SlideShare a Scribd company logo
1 of 25
FORMWORK
 Formwork (shuttering) in
concrete construction is used as
a mould for a structure in which
fresh concrete is poured only to
harden subsequently.
 Types of concrete formwork
construction depends on
formwork material and type of
structural element.
 Formworks can also be named
based on the type of structural
member construction, such as
slab formwork for use in a slab,
beam formwork, column
formwork for use in beams and
columns, respectively, etc.
Requirements of Formwork
Strong enough to
withstand all types
of dead and live
loads.
Rigidly constructed and
efficiently propped and
braced both horizontally
and vertically, to retain
its shape.
The joints in the
formwork should be
tight against leakage
of cement grout.
Construction of formwork
should permit removal of
various parts in desired
sequences without damage to
the concrete.
The material of the
formwork should be
cheap, readily
available, and should
be suitable for reuse.
It should rest on a firm
base and should be as
light as possible.
The material of the
formwork should not
warp or get distorted
when exposed to the
elements.
The formwork should
be set accurately to the
desired line, and levels
should have a plane
surface.
 Old technique
 Done in 2 forms
 First the skeleton of
the structure which
comprises of beams
and columns
 Foundations,
columns, beam slabs
are constructed using
plywood & timber MS
sheets.
 21 days to complete
one slab
 Large manpower
required
 Material wastage is
more
ADVANTAGES DISADVANTAGES
•Initial investment is quite
less
•Large number of manpower
required.
•Mostly used for small
scale structures.
•Slab cycle or 21 days.
•Duration of project will be
long.
•Large number supporting
materials required.
MODERN FORMWORK
1. Aluminum formwork
2. Precast system
3. Modular formwork
4. Tunnel formwork
5. Fiberglass formwork
 Used in construction of
residential units & mass
housing projects
 Made up of aluminum
materials molded into
required shapes and
sizes
 Used extensively in
various countries.
 10 days slab cycle can be
achieved.
 Manpower required is quit
minimal
 No blocks work required
 Shuttering wastages are
very less
ADVANTAGES DISADVANTAGES
Easy to fix and dismantle Huge capital cost
Handled easily due to its light
weight
Architectural modification are
not possible
Can be re used
The walls and slabs of
structure can be casted
simultaneously.
Monolithic crack free structure
can be built using aluminum
formwork.
Cement mortar plastering not
needed
 A new method of construction
 used worldwide.
 Concrete is poured in reusable mold
/shutters in a controlled environment.
 Elements are divided into various
members that are casted & cure at
plant and then transported to site for
erection.
 It is time saving
 required elements can be casted in
advance
 Quality is high in precast construction
as it’s built in an ideal environment
with exact measurements.
 Durable and stable
 Man power is very less compared to
any construction
•Though initial
investments are high
the returns are very
quick.
•Precast construction
gives increased
productivity and
reduces the
mobilization of labors
which saves a huge
amount of cost.
Advantages Disadvantages
•Very quick and precise •Comes with huge capital cost
•Saves huge time at site •Architectural modification are
not possible
•Low manpower required •It is being assembled more
number of joints to be closed
•No plastering required
•Minimal strength of concrete can
be achieved within hours with
acceleration.
SI.
NO
CHARACTERSTICS CONVENTIONAL
SYSTEM
SYSTEM
SHUTTERING
PRECAST SYSTEM
1. Material type Plywood, runners, MS sheets Aluminium Mild steel
2. Speed of construction Min cycle time is 21 days Ten days cycle per
floor.
Five days cycle per
floor.
3. Quality of surface finish Cement mortar plastering is
required
Cement mortar
plastering is not
required
Cement mortar
plastering is not
required
4. Pre – planning of formwork
system
Not required Required Required
5. Formwork wastages Huge Less Very less
6. Accuracy Less accurate More accurate Accurate
7. Suitable for high rise
construction
Not suitable Very much suitable Very much suitable
8. Initial investments Very less High Very high
9. Economy in construction Economical for small
scale
Suitable for mass
houses
Suitable for mass
houses with less
duration.
 Modular formwork systems are
designed with standardized
panels and component items to
reduce or limit the need for
cutting material on site.
 This speeds up the overall
process and therefore
requires less labour on site. They
are also interchangeable with
conventional methods.
 Modular Formwork Systems are
generally easy to assemble and
much faster than conventional
Formwork, saving time,
allowing you to pour sooner.
Advantages
Does not require
a crane to place
the formwork
Speed of
construction
with unskilled
labour
Fast assembly
comparably
There will be
less
complications
Designed with
standardised panels
to reduce or limit the
need for cutting
material on site
Hire cost were
significantly over than
the affiant purchases
for conventional
formwork
Modular Formwork can be used to:
1. Concrete housed construction
2. Elliptical columns construction
3. Large columns construction
4. Reinforced concrete pools construction
5. Bunker construction
6. Art stone textured panels
7. Integration
8. Wall construction
9. Lintels and curtain walls construction
10. Foundation plinths construction
Fibre glass
shuttering does not
require plastering
They represent in
the area of
shuttering because
of their lightness,
simplicity, durability,
solidity resistance
to temperature
changes
Advantages
Smoothest finish
among existing
concrete formwork
and shuttering
systems
Unmatched building
quality
Durability
Lower cost
No plastering
required
Faster project
delivery
Easy customization
and reparability
High re-usability
 Tunnel Formwork is a steel formwork
 It is used during the placing of the
concrete to form the floor and the wall at
the same time.
 They can be in different shapes, sizes
and modules.
 It allows to cost walls and slakes in an
operation on daily cycle
 Construction decorations are reduced
significantly in comparison to the others
 Hi tech technologies for steel formwork
makes its strong and durable
 It is known as most earthquake
structures
 Tower cranes are required for the
erection, removal and carriage of
formworks, scaffolds, and pre-cast
components.
 Skilled labours are required
Advantages
The project can be
completed in a short time
compared to traditional
construction systems.
Due to accelerated
production, effects of
climatic conditions on
productivity are minimized.
Smooth surfaces for the
walls and slabs are obtained
that can be covered with
wallpaper right after easy
and quick cleaning.
Standard dimensions for the
other components such as
carpet, windows, and doors
can be applicable due to
strict dimensions of load-
bearing system elements.
Due to smooth surfaces,
walls and slabs do not need
any additional finishing such
as plaster.
Early completion of project
provides financial
opportunities such as rental
incomes
BY
ADARSH T S
JAI KAUSHIK E R K
TCE

