SlideShare a Scribd company logo
1 of 11
Rufran’s Acumen Fuse 
Tips and Tricks 01-14 
1) Solution to Deltek Acumen Fuse import 
issue whereby the schedule from 
Primavera is imported into the tool but 
results in incorrect translation of P6 
original and remaining durations. 
2) When imported durations come in 
incorrectly, all the metrics using duration 
as a variable will come out wrong. 
3) We will troubleshoot and resolve this 
problem in this article. 
2014 
Rufran C. Frago, P. Eng., PMP®, CCP, PMI-RMP® 
Revision 0: September 14, 2014
TABLE OF CONTENTS 
PAGES 
1. SITUATION/PROBLEM ................................................................................................................. 4 
2. RELATED TOOLS .......................................................................................................................... 4 
3. DEFINITION ................................................................................................................................... 4 
4. PROBLEM ANALYSIS (PA) .......................................................................................................... 4 
5. EXPLANATION .............................................................................................................................. 7 
6. SOLUTION ...................................................................................................................................... 8 
7. REFERENCES ............................................................................................................................... 10 
8. ADDITIONAL READING MATERIALS ..................................................................................... 10 
9. APPENDICES ................................................................................................................................ 10 
9.1. NONE ......................................................................................................................................... 10 
10. INDEX ....................................................................................................................................... 11 
102013-Rufran's Primavera Scheduling Tips & Tricks 08-13 Page 2 of 11 9/14/2014 
Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
List of Figures 
FIGURE 1 -PRIMAVERA SCHEDULE (ORIGINAL) .................................................... 5 
FIGURE 2 –ACUMEN FUSE SCHEDULE (AFTER IMPORTING P6 XER) ................ 6 
FIGURE 3 – S1/PROJECT TAB SHOWING THE ACTIVITY VIEW BUTTON ........... 8 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 3 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
1. SITUATION/PROBLEM 
1.1. The durations of imported Primavera schedule into Acumen Fuse are not correct. 
1.2. Durations are not translating properly into Acumen Fuse. 
1.3. The original and remaining durations from the Primavera schedule multiplied 
three times. It comes over three times long. 
1.4. The priority level is critical because a gated review is upon the project team. 
Acumen Fuse will be utilized reviewing schedule quality. 
1.5. Many projects are on schedule for review in the next few days. 
1.6. This also puts into serious question the accuracy of all previous reviews. 
1.7. Wrong durations, means wrong inputs to the metric formulas, which means 
wrong results. 
1.8. A prompt resolution is called for. 
2. RELATED TOOLS 
2.1. Deltek Acumen Fuse V5.1.1.0 x 64 and lower 
2.2. Primavera v6.7 SP4 
3. DEFINITION 
3.1. The term “User” in this document is the person using the Acumen Fuse tool. He 
can be the planner, the scheduler, the Project Manager or anyone. 
4. PROBLEM ANALYSIS (PA) 
4.1. Create a Primavera test schedule called “TF-TEST” intended to replicate the 
problem. Use only one 24/7 calendar for all activities. This calendar has a setting 
of 24 hours per day (hours per time-period). 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 4 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
4.2. This simple schedule network has 21 activities (see Figure 1). 
Figure 1 -Primavera Schedule (Original) 
4.3. Export the schedule as “XER” file, saved to a common directory and folder. 
4.4. Import the XER file to Acumen Fuse. 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 5 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
4.5. Upon inspection, it is clear that all Acumen Fuse schedule durations are three 
times more than the original Primavera schedule; e.g. Activity A Clear Site has 
300 days instead of 100 days, Activity F with 150 days instead of 50 days, and so 
on. You can see the difference by comparing Figure 1 and 2. 
Figure 2 –Acumen Fuse Schedule (after importing P6 XER) 
4.6. Inspect the calendar. The assigned calendar in Acumen Fuse and in Primavera is 
the same. Assignment has translated correctly. So what is the problem? Since it is 
not a wrong setting in Primavera, it must be a default setting in Acumen Fuse. 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 6 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
4.7. We have to underscore that the problem affects the accuracy of several standard 
