SlideShare a Scribd company logo
1 of 92
Download to read offline
ME6005
PROCESS
PLANNING AND
COST
ESTIMATION
UNIT III
INTRODUCTION TO COST
ESTIMATION
 Importance of costing and estimation
 Methods of costing-elements of cost estimation
 Types of estimates
 Estimating procedure
 Estimation labor cost, material cost
 Allocation of over head charges
 Calculation of depreciation cost
WHAT IS MEAN BY COST ESTIMATION?
WHAT IS MEAN BY COST ESTIMATION?
 Estimation of the expected cost of producing a job
 Executing a manufacturing order before the
actual production is taken up
 Predicting what new products will cost before
they are made
DEFINITION
DEFINITION
Costing or cost accounting means classifying,
recording and allocating the appropriate expenditure for
determining the cost of production and achieved by
keeping a continuous record of all the costs involved in
manufacturing
REASONS FOR DOING ESTIMATES
REASONS FOR DOING ESTIMATES
 Should the product be produced?
 When a company designs a new product
 To assist management in making an intelligent decision
about producing the product.
GENERAL PROCEDURE
GENERAL PROCEDURE
 A cost estimate must be developed for jigs, fixtures,
tools, dies and gauges
 Also, the cost of any capital equipment must be entered
into the estimate
 These figures are usually supplied through quotation by
vendors
 An estimate of this nature will include a vast amount of
details, because if management approves the project, the
estimate now becomes the budget
OBJECTIVES (OR) PURPOSE OF
ESTIMATING
OBJECTIVES (OR) PURPOSE OF
ESTIMATING
 To establish the selling price of a product
 To ascertain whether a proposed product can be
manufactured and marketed profitably
 To determine how much must be invested in equipment
 To find whether parts or assemblies can be more cheaply
fabricated or purchased from outside (make or buy decision)
 To determine the most economical process, tooling or material
for making a product
FUNCTIONS OF ESTIMATING
FUNCTIONS OF ESTIMATING
 To calculate the cost of new material needed to
manufacture a product
 To find the cost of parts to be purchased from outside
vendors
 To find the cost of equipment, machinery, tools, jigs
and fixtures etc. required to be purchased to make the
product
 To calculate the direct and indirect labour cost
associated with the manufacture of the product, based
upon work study.
 To calculate various overhead charges associated with
the product.
 To decide about the profit to be charged, taking into consideration
other manufacturers of same product in the market
 To calculate the selling price of the product
 To maintain records of previous estimating activities of the
company for future references
 To decide the most economical method of making the product
 To submit cost estimates with the competent authority for further
action
FUNCTIONS OF ESTIMATING
FUNCTIONS OF ESTIMATING
Contd.,
COMPONENTS OF A COST
ESTIMATE OR JOB ESTIMATE
COMPONENTS OF A COST
ESTIMATE OR JOB ESTIMATE
1. Cost of design
2. Cost of drafting
3. Cost of research and development
4. Cost of raw materials
5. Cost of labour
6. Cost of inspection
7. Cost of tools, jigs and fixtures
8. Overhead cost
1. COST OF DESIGN
1. COST OF DESIGN
 The cost of design of a component or product is
estimated by ascertaining the expected time for the
design of that component
 The estimate design time multiplied by the salary of
designer per unit time gives the estimated cost of
design
 If the design of the component is done by some
outside agency, the total amount paid to outside
agency gives the cost of design.
2. COST OF DRAFTING
2. COST OF DRAFTING
 Once the design of the component is
complete, its drawings have to be prepared
by draftsman
 The expected time to be spent in drawing or
drafting is estimated and is then multiplied by
the standard drafting rate or by the salary of the
draftsman per unit time to get estimated cost of
drafting
3. COST OF RESEARCH AND DEVELOPMENT WORK
3. COST OF RESEARCH AND DEVELOPMENT WORK
 Before taking up the manufacturing of actual
components/parts considerable time and money has to
be spent on research and development
 The research may be theoretical, experimental or
developmental research.
 The cost of R and D can be estimated by considering
various items of expenditure incurred during R and D
work
4. COST OF RAW MATERIAL
4. COST OF RAW MATERIAL
 A list of all the materials used in the manufacture of the
product is made which includes the direct as well as
indirect materials
 The quantity (weight or volume) of all the material
expected to be used in the manufacture of the product
is estimated.
 The allowance for material wastage, spoilage and scarp
are also added for each component/part.
4. COST OF RAW MATERIAL
4. COST OF RAW MATERIAL
