SlideShare a Scribd company logo
1 of 8
Primavera Scheduling
Tips and Tricks 02-13
What is Schedule Level of Effort (LOE)?
Here’s a common planning & scheduling situation:
The Contractor’s scheduler was tasked to resource load the schedule using
the Level of Effort activities or LOEs.
He spent several hours assigning the links but could not seem to control
the start and end date of the LOE bars. He could not understand what’s
wrong. He has done the same thing in an older version of Primavera
scheduling tool (V3.1) and it worked perfectly well.
“An LOE is a Hammock, that’s what they are” he said to himself.
I think it is about time we help this guy out.
2013
Rufran C. Frago, P. Eng., PMP®, CCEC, PMI-RMP®
Revision 3: June 28, 2013
062813-Primavera Scheduling Tips & Tricks 02-13 Page 2 of 8 6/29/2013
Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
TABLE OF CONTENTS
PAGES
1.0 SITUATION/PROBLEM........................................................................................... 3
2.0 RELATED TOOLS .................................................................................................... 3
3.0 DEFINITION ........................................................................................................... 3
4.0 PROBLEM ANALYSIS (PA)....................................................................................... 4
5.0 EXPLANATION/SOLUTION ..................................................................................... 4
6.0 REFERENCES.......................................................................................................... 6
7.0 ADDITIONAL READING MATERIALS ....................................................................... 6
8.0 FOOD FOR THOUGHT............................................................................................ 6
9.0 ILLUSTRATIONS ..................................................................................................... 7
10.0 INDEX.................................................................................................................... 8
062813-Primavera Scheduling Tips & Tricks 02-13 Page 3 of 8 6/29/2013
Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
1.0 SITUATION/PROBLEM
1.1 Two schedulers were arguing about the LOE and Hammock. One said
they are the same while the other one said, they are quite different.
1.2 The Lead Planner looked at the P6 schedule he prepared with his Boss
and decided to use the LOEs for resource leveling. They worked on it
for the next two days but the leveling process just won’t work. “What
is the problem here?” asked the Project Manager.
1.3 The Contractor’s scheduler was tasked to resource load the schedule
using the LOEs. He spent several hours assigning the links but could
not seem to control the start and end date of the LOE bars. He could
not understand what’s wrong. He has done the same thing in an older
version of Primavera scheduling tool (V3.1) and it worked perfectly
well. “An LOE is a Hammock, that’s what they are” he thought.
2.0 RELATED TOOLS
2.1 Project Management (Primavera 6.1 SP1, 6.2, 6.7 SP1, 6.7 SP2 and
higher)
3.0 DEFINITION
3.1 The term “User” in this document is the person using the Primavera
scheduling tool. He can be the planner, the scheduler, the Project
Manager or anyone.
3.2 A Level of Effort activity has a duration that is determined by its
dependent activities. Administration-type activities are typically
assigned as Level of Effort.
062813-Primavera Scheduling Tips & Tricks 02-13 Page 4 of 8 6/29/2013
Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
4.0 PROBLEM ANALYSIS (PA)
4.1 The situations described in Section 1 of this document are quite
common. The problem often lies around the User’s understanding of
how the tool works. The proper logic to follow is that if one is an
equipment operator who thought that a reverse control lever is drive-
forward lever, then he/she will be in a lot of trouble. The same applies
to using Primavera. One must understand fully to gain the full benefit
and flexibility of the scheduling tool.
4.2 Section 5 will itemize some of the misconceptions that need to be
