SlideShare a Scribd company logo
1 of 8
Project Cost Management
(Module II: Project Management)
MBA(N) 3rd Semester
General Paper
Code: MB 301
What is ‘Project Cost Management’?
Project Cost Management is the process of planning and controlling
the project cost effectively. It defines what costs are required for each
deliverable.
The cost of the project can be estimated from various process sources
like
• Creating WBS
• Develop Schedule
• Plan human resources
• Identifying risks
The inputs of Project Cost management include,
• Project management plan
• Project charter
• Enterprise environmental factors
• Organizational process assets
While, the output of this is
• Cost Management Plan.
Project Cost Estimation
The Project Cost Estimation is the process of approximating the total
expenditure of the project. To estimate the cost of project you have to
categorize various cost types into categories like
• Labor cost
• Equipment cost
• Cost of supplies
• Travel cost
• Training cost
• Overhead cost, etc.
Techniques used to estimate Project Cost
Analogous Estimating: This estimating technique is based on expert
judgments and information based on similar previous projects. Where
previously done similar project cost is considered with plus or minus of 20%
for existing project.
Parametric estimating: Past data or record is used to estimate cost for the
current project.
Bottom-up estimating
Once you have defined the scope of the project, it is the most reliable form of
technique. In this technique, based on WBS, you estimate the cost for each
resource or deliverables.
Project Budget Planning
The main purpose of this activity is to allocate and authorize the monetary
resources required to complete the project. The main output for determining
the budget includes cost performance baseline. It not only specifies what cost
will be incurred but also when costs will be incurred.
The inputs for determining Project Budget includes
• Activity cost estimates
• Basis for estimates
• Scope baseline
• Project Schedule
• Resource calendars
• Contracts
• Organizational process assets
The output of this Project Budgeting process is
• Cost performance baseline
• Project funding requirements
• Project document updates
The project budgeting is performed in parallel with the project scheduling
process. It is highly dependent on three components -
• Cost estimation
• Task durations
• Allocated resources
During project budgeting, project manager communicates with different
people responsible for managing the work efforts as well as estimating
project costs. He will use various project prospects like WBS of the project, the
Cost Estimates, Historical Data and Records, Resource Information, and Policies.
Without risk assessment, the budgeting process is not completed. Risk
assessing process considers factors like time shortage, availability of
resources, development team experience, the technology used, etc. The risk
assessment can be an amount between 25 and 30 percent of the overall
project cost.
Types of Project Contract
Most of the contractual relationships are broadly categorized as either:
• Fixed-Price contract
• Cost reimbursable
• Time & Materials Contract
The third type of contract is seldom used.
1. Fixed Price Contracts:
In this category, the contract involves a fixed price for a defined product or
service or the result to be supplied/provided. These types of contracts are
recommended when the scope of service is completely defined and final.
Different Types Of Fixed Price Contracts Used In Managing Projects:
Firm Fixed Price (FFP):
The prices of the goods and services are set and are never subjected to change
unless the scope is changed and agreed mutually. This type is favorable mostly
to the buying organizations. Because the extent of buying the goods remains
unchanged and recurring buying happens.
Fixed Price Incentive Fee (FPIF):
The price ceiling is set, and the seller needs to perform and fulfill the contract
requirements within that price. All the costs above the price ceiling are the
responsibility of the seller. This type gives both the buyer and the seller some
flexibility for performance with technical incentives. The incentives are tied to
achieving agreed upon metrics such as cost, schedule and technical expertise of
the seller.
Fixed Price with Economic Price Adjustments (FPEPA):
It is suitable when the contracts are executed in different countries and
payments are made in a different currency. Also, if the seller’s work lasts for a
few years (3-5 years generally) this contract is fitting. This contract gives an
option to make adjustments in the predefined final payment as agreed to in the
contract. It can be due to changed conditions such as inflating rates (may
increase or decrease) on specific commodities.
2. Cost Reimbursable Contracts:
This type of contract involves cost reimbursement (payments to the work done)
for the costs incurred during completion of the contractual job. It is along with a
pre-defined fee representing seller profit. It is recommended if the scope of the
work is expected to change during the contract period.
This type of contract includes:
Cost Plus Fixed Fee (CPFF): The seller gets all the allowable costs agreed in the
contract. The seller also receives a fixed fee payment, which is calculated as a
percentage of initial estimated project costs. Unless the project scope changes,
this fee remains unchanged.
Cost Plus Incentive Fee (CPIF): The seller gets the reimbursements for all the
costs incurred on performing the work agreed in the contract. Based on the
final costs incurred (greater or lesser than the initial planned cost), both the
buyer and the seller share their expenses. The sharing is based upon a pre-
negotiated cost-sharing formula. Generally, it is an 80/20 split over the target
costs based on the actual performance of the seller.
Cost Plus Award Fee (CPAF): In this type, the seller gets his/her legitimate
reimbursements. But a majority of the fee is received upon meeting some
technical/subjective performance that is pre-set in the contract. This solely
depends on the buyer’s determination and the seller’s performance.
3. Time & Material Contracts (T&M):
This a hybrid type of contract combining the features of Fixed as well as Cost
Reimbursable contracts. This is often used when contractual requirements
(scope) is not known/ prescribed. Also, this type of contract is suitable for
acquisition/hiring of experts, project staff required for a particular period. It is
largely used when:
• Moderate level of certainty in the project
• Reasonable visibility towards effort and type of resources required
• Limited predictability of amount of resources required
• Moderate variability as the process, material, people required are predictable
Type of work best suited for Time & Material contract type:
Customized Software Development and staff augmentation requiring labor hire
for specific time periods.
Type of work best suited for Cost Reimbursable contract type:
Creative or innovative projects such as event décor, where you expect the
organizer to decide on the purchases and you are willing to pay for it. Media
Campaigns could also fall under this category.
Type of work best suited for Fixed Price Contract type:
Purchasing an apartment or a holiday package, off-the shelf software packages,
construction of road, etc.