Cost of each material is estimated by multiplying
the estimated quantity of each material with its
estimated future price
The estimate of future price of a material is made
keeping in view of present prices and general
trends and variations
Estimated cost of all the materials is added to get
the overall estimated material cost
Contd.,
5. COST OF LABOUR
5. COST OF LABOUR
 The cost of labour involved in the manufacture of a
product is estimated by estimating the labour time
needed to manufacture the product and multiplying it
by cost of labour per hour.
 In order to estimate the labour time expected to be
spent on a job, one must have thorough knowledge of
the various operations to be performed, machines to
be used, sequence of operations, tools to be used and
labour rates
6. COST OF INSPECTION
6. COST OF INSPECTION
 A product being manufactured is inspected at various
stages during its manufacture
 It may be inspection of raw material or in-process
inspection or inspection of finished goods
7. COST AND MAINTENANCE CHARGES OF TOOLS, JIGS
AND FIXTURES
7. COST AND MAINTENANCE CHARGES OF TOOLS, JIGS
AND FIXTURES
 The cost of tools, jigs, fixtures etc., is estimated
considering their present prices, market trend and the
number of times a particular tool can be used during
its life-time.
 The estimated cost divided by the number of jobs it
can make, gives the tool cost per unit produced
8. OVERHEAD COSTS
8. OVERHEAD COSTS
 Overhead or indirect costs are those which are
not incurred specifically for any one order or
product and these can not be charged directly to
a specific order or product
 The overhead costs may be estimated by
referring to the records of overhead costs in
similar items produced in past
BASIC STEPS IN COST ESTIMATION
BASIC STEPS IN COST ESTIMATION
1. Make thorough study of cost estimation request to understand it
fully.
2. Make an analysis of the product and prepare a bill of materials.
3. Make separate lists of parts to be purchased from the market and
parts to be manufactured in plant.
4. Determine the cost of parts to be purchased from outside.
5. Estimate the material cost for the parts/components to be
manufactured in plant.
BASIC STEPS IN COST ESTIMATION
BASIC STEPS IN COST ESTIMATION
6. Make manufacturing process plan for the parts to be manufactured
in plant.
7. Estimate the machining time for each operation listed in the
manufacturing process plan.
8. Multiply each operation time by the labour wage rate and add them
up to find direct labour cost
9. Add the estimate of step 4, 5, and 8 to get prime cost of
component.
10. Apply overhead costs to get the total cost of the component.
The selling price of the component is estimated by adding profit to
the total cost obtained in step 10.
TYPES OF COST ESTIMATES
TYPES OF COST ESTIMATES
(a) Factor Method of Cost Estimation
(b) Material Cost Method of Estimation
(c) Function Method of Cost Estimation
Other types
(i) Product comparison
(ii) Data base calculations
FACTOR METHOD OF COST ESTIMATION
FACTOR METHOD OF COST ESTIMATION
Estimated cost of an item = Factor for total cost
estimate × Amount of major cost item
Example:
(i) Cost of construction per km of highway
(ii) Cost of fabricated component per kg of casting
(iii) Cost of house construction per Sq.m. of
livable space
Example Problem:
If a casting weighed 15 kg, and the factor of the cost of
casting per kg of casting is Rs. 75, what is the estimated
cost of the casting ?
Estimated cost of the casting = Rs. 75 per kg of casting
× wt. of the casting (15 kg) = Rs. 1125 per casting
MATERIAL COST METHOD OF
ESTIMATION
MATERIAL COST METHOD OF
ESTIMATION
Material cost method predicts the total cost of the
product based on the ratio of the material cost of
the product to the material cost share of the total
cost.
Estimated cost of an item
=
Material cost of the item being estimated
Material cost share of item being estimated (in %)
Examples of material cost share :
Product Material cost share (%)
Passenger car 65%
Diesel engine 50%
Clocks, watches 25%
Glass product 10%
Example Problem:
If the material cost of an automobile was Rs. 2.50
Lakhs, what would be the total cost of the automobile ?
Use the table above.
Estimated total cost of automobile = Rs. 2.50 Lakhs /
0.65 = Rs. 3.85 Lakhs
 This method is similar to the factor method, but
more variables are used.
 Function method uses a mathematical expression
with constants and parameters derived for
specific process, such as casting or machining or
for specific classes of parts based on material,
size, weight or other cost parameters.
Function Method of Estimation
Function Method of Estimation
According to this method :
Estimated cost of an item = G × (a + b) + (R × c) + (N × d)
where
G = Weight of the item, kg
a = Material cost per kg