corrected when dealing with Level of Effort activities. Note that LOE is
a common term that up to now has always been misunderstood.
5.0 EXPLANATION/SOLUTION
5.1 Rules to follow when dealing with Level of Effort activities.
5.1.1 A level of effort activity's duration is dependent on its
predecessor and/or successor activities. Administration type
activities are typically assigned as Level of Effort.
5.1.2 Level of effort activities cannot have constraints assigned to
them. So, those who wanted to constrain an LOE…Forget it!
Even if you want it, it will not let you.
5.1.3 Here’s one for you. The Level of effort activity is not included
when leveling resources. You might think that it plays a role
when doing automatic leveling but they don’t. Only
resources loaded against normal task activities are included.
5.1.4 If an activity with an Actual Start is assigned to a Level of
Effort activity before being scheduled, the Original Duration
of the Level of Effort will be 0. For more information on this
see Oracle Primavera Solution ID: prim40131 "Why is the
Level of Effort (LOE) activity showing an Original Duration
(OD) of zero (0)?"
062813-Primavera Scheduling Tips & Tricks 02-13 Page 5 of 8 6/29/2013
Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
5.1.5 Users should use level of effort activities for on-going tasks
that depend on other activities. For example, you could
assign level of effort activities for clerical work, a security
guard, or even some aspects of project management.
5.1.6 A level of effort activity is similar to but different from a
hammock activity.
5.1.7 A level of effort activity uses its assigned calendar to
summarize its dates. Hammocks are not scheduled using their
own calendar.
5.1.8 Any type of relationship can be assigned to a level of effort
activity. Only a start-to-start and finish-to-finish relationship
can be assigned to a hammock activity.
5.1.9 All finish to start and start to start predecessors and start to
finish and start to start successors drive the start date of the
LOE activity.
5.1.10 All finish-finish and start-finish predecessors and finish-start
and finish-finish successors drive the finish date of the LOE
activity.
5.1.11 A hammock activity's duration is calculated from the earliest
early start of its predecessors to the latest early finish of its
successor activities.
5.1.12 Schedule calculation of a normal activity is affected by its
“Duration Type” setting (i.e. Fixed Duration and Units/Time,
Fixed Duration and Units, Fixed Units/Time and Fixed Units).
The work effort required to complete the activity does not
change. The calculation rules do not change for an LOE
activity.
062813-Primavera Scheduling Tips & Tricks 02-13 Page 6 of 8 6/29/2013
Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
6.0 REFERENCES
6.1 Help, About Primavera, Project Management (Primavera), V6.1 SP1,
V6.1 SP2, V6.7 SP1, V6.7 SP2 and higher.
6.2 Oracle Primavera Solution ID: 2003821145529
7.0 ADDITIONAL READING MATERIALS
7.1 Oracle Primavera Solution ID: prim40131
8.0 FOOD FOR THOUGHT
8.1 It’s been said, time and again but I will have to underline it one more
time. A level of effort activity is similar to but different from a
hammock activity.
8.2 The New User should practice linking the LOEs to controlling activities
described in Section 5.1.9 and 5.1.10 and as demonstrated in Section
9.0 Illustrations, Figure 1 and Figure 2.
062813-Primavera Scheduling Tips & Tricks 02-13 Page 7 of 8 6/29/2013
Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
9.0 ILLUSTRATIONS
9.1 Figure 1
Links that DRIVES THE START DATE of the LOE activity
9.2 Figure 2
Links that DRIVES THE FINISH DATE of the LOE activity
062813-Primavera Scheduling Tips & Tricks 02-13 Page 8 of 8 6/29/2013
Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP
10.0 INDEX
“Duration Type” setting 5
“User” 3
ADDITIONAL READING MATERIALS 6
DEFINITION 3
FOODS FOR THOUGHT 6
hammock 6
ILLUSTATIONS 7
INDEX 8
Links that DRIVES THE FINISH DATE 7
Links that DRIVES THE START DATE 7
PROBLEM ANALYSIS 4
REFERENCES 6
RELATED TOOLS 3
resources 4
SITUATION/PROBLEM 3
SOLUTION 4
User’s understanding 4