metrics that uses duration as one of the variables. 
4.8. Note that there was no reported error message. 
5. EXPLANATION 
5.1. There is no need to change anything in Primavera to correct the schedule before 
exporting. 
5.2. The reason for the discrepancy points to Acumen Fuse default setting under the 
Activity View pull down not properly set, making the Primavera activities with 
24/7 calendars to have their durations translated to three times as long (see 
Section 6.0 or specifically Section 6.5 for more explanation). 
5.3. A quick correction is available (see Section 6.3, 6.4 & 6.5) 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 7 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
6. SOLUTION 
6.1. Open Acumen Fuse 
6.2. Go to the S1//Projects tab (1) and click “Activity View” (2) 
Figure 3 – S1/Project Tab showing the Activity View Button 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 8 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
6.3. Make sure that Hours per Time Period is checked (3). It is a check box but it 
does not look like there is a box to check. 
6.4. After putting a “checkmark”, the Hours per Time Period, it should look like this. 
6.5. When this button is checked(selected), the assigned calendar per activity will 
govern, not Acumen Fuse’s default setting which uses hours per day set to 8 
hours. The reason why all Primavera durations with 24/7 calendars translating to 
three times as long point to the "check button" not selected. As such, the default 
of 8 hours per day took control of the conversion. 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 9 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
7. REFERENCES 
7.1.1. Frago, R. (2014). Log book-Troubleshooting records 
7.1.2. Frago, R. (2014).Deltek Support Case: 140908-000202Durations of 
Imported Schedule are incorrect 
8. ADDITIONAL READING MATERIALS 
8.1.1. Deltek Acumen Fuse V.5.1.1.0 x 64 User Manual 
9. APPENDICES 
9.1. NONE 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 10 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
10. INDEX 
“User” ................................................................................................................................. 4 
Activity View pull down ..................................................................................................... 7 
Acumen Fuse default setting ............................................................................................... 7 
ADDITIONAL READING MATERIALS ........................................................................ 10 
APPENDICES ................................................................................................................... 10 
assigned calendar ................................................................................................................ 6 
button is checked(selected) ................................................................................................. 9 
checkmark ........................................................................................................................... 9 
DEFINITION ...................................................................................................................... 4 
durations are three times more ............................................................................................ 6 
EXPLANATION ................................................................................................................. 7 
Hours per Time Period ........................................................................................................ 9 
INDEX .............................................................................................................................. 11 
PROBLEM ANALYSIS ...................................................................................................... 4 
REFERENCES .................................................................................................................. 10 
RELATED TOOLS ............................................................................................................. 4 
S1//Projects tab ................................................................................................................... 8 
SITUATION/PROBLEM .................................................................................................... 4 
SOLUTION ......................................................................................................................... 8 
standard metrics .................................................................................................................. 7 
TABLE OF CONTENTS ................................................................................................. 2 
wrong inputs........................................................................................................................ 4 
091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 11 of 11 
Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®

