views -> Tracking Gantt Chart  Select View-> Data -> Table -> Tracking
  • 23. Details of the tasks
  • 25. More Tips  Ctrl+Z (undo, repeatedly if necessary) if something unexpected happens, or close without saving and return to a saved version.  Check out templates available online:  E.g. Go to File -> New -> Select a Template -> Create  Browse, and get ideas about the wide range of applications
  • 26. Use MS Project in your project You can use MS Project to:  Draw Gantt Chart In the section of project planning.  Tract your project schedule with Tracking Gantt.  Summarize your project information with the statistics and report functions of MS Project
  • 27. References Some of the contents are adapted from  http://users.business.uconn.edu/bday/PMTutorial1.ppt  https://support.office.com/en-us/article/Project-2013- videos-and-tutorials-af7d1e17-5fa7-421f-a452- 9bbe2cd7b082  https://www.youtube.com/watch?v=sPwURRG9_Gs  https://www.youtube.com/watch?v=ZIrshh-0s3I