SlideShare a Scribd company logo
1 of 23
Prepared by-:K.Shashavali,
Pin -:18207-C-027,
Branch-:DCE,
Guided by-: P.Hemanth,
{Lecturer in Civil Engineering in
GPT-KLD}.
1
About MIVAN Technology
&
Construction
1)Introduction About MIVAN.
2)Stages Involved in MIVAN Construction.
3)MIVAN Form Work.
4)Difference between Normal Construction &
MIVAN Construction (Building).
5)Cost Comparison.
6)Advantages & Disadvantages of MIVAN
Formwork over Brick work.
7)Analysis Data.
8)Conclusion.
2
INDEX-:
I.INTRODUCTION-:
3
Mivan construction is firstly introduced in 1990 by a
European construction company whose name is
Mivan Company Ltd. This is mostly used for
residential building and group housing construction in
India. In this construction the load bearing walls are
constructed with RCC. In this method the wall, lintel,
slab is concreting at same time due to this the
duration of completion of project is reduce. And the
work finish is perfect. There is no need of plastering
hence it is more suitable for Indian condition and
mass construction. In this construction the load
bearing walls are constructed with RCC. And
aluminium formworks are used for high quality wall
finish. It is most suitable for constructing large number
of house in short time duration.
Stages Involved-:
4
 1. Setting up the wall reinforcing steel -
 The wall reinforcing steel is used to give a
structure to the building and support the concrete
until they gain half of the required strength. The
aluminium formworks are cast around the steel
mesh, which is factory made and directly erected
on the construction site.
 2. Placement of aluminium formwork
 Along the wall reinforcing steel, prefabricated
room sized walls and floor slabs are erected.
These aluminium alloy slabs are accurately made
and are easy to handle. Spaces for windows,
ducts, doors and other features such as
staircases, façade panels and chajjas are also
integrated in these structures. The forms are joint
together using the pin and wedge system, which
can be dismantled quickly after the concrete
structure is made.
5
After Placing Formwork-:
6
 3. Pouring concrete –
 After casting the forms, high-quality concrete is
poured. This concrete takes the form and shape
of the cast, which is later removed to make way
for a structure made entirely of cement concrete
supported by wall reinforcing steel. The
aluminium forms can be reused at least 250
times, resulting in minimum waste from the
construction site.
7
After Pouring Concrete-:
 The resulting structure is accurate, smooth and
finished. It has high tolerance and requires no
further plastering. As a result, it saves time, effort
and money.
The resulting structure is accurate, smooth and finished. It
has high tolerance and requires no further plastering. As a
result, it saves time, effort and money.
8
II.MIVAN FORMWORK-:
 Formwork is a mould for structure which is either
made up of wood, iron or aluminium. Into this mould,
fresh concrete is poured only to harden subsequently.
Timber is mostly used for formwork. But the
disadvantage with the timber formwork is that it will
swell and shrink due to the drying and wetting of
wood. To overcome these problems mivan formwork
is introduced in 1990 which is aluminium form work
system which is introduced by Mivan company ltd.
Aluminium form work is most cost effective and long
durability as compared to woodenformwork. In this
construction there is no need of block work or
masonry work and hence the speed of work
increases.
9
 The mivan aluminium formwork system allows easy
fixing and removal of form work due to which
construction speed increases, dimension tolerance
less which results in cost reduction. All the formwork
components are made up of high strength aluminium
alloy. The aim of mivan construction is to use modern
techniques and equipment in construction process.
Before dispatching all the panels from factory it is
clearly labelled to ensure that they are easily
identified and fitted together on site. The panels are
held on position by simply pin and wedge system that
pass through holes in the outside rib of each panel.
The panelsare fitted smoothly, precisely and doesn’t
require bracing. The formwork components used in
mivan construction is of light weight which reduces
the cost of heavy lifting crane and these formworks
are used upto 200 times. With the help of these
formwork components the chances of dimensional
error is also eliminated.10
III.MIVAN FORMWORK-:
11
IV)Difference between Normal Construction &
MIVAN Construction (Building).
 Conventional method of construction is brickwork
method in which the cost of construction is
increases due to the high labour cost and long
time period of construction as it require plastering
after brick masonry. It absorbs water which
results dampness and cause damage over time.
So mivan Construction is introduced which is an
advance construction technique. It will overcome
all the demerits of conventional brickwork
construction.
12
V)Cost Comparison-:
 The cost of mivan construction is low as
compared to the conventional brickwork
construction and the quality of the construction is
better as compared to the normal construction. In
this paper the cost is compare between mivan
construction and conventional brickwork
construction in this project we compare a building
having stilt parking on ground level and four
stories on top. It is compared on the basis of
AutoCAD drafting and Staad.pro analysis and the
cost of the project is calculated from SSR.
13
ADVANTAGES OF MIVAN
FORMWORK OVER BRICKWORK -
:
 Mivan construction offers Joint less construction
which gives better resistance in earthquake.
 It provides good durability and stability.
 It is mostly used in mass construction and group
housing.
 It gives smooth and precise finishing of wall and
slabs.
 Less manual labour is required in mivan
construction.
 Plastering is not required in it.
 The shuttering is used upto 200 times.
 In this construction less number of joints are
formed hence the chances of leakage is14
DISADVANTAGES OF MIVAN FORMWORK
OVER BRICKWORK -:
 It reduces the flexibility of the structure.
 Its initial setup takes more time.
 Skilled labour is required for this work
 Initial cost is high.
 Aluminium form work is more costlier than
conventional cost of construction .
 Creep is formed in it due to the shrinkage of
concrete.
 Small size component the finished structure could
have several finishing line visual on concrete
15
ANALYSIS DATA FOR
CONVENTIONAL BRICKWORK
CONSTRUCTION:
Description Quantity Cost
Total concrete used 12cu.m 1,11,907.2
Total Steel used 17,266.8kg 9,59,170.74
Total brick work 202.579 cu.m 12,88,807.6
Total plaster 2064.6 sq.m 6,31,767.6
Shuttering cost (M.S.
Material)
540 54,000
Steel binding rate 17,266.8 kg 1,12,234.2
Total cost ------------------ 31,57,887.34
16
Conventional Brick Work
Construction-:
17
ANALYSIS DATA FOR MIVAN
CONSTRUCTION:
Description Quantity Cost
Total concrete used 171 cu.m 15,94,677.6
Total Steel used 11,720 kg 6,51,046
Total brick work No need 0
Total plaster No need 0
Shuttering cost (M.S.
Material)
1,239.1194sq.m 1,29,649.06
Steel binding rate 11,720 kg 76,180
Total cost ----------------- 24,51,552.66
**NOTE: In both the cases foundation of the building is not consider.
And it is assumed that the cost of the slab construction and finishing
work such as paint, POP, electricity work, etc.is same in both type of
construction.
18
MIVAN Construction
19
VI.CONCLUSION
 It is concluded from the above data analysis that
mivan construction require less time and cost to
complete construction. In this construction there
is no requirement of plastering walls aluminium
formwork will provide better surface finish. Hence
it is much better than conventional brickwork
construction
20
Reference-:
 https://www.quora.com/What-is-Mivan-shuttering.
 https://www.ukessays.com/essays/construction/co
mparison-of-mivan-formwork-system-with-
conventionalsystem-construction-essay.php.
 https://cpwd.gov.in/Documents/cpwd_publication.
aspx
 https://www.google.co.in/url?sa=t&source=web&r
ct=j&url=https://www.erpublication.org/published_
pape
r/IJETR032419.pdf&ved=2ahUKEwiV8uf2ztvdAh
WBK48KHdhpB4oQFjAAegQIAhAB&usg=AOvVa
w0 XcrthHu3x3YK9cVDn2nnb21
Queries-:
Any
Questions
22
Thank you for all
23