b = Tolerance cost per, kg
R = Weight of material Removed, kg
c = Cost per kg of material removed
N = No. of dimensions of a product surface
d = Cost per dimension
Function Method of Estimation
Function Method of Estimation
Contd.,
(i) Product comparison :
The new product is compared with existing
products (of similar function, design etc.) and
adjustments/modifications are made for the differences.
(ii) Data base calculations :
The product cost estimate is determined from cost
data bases which a company is expected to maintain
over a period of time (Historical Cost Data Base).
ELEMENTS OF COST
ELEMENTS OF COST
 Material cost
(a) Direct material cost
(b) Indirect material cost
 Labour cost
(a) Direct labour cost
(b) Indirect labour cost
 Other expenses
(a) Direct expenses
(b) Indirect expenses
(i) Factory expenses
(ii) Administrative expenses
(iii) Selling and distribution expenses
MATERIAL COST
MATERIAL COST
Direct material cost
(i) From the product drawing, make a list of all the
components required to make the final product.
(ii) Calculate the volume of each component from the
drawing dimensions after adding machining allowances,
wherever necessary.
(iii) The volume of component multiplied by the density
of material used gives the weight of the material per
component.
MATERIAL COST
MATERIAL COST
Direct material cost
(iv) Add process rejection and other allowances like
cutting allowance to get the gross weight per
component.
(v) Multiply the gross weight by the cost of material per
unit weight to get the cost of raw material per
component.
(vi) The cost of raw material for all the components is,
similarly, calculated and added up which gives the cost
of direct material for the product.
Contd.,
MATERIAL COST
MATERIAL COST
Indirect material cost
 The indirect materials include oils, general tools,
grease, sand papers, coolants, cotton waste etc.
 The cost associated with indirect materials is
called indirect material cost.
LABOUR COST
LABOUR COST
Direct labour cost
 Direct labourer is one who actually works and
processes the materials to convert it into the final
shape.
 The cost associated with direct labour is called direct
labour cost.
 The direct labour are the workers operating lathes,
milling machines or welders, or assemblers in
assembly shop.
LABOUR COST
LABOUR COST
Indirect labour cost
 Indirect labourer is one who is not directly employed
in the manufacturing of the product but his services
are used in some indirect manner.
 The cost associated with indirect labour is called
indirect labour cost.
 The indirect labour includes supervisors, inspectors,
foreman, storekeeper, gatekeeper, maintenance staff,
crane driver etc.
OTHER EXPENSES
OTHER EXPENSES
Direct expenses
 Direct expenses include all that expenditure which can
be directly allocated and charged to a particular job.
 The direct expenses include cost of special jigs or
fixtures, patterns, toolings made for job, or cost of
research and development work done for that specific
job.
OTHER EXPENSES
OTHER EXPENSES
Indirect expenses
 Except direct expenses, all other indirect expenditure
incurred by the manufacturer is called indirect
expenses
 The indirect expenses are also called overhead
expenses or on-cost
The indirect expenses are further classified as
(i) Factory expenses
(ii) Administrative expenses
(iii) Selling and distribution expenses
OTHER EXPENSES
OTHER EXPENSES
Indirect expenses - Factory expenses
 Factory expenses comprise of the indirect
expenses incurred from the receipt of the order
to the completion of production.
 Includes rent of factory building, licence fee,
electricity and telephone bills of factory,
insurance charges etc.
OTHER EXPENSES
OTHER EXPENSES
Indirect expenses - Administrative expenses
 Administrative expenses or office expenses
include the expenditure incurred on control and
administration of the factory
 It includes the salaries of office and
administrative staff, rent of office building,
postage and telephone charges, water and
electricity charges for office, Director’s fee, legal
and audit charges etc.
OTHER EXPENSES
OTHER EXPENSES
Indirect expenses - Selling and distribution
expenses
 his is the expenditure incurred on Sales
Department for selling the product
 It includes the wages, salaries, commission and
travelling allowances of salesmen and officers in
Sales Department, cost of advertisement,
packing, delivery and distribution expenses, rent
of warehouses etc.
METHODS OF ESTIMATING
METHODS OF ESTIMATING
 Conference method
 Comparison method
 Detailed analysis method
CONFERENCE METHOD
CONFERENCE METHOD
 A co-ordinator from either accounting or
estimating collect costs and applies overhead
factors to develop a total manufacturing cost for
the product
 If vague or only verbal information is available,