More Related Content

What's hot

Microsoft project 2010 creating customized field with image & formula
Microsoft project 2010 creating customized field with image & formulaMicrosoft project 2010 creating customized field with image & formula
Microsoft project 2010 creating customized field with image & formulaNR Computer Learning Center
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Projectbobby
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013Ong-Art Sanpinit
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
CSCI-383 Lecture 5-6-7: Object-Oriented Design
CSCI-383 Lecture 5-6-7: Object-Oriented DesignCSCI-383 Lecture 5-6-7: Object-Oriented Design
CSCI-383 Lecture 5-6-7: Object-Oriented DesignJI Ruan
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)douggillis
 
Microsoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialMicrosoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialAnil Purushothaman
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baselineguest9da059
 
Msproject2010 in 16 minutes flat
Msproject2010 in 16 minutes flatMsproject2010 in 16 minutes flat
Msproject2010 in 16 minutes flatsoniachawla9
 
CMGT 410 HOMEWORK Education Planning--cmgt410homework.com
CMGT 410 HOMEWORK Education Planning--cmgt410homework.comCMGT 410 HOMEWORK Education Planning--cmgt410homework.com
CMGT 410 HOMEWORK Education Planning--cmgt410homework.comcampfort8
 
Establishing the performance measurement baseline (v4)
Establishing the performance measurement baseline (v4) Establishing the performance measurement baseline (v4)
Establishing the performance measurement baseline (v4) Glen Alleman
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDavid Greig
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joeNASAPMC
 
Ms project 2010 tutorial 2
Ms project 2010 tutorial   2Ms project 2010 tutorial   2
Ms project 2010 tutorial 2learningquotient
 

What's hot (20)

Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3
 
Microsoft project 2010 creating customized field with image & formula
Microsoft project 2010 creating customized field with image & formulaMicrosoft project 2010 creating customized field with image & formula
Microsoft project 2010 creating customized field with image & formula
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Project
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
PPTs on MS Project 2010
PPTs on MS Project 2010PPTs on MS Project 2010
PPTs on MS Project 2010
 
CSCI-383 Lecture 5-6-7: Object-Oriented Design
CSCI-383 Lecture 5-6-7: Object-Oriented DesignCSCI-383 Lecture 5-6-7: Object-Oriented Design
CSCI-383 Lecture 5-6-7: Object-Oriented Design
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
Microsoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialMicrosoft Office Project 2007 Tutorial
Microsoft Office Project 2007 Tutorial
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
 
Msproject2010 in 16 minutes flat
Msproject2010 in 16 minutes flatMsproject2010 in 16 minutes flat
Msproject2010 in 16 minutes flat
 
CMGT 410 HOMEWORK Education Planning--cmgt410homework.com
CMGT 410 HOMEWORK Education Planning--cmgt410homework.comCMGT 410 HOMEWORK Education Planning--cmgt410homework.com
CMGT 410 HOMEWORK Education Planning--cmgt410homework.com
 
Establishing the performance measurement baseline (v4)
Establishing the performance measurement baseline (v4) Establishing the performance measurement baseline (v4)
Establishing the performance measurement baseline (v4)
 
BhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual TrainingBhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual Training
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme Errors
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
 
Ms project 2010 tutorial 2
Ms project 2010 tutorial   2Ms project 2010 tutorial   2
Ms project 2010 tutorial 2
 

Viewers also liked

Owning Your Own Business Part I
Owning Your Own Business Part IOwning Your Own Business Part I
Owning Your Own Business Part IPeter Chen
 
Αυτοκίνητα και μηχανές
Αυτοκίνητα και μηχανέςΑυτοκίνητα και μηχανές
Αυτοκίνητα και μηχανέςKiki Lianou
 
Dolls from all the world
Dolls from all the worldDolls from all the world
Dolls from all the worldKiki Lianou
 
Delhi Public School
Delhi Public SchoolDelhi Public School
Delhi Public SchoolDFC2011
 
Ernie Morse Letter
Ernie Morse LetterErnie Morse Letter
Ernie Morse LetterErnie Morse
 
Mentor Culture Training
Mentor Culture TrainingMentor Culture Training
Mentor Culture Trainingprei20
 
Kitchen garden report
Kitchen garden reportKitchen garden report
Kitchen garden reportBill Kamadi
 
02_Pengaruh bahasa dalam pendidikan karakter bangsa
02_Pengaruh bahasa dalam pendidikan karakter bangsa02_Pengaruh bahasa dalam pendidikan karakter bangsa
02_Pengaruh bahasa dalam pendidikan karakter bangsaHamida ID
 
SOAL DAN PEMBAHASAN KIMIA UNSUR
SOAL DAN PEMBAHASAN KIMIA UNSURSOAL DAN PEMBAHASAN KIMIA UNSUR
SOAL DAN PEMBAHASAN KIMIA UNSURNesha Mutiara
 
