SlideShare a Scribd company logo
1 of 15
Download to read offline
Sheet1ActivityWork (hours)Resource NameLabor RateLabor
CostsMaterial CostsTravel CostsFacility CostsSubcontractor
CostsTotal Costs
Cost Management
235-AAH-CH
Professor: Behn Nikkhah
CLASS 3&4
2
3
Cost Estimation
Estimating project costs are important because:
• Can be used in feasibility study before starting the
project.
• It can facilitate decisions regarding project
financing and funding.
• It provides a standard against which actual costs
incurred during the execution can be compared.
• It gives the project manager a framework to
allocate scarce resources throughout the project.
4
Cost Estimation
This is a process of estimating the cost of the resources
required for each scheduled activity.
It is important to be certain to include all the costs
required to complete the work of the project.
5
Estimate Costs Inputs
• Project Management Plan (Cost management plan,
Quality Management Plan, Scope baseline)
• Project Documents (Lessons learned register, Project
schedule, resource requirements, Risk register)
• Enterprise environmental factors
• Organizational process assets.
6
Estimate Costs Inputs
Scope Baseline:
• Project scope statement
• WBS
• WBS dictionary
Project scope statement is a document that includes key
deliverables, constraints, assumptions, etc.
Constraints such as limited budget for the project can be
find in this document. There might be other constraints such
as delivery date that can impact the cost.
Project assumptions regarding costs might include
information regarding indirect costs in the estimate.
7
Estimate Costs Inputs
The WBS serves as the basis for estimating costs, as it includes
all
deliverables and the control accounts that are typically
established at the work package level.
The WBS dictionary describes the deliverables, work
components, and other elements of the WBS.
All these information can be helpful in estimation of the costs.
For example if one of the deliverables is to get licenses you
need
to see that as additional expenses to fulfill in the estimation.
8
Estimate Costs Inputs
The Project schedule along with the resource requirements for
each activity are key inputs in estimating costs of the project.t
You need to be aware of the duration as it can affect costs.
For example, you must account for costs such as interest
charges in a financed work of the project.
Another example is fluctuation in costs that can occur due to
seasonal or holiday demands.
9
Estimate Costs Inputs
The risk register contains the response plans, particularly for
those risks with negative impacts to the project.
When developing project cost estimates, you should consider
the cost of implementing risk response plans.
10
Estimate Costs Inputs
The enterprise environmental factors such as market conditions,
exchange rates and inflation are examples to be considered in
the project costs estimation.
The organization process assets such as lessons learned on
previous projects of similar scope and complexity can be useful
in determining estimates for the current project.
11
Tools and Techniques to Estimate Costs
The majority of these are also tools and techniques of the
estimate activity durations process used to determine schedule
estimates:
• Expert judgement
• Analogous estimating
• Parametric estimating
• Bottom-up estimating
• Three-point estimating
• Reserve analysis
• Project management information system
• Decision making (voting)
12
Cost Estimation
The total project cost is often estimated during the initiating
phase of the project and be indicated in the project charter.
However detailed plans are not usually prepared at the initiating
phase.
The detailed estimation can include the following elements:
Labor costs
Material costs
Equipment costs
Facilities costs
Subcontractor costs
Travel costs
Reserve
13
Labor costs
These are the estimated costs for the various types of human
resources who are expected to work on the project
Example, painters, developers, designers, general labor.
The labor costs are based on the estimated work time (not
necessary activity duration)
Activity may have one day as its duration, but it requires 2
hours
of work.
14
Material costs
It includes the estimated costs of materials that the project team
or contractors need to purchase for the project, such as paint,
lumber, pipes, cables, paper, food, software.
15
Equipment costs
A project may need a piece of equipment to be purchased.
Equipment can include items such as computers and
machinery.
For example, a project of upgrading a manufacturing facility
may include the purchase of new machinery
16
Facilities costs
Some projects may need special facilities or additional place for
the project team, for safety and security reasons, to store
materials, to assemble, or to test the project deliverables or
final
product.
For example cost of renting a place to store materials required
for the project is a facility cost.
17
Subcontractors costs
In a project your project team may not have expertise or