then the total product material, labour and tooling
will be estimated as one lump sum for each
 The degree of accuracy of this method depends
upon the availability of specificaitions, samples
and drawings
COMPARISON METHOD
COMPARISON METHOD
 In this method of estimating the costs of similar
parts are applied to the product and are adjusted to
suit variations in the workpiece, material and
labour costs.
 It is based on the accumulation of past experience
data
DETAILED ANALYSIS METHOD
DETAILED ANALYSIS METHOD
This method involves
I. Calculation of raw material usage including scrap
allowance and salvage material
II. Processing each individual component (writing the
operation sheet)
III. Determining the production time (direct labour) for each
operation
IV. The equipment required (new, network, or on hand)
V. Tools, gauges, and special fixtures or dies,
VI. Inspection and testing equipment
VII. Packaging and shipping requirements
COST ESTIMATING PROCEDURE
COST ESTIMATING PROCEDURE
Step 1: Study the cost estimation request thoroughly
and understand it completely
Step 2: Analyse the product and decide the
requirements and specifications of the product
Step 3: Prepare the list of all the parts of the product
and their bill of materials
Step 4: Take make or buy decisions and prepare
separate lists of parts to be manufactured within the
plant and parts to be purchased outside the plant
COST ESTIMATING PROCEDURE
COST ESTIMATING PROCEDURE
Step 5: Estimate the materials cost for the parts to be manufactured in
the plant
Material cost =
Weight of the
material
×
Material cost per
unit weight
Step 6 : Determine the cost of parts to be purchased from outside
Step 7: Make a manufacturing process plan for the parts to be
manufactured in the plant
Contd.,
COST ESTIMATING PROCEDURE
COST ESTIMATING PROCEDURE
Step 8: Estimate the machining time for each operations listed in
the manufacturing process plan
Step 9: Determine the direct labour cost
Direct labour cost =
Total operation
time
×
Labour
wage rate
Step 10: Determine the prime cost by adding direct expenses,
direct material cost, and direct labour cost
∴ Prime cost =
Direct
labour
cost
+
Direct
material cost
+
Direct
expenses
Contd.,
COST ESTIMATING PROCEDURE
COST ESTIMATING PROCEDURE
Step 11: Estimate the factory overheads, which include all
indirect expenditure incurred during production such as
indirect material cost, indirect labour cost, depreciation and
expenditure on maintenance of the plant, machinery, power,
etc.
Step 12: Estimate the administrative expenses
Contd.,
COST ESTIMATING PROCEDURE
COST ESTIMATING PROCEDURE
Step 13: Estimate the selling and distribution expenses
which include packing and delivery charges, advertisement
charges, etc.
Step 14: Now calculate the total cost of the product
Total Cost
=
Prime
Cost
+
Factory
overheads
+
Administrative
expenses
+
Selling and
distribution expenses
Contd.,
COST ESTIMATING PROCEDURE
COST ESTIMATING PROCEDURE
Step 15: Decide the profit and add the profit to the total cost
to fix the selling price of the part
Selling Price = Total cost + Profit
Step 16: Finally estimate the time of delivery in
consultation with the production and sales department
Contd.,
ESTIMATE FORM
ESTIMATE FORM
After estimating all the
elements of cost
estimate, these estimated
datas are entered into an
estimate form
COST OF PRODUCT
(LADDER OF COSTS)
COST OF PRODUCT
(LADDER OF COSTS)
1. Prime cost = Direct material cost + Direct
labour cost + Direct expenses
2. Factory cost = Prime cost + Factory expenses
3. Production cost = Factory cost + Administrative
expenses
4. Total or Ultimate cost = Production cost +
Selling and distribution expenses.
5. Selling price = Ultimate cost + Profit
BLOCK DIAGRAM
BLOCK DIAGRAM
Example: Calculate prime cost, factory cost, production cost, total cost and
selling price per item from the data given below for the year 2003-04.
Example : From the following data for a sewing machine manufacturer,
prepare a statement showing prime cost, Works/factory cost, production cost,
total cost and profit.
Example : From the following data for a sewing machine manufacturer,
prepare a statement showing prime cost, Works/factory cost, production cost,
total cost and profit.
ESTIMATION OF MATERIALS COST
ESTIMATION OF MATERIALS COST
Procedure
 Study the given drawing carefully. Then break up
the product into simple geometrical shapes such as
cubes, prisms, cylinders, etc.,
 Calculate the volume of each parts using formulae
 Add volumes to get total volume
 Calculate the weight of material by Volume ×
Density
 Material cost =
Weight of the
material
×
Material cost per
unit weight
Example
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii
Process planning and cost estimation  unit   iii