Awesome bedding Modern Bedroom Furniture
Awesome bedding Modern Bedroom FurnitureAwesome bedding Modern Bedroom Furniture
Awesome bedding Modern Bedroom Furnituresongpon pirom
 
Tips for improve your memory
Tips for improve your memoryTips for improve your memory
Tips for improve your memorySABU VU
 

Viewers also liked (11)

Owning Your Own Business Part I
Owning Your Own Business Part IOwning Your Own Business Part I
Owning Your Own Business Part I
 
Αυτοκίνητα και μηχανές
Αυτοκίνητα και μηχανέςΑυτοκίνητα και μηχανές
Αυτοκίνητα και μηχανές
 
Dolls from all the world
Dolls from all the worldDolls from all the world
Dolls from all the world
 
Delhi Public School
Delhi Public SchoolDelhi Public School
Delhi Public School
 
Ernie Morse Letter
Ernie Morse LetterErnie Morse Letter
Ernie Morse Letter
 
Mentor Culture Training
Mentor Culture TrainingMentor Culture Training
Mentor Culture Training
 
Kitchen garden report
Kitchen garden reportKitchen garden report
Kitchen garden report
 
02_Pengaruh bahasa dalam pendidikan karakter bangsa
02_Pengaruh bahasa dalam pendidikan karakter bangsa02_Pengaruh bahasa dalam pendidikan karakter bangsa
02_Pengaruh bahasa dalam pendidikan karakter bangsa
 
SOAL DAN PEMBAHASAN KIMIA UNSUR
SOAL DAN PEMBAHASAN KIMIA UNSURSOAL DAN PEMBAHASAN KIMIA UNSUR
SOAL DAN PEMBAHASAN KIMIA UNSUR
 
Awesome bedding Modern Bedroom Furniture
Awesome bedding Modern Bedroom FurnitureAwesome bedding Modern Bedroom Furniture
Awesome bedding Modern Bedroom Furniture
 
Tips for improve your memory
Tips for improve your memoryTips for improve your memory
Tips for improve your memory
 

Similar to 062813 Rufran's Primavera Scheduling Tips & Tricks 02-13

Approaches to real time scheduling
Approaches to real time schedulingApproaches to real time scheduling
Approaches to real time schedulingKamal Acharya
 
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction  B.docxPrintNetwork Diagrams and Resource UtilizationIntroduction  B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docxChantellPantoja184
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
 
Easy job scheduling with android
Easy job scheduling with androidEasy job scheduling with android
Easy job scheduling with androidkirubhakarans2
 
Managing Develop of Large Systems
Managing Develop of Large SystemsManaging Develop of Large Systems
Managing Develop of Large SystemsDaniloPereira341965
 
Naging The Development Of Large Software Systems
Naging The Development Of Large Software Systems Naging The Development Of Large Software Systems
Naging The Development Of Large Software Systems Software Guru
 
Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)Giovanni Asproni
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET Journal
 
Requirements engineering in the rational unified process
Requirements engineering in the rational unified processRequirements engineering in the rational unified process
Requirements engineering in the rational unified processJorge Baque
 
Software project scheduling
Software project schedulingSoftware project scheduling
Software project schedulinglokareminakshi
 
Project scheduling
Project schedulingProject scheduling
Project schedulingJaafer Saeed
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDavid Greig
 
How processes masquerading as projects are hurting your business v4
How processes masquerading as projects are hurting your business v4How processes masquerading as projects are hurting your business v4
How processes masquerading as projects are hurting your business v4Jonathan Sapir
 
QSM Executive Primer Estimation and demand Management
QSM Executive Primer Estimation and demand ManagementQSM Executive Primer Estimation and demand Management
QSM Executive Primer Estimation and demand ManagementTaylor Putnam-Majarian
 
QSM Executive Primer final version
QSM Executive Primer final versionQSM Executive Primer final version
QSM Executive Primer final versionDoug Putnam
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Hariharan Ponnusamy
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6IOSRJMCE
 

Similar to 062813 Rufran's Primavera Scheduling Tips & Tricks 02-13 (20)

Approaches to real time scheduling
Approaches to real time schedulingApproaches to real time scheduling
Approaches to real time scheduling
 
