SlideShare a Scribd company logo
1 of 15
Definitive
Estimation
Design/Engineering
Stage
Conceptual
Estimation
Detailed
Estimation
Conceptual
Stage
Execution
Phase
Project
Budget
Fair Cost
Estimation
Cost
Planning
Basic
for
Cost
Control
Feedback
Estimate
Class
Project Definition
(% of complete
definition)
End Usage (typical
purpose of estimate)
Methodology (typical
estimating method)
Accuracy Range (%
of variation in low
and high ranges) [a]
Preparation Effor
(index relative to
project cost)[b]
Class 5 0 -2 Concept screening Capacity factored, parametric
models, judgment or analogy
L: -20 to -50H: 30 to
100
1
Class 4 1-15 Study or feasibility Equipment factor and
parametric model
L:-15 to -30H: 20 to
50
2 to 4
Class 3 10-40 Budget authorization or
cost control
Semi-detailed unit cost with
assembly level line items
L:-10 to -20H: 10 to
30
3 to 10
Class 2 30-70 Control of bid or tender Detailed unit cost with forced
detailed take off
L:-5 to -15H: 5 t0 20 4 to 20
Class 1 50-100 Check estimate, bid or
tender
Detailed unit cost with
detailed take off
L:-3 to -10H: 3 to 15 5 to 100
The preparation of the first estimate, CCE would be
based on a variety of techniques, for example, historic
data or approximate quantities. When the client has
accepted the first estimate and instructs that the project
proceed to the next stage, then this becomes the first
cost plan against which further design developments
and changes are monitored.
During the process of design development the main duties of
the QS as part of the cost management team are as follows:
a) To check and report the cost of design solutions as they
are established or refined by the engineers
b) To prepare comparative estimates of various design
solutions or alternatives and advise the engineer
accordingly
c) As changes are introduced into the project, to estimate the
cost effect of the change and to report
Cost
Estimation
Project
Information
Current
Data
Data
Estimating
Methodology
Historical
Data
Cost
Estimator
Output
a) Project Information: the information about the current project,
including project scope and major building characteristics (such as
type and use)
b) Historical Data: the cost data for historical project and their building
characteristics
c) Current Data: the unit cost and rate (for material, labor, and
equipment), historical cost indices, and other items
d) Estimating Methodology: the method used for estimation, including
single-unit rate method, parametric cost modeling methods and
system/elemental cost analysis
e) Cost Estimator: the user who employs all the other element in
making an estimation and applying judgments during the estimating
process
Before the analysis can begin, the project costs need
to be adjusted or normalized (Ji et al., 2010;
Phaobunjong, 2002). Relevant data is extracted from
historical project cost. The data that are needed for
adjustment are a city cost index to quantity the
variability in project cost due to inflation (Sonmez,
2004).
Cost index are fundamental to cost planning since they provide a valuable
insight into changes in the cost of an item or group of items from one point
in time to another (time series). According to Ferry et al. (2010),
Consumer price index (CPI) can represents the ratio of exchange between
money and a basket of consumer goods. CPI published by Statistic
Indonesia (Badan Pusat Statistik, BPS) is a statistical estimate constructed
using the prices of a sample of representative items (goods and services)
whose prices are collected periodically. Construction cost index (CCI;
indek kemahalan konstruksi) that also published by BPS is more
appropriate to used because an indicator of the average cost movement
over time of a fixed basket of representative goods and services related to
construction industry. Moreover, CCI was deemed more suitable in the
sense that it more reflects price changes in construction
Dimana:
Cj = Cost at location j
Ci = Cost at location i
Regency/City 2010 2011 2012 2013 2014 2015
Kab Kepulauan Mentawai 111.73 112.88 176.09 187.76 181.95 162.9
Kab Pesisir Selatan 92 91.10 94.74 95.23 95.86 99.21
Kab Solok 85.38 87.10 85.45 91.63 92.31 94.71
Kab Sawahlunto/Sijunjung 87.47 85.82 96.54 101.39 101.48 92.82
Kab Tanah Datar 84.68 86.23 88.11 95.16 95.3 90.43
Kab Padang Pariaman 84.95 86.39 91.72 102.49 100.40 91.18
Kab Agam 88.34 92.31 98.68 97.44 99.60 91.44
Kab Lima Puluh Koto 85.42 84.22 94.51 96.41 98.96 87.74
Kab Pasaman 85.76 85.60 86.71 98.37 96.07 88.22
Kab Solok Selatan 85.97 84.13 80.92 98.05 95.25 101.97
Kab Dhamasraya 86.82 83.51 86.78 94.00 96.78 91.44
Kab Pasaman Barat 90.63 90.02 92.99 95.18 99.08 101.29
Kota Padang 82.83 84.10 104.82 101.94 100.68 97.27
Kota Solok 85.08 84.42 91.41 99.56 96.45 101.51
Kota Sawah Lunto 85.47 83.86 80.56 93.49 91.55 95.42
Kota Padang Panjang 86.02 84.75 87.05 98.32 97.16 98.01
Kota Bukittinggi 86.93 88.83 94.71 100.28 99.05 94.04
Kota Payakumbuh 84.9 84.86 88.71 98.05 99.08 88.33
Kota Pariaman 83.21 82.90 89.82 95.7 89.96 96.78
In economics, inflation is a sustained increase in the general price level of
goods and services in an economy over a period of time ( Blanchard, 2000).
Inflation affects economies in various positive and negative ways. The
negative effects of inflation include an increase in the opprtunity cost of
holding money, uncertainty over future inflation which may discourage
investment and savings, and if inflation were rapid enough, shortages of
goods as consumers begin hoarding out of concern that prices will increase
in the future. Positive effects include reducing the real burden of public and
private debt, keeping nominal interest rates above zero so that central banks
can adjust interest rates to stabilize the economy, and reducing
unemployment due to nominal wage rigidity (Mankiw, 2002).
Year Inflation (%)
2006 8.05
2007 6.90
2008 12.68
2009 2.05
2010 7.84
2011 5.37
2012 4.16
2013 10.87
2014 11.90
2015 12.74
To convert cost from one time (year) to another
year, the following formula was used
conceptual estimate