More Related Content

What's hot

Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologysravan kumar chilamakuri
 
Mivan aluminium formwork
Mivan  aluminium formworkMivan  aluminium formwork
Mivan aluminium formworkAnup Kude
 
Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)w ss
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniqueIEI GSC
 
Autoclaved Aerated Concrete Bricks (AAC) Seminar Report.
Autoclaved Aerated Concrete Bricks (AAC) Seminar Report.Autoclaved Aerated Concrete Bricks (AAC) Seminar Report.
Autoclaved Aerated Concrete Bricks (AAC) Seminar Report.Mr. Lucky
 
Glass Fiber Reinforced Gypsum Panel use in Building Construction
Glass Fiber Reinforced Gypsum Panel use in Building ConstructionGlass Fiber Reinforced Gypsum Panel use in Building Construction
Glass Fiber Reinforced Gypsum Panel use in Building ConstructionGRD Journals
 
Insulated Concrete Forms
Insulated Concrete FormsInsulated Concrete Forms
Insulated Concrete Formsguest64aa9a
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid shaikh khalid
 
Integral Crystalline Waterproofing Technology
Integral Crystalline Waterproofing TechnologyIntegral Crystalline Waterproofing Technology
Integral Crystalline Waterproofing TechnologyKryton International Inc.
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formworkMumtaz Alam
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueSandeep Jain
 