More Related Content

What's hot

Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structuresFAIZAL MUHAMMED
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and SteelRithika Ravishankar
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication constructionDivya Vishnoi
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materialsHamdija Velagic
 
Types of bricks and its bonds
Types of bricks and its bondsTypes of bricks and its bonds
Types of bricks and its bondsGiri Guru
 
Pre fabricated structures
Pre fabricated structuresPre fabricated structures
Pre fabricated structuresjamali husain
 
Prefabrication types and Applications explained
Prefabrication types and Applications explainedPrefabrication types and Applications explained
Prefabrication types and Applications explainedEyad Reda
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concreteRajat Nainwal
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated StructuresBoopathi Raja
 
Roof and roof covering
Roof and roof coveringRoof and roof covering
Roof and roof coveringDivya Vishnoi
 

What's hot (20)

Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and Steel
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Framed structures
Framed structures Framed structures
Framed structures
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materials
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Types of bricks and its bonds
Types of bricks and its bondsTypes of bricks and its bonds
Types of bricks and its bonds
 
Formwork
FormworkFormwork
Formwork
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Pre fabricated structures
Pre fabricated structuresPre fabricated structures
Pre fabricated structures
 
Prefabrication types and Applications explained
Prefabrication types and Applications explainedPrefabrication types and Applications explained
Prefabrication types and Applications explained
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concrete
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
Shear wall ppt
Shear wall ppt Shear wall ppt
Shear wall ppt
 