resources to do certain project tasks. In such case you may
outsource some of the work to subcontractors or consultants to
perform those activities.
For example you can have a subcontractor for a catering
activities.
18
Travel costs
If travel other than local travel is required during the project,
the
costs of airfare, lodging, and meals need to be seen under this
category.
19
Reserve
Contingencies to cover unexpected situations that may come
up during the project. It will be discussed later.
20
Cost Estimation
Now the question is “who is responsible for performing cost
estimation?”
It is a good practice to assign the person who will be
responsible
to do a task estimate the costs associated with it, as it can
generating commitment from the person and avoids the bias of
having one person doing all estimations.
In large projects which may take several years, it is not
practical
and possible to have each person or team estimate activity
costs.
21
Estimate Activity Costs
The estimated costs for an activity should be reasonable and
realistic.
If estimates become over conservative, the total costs for the
project is probably more than the budget of the sponsor or
customer.
In contrast, being very optimistic may cause cost overrun and
unexpected expenditure come up.
22
Estimate Activity Costs
In large project it is more practical to have contractors or
departments who are responsible for a work package to
estimate the costs of the work.
If an organization or contract has performed similar projects in
the past and has kept records of the actual costs, these
historical data can be used in cost estimation.
23
Determine Project Budget
Cost estimation and project budgeting are inseparably linked.
The project budget is determined by aggregating the estimated
costs for all the activities.
The project budgeting process involves two steps:
• Determine the total budgeted cost
• Develop a time-phased budget
24
Develop the total budgeted cost
The total budgeted cost is the aggregate amount of the
estimated costs of all the specific activities to perform and
complete the project (based on a WBS)
This is also referred to as budget at completion (BAC).
WBS with
work
package
budgets
25
26
Develop Cumulative Budgeted Cost
Once you determine the BAC, the second step is to distribute
budgeted cost for each work package over the expected time
span of its work package.
By performing that, a time-phased budget is created so that it
can be determined how much of the budget should have been
spent at any point in time (Planned value in EVM)
27
Example: Network Diagram
28
Example: distribute the budget
29
Example: Budgeted cost by period for the packaging
machine
30
Develop Cumulative Budgeted Cost
Once you determine the BAC, the second step is to distribute
budgeted cost for each work package over the expected time
span of its work package.
By performing that, a time-phased budget is created so that it
can be determined how much of the budget should have been
spent at any point in time (Planned value in EVM)
31
Cumulative budgeted cost curve
With the planned value
(cumulative budget cost), PV
curve can be drawn to
illustrate budgeted
expenditure over the
duration of the project
32
The importance of project cost
management
Two of the most important documents project
managers prepare for any project are the project
schedule and project budget.
These two documents will be used throughout the
executing and monitoring and controlling process
33
Cost Baseline
The cumulative budgeted cost for the entire project
provide a baseline against which actual cost and work
performance can be compared during the project.
For big projects that involves lots of activities, project
management software assist the project budgeting.
34
Actual Cost
To record and keep track of actual cost on a project, it
is necessary to establish a system to collect data on
costs expended on a regular and timely basis.
In many project weekly timesheets are used to collect
actual labor hours.
Workers working on the project fill it out with the
number of the work packages on which they worked
and the amount of hours they spend on each.
35
Committed Costs
Committed costs are amount of money that have
been beholden for an item that has been ordered or
purchases but not yet paid for.
Committed costs are not available to be spend
elsewhere on the project as they will be needed later.
For example you hire a contractor to fix your home
plumbing for $2,000. you have committed $2,000, even
though you may not actually pay until the work is
finished.
36
Committed Costs
Committed amount need to be set aside and be
treated in a special way.
To permit a realistic comparison of actual cost to
cumulative budgeted cost (PV), percentage of
committed costs should be assigned to actual cost
while the work is being performed (as it is like progress
payments), rather than waiting till it is finished and
convert it to actual costs.
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx

More Related Content

Similar to Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx

Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Project and process engineering management industrial engineering management
Project and process engineering management industrial engineering managementProject and process engineering management industrial engineering management
Project and process engineering management industrial engineering managementLuis Cabrera
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
Cost management
Cost managementCost management
Cost managementshkadry
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educCicelyBourqueju
 
1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educChantellPantoja184
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
This is a two step process.First write a one-page paper in which
This is a two step process.First write a one-page paper in whichThis is a two step process.First write a one-page paper in which
This is a two step process.First write a one-page paper in whichGrazynaBroyles24
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptxAberraBeri
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01Amy Roman
 
1.7 project management
1.7 project management1.7 project management
1.7 project managementexemplar2401
 
Lecture 3 Project Management.ppt
Lecture 3 Project Management.pptLecture 3 Project Management.ppt
Lecture 3 Project Management.pptMehediHasan636262
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 

Similar to Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx (20)

Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Project and process engineering management industrial engineering management
Project and process engineering management industrial engineering managementProject and process engineering management industrial engineering management
Project and process engineering management industrial engineering management
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
 
Cost management
Cost managementCost management
Cost management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ
 
1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
This is a two step process.First write a one-page paper in which
This is a two step process.First write a one-page paper in whichThis is a two step process.First write a one-page paper in which
This is a two step process.First write a one-page paper in which
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptx
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
 
Project Mangement
Project MangementProject Mangement
Project Mangement
 
Lecture 3 Project Management.ppt
Lecture 3 Project Management.pptLecture 3 Project Management.ppt
Lecture 3 Project Management.ppt
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 

More from bjohn46

Sheet1Risk Register for the Recreation and Wellness Internet Proje.docx
Sheet1Risk Register for the Recreation and Wellness Internet Proje.docxSheet1Risk Register for the Recreation and Wellness Internet Proje.docx
Sheet1Risk Register for the Recreation and Wellness Internet Proje.docxbjohn46
 
Sheet1RegionProduct TypeItemProjected Sales 2022 (in millions)Proj.docx
Sheet1RegionProduct TypeItemProjected Sales 2022 (in millions)Proj.docxSheet1RegionProduct TypeItemProjected Sales 2022 (in millions)Proj.docx
Sheet1RegionProduct TypeItemProjected Sales 2022 (in millions)Proj.docxbjohn46
 
Sheet1REQUIREMENTS TRACEABILITY MATRIXProject Name Outsourcing pr.docx
Sheet1REQUIREMENTS TRACEABILITY MATRIXProject Name Outsourcing pr.docxSheet1REQUIREMENTS TRACEABILITY MATRIXProject Name Outsourcing pr.docx
Sheet1REQUIREMENTS TRACEABILITY MATRIXProject Name Outsourcing pr.docxbjohn46
 
Sheet1Purchase Price$ 110,000Recovery Period 7yearsSalvage Value.docx
Sheet1Purchase Price$   110,000Recovery Period 7yearsSalvage Value.docxSheet1Purchase Price$   110,000Recovery Period 7yearsSalvage Value.docx
Sheet1Purchase Price$ 110,000Recovery Period 7yearsSalvage Value.docxbjohn46
 
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docx
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docxSheet1Rate your skills using the following scaleChapter 1 You Ma.docx
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docxbjohn46
 
Sheet1QuarterRegionCityProductRevenueQ1EastBostonMaple34333Q1EastB.docx
Sheet1QuarterRegionCityProductRevenueQ1EastBostonMaple34333Q1EastB.docxSheet1QuarterRegionCityProductRevenueQ1EastBostonMaple34333Q1EastB.docx
Sheet1QuarterRegionCityProductRevenueQ1EastBostonMaple34333Q1EastB.docxbjohn46
 
Sheet1Quarter Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
Sheet1Quarter Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docxSheet1Quarter Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
Sheet1Quarter Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docxbjohn46
 
Sheet1Question 1A. TotalsActualBudgetedVarianceFavorableUnfavorab.docx
Sheet1Question 1A. TotalsActualBudgetedVarianceFavorableUnfavorab.docxSheet1Question 1A. TotalsActualBudgetedVarianceFavorableUnfavorab.docx
Sheet1Question 1A. TotalsActualBudgetedVarianceFavorableUnfavorab.docxbjohn46
 
Sheet1project codeproject nameEmployeesQB280001Account Management .docx
Sheet1project codeproject nameEmployeesQB280001Account Management .docxSheet1project codeproject nameEmployeesQB280001Account Management .docx
Sheet1project codeproject nameEmployeesQB280001Account Management .docxbjohn46
 
Sheet1PROJECT NAMEProject ManagerPhoneProject SponsorPhoneCustome.docx
Sheet1PROJECT NAMEProject ManagerPhoneProject SponsorPhoneCustome.docxSheet1PROJECT NAMEProject ManagerPhoneProject SponsorPhoneCustome.docx
Sheet1PROJECT NAMEProject ManagerPhoneProject SponsorPhoneCustome.docxbjohn46
 
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docxSheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docxbjohn46
 
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docxSheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docxbjohn46
 
Sheet1PMGT 576 Assignment Rubric – Unit 8 Assignment20Is the Lean .docx
Sheet1PMGT 576 Assignment Rubric – Unit 8 Assignment20Is the Lean .docxSheet1PMGT 576 Assignment Rubric – Unit 8 Assignment20Is the Lean .docx
Sheet1PMGT 576 Assignment Rubric – Unit 8 Assignment20Is the Lean .docxbjohn46
 