Design of columns uniaxial load as per IS 456-2000
Design of columns  uniaxial load as per IS 456-2000Design of columns  uniaxial load as per IS 456-2000
Design of columns uniaxial load as per IS 456-2000PraveenKumar Shanmugam
 
Silica Fume in Concrete
Silica Fume in ConcreteSilica Fume in Concrete
Silica Fume in ConcreteKanav Chandan
 
Specifications of excavation and foundation
Specifications of excavation and foundationSpecifications of excavation and foundation
Specifications of excavation and foundationPrabhat chhirolya
 
Case study on floating foundation
Case study on floating foundationCase study on floating foundation
Case study on floating foundationAbhishek Mangukiya
 

What's hot (20)

Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnology
 
Mivan shuttering
Mivan shutteringMivan shuttering
Mivan shuttering
 
Mivan tech
Mivan techMivan tech
Mivan tech
 
Mivan aluminium formwork
Mivan  aluminium formworkMivan  aluminium formwork
Mivan aluminium formwork
 
Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
Autoclaved Aerated Concrete Bricks (AAC) Seminar Report.
Autoclaved Aerated Concrete Bricks (AAC) Seminar Report.Autoclaved Aerated Concrete Bricks (AAC) Seminar Report.
Autoclaved Aerated Concrete Bricks (AAC) Seminar Report.
 
Glass Fiber Reinforced Gypsum Panel use in Building Construction
Glass Fiber Reinforced Gypsum Panel use in Building ConstructionGlass Fiber Reinforced Gypsum Panel use in Building Construction
Glass Fiber Reinforced Gypsum Panel use in Building Construction
 
Insulated Concrete Forms
Insulated Concrete FormsInsulated Concrete Forms
Insulated Concrete Forms
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid
 
Structural lightweight concrete
Structural lightweight concreteStructural lightweight concrete
Structural lightweight concrete
 
Integral Crystalline Waterproofing Technology
Integral Crystalline Waterproofing TechnologyIntegral Crystalline Waterproofing Technology
Integral Crystalline Waterproofing Technology
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formwork
 
Geopolymer concrete
Geopolymer concreteGeopolymer concrete
Geopolymer concrete
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction Technique
 
Bricks
Bricks Bricks
Bricks
 
Design of columns uniaxial load as per IS 456-2000
Design of columns  uniaxial load as per IS 456-2000Design of columns  uniaxial load as per IS 456-2000
Design of columns uniaxial load as per IS 456-2000
 
Silica Fume in Concrete
Silica Fume in ConcreteSilica Fume in Concrete
Silica Fume in Concrete
 
Specifications of excavation and foundation
Specifications of excavation and foundationSpecifications of excavation and foundation
Specifications of excavation and foundation
 
Case study on floating foundation
Case study on floating foundationCase study on floating foundation
Case study on floating foundation
 

Similar to About mivan technology

404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................KeshavaPrajwal
 
Modeling of Interlocking Soil Stabilized Bricks for Improved Wall Constructio...
Modeling of Interlocking Soil Stabilized Bricks for Improved Wall Constructio...Modeling of Interlocking Soil Stabilized Bricks for Improved Wall Constructio...
Modeling of Interlocking Soil Stabilized Bricks for Improved Wall Constructio...IRJET Journal
 
Development OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallDevelopment OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallIRJET Journal
 
study of self-compacting concrete for economical construction
study of self-compacting concrete for economical constructionstudy of self-compacting concrete for economical construction
study of self-compacting concrete for economical constructionTejas6957
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formworkchaitanyakrsk
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET Journal
 
MIVAN-A Versite aluminium firmwork construction technique
MIVAN-A Versite aluminium firmwork construction techniqueMIVAN-A Versite aluminium firmwork construction technique
MIVAN-A Versite aluminium firmwork construction techniquekvijay31
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelIRJET Journal
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for constPradeepPandya1
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork adarshkaushik6
 
internship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteinternship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteSrikanthReddy345872
 
Floating Concrete to Solve Land Crises
Floating Concrete to Solve Land CrisesFloating Concrete to Solve Land Crises
Floating Concrete to Solve Land CrisesIRJET Journal
 
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET Journal
 
Concrete cloth - PowerPoint by Hrishikesh Kane
Concrete cloth - PowerPoint by Hrishikesh KaneConcrete cloth - PowerPoint by Hrishikesh Kane
Concrete cloth - PowerPoint by Hrishikesh KaneHrishikesh Kane
 
Site report
Site reportSite report
Site reportEric Teo
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesSayedaAmrin
 
TWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxTWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxSomeshMathad
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationCivilTY09AdityaGaval
 

Similar to About mivan technology (20)

404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................
 