Walls
WallsWalls
Walls
 
High rise construction
High rise constructionHigh rise construction
High rise construction
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
 
Plastering
PlasteringPlastering
Plastering
 
Roof and roof covering
Roof and roof coveringRoof and roof covering
Roof and roof covering
 

Similar to Types of modern construction formwork

Precast concrete - drywall
Precast  concrete - drywallPrecast  concrete - drywall
Precast concrete - drywallDenis Patel
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentationsomitra bhardwaj
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptxssuserc0bf9b
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSjagrutib22
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy constructionMudassir khan
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSOUMYA KHANDELWAL
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Yee Len Wan
 
PREFABRICATED CONSTRUCTION
PREFABRICATED CONSTRUCTIONPREFABRICATED CONSTRUCTION
PREFABRICATED CONSTRUCTIONAnushka Bhargava
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formworkchaitanyakrsk
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniqueIEI GSC
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesSayedaAmrin
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSakshiMahadik3
 
Development OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallDevelopment OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallIRJET Journal
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wallHarsh Bothra
 

Similar to Types of modern construction formwork (20)

Precast concrete - drywall
Precast  concrete - drywallPrecast  concrete - drywall
Precast concrete - drywall
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy construction
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
 
Special Concrete - Concrete Technology
Special Concrete - Concrete TechnologySpecial Concrete - Concrete Technology
Special Concrete - Concrete Technology
 
PREFABRICATED CONSTRUCTION
PREFABRICATED CONSTRUCTIONPREFABRICATED CONSTRUCTION
PREFABRICATED CONSTRUCTION
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formwork
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
Shuttering PPT.pptx
Shuttering PPT.pptxShuttering PPT.pptx
Shuttering PPT.pptx
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
 
Development OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallDevelopment OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound Wall
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
40.pdf
40.pdf40.pdf
40.pdf
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 

Recently uploaded

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 

Recently uploaded (20)