Sheet1Primordial PreventionPrimary PreventionSecondary PreventionT.docx
Sheet1Primordial PreventionPrimary PreventionSecondary PreventionT.docxSheet1Primordial PreventionPrimary PreventionSecondary PreventionT.docx
Sheet1Primordial PreventionPrimary PreventionSecondary PreventionT.docxbjohn46
 
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docxSheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docxbjohn46
 
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docxSheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docxbjohn46
 
Sheet1PMGT 576 Assignment Rubric – Unit 7 Assignment20Are all of t.docx
Sheet1PMGT 576 Assignment Rubric – Unit 7 Assignment20Are all of t.docxSheet1PMGT 576 Assignment Rubric – Unit 7 Assignment20Are all of t.docx
Sheet1PMGT 576 Assignment Rubric – Unit 7 Assignment20Are all of t.docxbjohn46
 
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docxSheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docxbjohn46
 
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docx
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docxSheet1Phase of Business Financal Management needsDebt FinancingEq.docx
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docxbjohn46
 
Sheet1phonessaturatedanimaldeaths124338814931655181388804172242220.docx
Sheet1phonessaturatedanimaldeaths124338814931655181388804172242220.docxSheet1phonessaturatedanimaldeaths124338814931655181388804172242220.docx
Sheet1phonessaturatedanimaldeaths124338814931655181388804172242220.docxbjohn46
 

More from bjohn46 (20)

Sheet1Risk Register for the Recreation and Wellness Internet Proje.docx
Sheet1Risk Register for the Recreation and Wellness Internet Proje.docxSheet1Risk Register for the Recreation and Wellness Internet Proje.docx
Sheet1Risk Register for the Recreation and Wellness Internet Proje.docx
 
Sheet1RegionProduct TypeItemProjected Sales 2022 (in millions)Proj.docx
Sheet1RegionProduct TypeItemProjected Sales 2022 (in millions)Proj.docxSheet1RegionProduct TypeItemProjected Sales 2022 (in millions)Proj.docx
Sheet1RegionProduct TypeItemProjected Sales 2022 (in millions)Proj.docx
 
Sheet1REQUIREMENTS TRACEABILITY MATRIXProject Name Outsourcing pr.docx
Sheet1REQUIREMENTS TRACEABILITY MATRIXProject Name Outsourcing pr.docxSheet1REQUIREMENTS TRACEABILITY MATRIXProject Name Outsourcing pr.docx
Sheet1REQUIREMENTS TRACEABILITY MATRIXProject Name Outsourcing pr.docx
 
Sheet1Purchase Price$ 110,000Recovery Period 7yearsSalvage Value.docx
Sheet1Purchase Price$   110,000Recovery Period 7yearsSalvage Value.docxSheet1Purchase Price$   110,000Recovery Period 7yearsSalvage Value.docx
Sheet1Purchase Price$ 110,000Recovery Period 7yearsSalvage Value.docx
 
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docx
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docxSheet1Rate your skills using the following scaleChapter 1 You Ma.docx
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docx
 
Sheet1QuarterRegionCityProductRevenueQ1EastBostonMaple34333Q1EastB.docx
Sheet1QuarterRegionCityProductRevenueQ1EastBostonMaple34333Q1EastB.docxSheet1QuarterRegionCityProductRevenueQ1EastBostonMaple34333Q1EastB.docx
Sheet1QuarterRegionCityProductRevenueQ1EastBostonMaple34333Q1EastB.docx
 
Sheet1Quarter Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
Sheet1Quarter Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docxSheet1Quarter Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
Sheet1Quarter Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
 
Sheet1Question 1A. TotalsActualBudgetedVarianceFavorableUnfavorab.docx
Sheet1Question 1A. TotalsActualBudgetedVarianceFavorableUnfavorab.docxSheet1Question 1A. TotalsActualBudgetedVarianceFavorableUnfavorab.docx
Sheet1Question 1A. TotalsActualBudgetedVarianceFavorableUnfavorab.docx
 
Sheet1project codeproject nameEmployeesQB280001Account Management .docx
Sheet1project codeproject nameEmployeesQB280001Account Management .docxSheet1project codeproject nameEmployeesQB280001Account Management .docx
Sheet1project codeproject nameEmployeesQB280001Account Management .docx
 