More Related Content

What's hot

Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Pratik Gandhi
 
Process planning and cost estimation unit i
Process planning and cost estimation  unit   iProcess planning and cost estimation  unit   i
Process planning and cost estimation unit is Kumaravel
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONSathishkumarM89
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )TAMILMECHKIT
 
Intro to CAD CAM Tools
Intro to CAD CAM ToolsIntro to CAD CAM Tools
Intro to CAD CAM ToolsAbhay Gore
 
CUTTING TOOL SELECTION
CUTTING TOOL SELECTIONCUTTING TOOL SELECTION
CUTTING TOOL SELECTIONarunkumar6836
 
Unit 5 -1-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
Unit 5 -1-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURINGUnit 5 -1-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURING
Unit 5 -1-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURINGMohanumar S
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation Prabhu Bose
 
Group Technology, coding and cell design
Group Technology, coding and cell designGroup Technology, coding and cell design
Group Technology, coding and cell designNauman khan
 
Solid Modeling Schemes CAM
Solid Modeling Schemes CAMSolid Modeling Schemes CAM
Solid Modeling Schemes CAMCDO
 
Unit 2-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
Unit 2-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURINGUnit 2-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURING
Unit 2-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURINGMohanumar S
 
Machinability data syste
Machinability data systeMachinability data syste
Machinability data systeVenu Yadav
 
Design for manufacture_and_assembly
Design for manufacture_and_assemblyDesign for manufacture_and_assembly
Design for manufacture_and_assemblyR PANNEER
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process PlanningPraveenManickam2
 
Introduction to engineering graphics
Introduction to engineering graphicsIntroduction to engineering graphics
Introduction to engineering graphicsSuraj Meshram
 
Design for assembly methods
Design for assembly methodsDesign for assembly methods
Design for assembly methodsaman1312
 

What's hot (20)

Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)
 
Process planning and cost estimation unit i
Process planning and cost estimation  unit   iProcess planning and cost estimation  unit   i
Process planning and cost estimation unit i
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATION
 
Unit 2.1 cim
Unit 2.1 cimUnit 2.1 cim
Unit 2.1 cim
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
 
Intro to CAD CAM Tools
Intro to CAD CAM ToolsIntro to CAD CAM Tools
Intro to CAD CAM Tools
 