More Related Content

What's hot

Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 
Ici qs
Ici qsIci qs
Ici qsGynie
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment마 이환
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentationmasonsth
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-projecthlksd
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and EstimationGide India
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningGalala University
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentationcynfang Fong
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)Jy Chong
 

What's hot (20)

Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Tender
TenderTender
Tender
 
Ici qs
Ici qsIci qs
Ici qs
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentation
 
Quantity take off
Quantity take offQuantity take off
Quantity take off
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-project
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
 
Aiab089228
Aiab089228Aiab089228
Aiab089228
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
jeremiah lukwesa kaluba
jeremiah lukwesa kalubajeremiah lukwesa kaluba
jeremiah lukwesa kaluba
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost Planning
 
Qsx
QsxQsx
Qsx
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 

Similar to conceptual estimate

Similar to conceptual estimate (20)

Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
Cost studies model_answers_2014_jan
Cost studies model_answers_2014_janCost studies model_answers_2014_jan
Cost studies model_answers_2014_jan
 
Final Benchmarking Presentation (DSC)
Final Benchmarking Presentation (DSC)Final Benchmarking Presentation (DSC)
Final Benchmarking Presentation (DSC)
 
Economic Surplus Model
Economic Surplus ModelEconomic Surplus Model
Economic Surplus Model
 
Credit Seminar
Credit SeminarCredit Seminar
Credit Seminar
 
Cost managment
Cost managmentCost managment
Cost managment
 
Concept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyConcept of Value Engineering with Case Study
Concept of Value Engineering with Case Study
 
Economic incentieves and water demand mamangent 2
Economic incentieves and water demand mamangent 2Economic incentieves and water demand mamangent 2
Economic incentieves and water demand mamangent 2
 
Costing
CostingCosting
Costing
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
Thesis proposal
Thesis proposalThesis proposal
Thesis proposal
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
 