More Related Content

Viewers also liked

Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Acumen
 
Improved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric AssessmentImproved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric AssessmentAcumen
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute ResolutionAcumen
 
Acumen Fuse Metrics & Descriptions Guide
Acumen Fuse Metrics & Descriptions GuideAcumen Fuse Metrics & Descriptions Guide
Acumen Fuse Metrics & Descriptions GuideAcumen
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Acumen
 
Schedule Execution Metrics Dashboard
Schedule Execution Metrics DashboardSchedule Execution Metrics Dashboard
Schedule Execution Metrics DashboardDaniel Castro
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityAcumen
 
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...p6academy
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyAcumen
 
Schedule Risk Analysis
Schedule Risk AnalysisSchedule Risk Analysis
Schedule Risk AnalysisGd Suryawan
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskAcumen
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Acumen
 
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Pedram Danesh-Mand
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShareKapost
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great InfographicsSlideShare
 

Viewers also liked (20)

Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Improved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric AssessmentImproved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric Assessment
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Acumen Fuse Metrics & Descriptions Guide
Acumen Fuse Metrics & Descriptions GuideAcumen Fuse Metrics & Descriptions Guide
Acumen Fuse Metrics & Descriptions Guide
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule Assessment
 
072213 Understanding Acumen Fuse Scoring Methods
072213 Understanding Acumen Fuse Scoring Methods072213 Understanding Acumen Fuse Scoring Methods
072213 Understanding Acumen Fuse Scoring Methods
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Schedule Execution Metrics Dashboard
Schedule Execution Metrics DashboardSchedule Execution Metrics Dashboard
Schedule Execution Metrics Dashboard
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
 
Project Management Essentials
Project Management EssentialsProject Management Essentials
Project Management Essentials
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Schedule Risk Analysis
Schedule Risk AnalysisSchedule Risk Analysis
Schedule Risk Analysis
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShare
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great Infographics
 

Similar to 091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)

Refinery turnaround oil and gas
Refinery turnaround oil and gasRefinery turnaround oil and gas
Refinery turnaround oil and gasKaizenlogcom
 
Refinery turnaround oil and gas
Refinery turnaround oil and gasRefinery turnaround oil and gas
Refinery turnaround oil and gasKaizenlogcom
 
Refinery turnaround oil and gas
Refinery turnaround oil and gasRefinery turnaround oil and gas
Refinery turnaround oil and gasKaizenlogcom
 
COSC2737 Assignment 2 IT Infrastructure in the Cloud. .docx
COSC2737 Assignment 2  IT Infrastructure in the Cloud.  .docxCOSC2737 Assignment 2  IT Infrastructure in the Cloud.  .docx
COSC2737 Assignment 2 IT Infrastructure in the Cloud. .docxvoversbyobersby
 
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...IRJET Journal
 
cuACS Requirements Analysis Document Nicholas Aubé.docx
cuACS Requirements Analysis Document Nicholas Aubé.docxcuACS Requirements Analysis Document Nicholas Aubé.docx
cuACS Requirements Analysis Document Nicholas Aubé.docxdorishigh
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET Journal
 
C0362015022
C0362015022C0362015022
C0362015022theijes
 
Implementation-Plan_X_Corp
Implementation-Plan_X_CorpImplementation-Plan_X_Corp
Implementation-Plan_X_CorpJared Bourne
 
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety-Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety-Critical ...IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety-Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety-Critical ...IRJET Journal
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
IRJET- Real Time Monitoring of Servers with Prometheus and Grafana for High A...
IRJET- Real Time Monitoring of Servers with Prometheus and Grafana for High A...IRJET- Real Time Monitoring of Servers with Prometheus and Grafana for High A...
IRJET- Real Time Monitoring of Servers with Prometheus and Grafana for High A...IRJET Journal
 

Similar to 091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations) (20)

080714-Rufran's Primavera Scheduling Tips Tricks 02-14
080714-Rufran's Primavera Scheduling Tips  Tricks 02-14080714-Rufran's Primavera Scheduling Tips  Tricks 02-14
080714-Rufran's Primavera Scheduling Tips Tricks 02-14
 
062613 Rufran's Primavera Scheduling Tips & Tricks 01-13
062613 Rufran's Primavera Scheduling Tips & Tricks 01-13062613 Rufran's Primavera Scheduling Tips & Tricks 01-13
062613 Rufran's Primavera Scheduling Tips & Tricks 01-13
 
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
 
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
 
Refinery turnaround oil and gas
Refinery turnaround oil and gasRefinery turnaround oil and gas
Refinery turnaround oil and gas
 
Refinery turnaround oil and gas
Refinery turnaround oil and gasRefinery turnaround oil and gas
Refinery turnaround oil and gas
 
Refinery turnaround oil and gas
Refinery turnaround oil and gasRefinery turnaround oil and gas
Refinery turnaround oil and gas
 
062813 Rufran's Primavera Scheduling Tips & Tricks 02-13
062813 Rufran's Primavera Scheduling Tips & Tricks 02-13062813 Rufran's Primavera Scheduling Tips & Tricks 02-13
062813 Rufran's Primavera Scheduling Tips & Tricks 02-13
 
COSC2737 Assignment 2 IT Infrastructure in the Cloud. .docx
COSC2737 Assignment 2  IT Infrastructure in the Cloud.  .docxCOSC2737 Assignment 2  IT Infrastructure in the Cloud.  .docx
COSC2737 Assignment 2 IT Infrastructure in the Cloud. .docx
 
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...
 
cuACS Requirements Analysis Document Nicholas Aubé.docx
cuACS Requirements Analysis Document Nicholas Aubé.docxcuACS Requirements Analysis Document Nicholas Aubé.docx
cuACS Requirements Analysis Document Nicholas Aubé.docx
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
 
C0362015022
C0362015022C0362015022
C0362015022
 
13 project management
13 project management13 project management
13 project management
 
Implementation-Plan_X_Corp
Implementation-Plan_X_CorpImplementation-Plan_X_Corp
Implementation-Plan_X_Corp
 
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety-Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety-Critical ...IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety-Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety-Critical ...
 