More Related Content

What's hot

What's hot (18)

Project cost management
Project cost management Project cost management
Project cost management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
The basics of cost analysis ppt @ mba
The basics of cost analysis ppt @ mbaThe basics of cost analysis ppt @ mba
The basics of cost analysis ppt @ mba
 
Contract Management
Contract ManagementContract Management
Contract Management
 
Cost analysis of project
Cost analysis of projectCost analysis of project
Cost analysis of project
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
ACH 231 Lecture 05 (Design Contracts Part 1)
ACH 231 Lecture 05 (Design Contracts Part 1)ACH 231 Lecture 05 (Design Contracts Part 1)
ACH 231 Lecture 05 (Design Contracts Part 1)
 
Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on Procurement
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement Strategies
 
Cost Analysis and Control
Cost Analysis and ControlCost Analysis and Control
Cost Analysis and Control
 
Procurment Management
Procurment ManagementProcurment Management
Procurment Management
 
Contract Administration Presentation
Contract Administration PresentationContract Administration Presentation
Contract Administration Presentation
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Contract management
Contract managementContract management
Contract management
 
Project Cost Management
Project Cost Management Project Cost Management
Project Cost Management
 
Managing contracts
Managing contractsManaging contracts
Managing contracts
 

Similar to Project Cost Management_

con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
EXPLANATION-FOR-EVERY-SLIDE-IN-PROCUREMENT-AND-PROJ-INTEGRATION.pptx
EXPLANATION-FOR-EVERY-SLIDE-IN-PROCUREMENT-AND-PROJ-INTEGRATION.pptxEXPLANATION-FOR-EVERY-SLIDE-IN-PROCUREMENT-AND-PROJ-INTEGRATION.pptx
EXPLANATION-FOR-EVERY-SLIDE-IN-PROCUREMENT-AND-PROJ-INTEGRATION.pptxDanicaCombalicerCabl
 
What is feasibility study and what is contracts and its type
What is feasibility study and what is contracts and its typeWhat is feasibility study and what is contracts and its type
What is feasibility study and what is contracts and its typeAdil Mehmoood
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxbjohn46
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
Project Management 2nd assignment
Project Management 2nd assignmentProject Management 2nd assignment
Project Management 2nd assignmentDanish Saqi
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptxAberraBeri
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxtienmixon
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 ProjectManagementDocs.comProcurement Management Plan Temp.docx ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxgertrudebellgrove
 
Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015SONU61709
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimatesnagashree123
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web readySumit Gupta
 
Pm0012 project finance and budgeting
Pm0012   project finance and budgetingPm0012   project finance and budgeting
Pm0012 project finance and budgetingsmumbahelp
 