CUTTING TOOL SELECTION
CUTTING TOOL SELECTIONCUTTING TOOL SELECTION
CUTTING TOOL SELECTION
 
Unit 5 -1-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
Unit 5 -1-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURINGUnit 5 -1-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURING
Unit 5 -1-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
Group Technology, coding and cell design
Group Technology, coding and cell designGroup Technology, coding and cell design
Group Technology, coding and cell design
 
Solid Modeling Schemes CAM
Solid Modeling Schemes CAMSolid Modeling Schemes CAM
Solid Modeling Schemes CAM
 
Unit 2-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
Unit 2-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURINGUnit 2-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURING
Unit 2-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
 
Machinability data syste
Machinability data systeMachinability data syste
Machinability data syste
 
Design for manufacture_and_assembly
Design for manufacture_and_assemblyDesign for manufacture_and_assembly
Design for manufacture_and_assembly
 
Dfma
DfmaDfma
Dfma
 
Unit 1
Unit   1Unit   1
Unit 1
 
Cad
CadCad
Cad
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process Planning
 
Introduction to engineering graphics
Introduction to engineering graphicsIntroduction to engineering graphics
Introduction to engineering graphics
 
Design for assembly methods
Design for assembly methodsDesign for assembly methods
Design for assembly methods
 

Similar to Process planning and cost estimation unit iii

PPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxPPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxAravind Ra
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONDJAGADEESH1
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptxDJAGADEESH1
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONSathishkumarM89
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONSIVASHANKAR N
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION) TAMILMECHKIT
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONMohanKirthik
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 
Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02hlksd
 
Cost estimating & Costing
Cost estimating & CostingCost estimating & Costing
Cost estimating & CostingGanesh Murugan
 
importance of estimation power point presentation
importance of estimation power point presentationimportance of estimation power point presentation
importance of estimation power point presentationniyatishah939575
 
ppceunit3-211117103659 (1)-2-81 (3).pptx
ppceunit3-211117103659 (1)-2-81 (3).pptxppceunit3-211117103659 (1)-2-81 (3).pptx
ppceunit3-211117103659 (1)-2-81 (3).pptxmani617576
 
Job Costing & ABC costing
Job Costing & ABC costingJob Costing & ABC costing
Job Costing & ABC costingRakesh Singh
 
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhinPreparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhinAragaw Gebremedhin
 
cost accounting , Element & cost sheet.pptx
cost accounting  , Element  & cost sheet.pptxcost accounting  , Element  & cost sheet.pptx
cost accounting , Element & cost sheet.pptxRohitKumarUpadhyay3
 

Similar to Process planning and cost estimation unit iii (20)

Unit 3
Unit 3Unit 3
Unit 3
 
PPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxPPCE UNIT- 3.pptx
PPCE UNIT- 3.pptx
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02
 
Cost estimating & Costing
Cost estimating & CostingCost estimating & Costing
Cost estimating & Costing
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
 
importance of estimation power point presentation
importance of estimation power point presentationimportance of estimation power point presentation
importance of estimation power point presentation
 
ppceunit3-211117103659 (1)-2-81 (3).pptx
ppceunit3-211117103659 (1)-2-81 (3).pptxppceunit3-211117103659 (1)-2-81 (3).pptx
ppceunit3-211117103659 (1)-2-81 (3).pptx
 
Job Costing & ABC costing
Job Costing & ABC costingJob Costing & ABC costing
Job Costing & ABC costing
 
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdfPreparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
 
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhinPreparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
 
cost accounting , Element & cost sheet.pptx
cost accounting  , Element  & cost sheet.pptxcost accounting  , Element  & cost sheet.pptx
cost accounting , Element & cost sheet.pptx
 
PPT on PM_Unit 1 .pptx.
PPT                  on PM_Unit 1 .pptx.PPT                  on PM_Unit 1 .pptx.
PPT on PM_Unit 1 .pptx.
 