113015 - Understanding ALAP
113015 - Understanding ALAP113015 - Understanding ALAP
113015 - Understanding ALAP
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
IRJET- Real Time Monitoring of Servers with Prometheus and Grafana for High A...
IRJET- Real Time Monitoring of Servers with Prometheus and Grafana for High A...IRJET- Real Time Monitoring of Servers with Prometheus and Grafana for High A...
IRJET- Real Time Monitoring of Servers with Prometheus and Grafana for High A...
 

More from PM SOLUTION PRO| Risk-based Management and Services Inc.

More from PM SOLUTION PRO| Risk-based Management and Services Inc. (20)

121717 Kindle Issue 2 : Figures become so small than desired
121717 Kindle Issue 2 : Figures become so small than desired121717 Kindle Issue 2 : Figures become so small than desired
121717 Kindle Issue 2 : Figures become so small than desired
 
121717 Kindle Issue : Table lines were showing in kindle
121717 Kindle Issue : Table lines were showing in kindle121717 Kindle Issue : Table lines were showing in kindle
121717 Kindle Issue : Table lines were showing in kindle
 
101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)
 
063016 Man is the Center of the Risk Universe
063016 Man is the Center of the Risk Universe063016 Man is the Center of the Risk Universe
063016 Man is the Center of the Risk Universe
 
032815 DBM Schedule Development Workshop
032815 DBM Schedule Development Workshop032815 DBM Schedule Development Workshop
032815 DBM Schedule Development Workshop
 
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
 
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique 102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
 
091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)
 
082314 Road to Operational Excellence
082314 Road to Operational Excellence082314 Road to Operational Excellence
082314 Road to Operational Excellence
 
072414 Resource Distribution Copy-Paste Problem
072414 Resource Distribution Copy-Paste Problem072414 Resource Distribution Copy-Paste Problem
072414 Resource Distribution Copy-Paste Problem
 
011614 Scaffolding, what is it? Direct or Indirect?
011614 Scaffolding, what is it? Direct or Indirect?011614 Scaffolding, what is it? Direct or Indirect?
011614 Scaffolding, what is it? Direct or Indirect?
 
121013 Blackberry Business Audit (BMC 205 @ UofC)
121013 Blackberry Business Audit (BMC 205 @ UofC)121013 Blackberry Business Audit (BMC 205 @ UofC)
121013 Blackberry Business Audit (BMC 205 @ UofC)
 
103013 Case Study, Potash Corporation (BMC205, UofC)
103013 Case Study, Potash Corporation (BMC205, UofC)103013 Case Study, Potash Corporation (BMC205, UofC)
103013 Case Study, Potash Corporation (BMC205, UofC)
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
071513 How to Prepare for Schedule Quantitative Risk Analysis
071513 How to Prepare for Schedule Quantitative Risk Analysis071513 How to Prepare for Schedule Quantitative Risk Analysis
071513 How to Prepare for Schedule Quantitative Risk Analysis
 
070613 Managing P6 Database Security Using RMC
070613 Managing P6 Database Security Using RMC070613 Managing P6 Database Security Using RMC
070613 Managing P6 Database Security Using RMC
 
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
 
022114-Managing Diversity in the Canadian Workplace
022114-Managing Diversity in the Canadian Workplace022114-Managing Diversity in the Canadian Workplace
022114-Managing Diversity in the Canadian Workplace
 
110614-Unit Cost Approach to Estimating Operational Materials Budget
110614-Unit Cost Approach to Estimating Operational Materials Budget110614-Unit Cost Approach to Estimating Operational Materials Budget
110614-Unit Cost Approach to Estimating Operational Materials Budget
 