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction  B.docxPrintNetwork Diagrams and Resource UtilizationIntroduction  B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Easy job scheduling with android
Easy job scheduling with androidEasy job scheduling with android
Easy job scheduling with android
 
Managing Develop of Large Systems
Managing Develop of Large SystemsManaging Develop of Large Systems
Managing Develop of Large Systems
 
Naging The Development Of Large Software Systems
Naging The Development Of Large Software Systems Naging The Development Of Large Software Systems
Naging The Development Of Large Software Systems
 
Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
 
080714-Rufran's Primavera Scheduling Tips Tricks 02-14
080714-Rufran's Primavera Scheduling Tips  Tricks 02-14080714-Rufran's Primavera Scheduling Tips  Tricks 02-14
080714-Rufran's Primavera Scheduling Tips Tricks 02-14
 
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
 
Requirements engineering in the rational unified process
Requirements engineering in the rational unified processRequirements engineering in the rational unified process
Requirements engineering in the rational unified process
 
Software project scheduling
Software project schedulingSoftware project scheduling
Software project scheduling
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme Errors
 
How processes masquerading as projects are hurting your business v4
How processes masquerading as projects are hurting your business v4How processes masquerading as projects are hurting your business v4
How processes masquerading as projects are hurting your business v4
 
QSM Executive Primer Estimation and demand Management
QSM Executive Primer Estimation and demand ManagementQSM Executive Primer Estimation and demand Management
QSM Executive Primer Estimation and demand Management
 
QSM Executive Primer final version
QSM Executive Primer final versionQSM Executive Primer final version
QSM Executive Primer final version
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 

More from PM SOLUTION PRO| Risk-based Management and Services Inc.

More from PM SOLUTION PRO| Risk-based Management and Services Inc. (20)

121717 Kindle Issue 2 : Figures become so small than desired
121717 Kindle Issue 2 : Figures become so small than desired121717 Kindle Issue 2 : Figures become so small than desired
121717 Kindle Issue 2 : Figures become so small than desired
 
121717 Kindle Issue : Table lines were showing in kindle
121717 Kindle Issue : Table lines were showing in kindle121717 Kindle Issue : Table lines were showing in kindle
121717 Kindle Issue : Table lines were showing in kindle
 
101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)
 
063016 Man is the Center of the Risk Universe
063016 Man is the Center of the Risk Universe063016 Man is the Center of the Risk Universe
063016 Man is the Center of the Risk Universe
 
032815 DBM Schedule Development Workshop
032815 DBM Schedule Development Workshop032815 DBM Schedule Development Workshop
032815 DBM Schedule Development Workshop
 
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
 
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique 102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
 
091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)
 
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
 
082314 Road to Operational Excellence
082314 Road to Operational Excellence082314 Road to Operational Excellence
082314 Road to Operational Excellence
 
072414 Resource Distribution Copy-Paste Problem
072414 Resource Distribution Copy-Paste Problem072414 Resource Distribution Copy-Paste Problem
072414 Resource Distribution Copy-Paste Problem
 
011614 Scaffolding, what is it? Direct or Indirect?
011614 Scaffolding, what is it? Direct or Indirect?011614 Scaffolding, what is it? Direct or Indirect?
011614 Scaffolding, what is it? Direct or Indirect?
 
121013 Blackberry Business Audit (BMC 205 @ UofC)
121013 Blackberry Business Audit (BMC 205 @ UofC)121013 Blackberry Business Audit (BMC 205 @ UofC)
121013 Blackberry Business Audit (BMC 205 @ UofC)
 
103013 Case Study, Potash Corporation (BMC205, UofC)
103013 Case Study, Potash Corporation (BMC205, UofC)103013 Case Study, Potash Corporation (BMC205, UofC)
103013 Case Study, Potash Corporation (BMC205, UofC)
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
072213 Understanding Acumen Fuse Scoring Methods
072213 Understanding Acumen Fuse Scoring Methods072213 Understanding Acumen Fuse Scoring Methods
072213 Understanding Acumen Fuse Scoring Methods
 