Modeling of Interlocking Soil Stabilized Bricks for Improved Wall Constructio...
Modeling of Interlocking Soil Stabilized Bricks for Improved Wall Constructio...Modeling of Interlocking Soil Stabilized Bricks for Improved Wall Constructio...
Modeling of Interlocking Soil Stabilized Bricks for Improved Wall Constructio...
 
Development OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallDevelopment OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound Wall
 
study of self-compacting concrete for economical construction
study of self-compacting concrete for economical constructionstudy of self-compacting concrete for economical construction
study of self-compacting concrete for economical construction
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formwork
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
 
MIVAN-A Versite aluminium firmwork construction technique
MIVAN-A Versite aluminium firmwork construction techniqueMIVAN-A Versite aluminium firmwork construction technique
MIVAN-A Versite aluminium firmwork construction technique
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for const
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
internship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteinternship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering institute
 
Special Concrete - Concrete Technology
Special Concrete - Concrete TechnologySpecial Concrete - Concrete Technology
Special Concrete - Concrete Technology
 
Floating Concrete to Solve Land Crises
Floating Concrete to Solve Land CrisesFloating Concrete to Solve Land Crises
Floating Concrete to Solve Land Crises
 
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
 
Concrete cloth - PowerPoint by Hrishikesh Kane
Concrete cloth - PowerPoint by Hrishikesh KaneConcrete cloth - PowerPoint by Hrishikesh Kane
Concrete cloth - PowerPoint by Hrishikesh Kane
 
Site report
Site reportSite report
Site report
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
TWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxTWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptx
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentation
 

Recently uploaded

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 

Recently uploaded (20)

