SlideShare a Scribd company logo
1 of 21
Time Management
Problem-Set-1
Dr. Syed Amir Iqbal.
Produce a network diagram using the data below, identify the critical
path and record the project duration.
Task Duration Predecessor
A 5 Start
B 8 A
C 3 B
D 4 A
E 5 C
F 7 C
G 6 D,E
H 8 F
I 6 G
J 5 H,I
Task Duration Predecessor
A 1
B 8 A
C 4 A
P 7 A
L 2 B
M 4 C
Q 4 P,C
N 9 P
Y 5 L,Q
F 10 M
J 2 Q
S 2 N
V 5 Y,F,J
Z 1 V,S
• Construct a
precedence diagram.
• On the diagram,
compute the four
schedule times for
each activity.
• Identify the critical
path
An automobile
manufacturer is
developing a new
model of car, and the
following table shows
some of the
information relating to
the major activities
involved in this project:
For the following table of information,
1. Draw the network diagram
2. List the network paths
3. Determine the critical path(s)
4. Determine the float for each activity
For the following table of information,
1. Draw the network diagram 3. Determine the critical path(s)
2. List the network paths 4. Determine the float for each activity
Task Duration Predecessor
Start 0
A 5 Start
B 2 Start
C 3 A, B
D 5 Start
E 6 Start
F 4 D, E
G 2 C, F
H 5 G
I 7 G
J 3 H
Finish 0 I, J
Perform a Forward Pass and a Backward Pass of the network
diagram given and identify critical path?
For the information given find:
a) Critical Path
b) Cost of completing the project 3 weeks earlier.
Activity Precedence Time (Weeks) Cost ($)
Normal Crash Normal Crash
A - 4 2 10000 11000
B A 3 2 6000 9000
C A 2 1 4000 6000
D B 5 3 14000 18000
E B,C 1 1 9000 9000
F C 3 2 7000 8000
G E,F 4 2 13000 25000
H D,E 4 1 11000 18000
I H,G 6 5 20000 29000
Activity Precedence Time (Weeks) Cost ($) Cost/Week Weeks to Compress
Normal Crash Normal Crash
A - 4 2 10000 11000 500 2
B A 3 2 6000 9000 3000 1
C A 2 1 4000 6000 2000 1
D B 5 3 14000 18000 2000 2
E B,C 1 1 9000 9000 0 0
F C 3 2 7000 8000 1000 1
G E,F 4 2 13000 25000 6000 2
H D,E 4 1 11000 18000 2333 3
I H,G 6 5 20000 29000 9000 1
A=4
B=3
E=1
F=3
G=4
I=6
H=4
D=5
C=2
A-B-D-H-I = 22
A-B-E-H-I = 18
A-B-E-G-I = 18
A-C-E-H-I = 17
A-C-E-G-I = 17
A-C-F-G-I = 19
Activity Precedence Time (Weeks) Cost ($) Cost ($) /Week Weeks to Compress
Normal Crash Normal Crash
A - 4 2 10000 11000 500 2
B A 3 2 6000 9000 3000 1
C A 2 1 4000 6000 2000 1
D B 5 3 14000 18000 2000 2
E B,C 1 1 9000 9000 0 0
F C 3 2 7000 8000 1000 1
G E,F 4 2 13000 25000 6000 2
H D,E 4 1 11000 18000 2333 3
I H,G 6 5 20000 29000 9000 1
A-B-D-H-I = 22
A-B-E-H-I = 18
A-B-E-G-I = 18
A-C-E-H-I = 17
A-C-E-G-I = 17
A-C-F-G-I = 19
A=4
B=3
E=1
F=3
G=4
I=6
H=4
D=5
C=2
For Week-1
• Reduce activity A to 3 weeks and additional cost will be $500.
• Now path A-B-D-H-I will be 21 weeks and is still the critical path.
For Week-2
• Activity A still have 1 week cushion for time reduction. So Reduce
activity A to one more week. So current duration of activity A is 2
weeks with additional cost of $500.
• New duration of path A-B-D-H-I is 20 weeks and it is still the
critical path. Activity A is now exhausted and further reduction in
this activity is not possible.
For Week-3
• Now among activities B-D-H-I, activity D has the lowest reduction
cost/week. So reduce activity D by one week with additional cost
of $ 2000. New duration of activity D is 4 weeks. The total
duration of A-B-D-H-I is 19 weeks.
• Now the project duration is reduced from 22 weeks to 19 weeks
and the project has two critical paths A-B-D-H-I & A-C-F-G-I.
A None 7
B A 3
C A 4
D B,C 5
E D 2
F D 4
G E,F 5
Act. Imed. Pred. Time
A(7)
B(3)
C(4)
D(5)
E(2)
F(4)
G(5)
Time – Cost Analysis
Crashing the Project (Crash 4 days)
Activity Normal
Time
Crash
Time
Normal
Cost
Crash
Cost
Cost/Day
A 7 6 $7,000 $8,000 $1,000
B 3 2 5,000 7,000 2,000
C 4 3 9,000 10,200 1,200
D 5 4 3,000 4,500 1,500
E 2 1 2,000 3,000 1,000
F 4 2 4,000 7,000 1,500
G 5 4 5,000 8,000 3,000
17
For the data given in the table, Compute critical
path using PERT technique.
Activity Predecessor
Time
Te S.D.
To Tm Tp
A - 2 4 6 4 0.667
B A 8 11 20 12 2.000
C A 10 15 20 15 1.667
D B 12 18 24 18 2.000
E C 8 13 24 14 2.667
F C 4 7 16 8 2.000
G D,F 14 18 28 19 2.333
H E 10 12 14 12 0.667
I G,H 7 10 19 11 2.000
For the data given in the table,
Compute critical path using PERT
technique.
Activity Predecessor
Time
Te S.D.
To Tm Tp
A - 12 14 22 15 1.667
B - 16 17 24 18 1.333
C A 14 15 16 15 0.333
D A 13 18 23 18 1.667
E B 16 18 20 18 0.667
F D,E 13 14 21 15 1.333
G C,F 6 8 10 8 0.667

