The Blue Grass Chemical Agent-Destruction Pilot Plant Systems Contractor Update provides the following information in 3 sentences: The Bechtel Parsons Blue Grass project has a strong safety record, is currently staffed by over 1,000 employees (mostly from Kentucky), and has paid over $400 million in local payroll and procured over $100 million from Kentucky companies to date. Construction updates were provided on the Control and Support Building, Munitions Demilitarization Building, Supercritical Water Oxidation Process Building, Hydrolysate Storage Area, and Utility Building, where various trades are working on electrical, structural steel, siding installation, and other activities. Specific equipment for neutralizing energetics,