Crashing Example: The network and durations given below shows the normal schedule for a
project. You can decrease (crash) the durations at an additional expense. The Table given
below summarizes the time-cost information for the activities. The owner wants you to you
to finish the project in 110 days. Find the minimum possible cost for the project if you want to
finish it on 110 days. (Assume that for each activity there is a single linear, continuous
function between the crash duration and normal duration points).
Activity
Normal
duration
(days)
Crash
Duration
(days)
Normal
Cost
Crash
Cost
A 120 100 12000 14000
B 20 15 1800 2800
C 40 30 16000 22000
D 30 20 1400 2000
E 50 40 3600 4800
F 60 45 13500 18000
Solution:
Assume that the duration-cost relationship for each activity is a single linear, continuous
function between the crash duration and normal duration points. Using the normal duration
(ND), crash duration (CD), normal cost (NC), and crash cost (CC), the crash cost slope for
each activity can be determined as follows;
CD
ND
NC
CC
SA
−
−
=
day
SA /
100
$
100
120
12000
14000
=
−
−
=
SB = $200/day
SC = $600/day
SD = $60/day
SE = $120/day
SF = $300/day
A
120
B
20
C D E
F
40 30 50
60
1 2 3 4 5
The normal cost for the project is the sum of a normal cost for each activity. The normal cost
for the project is $48300 and the normal duration is 140 days. The activity which should be
crashed is the one on the critical path which will add the least amount to the overall project
cost. This will be the activity with the flattest or least-cost slope. The duration can be reduced
as long as the critical path is not changed or a new critical path is created. In addition, the
activity duration cannot be less than the crash duration.
SD = $60/day (least-cost slope) Maximum of 10 days can be cut from this schedule by
reducing the duration of activity D to the crash duration of 20 days.
Overall duration is 130 days and there are multiple critical paths (B-F-E and B-C-D-E). Total
project cost at this duration is the normal cost of $48300 plus the cost of crashing the activity
D by 10 days (60 * 10 = $600) for a total of $48900.
The next activity to be crashed would be the activity E, since it has the least-cost slope ($120
per day) of any of the activities on the critical path. Activity E can be crashed by a total of 10
days. Crashing the activity E by 10 days will cost an additional $120 per day or $1200.
The project duration is now 120 days and the total project cost is $50100. There are now three
critical paths (A, B-C-D-E, and B-F-E). The next stage of crashing requires a more through
analysis since it is impossible to crash one activity alone and achieve a reduction in the
overall project duration. Activity A is paired with each of the other activities to determine
which has the least overall cost slope for those activities which have remaining days to be
crashed.
Activity A ($100) + activity B ($200)
Activity A ($100) + activity C ($600) + activity F ($300)
A
120
B
20
C D E
F
40 30 50
20 40
60
1 2 3 4 5
A
120
B
20
C D E
F
40 30 50
20
60
1 2 3 4 5
The least-cost slope will be activity A + activity B for a cost increase of $300 per day.
Reducing the project duration by 5 days will add 5*300 = $1500 dollar crashing cost and the
total project cost would be $51600. Activity B can not be crashed any more.
Final step in crashing the project to 110 days would be accomplished by reducing the duration
of activity A by 5 days to 110 days, reducing activity C by 5 days to 35 days, and reducing
activity F by 5 days to 55 days. The combined cost slope for the simultaneous reduction of
activity A, activity C, and activity F would be $1000 per day. For 5 days of reduction this
would be an additional $5000 in total project cost. The total project cost for the crashed
schedule to 110 days of duration would be $56600.
A
120
B
20
C D E
F
40 30 50
20 40
60
15
115
55
110
35
1 2 3 4 5
A
120
B
20
C D E
F
40 30 50
20 40
60
15
115
1 2 3 4 5

More Related Content

What's hot (20)

08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
9 penjadwalan proyek dengan cpm
9 penjadwalan proyek dengan cpm9 penjadwalan proyek dengan cpm
9 penjadwalan proyek dengan cpm
 
EKMA4413 - Riset Operasi - Modul 6
EKMA4413 - Riset Operasi - Modul 6EKMA4413 - Riset Operasi - Modul 6
EKMA4413 - Riset Operasi - Modul 6
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project cost control
Project cost controlProject cost control
Project cost control
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
Pmp5
Pmp5Pmp5
Pmp5
 
Manajemen proyek
Manajemen proyekManajemen proyek
Manajemen proyek
 
CPM DAN PERT
CPM DAN PERTCPM DAN PERT
CPM DAN PERT
 
Human Factor In Project Management
Human Factor In Project ManagementHuman Factor In Project Management
Human Factor In Project Management
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)
 
Pmp2
Pmp2Pmp2
Pmp2
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Konsep Biaya dan Perilaku Biaya
Konsep Biaya dan Perilaku BiayaKonsep Biaya dan Perilaku Biaya
Konsep Biaya dan Perilaku Biaya
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
Pmp4
Pmp4Pmp4
Pmp4
 