Similar to Project Cost Management_ (20)

Contract Negotiations
Contract NegotiationsContract Negotiations
Contract Negotiations
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
EXPLANATION-FOR-EVERY-SLIDE-IN-PROCUREMENT-AND-PROJ-INTEGRATION.pptx
EXPLANATION-FOR-EVERY-SLIDE-IN-PROCUREMENT-AND-PROJ-INTEGRATION.pptxEXPLANATION-FOR-EVERY-SLIDE-IN-PROCUREMENT-AND-PROJ-INTEGRATION.pptx
EXPLANATION-FOR-EVERY-SLIDE-IN-PROCUREMENT-AND-PROJ-INTEGRATION.pptx
 
9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
 
What is feasibility study and what is contracts and its type
What is feasibility study and what is contracts and its typeWhat is feasibility study and what is contracts and its type
What is feasibility study and what is contracts and its type
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
 
Project contracts
Project contractsProject contracts
Project contracts
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Project Management 2nd assignment
Project Management 2nd assignmentProject Management 2nd assignment
Project Management 2nd assignment
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptx
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 ProjectManagementDocs.comProcurement Management Plan Temp.docx ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 
Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web ready
 
Pm0012 project finance and budgeting
Pm0012   project finance and budgetingPm0012   project finance and budgeting
Pm0012 project finance and budgeting
 

More from Siliguri Institute of Technology ( A unit of Techno India Group)

More from Siliguri Institute of Technology ( A unit of Techno India Group) (13)

IS-LM model
IS-LM modelIS-LM model
IS-LM model
 
Economics of Demand & Supply
Economics of Demand & SupplyEconomics of Demand & Supply
Economics of Demand & Supply
 
Consumer Surplus & Producer Surplus
Consumer Surplus & Producer SurplusConsumer Surplus & Producer Surplus
Consumer Surplus & Producer Surplus
 
Break Even Analysis
Break Even AnalysisBreak Even Analysis
Break Even Analysis
 
Banking Operations
Banking OperationsBanking Operations
Banking Operations
 
Basics of Optimization Theory
Basics of Optimization Theory Basics of Optimization Theory
Basics of Optimization Theory
 
Multiplier Theory in Economics
Multiplier Theory in EconomicsMultiplier Theory in Economics
Multiplier Theory in Economics
 
Break even analysis_Numerical
Break even analysis_NumericalBreak even analysis_Numerical
Break even analysis_Numerical
 
Game Theory Economics
Game Theory EconomicsGame Theory Economics
Game Theory Economics
 
Economic Optimization Numerical
Economic Optimization NumericalEconomic Optimization Numerical
Economic Optimization Numerical
 
Constrained Optimization
Constrained OptimizationConstrained Optimization
Constrained Optimization
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 

Recently uploaded

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 

Recently uploaded (20)