071513 How to Prepare for Schedule Quantitative Risk Analysis
071513 How to Prepare for Schedule Quantitative Risk Analysis071513 How to Prepare for Schedule Quantitative Risk Analysis
071513 How to Prepare for Schedule Quantitative Risk Analysis
 
070613 Managing P6 Database Security Using RMC
070613 Managing P6 Database Security Using RMC070613 Managing P6 Database Security Using RMC
070613 Managing P6 Database Security Using RMC
 
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
 
022114-Managing Diversity in the Canadian Workplace
022114-Managing Diversity in the Canadian Workplace022114-Managing Diversity in the Canadian Workplace
022114-Managing Diversity in the Canadian Workplace
 

Recently uploaded

Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 

Recently uploaded (20)

Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 

062813 Rufran's Primavera Scheduling Tips & Tricks 02-13

  • 1. Primavera Scheduling Tips and Tricks 02-13 What is Schedule Level of Effort (LOE)? Here’s a common planning & scheduling situation: The Contractor’s scheduler was tasked to resource load the schedule using the Level of Effort activities or LOEs. He spent several hours assigning the links but could not seem to control the start and end date of the LOE bars. He could not understand what’s wrong. He has done the same thing in an older version of Primavera scheduling tool (V3.1) and it worked perfectly well. “An LOE is a Hammock, that’s what they are” he said to himself. I think it is about time we help this guy out. 2013 Rufran C. Frago, P. Eng., PMP®, CCEC, PMI-RMP® Revision 3: June 28, 2013
  • 2. 062813-Primavera Scheduling Tips & Tricks 02-13 Page 2 of 8 6/29/2013 Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP TABLE OF CONTENTS PAGES 1.0 SITUATION/PROBLEM........................................................................................... 3 2.0 RELATED TOOLS .................................................................................................... 3 3.0 DEFINITION ........................................................................................................... 3 4.0 PROBLEM ANALYSIS (PA)....................................................................................... 4 5.0 EXPLANATION/SOLUTION ..................................................................................... 4 6.0 REFERENCES.......................................................................................................... 6 7.0 ADDITIONAL READING MATERIALS ....................................................................... 6 8.0 FOOD FOR THOUGHT............................................................................................ 6 9.0 ILLUSTRATIONS ..................................................................................................... 7 10.0 INDEX.................................................................................................................... 8
  • 3. 062813-Primavera Scheduling Tips & Tricks 02-13 Page 3 of 8 6/29/2013 Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP 1.0 SITUATION/PROBLEM 1.1 Two schedulers were arguing about the LOE and Hammock. One said they are the same while the other one said, they are quite different. 1.2 The Lead Planner looked at the P6 schedule he prepared with his Boss and decided to use the LOEs for resource leveling. They worked on it for the next two days but the leveling process just won’t work. “What is the problem here?” asked the Project Manager. 1.3 The Contractor’s scheduler was tasked to resource load the schedule using the LOEs. He spent several hours assigning the links but could not seem to control the start and end date of the LOE bars. He could not understand what’s wrong. He has done the same thing in an older version of Primavera scheduling tool (V3.1) and it worked perfectly well. “An LOE is a Hammock, that’s what they are” he thought. 2.0 RELATED TOOLS 2.1 Project Management (Primavera 6.1 SP1, 6.2, 6.7 SP1, 6.7 SP2 and higher) 3.0 DEFINITION 3.1 The term “User” in this document is the person using the Primavera scheduling tool. He can be the planner, the scheduler, the Project Manager or anyone. 3.2 A Level of Effort activity has a duration that is determined by its dependent activities. Administration-type activities are typically assigned as Level of Effort.