Sheet1PROJECT NAMEProject ManagerPhoneProject SponsorPhoneCustome.docx
Sheet1PROJECT NAMEProject ManagerPhoneProject SponsorPhoneCustome.docxSheet1PROJECT NAMEProject ManagerPhoneProject SponsorPhoneCustome.docx
Sheet1PROJECT NAMEProject ManagerPhoneProject SponsorPhoneCustome.docx
 
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docxSheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
 
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docxSheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
 
Sheet1PMGT 576 Assignment Rubric – Unit 8 Assignment20Is the Lean .docx
Sheet1PMGT 576 Assignment Rubric – Unit 8 Assignment20Is the Lean .docxSheet1PMGT 576 Assignment Rubric – Unit 8 Assignment20Is the Lean .docx
Sheet1PMGT 576 Assignment Rubric – Unit 8 Assignment20Is the Lean .docx
 
Sheet1Primordial PreventionPrimary PreventionSecondary PreventionT.docx
Sheet1Primordial PreventionPrimary PreventionSecondary PreventionT.docxSheet1Primordial PreventionPrimary PreventionSecondary PreventionT.docx
Sheet1Primordial PreventionPrimary PreventionSecondary PreventionT.docx
 
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docxSheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
 
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docxSheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
 
Sheet1PMGT 576 Assignment Rubric – Unit 7 Assignment20Are all of t.docx
Sheet1PMGT 576 Assignment Rubric – Unit 7 Assignment20Are all of t.docxSheet1PMGT 576 Assignment Rubric – Unit 7 Assignment20Are all of t.docx
Sheet1PMGT 576 Assignment Rubric – Unit 7 Assignment20Are all of t.docx
 
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docxSheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
 
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docx
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docxSheet1Phase of Business Financal Management needsDebt FinancingEq.docx
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docx
 
Sheet1phonessaturatedanimaldeaths124338814931655181388804172242220.docx
Sheet1phonessaturatedanimaldeaths124338814931655181388804172242220.docxSheet1phonessaturatedanimaldeaths124338814931655181388804172242220.docx
Sheet1phonessaturatedanimaldeaths124338814931655181388804172242220.docx
 

Recently uploaded

How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17Celine George
 
EBUS5423 Data Analytics and Reporting Bl
EBUS5423 Data Analytics and Reporting BlEBUS5423 Data Analytics and Reporting Bl
EBUS5423 Data Analytics and Reporting BlDr. Bruce A. Johnson
 
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...Nguyen Thanh Tu Collection
 
HED Office Sohayok Exam Question Solution 2023.pdf
HED Office Sohayok Exam Question Solution 2023.pdfHED Office Sohayok Exam Question Solution 2023.pdf
HED Office Sohayok Exam Question Solution 2023.pdfMohonDas
 
How to Solve Singleton Error in the Odoo 17
How to Solve Singleton Error in the  Odoo 17How to Solve Singleton Error in the  Odoo 17
How to Solve Singleton Error in the Odoo 17Celine George
 
Unveiling the Intricacies of Leishmania donovani: Structure, Life Cycle, Path...
Unveiling the Intricacies of Leishmania donovani: Structure, Life Cycle, Path...Unveiling the Intricacies of Leishmania donovani: Structure, Life Cycle, Path...
Unveiling the Intricacies of Leishmania donovani: Structure, Life Cycle, Path...Dr. Asif Anas
 
How to Send Emails From Odoo 17 Using Code
How to Send Emails From Odoo 17 Using CodeHow to Send Emails From Odoo 17 Using Code
How to Send Emails From Odoo 17 Using CodeCeline George
 
3.21.24 The Origins of Black Power.pptx
3.21.24  The Origins of Black Power.pptx3.21.24  The Origins of Black Power.pptx
3.21.24 The Origins of Black Power.pptxmary850239
 
KARNAADA.pptx made by - saransh dwivedi ( SD ) - SHALAKYA TANTRA - ENT - 4...
KARNAADA.pptx  made by -  saransh dwivedi ( SD ) -  SHALAKYA TANTRA - ENT - 4...KARNAADA.pptx  made by -  saransh dwivedi ( SD ) -  SHALAKYA TANTRA - ENT - 4...
KARNAADA.pptx made by - saransh dwivedi ( SD ) - SHALAKYA TANTRA - ENT - 4...M56BOOKSTORE PRODUCT/SERVICE
 