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 

About mivan technology

  • 1. Prepared by-:K.Shashavali, Pin -:18207-C-027, Branch-:DCE, Guided by-: P.Hemanth, {Lecturer in Civil Engineering in GPT-KLD}. 1 About MIVAN Technology & Construction
  • 2. 1)Introduction About MIVAN. 2)Stages Involved in MIVAN Construction. 3)MIVAN Form Work. 4)Difference between Normal Construction & MIVAN Construction (Building). 5)Cost Comparison. 6)Advantages & Disadvantages of MIVAN Formwork over Brick work. 7)Analysis Data. 8)Conclusion. 2 INDEX-:
  • 3. I.INTRODUCTION-: 3 Mivan construction is firstly introduced in 1990 by a European construction company whose name is Mivan Company Ltd. This is mostly used for residential building and group housing construction in India. In this construction the load bearing walls are constructed with RCC. In this method the wall, lintel, slab is concreting at same time due to this the duration of completion of project is reduce. And the work finish is perfect. There is no need of plastering hence it is more suitable for Indian condition and mass construction. In this construction the load bearing walls are constructed with RCC. And aluminium formworks are used for high quality wall finish. It is most suitable for constructing large number of house in short time duration.
  • 4. Stages Involved-: 4  1. Setting up the wall reinforcing steel -  The wall reinforcing steel is used to give a structure to the building and support the concrete until they gain half of the required strength. The aluminium formworks are cast around the steel mesh, which is factory made and directly erected on the construction site.
  • 5.  2. Placement of aluminium formwork  Along the wall reinforcing steel, prefabricated room sized walls and floor slabs are erected. These aluminium alloy slabs are accurately made and are easy to handle. Spaces for windows, ducts, doors and other features such as staircases, façade panels and chajjas are also integrated in these structures. The forms are joint together using the pin and wedge system, which can be dismantled quickly after the concrete structure is made. 5
  • 7.  3. Pouring concrete –  After casting the forms, high-quality concrete is poured. This concrete takes the form and shape of the cast, which is later removed to make way for a structure made entirely of cement concrete supported by wall reinforcing steel. The aluminium forms can be reused at least 250 times, resulting in minimum waste from the construction site. 7
  • 8. After Pouring Concrete-:  The resulting structure is accurate, smooth and finished. It has high tolerance and requires no further plastering. As a result, it saves time, effort and money. The resulting structure is accurate, smooth and finished. It has high tolerance and requires no further plastering. As a result, it saves time, effort and money. 8
  • 9. II.MIVAN FORMWORK-:  Formwork is a mould for structure which is either made up of wood, iron or aluminium. Into this mould, fresh concrete is poured only to harden subsequently. Timber is mostly used for formwork. But the disadvantage with the timber formwork is that it will swell and shrink due to the drying and wetting of wood. To overcome these problems mivan formwork is introduced in 1990 which is aluminium form work system which is introduced by Mivan company ltd. Aluminium form work is most cost effective and long durability as compared to woodenformwork. In this construction there is no need of block work or masonry work and hence the speed of work increases. 9
  • 10.  The mivan aluminium formwork system allows easy fixing and removal of form work due to which construction speed increases, dimension tolerance less which results in cost reduction. All the formwork components are made up of high strength aluminium alloy. The aim of mivan construction is to use modern techniques and equipment in construction process. Before dispatching all the panels from factory it is clearly labelled to ensure that they are easily identified and fitted together on site. The panels are held on position by simply pin and wedge system that pass through holes in the outside rib of each panel. The panelsare fitted smoothly, precisely and doesn’t require bracing. The formwork components used in mivan construction is of light weight which reduces the cost of heavy lifting crane and these formworks are used upto 200 times. With the help of these formwork components the chances of dimensional error is also eliminated.10
  • 12. IV)Difference between Normal Construction & MIVAN Construction (Building).  Conventional method of construction is brickwork method in which the cost of construction is increases due to the high labour cost and long time period of construction as it require plastering after brick masonry. It absorbs water which results dampness and cause damage over time. So mivan Construction is introduced which is an advance construction technique. It will overcome all the demerits of conventional brickwork construction. 12
  • 13. V)Cost Comparison-:  The cost of mivan construction is low as compared to the conventional brickwork construction and the quality of the construction is better as compared to the normal construction. In this paper the cost is compare between mivan construction and conventional brickwork construction in this project we compare a building having stilt parking on ground level and four stories on top. It is compared on the basis of AutoCAD drafting and Staad.pro analysis and the cost of the project is calculated from SSR. 13
  • 14. ADVANTAGES OF MIVAN FORMWORK OVER BRICKWORK - :  Mivan construction offers Joint less construction which gives better resistance in earthquake.  It provides good durability and stability.  It is mostly used in mass construction and group housing.  It gives smooth and precise finishing of wall and slabs.  Less manual labour is required in mivan construction.  Plastering is not required in it.  The shuttering is used upto 200 times.  In this construction less number of joints are formed hence the chances of leakage is14
  • 15. DISADVANTAGES OF MIVAN FORMWORK OVER BRICKWORK -:  It reduces the flexibility of the structure.  Its initial setup takes more time.  Skilled labour is required for this work  Initial cost is high.  Aluminium form work is more costlier than conventional cost of construction .  Creep is formed in it due to the shrinkage of concrete.  Small size component the finished structure could have several finishing line visual on concrete 15
  • 16. ANALYSIS DATA FOR CONVENTIONAL BRICKWORK CONSTRUCTION: Description Quantity Cost Total concrete used 12cu.m 1,11,907.2 Total Steel used 17,266.8kg 9,59,170.74 Total brick work 202.579 cu.m 12,88,807.6 Total plaster 2064.6 sq.m 6,31,767.6 Shuttering cost (M.S. Material) 540 54,000 Steel binding rate 17,266.8 kg 1,12,234.2 Total cost ------------------ 31,57,887.34 16
  • 18. ANALYSIS DATA FOR MIVAN CONSTRUCTION: Description Quantity Cost Total concrete used 171 cu.m 15,94,677.6 Total Steel used 11,720 kg 6,51,046 Total brick work No need 0 Total plaster No need 0 Shuttering cost (M.S. Material) 1,239.1194sq.m 1,29,649.06 Steel binding rate 11,720 kg 76,180 Total cost ----------------- 24,51,552.66 **NOTE: In both the cases foundation of the building is not consider. And it is assumed that the cost of the slab construction and finishing work such as paint, POP, electricity work, etc.is same in both type of construction. 18
  • 20. VI.CONCLUSION  It is concluded from the above data analysis that mivan construction require less time and cost to complete construction. In this construction there is no requirement of plastering walls aluminium formwork will provide better surface finish. Hence it is much better than conventional brickwork construction 20
  • 21. Reference-:  https://www.quora.com/What-is-Mivan-shuttering.  https://www.ukessays.com/essays/construction/co mparison-of-mivan-formwork-system-with- conventionalsystem-construction-essay.php.  https://cpwd.gov.in/Documents/cpwd_publication. aspx  https://www.google.co.in/url?sa=t&source=web&r ct=j&url=https://www.erpublication.org/published_ pape r/IJETR032419.pdf&ved=2ahUKEwiV8uf2ztvdAh WBK48KHdhpB4oQFjAAegQIAhAB&usg=AOvVa w0 XcrthHu3x3YK9cVDn2nnb21
  • 23. Thank you for all 23