012614-Management of Schedule Quality
012614-Management of Schedule Quality012614-Management of Schedule Quality
012614-Management of Schedule Quality
 

Recently uploaded

Asset Management Software - Infographic
Asset Management Software - InfographicAsset Management Software - Infographic
Asset Management Software - InfographicHr365.us smith
 
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...gurkirankumar98700
 
XpertSolvers: Your Partner in Building Innovative Software Solutions
XpertSolvers: Your Partner in Building Innovative Software SolutionsXpertSolvers: Your Partner in Building Innovative Software Solutions
XpertSolvers: Your Partner in Building Innovative Software SolutionsMehedi Hasan Shohan
 
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...soniya singh
 
Automate your Kamailio Test Calls - Kamailio World 2024
Automate your Kamailio Test Calls - Kamailio World 2024Automate your Kamailio Test Calls - Kamailio World 2024
Automate your Kamailio Test Calls - Kamailio World 2024Andreas Granig
 
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...MyIntelliSource, Inc.
 
Intelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmIntelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmSujith Sukumaran
 
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...kellynguyen01
 
Cloud Management Software Platforms: OpenStack
Cloud Management Software Platforms: OpenStackCloud Management Software Platforms: OpenStack
Cloud Management Software Platforms: OpenStackVICTOR MAESTRE RAMIREZ
 
Adobe Marketo Engage Deep Dives: Using Webhooks to Transfer Data
Adobe Marketo Engage Deep Dives: Using Webhooks to Transfer DataAdobe Marketo Engage Deep Dives: Using Webhooks to Transfer Data
Adobe Marketo Engage Deep Dives: Using Webhooks to Transfer DataBradBedford3
 
cybersecurity notes for mca students for learning
cybersecurity notes for mca students for learningcybersecurity notes for mca students for learning
cybersecurity notes for mca students for learningVitsRangannavar
 
Engage Usergroup 2024 - The Good The Bad_The Ugly
Engage Usergroup 2024 - The Good The Bad_The UglyEngage Usergroup 2024 - The Good The Bad_The Ugly
Engage Usergroup 2024 - The Good The Bad_The UglyFrank van der Linden
 
why an Opensea Clone Script might be your perfect match.pdf
why an Opensea Clone Script might be your perfect match.pdfwhy an Opensea Clone Script might be your perfect match.pdf
why an Opensea Clone Script might be your perfect match.pdfjoe51371421
 
Call Girls in Naraina Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Naraina Delhi 💯Call Us 🔝8264348440🔝Call Girls in Naraina Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Naraina Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
The Evolution of Karaoke From Analog to App.pdf
The Evolution of Karaoke From Analog to App.pdfThe Evolution of Karaoke From Analog to App.pdf
The Evolution of Karaoke From Analog to App.pdfPower Karaoke
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software DevelopersVinodh Ram
 
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...stazi3110
 
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio, Inc.
 
Salesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantSalesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantAxelRicardoTrocheRiq
 
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...OnePlan Solutions
 

Recently uploaded (20)

Asset Management Software - Infographic
Asset Management Software - InfographicAsset Management Software - Infographic
Asset Management Software - Infographic
 
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
 
XpertSolvers: Your Partner in Building Innovative Software Solutions
XpertSolvers: Your Partner in Building Innovative Software SolutionsXpertSolvers: Your Partner in Building Innovative Software Solutions
XpertSolvers: Your Partner in Building Innovative Software Solutions
 
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
Russian Call Girls in Karol Bagh Aasnvi ➡️ 8264348440 💋📞 Independent Escort S...
 