More Related Content

Similar to CPM-PERT-Examples .pptx

Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newuopassignment
 
Project management
Project managementProject management
Project managementTrade Expert
 
1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docxjackiewalcutt
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdfssuserc9da59
 
Project management project scheduling
Project management  project schedulingProject management  project scheduling
Project management project schedulingTadele Asmare
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docxdrennanmicah
 
Consider the following resource loading table. Assume that we canno.docx
Consider the following resource loading table.  Assume that we canno.docxConsider the following resource loading table.  Assume that we canno.docx
Consider the following resource loading table. Assume that we canno.docxdonnajames55
 
Project management activity task
Project management activity taskProject management activity task
Project management activity taskTadele Asmare
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptxkimkov119
 
Quantitative Techniques
Quantitative TechniquesQuantitative Techniques
Quantitative TechniquesSanaRiaz789
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpmJulius Cuaresma
 
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...Siddharth Modi
 

Similar to CPM-PERT-Examples .pptx (20)

Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
 
Project management
Project managementProject management
Project management
 
1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Project management project scheduling
Project management  project schedulingProject management  project scheduling
Project management project scheduling
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
 
Consider the following resource loading table. Assume that we canno.docx
Consider the following resource loading table.  Assume that we canno.docxConsider the following resource loading table.  Assume that we canno.docx
Consider the following resource loading table. Assume that we canno.docx
 
Project management activity task
Project management activity taskProject management activity task
Project management activity task
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
 
Quantitative Techniques
Quantitative TechniquesQuantitative Techniques
Quantitative Techniques
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Time-Cost Tradeoff by Examples
Time-Cost Tradeoff by ExamplesTime-Cost Tradeoff by Examples
Time-Cost Tradeoff by Examples
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
 
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
 
Cpm crashing example
Cpm crashing exampleCpm crashing example
Cpm crashing example
 
Crashing
CrashingCrashing
Crashing
 
Assignment 101
Assignment 101Assignment 101
Assignment 101
 
MODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdfMODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdf
 

Recently uploaded

VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 

Recently uploaded (20)

Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 

CPM-PERT-Examples .pptx

  • 2. Produce a network diagram using the data below, identify the critical path and record the project duration. Task Duration Predecessor A 5 Start B 8 A C 3 B D 4 A E 5 C F 7 C G 6 D,E H 8 F I 6 G J 5 H,I
  • 3.
  • 4. Task Duration Predecessor A 1 B 8 A C 4 A P 7 A L 2 B M 4 C Q 4 P,C N 9 P Y 5 L,Q F 10 M J 2 Q S 2 N V 5 Y,F,J Z 1 V,S • Construct a precedence diagram. • On the diagram, compute the four schedule times for each activity. • Identify the critical path
  • 5. An automobile manufacturer is developing a new model of car, and the following table shows some of the information relating to the major activities involved in this project:
  • 6. For the following table of information, 1. Draw the network diagram 2. List the network paths 3. Determine the critical path(s) 4. Determine the float for each activity
  • 7.
  • 8. For the following table of information, 1. Draw the network diagram 3. Determine the critical path(s) 2. List the network paths 4. Determine the float for each activity Task Duration Predecessor Start 0 A 5 Start B 2 Start C 3 A, B D 5 Start E 6 Start F 4 D, E G 2 C, F H 5 G I 7 G J 3 H Finish 0 I, J
  • 9.
  • 10. Perform a Forward Pass and a Backward Pass of the network diagram given and identify critical path?
  • 11. For the information given find: a) Critical Path b) Cost of completing the project 3 weeks earlier. Activity Precedence Time (Weeks) Cost ($) Normal Crash Normal Crash A - 4 2 10000 11000 B A 3 2 6000 9000 C A 2 1 4000 6000 D B 5 3 14000 18000 E B,C 1 1 9000 9000 F C 3 2 7000 8000 G E,F 4 2 13000 25000 H D,E 4 1 11000 18000 I H,G 6 5 20000 29000
  • 12. Activity Precedence Time (Weeks) Cost ($) Cost/Week Weeks to Compress Normal Crash Normal Crash A - 4 2 10000 11000 500 2 B A 3 2 6000 9000 3000 1 C A 2 1 4000 6000 2000 1 D B 5 3 14000 18000 2000 2 E B,C 1 1 9000 9000 0 0 F C 3 2 7000 8000 1000 1 G E,F 4 2 13000 25000 6000 2 H D,E 4 1 11000 18000 2333 3 I H,G 6 5 20000 29000 9000 1
  • 13. A=4 B=3 E=1 F=3 G=4 I=6 H=4 D=5 C=2 A-B-D-H-I = 22 A-B-E-H-I = 18 A-B-E-G-I = 18 A-C-E-H-I = 17 A-C-E-G-I = 17 A-C-F-G-I = 19
  • 14. Activity Precedence Time (Weeks) Cost ($) Cost ($) /Week Weeks to Compress Normal Crash Normal Crash A - 4 2 10000 11000 500 2 B A 3 2 6000 9000 3000 1 C A 2 1 4000 6000 2000 1 D B 5 3 14000 18000 2000 2 E B,C 1 1 9000 9000 0 0 F C 3 2 7000 8000 1000 1 G E,F 4 2 13000 25000 6000 2 H D,E 4 1 11000 18000 2333 3 I H,G 6 5 20000 29000 9000 1
  • 15. A-B-D-H-I = 22 A-B-E-H-I = 18 A-B-E-G-I = 18 A-C-E-H-I = 17 A-C-E-G-I = 17 A-C-F-G-I = 19 A=4 B=3 E=1 F=3 G=4 I=6 H=4 D=5 C=2 For Week-1 • Reduce activity A to 3 weeks and additional cost will be $500. • Now path A-B-D-H-I will be 21 weeks and is still the critical path. For Week-2 • Activity A still have 1 week cushion for time reduction. So Reduce activity A to one more week. So current duration of activity A is 2 weeks with additional cost of $500. • New duration of path A-B-D-H-I is 20 weeks and it is still the critical path. Activity A is now exhausted and further reduction in this activity is not possible. For Week-3 • Now among activities B-D-H-I, activity D has the lowest reduction cost/week. So reduce activity D by one week with additional cost of $ 2000. New duration of activity D is 4 weeks. The total duration of A-B-D-H-I is 19 weeks. • Now the project duration is reduced from 22 weeks to 19 weeks and the project has two critical paths A-B-D-H-I & A-C-F-G-I.
  • 16. A None 7 B A 3 C A 4 D B,C 5 E D 2 F D 4 G E,F 5 Act. Imed. Pred. Time A(7) B(3) C(4) D(5) E(2) F(4) G(5)
  • 17. Time – Cost Analysis Crashing the Project (Crash 4 days) Activity Normal Time Crash Time Normal Cost Crash Cost Cost/Day A 7 6 $7,000 $8,000 $1,000 B 3 2 5,000 7,000 2,000 C 4 3 9,000 10,200 1,200 D 5 4 3,000 4,500 1,500 E 2 1 2,000 3,000 1,000 F 4 2 4,000 7,000 1,500 G 5 4 5,000 8,000 3,000 17
  • 18. For the data given in the table, Compute critical path using PERT technique.
  • 19. Activity Predecessor Time Te S.D. To Tm Tp A - 2 4 6 4 0.667 B A 8 11 20 12 2.000 C A 10 15 20 15 1.667 D B 12 18 24 18 2.000 E C 8 13 24 14 2.667 F C 4 7 16 8 2.000 G D,F 14 18 28 19 2.333 H E 10 12 14 12 0.667 I G,H 7 10 19 11 2.000
  • 20. For the data given in the table, Compute critical path using PERT technique.
  • 21. Activity Predecessor Time Te S.D. To Tm Tp A - 12 14 22 15 1.667 B - 16 17 24 18 1.333 C A 14 15 16 15 0.333 D A 13 18 23 18 1.667 E B 16 18 20 18 0.667 F D,E 13 14 21 15 1.333 G C,F 6 8 10 8 0.667