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 

Types of modern construction formwork

  • 1.
  • 2. FORMWORK  Formwork (shuttering) in concrete construction is used as a mould for a structure in which fresh concrete is poured only to harden subsequently.  Types of concrete formwork construction depends on formwork material and type of structural element.  Formworks can also be named based on the type of structural member construction, such as slab formwork for use in a slab, beam formwork, column formwork for use in beams and columns, respectively, etc.
  • 3. Requirements of Formwork Strong enough to withstand all types of dead and live loads. Rigidly constructed and efficiently propped and braced both horizontally and vertically, to retain its shape. The joints in the formwork should be tight against leakage of cement grout. Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete. The material of the formwork should be cheap, readily available, and should be suitable for reuse. It should rest on a firm base and should be as light as possible. The material of the formwork should not warp or get distorted when exposed to the elements. The formwork should be set accurately to the desired line, and levels should have a plane surface.
  • 4.
  • 5.  Old technique  Done in 2 forms  First the skeleton of the structure which comprises of beams and columns  Foundations, columns, beam slabs are constructed using plywood & timber MS sheets.  21 days to complete one slab  Large manpower required  Material wastage is more
  • 6. ADVANTAGES DISADVANTAGES •Initial investment is quite less •Large number of manpower required. •Mostly used for small scale structures. •Slab cycle or 21 days. •Duration of project will be long. •Large number supporting materials required.
  • 7. MODERN FORMWORK 1. Aluminum formwork 2. Precast system 3. Modular formwork 4. Tunnel formwork 5. Fiberglass formwork
  • 8.
  • 9.  Used in construction of residential units & mass housing projects  Made up of aluminum materials molded into required shapes and sizes  Used extensively in various countries.  10 days slab cycle can be achieved.  Manpower required is quit minimal  No blocks work required  Shuttering wastages are very less
  • 10. ADVANTAGES DISADVANTAGES Easy to fix and dismantle Huge capital cost Handled easily due to its light weight Architectural modification are not possible Can be re used The walls and slabs of structure can be casted simultaneously. Monolithic crack free structure can be built using aluminum formwork. Cement mortar plastering not needed
  • 11.
  • 12.  A new method of construction  used worldwide.  Concrete is poured in reusable mold /shutters in a controlled environment.  Elements are divided into various members that are casted & cure at plant and then transported to site for erection.  It is time saving  required elements can be casted in advance  Quality is high in precast construction as it’s built in an ideal environment with exact measurements.  Durable and stable  Man power is very less compared to any construction •Though initial investments are high the returns are very quick. •Precast construction gives increased productivity and reduces the mobilization of labors which saves a huge amount of cost.
  • 13. Advantages Disadvantages •Very quick and precise •Comes with huge capital cost •Saves huge time at site •Architectural modification are not possible •Low manpower required •It is being assembled more number of joints to be closed •No plastering required •Minimal strength of concrete can be achieved within hours with acceleration.
  • 14. SI. NO CHARACTERSTICS CONVENTIONAL SYSTEM SYSTEM SHUTTERING PRECAST SYSTEM 1. Material type Plywood, runners, MS sheets Aluminium Mild steel 2. Speed of construction Min cycle time is 21 days Ten days cycle per floor. Five days cycle per floor. 3. Quality of surface finish Cement mortar plastering is required Cement mortar plastering is not required Cement mortar plastering is not required 4. Pre – planning of formwork system Not required Required Required 5. Formwork wastages Huge Less Very less 6. Accuracy Less accurate More accurate Accurate 7. Suitable for high rise construction Not suitable Very much suitable Very much suitable 8. Initial investments Very less High Very high 9. Economy in construction Economical for small scale Suitable for mass houses Suitable for mass houses with less duration.
  • 15.
  • 16.  Modular formwork systems are designed with standardized panels and component items to reduce or limit the need for cutting material on site.  This speeds up the overall process and therefore requires less labour on site. They are also interchangeable with conventional methods.  Modular Formwork Systems are generally easy to assemble and much faster than conventional Formwork, saving time, allowing you to pour sooner.
  • 17. Advantages Does not require a crane to place the formwork Speed of construction with unskilled labour Fast assembly comparably There will be less complications Designed with standardised panels to reduce or limit the need for cutting material on site Hire cost were significantly over than the affiant purchases for conventional formwork
  • 18. Modular Formwork can be used to: 1. Concrete housed construction 2. Elliptical columns construction 3. Large columns construction 4. Reinforced concrete pools construction 5. Bunker construction 6. Art stone textured panels 7. Integration 8. Wall construction 9. Lintels and curtain walls construction 10. Foundation plinths construction
  • 19.
  • 20. Fibre glass shuttering does not require plastering They represent in the area of shuttering because of their lightness, simplicity, durability, solidity resistance to temperature changes
  • 21. Advantages Smoothest finish among existing concrete formwork and shuttering systems Unmatched building quality Durability Lower cost No plastering required Faster project delivery Easy customization and reparability High re-usability
  • 22.
  • 23.  Tunnel Formwork is a steel formwork  It is used during the placing of the concrete to form the floor and the wall at the same time.  They can be in different shapes, sizes and modules.  It allows to cost walls and slakes in an operation on daily cycle  Construction decorations are reduced significantly in comparison to the others  Hi tech technologies for steel formwork makes its strong and durable  It is known as most earthquake structures  Tower cranes are required for the erection, removal and carriage of formworks, scaffolds, and pre-cast components.  Skilled labours are required
  • 24. Advantages The project can be completed in a short time compared to traditional construction systems. Due to accelerated production, effects of climatic conditions on productivity are minimized. Smooth surfaces for the walls and slabs are obtained that can be covered with wallpaper right after easy and quick cleaning. Standard dimensions for the other components such as carpet, windows, and doors can be applicable due to strict dimensions of load- bearing system elements. Due to smooth surfaces, walls and slabs do not need any additional finishing such as plaster. Early completion of project provides financial opportunities such as rental incomes
  • 25. BY ADARSH T S JAI KAUSHIK E R K TCE

Editor's Notes

  1. ORMWORK