Clinical Pharmacy Introduction to Clinical Pharmacy, Concept of clinical pptx
Clinical Pharmacy  Introduction to Clinical Pharmacy, Concept of clinical pptxClinical Pharmacy  Introduction to Clinical Pharmacy, Concept of clinical pptx
Clinical Pharmacy Introduction to Clinical Pharmacy, Concept of clinical pptxraviapr7
 
CapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapitolTechU
 
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRADUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRATanmoy Mishra
 
Work Experience for psp3 portfolio sasha
Work Experience for psp3 portfolio sashaWork Experience for psp3 portfolio sasha
Work Experience for psp3 portfolio sashasashalaycock03
 
How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17Celine George
 
3.26.24 Race, the Draft, and the Vietnam War.pptx
3.26.24 Race, the Draft, and the Vietnam War.pptx3.26.24 Race, the Draft, and the Vietnam War.pptx
3.26.24 Race, the Draft, and the Vietnam War.pptxmary850239
 
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptxSandy Millin
 
In - Vivo and In - Vitro Correlation.pptx
In - Vivo and In - Vitro Correlation.pptxIn - Vivo and In - Vitro Correlation.pptx
In - Vivo and In - Vitro Correlation.pptxAditiChauhan701637
 
How to Create a Toggle Button in Odoo 17
How to Create a Toggle Button in Odoo 17How to Create a Toggle Button in Odoo 17
How to Create a Toggle Button in Odoo 17Celine George
 
Prescribed medication order and communication skills.pptx
Prescribed medication order and communication skills.pptxPrescribed medication order and communication skills.pptx
Prescribed medication order and communication skills.pptxraviapr7
 
Slides CapTechTalks Webinar March 2024 Joshua Sinai.pptx
Slides CapTechTalks Webinar March 2024 Joshua Sinai.pptxSlides CapTechTalks Webinar March 2024 Joshua Sinai.pptx
Slides CapTechTalks Webinar March 2024 Joshua Sinai.pptxCapitolTechU
 

Recently uploaded (20)

How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17
 
EBUS5423 Data Analytics and Reporting Bl
EBUS5423 Data Analytics and Reporting BlEBUS5423 Data Analytics and Reporting Bl
EBUS5423 Data Analytics and Reporting Bl
 
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
 
HED Office Sohayok Exam Question Solution 2023.pdf
HED Office Sohayok Exam Question Solution 2023.pdfHED Office Sohayok Exam Question Solution 2023.pdf
HED Office Sohayok Exam Question Solution 2023.pdf
 
How to Solve Singleton Error in the Odoo 17
How to Solve Singleton Error in the  Odoo 17How to Solve Singleton Error in the  Odoo 17
How to Solve Singleton Error in the Odoo 17
 
Unveiling the Intricacies of Leishmania donovani: Structure, Life Cycle, Path...
Unveiling the Intricacies of Leishmania donovani: Structure, Life Cycle, Path...Unveiling the Intricacies of Leishmania donovani: Structure, Life Cycle, Path...
Unveiling the Intricacies of Leishmania donovani: Structure, Life Cycle, Path...
 
How to Send Emails From Odoo 17 Using Code
How to Send Emails From Odoo 17 Using CodeHow to Send Emails From Odoo 17 Using Code
How to Send Emails From Odoo 17 Using Code
 
3.21.24 The Origins of Black Power.pptx
3.21.24  The Origins of Black Power.pptx3.21.24  The Origins of Black Power.pptx
3.21.24 The Origins of Black Power.pptx
 
KARNAADA.pptx made by - saransh dwivedi ( SD ) - SHALAKYA TANTRA - ENT - 4...
KARNAADA.pptx  made by -  saransh dwivedi ( SD ) -  SHALAKYA TANTRA - ENT - 4...KARNAADA.pptx  made by -  saransh dwivedi ( SD ) -  SHALAKYA TANTRA - ENT - 4...
KARNAADA.pptx made by - saransh dwivedi ( SD ) - SHALAKYA TANTRA - ENT - 4...
 
