Prefabricated house assembly is simpler than assembling a puzzle.
The job is to put the home or building components together that been pre-arranged and numbered at the factory.
Prefabricated house assembly is simpler than assembling a puzzle.
The job is to put the home or building components together that been pre-arranged and numbered at the factory.
African Kings Ltd <www.africankings.co.ug> and Ugavilla Development Co. Ltd < www.ugavilla.ug > have partnered to provide affordable housing in Uganda and Sub Sahara Africa using Lightweight Concrete Methodology < www.africankings.co.ug/lightweight-concrete-construction/ > an Industrial Building System which is efficient.
Airport Boulevard Railroad Grade Separation Project presented August 20, 2015, at the ASCE OC Branch Meeting, by John Ashlock, PE from County of Riverside Transportation.
IT IS A PRESENTATION MADE FOR THE INTERNSHIP,WHICH I HAVE ATTENDED,IT HAS INFORMATION ABOUT THE FORMWORK,CONCRETE PREPARATION AND ERECTION OF THE COLUMN
African Kings Ltd <www.africankings.co.ug> and Ugavilla Development Co. Ltd < www.ugavilla.ug > have partnered to provide affordable housing in Uganda and Sub Sahara Africa using Lightweight Concrete Methodology < www.africankings.co.ug/lightweight-concrete-construction/ > an Industrial Building System which is efficient.
Airport Boulevard Railroad Grade Separation Project presented August 20, 2015, at the ASCE OC Branch Meeting, by John Ashlock, PE from County of Riverside Transportation.
IT IS A PRESENTATION MADE FOR THE INTERNSHIP,WHICH I HAVE ATTENDED,IT HAS INFORMATION ABOUT THE FORMWORK,CONCRETE PREPARATION AND ERECTION OF THE COLUMN
Cement and concrete are used interchangeably but there are technical distinctions and the meaning of cement has changed since the mid-nineteenth century when ferrocement originated. Ferro- means iron although metal commonly used in ferro-cement is the iron alloy steel. Cement in the nineteenth century and earlier meant mortar[2] or broken stone or tile mixed with lime and water to form a strong mortar.[3] Today cement usually means Portland cement,[4] Mortar is a paste of a binder (usually Portland cement), sand and water; and concrete is a fluid mixture of Portland cement, sand, water and crushed stone aggregate which is poured into formwork (shuttering). Ferro-concrete is the original name of reinforced concrete (armored concrete) known at least since the 1890s and in 1903 it was well described in London's Society of Engineer's Journal[5] but is now widely confused with ferrocement.
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTIONRajesh Kolli
Construction and civil engineering activities have experienced a rapid growth due to improvements in procurement of building materials.
However, the current scenario in the developing construction industry has posed many challenges due to some unsustainable aspects of the highly polluting and the exhaustive nature of building materials.
At the same time, it has also created opportunities for innovative and unconventional resources to emerge due to the widening gap in demand and supply of building materials, as well as the need for energy efficient and economical methods of construction.
Purpose, Need, Importance, Methods, Causes and types of defects in buildings, Preparation of report on maintenance work, Remedial measures and execution procedure of any one, Types of building maintenance work.
•The National Eco House Competition
•The HCT Eco House
•Technologies in the Eco House
•Focus on Insulated Concrete Forms
•The build process of HCT
•Student and staff participation
•The monitoring and results phase
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
2. Notes
• The following project schedule is from actual
project. It was performed August 2014 in North-
East Zambia, very rural area close to Tanzanian
border
• Crew for 14 on-site days consisted
– 1 Master Engineer / Chief Supervisor (EHS)
– 1 Project Manager / Supervisor (EHZ)
– 2 Master Builders (EHZ)
– 3 Bricklayers
– 10-15 Workers (depending on day and tasks)
– 4 women to carry water and gather grass
– 2 women for support functions
3. About tools and methods
• No construction equipment was used
• The Earth House Crew provided all hand-held
tools
• Even gravel was crushed in place using
small sledges
4. Rough Timeline
Week 1 Week 2 Week 3 Week 4 Week 5
Area cleaning
Trenches for
strip foundation
Interlocking
brick mfg
Adobe brick mfg
Strip foundation
Interlock & adobe curing
Steel pre-cut
Week 6 Week 7 Week 8 Week 9 Week 10
Procurement
and pre-staging
Logistics
On Site work and delivery
5. Preparatory work
• 2 days - area cleaning and baselines for
strip foundation
• 1 day to cast and few days to cure
6. Adobe and clay works
• 3 days to create
interlocking bricks for
plinth
• 5 days to create
adobe bricks for in-filling
• 2-3 weeks to cure the
bricks
7. Steel preparation
and logistics
• Earth House Systems™ frames are
manufactured in Lusaka
• Roof and span structure is subcontracted
• 4 days (two men) - structural steel cutting
and tension rod manufacturing
• All material and tools are pre-staged in
warehouse and loaded to a single, 7 ton
truck
8. Site Day 1
• Set up work site, perimeter and occupational
safety
• Double-check strip foundation dimensions and
lay up baselines
9. Site Day 2
• Create plinth from
interlocking bricks
• Start frame assembly
10. Site Day 3
• Detail, plaster and finish plinth
• Continue frame assembly
11. Site Day 4
• Cast and finish concrete slab
• Finish frame assembly
12. Site Day 5
• Lay up assembly plates
• Start steel works
13. Site Day 6
• Preparations for clay
works
• Finish steel works
14. Site Day 7
• Clay works
starting from the
lower frames
15. Site Day 8
• Finish in filling with
adobe bricks,
shaving and
smoothing of walls
• First coat
plastering, lower
frames
• Start roof assembly
16. Site Day 9
• Attach heavy-duty
expanded wire to
exterior walls
• First coat
plastering, interior
walls, upper frames
• First coat
plastering, exterior
walls
17. Site Day 10
• Second coat,
exterior plastering
• Finishing exterior
plastering
• Electrical work
preparations
18. Site Day 11
• Second coat, interior plastering
• Finishing, interior plastering
19. Site Day 12
• Limewashing inside
and outside
• Electrical assembly
20. Site Day 13
• Door and panel
mounting
• Limewash inside
and outside
• Cement floor
casting
21. Site Day 14
• Final detailing
• Handover to customer