  • 4. 062813-Primavera Scheduling Tips & Tricks 02-13 Page 4 of 8 6/29/2013 Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP 4.0 PROBLEM ANALYSIS (PA) 4.1 The situations described in Section 1 of this document are quite common. The problem often lies around the User’s understanding of how the tool works. The proper logic to follow is that if one is an equipment operator who thought that a reverse control lever is drive- forward lever, then he/she will be in a lot of trouble. The same applies to using Primavera. One must understand fully to gain the full benefit and flexibility of the scheduling tool. 4.2 Section 5 will itemize some of the misconceptions that need to be corrected when dealing with Level of Effort activities. Note that LOE is a common term that up to now has always been misunderstood. 5.0 EXPLANATION/SOLUTION 5.1 Rules to follow when dealing with Level of Effort activities. 5.1.1 A level of effort activity's duration is dependent on its predecessor and/or successor activities. Administration type activities are typically assigned as Level of Effort. 5.1.2 Level of effort activities cannot have constraints assigned to them. So, those who wanted to constrain an LOE…Forget it! Even if you want it, it will not let you. 5.1.3 Here’s one for you. The Level of effort activity is not included when leveling resources. You might think that it plays a role when doing automatic leveling but they don’t. Only resources loaded against normal task activities are included. 5.1.4 If an activity with an Actual Start is assigned to a Level of Effort activity before being scheduled, the Original Duration of the Level of Effort will be 0. For more information on this see Oracle Primavera Solution ID: prim40131 "Why is the Level of Effort (LOE) activity showing an Original Duration (OD) of zero (0)?"
  • 5. 062813-Primavera Scheduling Tips & Tricks 02-13 Page 5 of 8 6/29/2013 Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP 5.1.5 Users should use level of effort activities for on-going tasks that depend on other activities. For example, you could assign level of effort activities for clerical work, a security guard, or even some aspects of project management. 5.1.6 A level of effort activity is similar to but different from a hammock activity. 5.1.7 A level of effort activity uses its assigned calendar to summarize its dates. Hammocks are not scheduled using their own calendar. 5.1.8 Any type of relationship can be assigned to a level of effort activity. Only a start-to-start and finish-to-finish relationship can be assigned to a hammock activity. 5.1.9 All finish to start and start to start predecessors and start to finish and start to start successors drive the start date of the LOE activity. 5.1.10 All finish-finish and start-finish predecessors and finish-start and finish-finish successors drive the finish date of the LOE activity. 5.1.11 A hammock activity's duration is calculated from the earliest early start of its predecessors to the latest early finish of its successor activities. 5.1.12 Schedule calculation of a normal activity is affected by its “Duration Type” setting (i.e. Fixed Duration and Units/Time, Fixed Duration and Units, Fixed Units/Time and Fixed Units). The work effort required to complete the activity does not change. The calculation rules do not change for an LOE activity.
  • 6. 062813-Primavera Scheduling Tips & Tricks 02-13 Page 6 of 8 6/29/2013 Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP 6.0 REFERENCES 6.1 Help, About Primavera, Project Management (Primavera), V6.1 SP1, V6.1 SP2, V6.7 SP1, V6.7 SP2 and higher. 6.2 Oracle Primavera Solution ID: 2003821145529 7.0 ADDITIONAL READING MATERIALS 7.1 Oracle Primavera Solution ID: prim40131 8.0 FOOD FOR THOUGHT 8.1 It’s been said, time and again but I will have to underline it one more time. A level of effort activity is similar to but different from a hammock activity. 8.2 The New User should practice linking the LOEs to controlling activities described in Section 5.1.9 and 5.1.10 and as demonstrated in Section 9.0 Illustrations, Figure 1 and Figure 2.
  • 7. 062813-Primavera Scheduling Tips & Tricks 02-13 Page 7 of 8 6/29/2013 Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP 9.0 ILLUSTRATIONS 9.1 Figure 1 Links that DRIVES THE START DATE of the LOE activity 9.2 Figure 2 Links that DRIVES THE FINISH DATE of the LOE activity
  • 8. 062813-Primavera Scheduling Tips & Tricks 02-13 Page 8 of 8 6/29/2013 Author: Rufran C. Frago, P. Eng., PMP, CCEC, PMI-RMP 10.0 INDEX “Duration Type” setting 5 “User” 3 ADDITIONAL READING MATERIALS 6 DEFINITION 3 FOODS FOR THOUGHT 6 hammock 6 ILLUSTATIONS 7 INDEX 8 Links that DRIVES THE FINISH DATE 7 Links that DRIVES THE START DATE 7 PROBLEM ANALYSIS 4 REFERENCES 6 RELATED TOOLS 3 resources 4 SITUATION/PROBLEM 3 SOLUTION 4 User’s understanding 4