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 

Project Cost Management_

  • 1. Project Cost Management (Module II: Project Management) MBA(N) 3rd Semester General Paper Code: MB 301
  • 2. What is ‘Project Cost Management’? Project Cost Management is the process of planning and controlling the project cost effectively. It defines what costs are required for each deliverable. The cost of the project can be estimated from various process sources like • Creating WBS • Develop Schedule • Plan human resources • Identifying risks The inputs of Project Cost management include, • Project management plan • Project charter • Enterprise environmental factors • Organizational process assets While, the output of this is • Cost Management Plan.
  • 3. Project Cost Estimation The Project Cost Estimation is the process of approximating the total expenditure of the project. To estimate the cost of project you have to categorize various cost types into categories like • Labor cost • Equipment cost • Cost of supplies • Travel cost • Training cost • Overhead cost, etc. Techniques used to estimate Project Cost Analogous Estimating: This estimating technique is based on expert judgments and information based on similar previous projects. Where previously done similar project cost is considered with plus or minus of 20% for existing project. Parametric estimating: Past data or record is used to estimate cost for the current project. Bottom-up estimating Once you have defined the scope of the project, it is the most reliable form of technique. In this technique, based on WBS, you estimate the cost for each resource or deliverables.
  • 4. Project Budget Planning The main purpose of this activity is to allocate and authorize the monetary resources required to complete the project. The main output for determining the budget includes cost performance baseline. It not only specifies what cost will be incurred but also when costs will be incurred. The inputs for determining Project Budget includes • Activity cost estimates • Basis for estimates • Scope baseline • Project Schedule • Resource calendars • Contracts • Organizational process assets The output of this Project Budgeting process is • Cost performance baseline • Project funding requirements • Project document updates The project budgeting is performed in parallel with the project scheduling process. It is highly dependent on three components - • Cost estimation • Task durations • Allocated resources
  • 5. During project budgeting, project manager communicates with different people responsible for managing the work efforts as well as estimating project costs. He will use various project prospects like WBS of the project, the Cost Estimates, Historical Data and Records, Resource Information, and Policies. Without risk assessment, the budgeting process is not completed. Risk assessing process considers factors like time shortage, availability of resources, development team experience, the technology used, etc. The risk assessment can be an amount between 25 and 30 percent of the overall project cost. Types of Project Contract Most of the contractual relationships are broadly categorized as either: • Fixed-Price contract • Cost reimbursable • Time & Materials Contract The third type of contract is seldom used. 1. Fixed Price Contracts: In this category, the contract involves a fixed price for a defined product or service or the result to be supplied/provided. These types of contracts are recommended when the scope of service is completely defined and final.
  • 6. Different Types Of Fixed Price Contracts Used In Managing Projects: Firm Fixed Price (FFP): The prices of the goods and services are set and are never subjected to change unless the scope is changed and agreed mutually. This type is favorable mostly to the buying organizations. Because the extent of buying the goods remains unchanged and recurring buying happens. Fixed Price Incentive Fee (FPIF): The price ceiling is set, and the seller needs to perform and fulfill the contract requirements within that price. All the costs above the price ceiling are the responsibility of the seller. This type gives both the buyer and the seller some flexibility for performance with technical incentives. The incentives are tied to achieving agreed upon metrics such as cost, schedule and technical expertise of the seller. Fixed Price with Economic Price Adjustments (FPEPA): It is suitable when the contracts are executed in different countries and payments are made in a different currency. Also, if the seller’s work lasts for a few years (3-5 years generally) this contract is fitting. This contract gives an option to make adjustments in the predefined final payment as agreed to in the contract. It can be due to changed conditions such as inflating rates (may increase or decrease) on specific commodities.
  • 7. 2. Cost Reimbursable Contracts: This type of contract involves cost reimbursement (payments to the work done) for the costs incurred during completion of the contractual job. It is along with a pre-defined fee representing seller profit. It is recommended if the scope of the work is expected to change during the contract period. This type of contract includes: Cost Plus Fixed Fee (CPFF): The seller gets all the allowable costs agreed in the contract. The seller also receives a fixed fee payment, which is calculated as a percentage of initial estimated project costs. Unless the project scope changes, this fee remains unchanged. Cost Plus Incentive Fee (CPIF): The seller gets the reimbursements for all the costs incurred on performing the work agreed in the contract. Based on the final costs incurred (greater or lesser than the initial planned cost), both the buyer and the seller share their expenses. The sharing is based upon a pre- negotiated cost-sharing formula. Generally, it is an 80/20 split over the target costs based on the actual performance of the seller. Cost Plus Award Fee (CPAF): In this type, the seller gets his/her legitimate reimbursements. But a majority of the fee is received upon meeting some technical/subjective performance that is pre-set in the contract. This solely depends on the buyer’s determination and the seller’s performance.
  • 8. 3. Time & Material Contracts (T&M): This a hybrid type of contract combining the features of Fixed as well as Cost Reimbursable contracts. This is often used when contractual requirements (scope) is not known/ prescribed. Also, this type of contract is suitable for acquisition/hiring of experts, project staff required for a particular period. It is largely used when: • Moderate level of certainty in the project • Reasonable visibility towards effort and type of resources required • Limited predictability of amount of resources required • Moderate variability as the process, material, people required are predictable Type of work best suited for Time & Material contract type: Customized Software Development and staff augmentation requiring labor hire for specific time periods. Type of work best suited for Cost Reimbursable contract type: Creative or innovative projects such as event décor, where you expect the organizer to decide on the purchases and you are willing to pay for it. Media Campaigns could also fall under this category. Type of work best suited for Fixed Price Contract type: Purchasing an apartment or a holiday package, off-the shelf software packages, construction of road, etc.