Similar to Cpm crashing example

Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdfssuserc9da59
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
Running Head DIRECT COST .docx
 Running Head DIRECT COST                                        .docx Running Head DIRECT COST                                        .docx
Running Head DIRECT COST .docxaryan532920
 
Crash management
Crash managementCrash management
Crash managementAhmed Gamal
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptxkimkov119
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxssuser9b876d
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisationCharul Sharma
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxssuser85ddaa
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpmJulius Cuaresma
 
economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami Louy Alhamy
 
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...mianmohsinmumtazshb
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 

Similar to Cpm crashing example (20)

Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
MODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdfMODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdf
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Running Head DIRECT COST .docx
 Running Head DIRECT COST                                        .docx Running Head DIRECT COST                                        .docx
Running Head DIRECT COST .docx
 
Crashing
CrashingCrashing
Crashing
 
Crash management
Crash managementCrash management
Crash management
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptx
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 
vk1
vk1vk1
vk1
 
Ise 307- chapter 9
Ise 307- chapter 9 Ise 307- chapter 9
Ise 307- chapter 9
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
 
economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami
 
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Ch2(2011
Ch2(2011Ch2(2011
Ch2(2011
 
Ch12ppt
Ch12pptCh12ppt
Ch12ppt
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 

Cpm crashing example

  • 1. Crashing Example: The network and durations given below shows the normal schedule for a project. You can decrease (crash) the durations at an additional expense. The Table given below summarizes the time-cost information for the activities. The owner wants you to you to finish the project in 110 days. Find the minimum possible cost for the project if you want to finish it on 110 days. (Assume that for each activity there is a single linear, continuous function between the crash duration and normal duration points). Activity Normal duration (days) Crash Duration (days) Normal Cost Crash Cost A 120 100 12000 14000 B 20 15 1800 2800 C 40 30 16000 22000 D 30 20 1400 2000 E 50 40 3600 4800 F 60 45 13500 18000 Solution: Assume that the duration-cost relationship for each activity is a single linear, continuous function between the crash duration and normal duration points. Using the normal duration (ND), crash duration (CD), normal cost (NC), and crash cost (CC), the crash cost slope for each activity can be determined as follows; CD ND NC CC SA − − = day SA / 100 $ 100 120 12000 14000 = − − = SB = $200/day SC = $600/day SD = $60/day SE = $120/day SF = $300/day A 120 B 20 C D E F 40 30 50 60 1 2 3 4 5
  • 2. The normal cost for the project is the sum of a normal cost for each activity. The normal cost for the project is $48300 and the normal duration is 140 days. The activity which should be crashed is the one on the critical path which will add the least amount to the overall project cost. This will be the activity with the flattest or least-cost slope. The duration can be reduced as long as the critical path is not changed or a new critical path is created. In addition, the activity duration cannot be less than the crash duration. SD = $60/day (least-cost slope) Maximum of 10 days can be cut from this schedule by reducing the duration of activity D to the crash duration of 20 days. Overall duration is 130 days and there are multiple critical paths (B-F-E and B-C-D-E). Total project cost at this duration is the normal cost of $48300 plus the cost of crashing the activity D by 10 days (60 * 10 = $600) for a total of $48900. The next activity to be crashed would be the activity E, since it has the least-cost slope ($120 per day) of any of the activities on the critical path. Activity E can be crashed by a total of 10 days. Crashing the activity E by 10 days will cost an additional $120 per day or $1200. The project duration is now 120 days and the total project cost is $50100. There are now three critical paths (A, B-C-D-E, and B-F-E). The next stage of crashing requires a more through analysis since it is impossible to crash one activity alone and achieve a reduction in the overall project duration. Activity A is paired with each of the other activities to determine which has the least overall cost slope for those activities which have remaining days to be crashed. Activity A ($100) + activity B ($200) Activity A ($100) + activity C ($600) + activity F ($300) A 120 B 20 C D E F 40 30 50 20 40 60 1 2 3 4 5 A 120 B 20 C D E F 40 30 50 20 60 1 2 3 4 5
  • 3. The least-cost slope will be activity A + activity B for a cost increase of $300 per day. Reducing the project duration by 5 days will add 5*300 = $1500 dollar crashing cost and the total project cost would be $51600. Activity B can not be crashed any more. Final step in crashing the project to 110 days would be accomplished by reducing the duration of activity A by 5 days to 110 days, reducing activity C by 5 days to 35 days, and reducing activity F by 5 days to 55 days. The combined cost slope for the simultaneous reduction of activity A, activity C, and activity F would be $1000 per day. For 5 days of reduction this would be an additional $5000 in total project cost. The total project cost for the crashed schedule to 110 days of duration would be $56600. A 120 B 20 C D E F 40 30 50 20 40 60 15 115 55 110 35 1 2 3 4 5 A 120 B 20 C D E F 40 30 50 20 40 60 15 115 1 2 3 4 5