MG6863-Unit-1.pdf
MG6863-Unit-1.pdfMG6863-Unit-1.pdf
MG6863-Unit-1.pdf
 
Eca workshop
Eca workshopEca workshop
Eca workshop
 
Ecv
EcvEcv
Ecv
 
Lecture2
Lecture2Lecture2
Lecture2
 
Lecture2
Lecture2Lecture2
Lecture2
 

Recently uploaded

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

conceptual estimate

  • 1.
  • 3. Estimate Class Project Definition (% of complete definition) End Usage (typical purpose of estimate) Methodology (typical estimating method) Accuracy Range (% of variation in low and high ranges) [a] Preparation Effor (index relative to project cost)[b] Class 5 0 -2 Concept screening Capacity factored, parametric models, judgment or analogy L: -20 to -50H: 30 to 100 1 Class 4 1-15 Study or feasibility Equipment factor and parametric model L:-15 to -30H: 20 to 50 2 to 4 Class 3 10-40 Budget authorization or cost control Semi-detailed unit cost with assembly level line items L:-10 to -20H: 10 to 30 3 to 10 Class 2 30-70 Control of bid or tender Detailed unit cost with forced detailed take off L:-5 to -15H: 5 t0 20 4 to 20 Class 1 50-100 Check estimate, bid or tender Detailed unit cost with detailed take off L:-3 to -10H: 3 to 15 5 to 100
  • 4. The preparation of the first estimate, CCE would be based on a variety of techniques, for example, historic data or approximate quantities. When the client has accepted the first estimate and instructs that the project proceed to the next stage, then this becomes the first cost plan against which further design developments and changes are monitored.
  • 5. During the process of design development the main duties of the QS as part of the cost management team are as follows: a) To check and report the cost of design solutions as they are established or refined by the engineers b) To prepare comparative estimates of various design solutions or alternatives and advise the engineer accordingly c) As changes are introduced into the project, to estimate the cost effect of the change and to report
  • 7. a) Project Information: the information about the current project, including project scope and major building characteristics (such as type and use) b) Historical Data: the cost data for historical project and their building characteristics c) Current Data: the unit cost and rate (for material, labor, and equipment), historical cost indices, and other items d) Estimating Methodology: the method used for estimation, including single-unit rate method, parametric cost modeling methods and system/elemental cost analysis e) Cost Estimator: the user who employs all the other element in making an estimation and applying judgments during the estimating process
  • 8. Before the analysis can begin, the project costs need to be adjusted or normalized (Ji et al., 2010; Phaobunjong, 2002). Relevant data is extracted from historical project cost. The data that are needed for adjustment are a city cost index to quantity the variability in project cost due to inflation (Sonmez, 2004).
  • 9. Cost index are fundamental to cost planning since they provide a valuable insight into changes in the cost of an item or group of items from one point in time to another (time series). According to Ferry et al. (2010), Consumer price index (CPI) can represents the ratio of exchange between money and a basket of consumer goods. CPI published by Statistic Indonesia (Badan Pusat Statistik, BPS) is a statistical estimate constructed using the prices of a sample of representative items (goods and services) whose prices are collected periodically. Construction cost index (CCI; indek kemahalan konstruksi) that also published by BPS is more appropriate to used because an indicator of the average cost movement over time of a fixed basket of representative goods and services related to construction industry. Moreover, CCI was deemed more suitable in the sense that it more reflects price changes in construction
  • 10. Dimana: Cj = Cost at location j Ci = Cost at location i
  • 11. Regency/City 2010 2011 2012 2013 2014 2015 Kab Kepulauan Mentawai 111.73 112.88 176.09 187.76 181.95 162.9 Kab Pesisir Selatan 92 91.10 94.74 95.23 95.86 99.21 Kab Solok 85.38 87.10 85.45 91.63 92.31 94.71 Kab Sawahlunto/Sijunjung 87.47 85.82 96.54 101.39 101.48 92.82 Kab Tanah Datar 84.68 86.23 88.11 95.16 95.3 90.43 Kab Padang Pariaman 84.95 86.39 91.72 102.49 100.40 91.18 Kab Agam 88.34 92.31 98.68 97.44 99.60 91.44 Kab Lima Puluh Koto 85.42 84.22 94.51 96.41 98.96 87.74 Kab Pasaman 85.76 85.60 86.71 98.37 96.07 88.22 Kab Solok Selatan 85.97 84.13 80.92 98.05 95.25 101.97 Kab Dhamasraya 86.82 83.51 86.78 94.00 96.78 91.44 Kab Pasaman Barat 90.63 90.02 92.99 95.18 99.08 101.29 Kota Padang 82.83 84.10 104.82 101.94 100.68 97.27 Kota Solok 85.08 84.42 91.41 99.56 96.45 101.51 Kota Sawah Lunto 85.47 83.86 80.56 93.49 91.55 95.42 Kota Padang Panjang 86.02 84.75 87.05 98.32 97.16 98.01 Kota Bukittinggi 86.93 88.83 94.71 100.28 99.05 94.04 Kota Payakumbuh 84.9 84.86 88.71 98.05 99.08 88.33 Kota Pariaman 83.21 82.90 89.82 95.7 89.96 96.78
  • 12. In economics, inflation is a sustained increase in the general price level of goods and services in an economy over a period of time ( Blanchard, 2000). Inflation affects economies in various positive and negative ways. The negative effects of inflation include an increase in the opprtunity cost of holding money, uncertainty over future inflation which may discourage investment and savings, and if inflation were rapid enough, shortages of goods as consumers begin hoarding out of concern that prices will increase in the future. Positive effects include reducing the real burden of public and private debt, keeping nominal interest rates above zero so that central banks can adjust interest rates to stabilize the economy, and reducing unemployment due to nominal wage rigidity (Mankiw, 2002).
  • 13. Year Inflation (%) 2006 8.05 2007 6.90 2008 12.68 2009 2.05 2010 7.84 2011 5.37 2012 4.16 2013 10.87 2014 11.90 2015 12.74
  • 14. To convert cost from one time (year) to another year, the following formula was used