Clinical Pharmacy Introduction to Clinical Pharmacy, Concept of clinical pptx
Clinical Pharmacy  Introduction to Clinical Pharmacy, Concept of clinical pptxClinical Pharmacy  Introduction to Clinical Pharmacy, Concept of clinical pptx
Clinical Pharmacy Introduction to Clinical Pharmacy, Concept of clinical pptx
 
CapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptx
 
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRADUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
 
Work Experience for psp3 portfolio sasha
Work Experience for psp3 portfolio sashaWork Experience for psp3 portfolio sasha
Work Experience for psp3 portfolio sasha
 
How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17
 
3.26.24 Race, the Draft, and the Vietnam War.pptx
3.26.24 Race, the Draft, and the Vietnam War.pptx3.26.24 Race, the Draft, and the Vietnam War.pptx
3.26.24 Race, the Draft, and the Vietnam War.pptx
 
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
 
In - Vivo and In - Vitro Correlation.pptx
In - Vivo and In - Vitro Correlation.pptxIn - Vivo and In - Vitro Correlation.pptx
In - Vivo and In - Vitro Correlation.pptx
 
How to Create a Toggle Button in Odoo 17
How to Create a Toggle Button in Odoo 17How to Create a Toggle Button in Odoo 17
How to Create a Toggle Button in Odoo 17
 
Prescribed medication order and communication skills.pptx
Prescribed medication order and communication skills.pptxPrescribed medication order and communication skills.pptx
Prescribed medication order and communication skills.pptx
 
Slides CapTechTalks Webinar March 2024 Joshua Sinai.pptx
Slides CapTechTalks Webinar March 2024 Joshua Sinai.pptxSlides CapTechTalks Webinar March 2024 Joshua Sinai.pptx
Slides CapTechTalks Webinar March 2024 Joshua Sinai.pptx
 

Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx

  • 1. Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMaterial CostsTravel CostsFacility CostsSubcontractor CostsTotal Costs Cost Management 235-AAH-CH Professor: Behn Nikkhah CLASS 3&4 2 3 Cost Estimation Estimating project costs are important because: • Can be used in feasibility study before starting the project. • It can facilitate decisions regarding project financing and funding. • It provides a standard against which actual costs incurred during the execution can be compared.
  • 2. • It gives the project manager a framework to allocate scarce resources throughout the project. 4 Cost Estimation This is a process of estimating the cost of the resources required for each scheduled activity. It is important to be certain to include all the costs required to complete the work of the project. 5 Estimate Costs Inputs • Project Management Plan (Cost management plan, Quality Management Plan, Scope baseline) • Project Documents (Lessons learned register, Project schedule, resource requirements, Risk register) • Enterprise environmental factors • Organizational process assets. 6 Estimate Costs Inputs
  • 3. Scope Baseline: • Project scope statement • WBS • WBS dictionary Project scope statement is a document that includes key deliverables, constraints, assumptions, etc. Constraints such as limited budget for the project can be find in this document. There might be other constraints such as delivery date that can impact the cost. Project assumptions regarding costs might include information regarding indirect costs in the estimate. 7 Estimate Costs Inputs The WBS serves as the basis for estimating costs, as it includes all deliverables and the control accounts that are typically established at the work package level. The WBS dictionary describes the deliverables, work components, and other elements of the WBS. All these information can be helpful in estimation of the costs. For example if one of the deliverables is to get licenses you need to see that as additional expenses to fulfill in the estimation.
  • 4. 8 Estimate Costs Inputs The Project schedule along with the resource requirements for each activity are key inputs in estimating costs of the project.t You need to be aware of the duration as it can affect costs. For example, you must account for costs such as interest charges in a financed work of the project. Another example is fluctuation in costs that can occur due to seasonal or holiday demands. 9 Estimate Costs Inputs The risk register contains the response plans, particularly for those risks with negative impacts to the project. When developing project cost estimates, you should consider the cost of implementing risk response plans. 10 Estimate Costs Inputs The enterprise environmental factors such as market conditions,
  • 5. exchange rates and inflation are examples to be considered in the project costs estimation. The organization process assets such as lessons learned on previous projects of similar scope and complexity can be useful in determining estimates for the current project. 11 Tools and Techniques to Estimate Costs The majority of these are also tools and techniques of the estimate activity durations process used to determine schedule estimates: • Expert judgement • Analogous estimating • Parametric estimating • Bottom-up estimating • Three-point estimating • Reserve analysis • Project management information system • Decision making (voting) 12 Cost Estimation The total project cost is often estimated during the initiating phase of the project and be indicated in the project charter. However detailed plans are not usually prepared at the initiating phase.
  • 6. The detailed estimation can include the following elements: Labor costs Material costs Equipment costs Facilities costs Subcontractor costs Travel costs Reserve 13 Labor costs These are the estimated costs for the various types of human resources who are expected to work on the project Example, painters, developers, designers, general labor. The labor costs are based on the estimated work time (not necessary activity duration) Activity may have one day as its duration, but it requires 2 hours of work. 14 Material costs It includes the estimated costs of materials that the project team or contractors need to purchase for the project, such as paint, lumber, pipes, cables, paper, food, software.
  • 7. 15 Equipment costs A project may need a piece of equipment to be purchased. Equipment can include items such as computers and machinery. For example, a project of upgrading a manufacturing facility may include the purchase of new machinery 16 Facilities costs Some projects may need special facilities or additional place for the project team, for safety and security reasons, to store materials, to assemble, or to test the project deliverables or final product. For example cost of renting a place to store materials required for the project is a facility cost. 17 Subcontractors costs
  • 8. In a project your project team may not have expertise or resources to do certain project tasks. In such case you may outsource some of the work to subcontractors or consultants to perform those activities. For example you can have a subcontractor for a catering activities. 18 Travel costs If travel other than local travel is required during the project, the costs of airfare, lodging, and meals need to be seen under this category. 19 Reserve Contingencies to cover unexpected situations that may come up during the project. It will be discussed later. 20 Cost Estimation Now the question is “who is responsible for performing cost estimation?”
  • 9. It is a good practice to assign the person who will be responsible to do a task estimate the costs associated with it, as it can generating commitment from the person and avoids the bias of having one person doing all estimations. In large projects which may take several years, it is not practical and possible to have each person or team estimate activity costs. 21 Estimate Activity Costs The estimated costs for an activity should be reasonable and realistic. If estimates become over conservative, the total costs for the project is probably more than the budget of the sponsor or customer. In contrast, being very optimistic may cause cost overrun and unexpected expenditure come up. 22 Estimate Activity Costs In large project it is more practical to have contractors or departments who are responsible for a work package to estimate the costs of the work. If an organization or contract has performed similar projects in
  • 10. the past and has kept records of the actual costs, these historical data can be used in cost estimation. 23 Determine Project Budget Cost estimation and project budgeting are inseparably linked. The project budget is determined by aggregating the estimated costs for all the activities. The project budgeting process involves two steps: • Determine the total budgeted cost • Develop a time-phased budget 24 Develop the total budgeted cost The total budgeted cost is the aggregate amount of the estimated costs of all the specific activities to perform and complete the project (based on a WBS) This is also referred to as budget at completion (BAC). WBS with work package
  • 11. budgets 25 26 Develop Cumulative Budgeted Cost Once you determine the BAC, the second step is to distribute budgeted cost for each work package over the expected time span of its work package. By performing that, a time-phased budget is created so that it can be determined how much of the budget should have been spent at any point in time (Planned value in EVM) 27 Example: Network Diagram 28 Example: distribute the budget 29 Example: Budgeted cost by period for the packaging machine
  • 12. 30 Develop Cumulative Budgeted Cost Once you determine the BAC, the second step is to distribute budgeted cost for each work package over the expected time span of its work package. By performing that, a time-phased budget is created so that it can be determined how much of the budget should have been spent at any point in time (Planned value in EVM) 31 Cumulative budgeted cost curve With the planned value (cumulative budget cost), PV curve can be drawn to illustrate budgeted expenditure over the duration of the project 32 The importance of project cost management Two of the most important documents project managers prepare for any project are the project schedule and project budget.
  • 13. These two documents will be used throughout the executing and monitoring and controlling process 33 Cost Baseline The cumulative budgeted cost for the entire project provide a baseline against which actual cost and work performance can be compared during the project. For big projects that involves lots of activities, project management software assist the project budgeting. 34 Actual Cost To record and keep track of actual cost on a project, it is necessary to establish a system to collect data on costs expended on a regular and timely basis. In many project weekly timesheets are used to collect actual labor hours. Workers working on the project fill it out with the number of the work packages on which they worked and the amount of hours they spend on each.
  • 14. 35 Committed Costs Committed costs are amount of money that have been beholden for an item that has been ordered or purchases but not yet paid for. Committed costs are not available to be spend elsewhere on the project as they will be needed later. For example you hire a contractor to fix your home plumbing for $2,000. you have committed $2,000, even though you may not actually pay until the work is finished. 36 Committed Costs Committed amount need to be set aside and be treated in a special way. To permit a realistic comparison of actual cost to cumulative budgeted cost (PV), percentage of committed costs should be assigned to actual cost while the work is being performed (as it is like progress payments), rather than waiting till it is finished and convert it to actual costs.