Automate your Kamailio Test Calls - Kamailio World 2024
Automate your Kamailio Test Calls - Kamailio World 2024Automate your Kamailio Test Calls - Kamailio World 2024
Automate your Kamailio Test Calls - Kamailio World 2024
 
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
 
Intelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmIntelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalm
 
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
 
Cloud Management Software Platforms: OpenStack
Cloud Management Software Platforms: OpenStackCloud Management Software Platforms: OpenStack
Cloud Management Software Platforms: OpenStack
 
Adobe Marketo Engage Deep Dives: Using Webhooks to Transfer Data
Adobe Marketo Engage Deep Dives: Using Webhooks to Transfer DataAdobe Marketo Engage Deep Dives: Using Webhooks to Transfer Data
Adobe Marketo Engage Deep Dives: Using Webhooks to Transfer Data
 
cybersecurity notes for mca students for learning
cybersecurity notes for mca students for learningcybersecurity notes for mca students for learning
cybersecurity notes for mca students for learning
 
Engage Usergroup 2024 - The Good The Bad_The Ugly
Engage Usergroup 2024 - The Good The Bad_The UglyEngage Usergroup 2024 - The Good The Bad_The Ugly
Engage Usergroup 2024 - The Good The Bad_The Ugly
 
why an Opensea Clone Script might be your perfect match.pdf
why an Opensea Clone Script might be your perfect match.pdfwhy an Opensea Clone Script might be your perfect match.pdf
why an Opensea Clone Script might be your perfect match.pdf
 
Call Girls in Naraina Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Naraina Delhi 💯Call Us 🔝8264348440🔝Call Girls in Naraina Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Naraina Delhi 💯Call Us 🔝8264348440🔝
 
The Evolution of Karaoke From Analog to App.pdf
The Evolution of Karaoke From Analog to App.pdfThe Evolution of Karaoke From Analog to App.pdf
The Evolution of Karaoke From Analog to App.pdf
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software Developers
 
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
 
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
 
Salesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantSalesforce Certified Field Service Consultant
Salesforce Certified Field Service Consultant
 
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...
 

091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)

  • 1. Rufran’s Acumen Fuse Tips and Tricks 01-14 1) Solution to Deltek Acumen Fuse import issue whereby the schedule from Primavera is imported into the tool but results in incorrect translation of P6 original and remaining durations. 2) When imported durations come in incorrectly, all the metrics using duration as a variable will come out wrong. 3) We will troubleshoot and resolve this problem in this article. 2014 Rufran C. Frago, P. Eng., PMP®, CCP, PMI-RMP® Revision 0: September 14, 2014
  • 2. TABLE OF CONTENTS PAGES 1. SITUATION/PROBLEM ................................................................................................................. 4 2. RELATED TOOLS .......................................................................................................................... 4 3. DEFINITION ................................................................................................................................... 4 4. PROBLEM ANALYSIS (PA) .......................................................................................................... 4 5. EXPLANATION .............................................................................................................................. 7 6. SOLUTION ...................................................................................................................................... 8 7. REFERENCES ............................................................................................................................... 10 8. ADDITIONAL READING MATERIALS ..................................................................................... 10 9. APPENDICES ................................................................................................................................ 10 9.1. NONE ......................................................................................................................................... 10 10. INDEX ....................................................................................................................................... 11 102013-Rufran's Primavera Scheduling Tips & Tricks 08-13 Page 2 of 11 9/14/2014 Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
  • 3. List of Figures FIGURE 1 -PRIMAVERA SCHEDULE (ORIGINAL) .................................................... 5 FIGURE 2 –ACUMEN FUSE SCHEDULE (AFTER IMPORTING P6 XER) ................ 6 FIGURE 3 – S1/PROJECT TAB SHOWING THE ACTIVITY VIEW BUTTON ........... 8 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 3 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
  • 4. 1. SITUATION/PROBLEM 1.1. The durations of imported Primavera schedule into Acumen Fuse are not correct. 1.2. Durations are not translating properly into Acumen Fuse. 1.3. The original and remaining durations from the Primavera schedule multiplied three times. It comes over three times long. 1.4. The priority level is critical because a gated review is upon the project team. Acumen Fuse will be utilized reviewing schedule quality. 1.5. Many projects are on schedule for review in the next few days. 1.6. This also puts into serious question the accuracy of all previous reviews. 1.7. Wrong durations, means wrong inputs to the metric formulas, which means wrong results. 1.8. A prompt resolution is called for. 2. RELATED TOOLS 2.1. Deltek Acumen Fuse V5.1.1.0 x 64 and lower 2.2. Primavera v6.7 SP4 3. DEFINITION 3.1. The term “User” in this document is the person using the Acumen Fuse tool. He can be the planner, the scheduler, the Project Manager or anyone. 4. PROBLEM ANALYSIS (PA) 4.1. Create a Primavera test schedule called “TF-TEST” intended to replicate the problem. Use only one 24/7 calendar for all activities. This calendar has a setting of 24 hours per day (hours per time-period). 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 4 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
  • 5. 4.2. This simple schedule network has 21 activities (see Figure 1). Figure 1 -Primavera Schedule (Original) 4.3. Export the schedule as “XER” file, saved to a common directory and folder. 4.4. Import the XER file to Acumen Fuse. 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 5 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
  • 6. 4.5. Upon inspection, it is clear that all Acumen Fuse schedule durations are three times more than the original Primavera schedule; e.g. Activity A Clear Site has 300 days instead of 100 days, Activity F with 150 days instead of 50 days, and so on. You can see the difference by comparing Figure 1 and 2. Figure 2 –Acumen Fuse Schedule (after importing P6 XER) 4.6. Inspect the calendar. The assigned calendar in Acumen Fuse and in Primavera is the same. Assignment has translated correctly. So what is the problem? Since it is not a wrong setting in Primavera, it must be a default setting in Acumen Fuse. 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 6 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
  • 7. 4.7. We have to underscore that the problem affects the accuracy of several standard metrics that uses duration as one of the variables. 4.8. Note that there was no reported error message. 5. EXPLANATION 5.1. There is no need to change anything in Primavera to correct the schedule before exporting. 5.2. The reason for the discrepancy points to Acumen Fuse default setting under the Activity View pull down not properly set, making the Primavera activities with 24/7 calendars to have their durations translated to three times as long (see Section 6.0 or specifically Section 6.5 for more explanation). 5.3. A quick correction is available (see Section 6.3, 6.4 & 6.5) 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 7 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
  • 8. 6. SOLUTION 6.1. Open Acumen Fuse 6.2. Go to the S1//Projects tab (1) and click “Activity View” (2) Figure 3 – S1/Project Tab showing the Activity View Button 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 8 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
  • 9. 6.3. Make sure that Hours per Time Period is checked (3). It is a check box but it does not look like there is a box to check. 6.4. After putting a “checkmark”, the Hours per Time Period, it should look like this. 6.5. When this button is checked(selected), the assigned calendar per activity will govern, not Acumen Fuse’s default setting which uses hours per day set to 8 hours. The reason why all Primavera durations with 24/7 calendars translating to three times as long point to the "check button" not selected. As such, the default of 8 hours per day took control of the conversion. 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 9 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
  • 10. 7. REFERENCES 7.1.1. Frago, R. (2014). Log book-Troubleshooting records 7.1.2. Frago, R. (2014).Deltek Support Case: 140908-000202Durations of Imported Schedule are incorrect 8. ADDITIONAL READING MATERIALS 8.1.1. Deltek Acumen Fuse V.5.1.1.0 x 64 User Manual 9. APPENDICES 9.1. NONE 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 10 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®
  • 11. 10. INDEX “User” ................................................................................................................................. 4 Activity View pull down ..................................................................................................... 7 Acumen Fuse default setting ............................................................................................... 7 ADDITIONAL READING MATERIALS ........................................................................ 10 APPENDICES ................................................................................................................... 10 assigned calendar ................................................................................................................ 6 button is checked(selected) ................................................................................................. 9 checkmark ........................................................................................................................... 9 DEFINITION ...................................................................................................................... 4 durations are three times more ............................................................................................ 6 EXPLANATION ................................................................................................................. 7 Hours per Time Period ........................................................................................................ 9 INDEX .............................................................................................................................. 11 PROBLEM ANALYSIS ...................................................................................................... 4 REFERENCES .................................................................................................................. 10 RELATED TOOLS ............................................................................................................. 4 S1//Projects tab ................................................................................................................... 8 SITUATION/PROBLEM .................................................................................................... 4 SOLUTION ......................................................................................................................... 8 standard metrics .................................................................................................................. 7 TABLE OF CONTENTS ................................................................................................. 2 wrong inputs........................................................................................................................ 4 091414-Rufran's Acumen Fuse Tips Tricks 01-14 (Duration Issues) Page 11 of 11 Author: RUFRAN C. FRAGO, P. Eng., PMP®, CCP, PMI-RMP®