More from s Kumaravel

TOTAL QUALITY MANAGEMENT-UNIT III TQM TOOLS
TOTAL QUALITY MANAGEMENT-UNIT III TQM TOOLS TOTAL QUALITY MANAGEMENT-UNIT III TQM TOOLS
TOTAL QUALITY MANAGEMENT-UNIT III TQM TOOLS s Kumaravel
 
TOTAL QUALITY MANAGEMENT-UNIT II TQM PRINCIPLES
TOTAL QUALITY MANAGEMENT-UNIT II TQM PRINCIPLES TOTAL QUALITY MANAGEMENT-UNIT II TQM PRINCIPLES
TOTAL QUALITY MANAGEMENT-UNIT II TQM PRINCIPLES s Kumaravel
 
TOTAL QUALITY MANAGEMENT-UNIT IV TQM TECHNIQUES
TOTAL QUALITY MANAGEMENT-UNIT IV TQM TECHNIQUES TOTAL QUALITY MANAGEMENT-UNIT IV TQM TECHNIQUES
TOTAL QUALITY MANAGEMENT-UNIT IV TQM TECHNIQUES s Kumaravel
 
TOTAL QUALITY MANAGEMENT-UNIT I INTRODUCTION
TOTAL QUALITY MANAGEMENT-UNIT I INTRODUCTIONTOTAL QUALITY MANAGEMENT-UNIT I INTRODUCTION
TOTAL QUALITY MANAGEMENT-UNIT I INTRODUCTIONs Kumaravel
 
TOTAL QUALITY MANAGEMENT-UNIT V QUALITY SYSTEMS
TOTAL QUALITY MANAGEMENT-UNIT V QUALITY SYSTEMS TOTAL QUALITY MANAGEMENT-UNIT V QUALITY SYSTEMS
TOTAL QUALITY MANAGEMENT-UNIT V QUALITY SYSTEMS s Kumaravel
 
Unit I Introduction to Indian constitution
Unit I Introduction to Indian constitutionUnit I Introduction to Indian constitution
Unit I Introduction to Indian constitutions Kumaravel
 
Unit III Governments of the States and Local Government
Unit III Governments of the States and Local GovernmentUnit III Governments of the States and Local Government
Unit III Governments of the States and Local Governments Kumaravel
 
Unit IV The Judicature
Unit IV The Judicature Unit IV The Judicature
Unit IV The Judicature s Kumaravel
 
Unit V The Federal System
Unit V The Federal System Unit V The Federal System
Unit V The Federal System s Kumaravel
 
Unit II Government of the Union
Unit II Government of the UnionUnit II Government of the Union
Unit II Government of the Unions Kumaravel
 
TQM - QUESTION BANK.pdf
TQM - QUESTION BANK.pdfTQM - QUESTION BANK.pdf
TQM - QUESTION BANK.pdfs Kumaravel
 
COI UNITWISE QUESTION BANK.pdf
COI UNITWISE QUESTION BANK.pdfCOI UNITWISE QUESTION BANK.pdf
COI UNITWISE QUESTION BANK.pdfs Kumaravel
 
Process planning and cost estimation unit ii
Process planning and cost estimation  unit   iiProcess planning and cost estimation  unit   ii
Process planning and cost estimation unit iis Kumaravel
 
Process planning and cost estimation unit v
Process planning and cost estimation  unit   vProcess planning and cost estimation  unit   v
Process planning and cost estimation unit vs Kumaravel
 
Process planning and cost estimation unit iv
Process planning and cost estimation  unit   ivProcess planning and cost estimation  unit   iv
Process planning and cost estimation unit ivs Kumaravel
 
Design of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 ProcedureDesign of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 Procedures Kumaravel
 
Design of Machine Elements - Unit 4 Procedures
 Design of Machine Elements - Unit 4 Procedures Design of Machine Elements - Unit 4 Procedures
Design of Machine Elements - Unit 4 Proceduress Kumaravel
 
Design of Machine Elements - Unit 3 Procedures
 Design of Machine Elements - Unit 3 Procedures Design of Machine Elements - Unit 3 Procedures
Design of Machine Elements - Unit 3 Proceduress Kumaravel
 
Design of Machine Elements- Unit 2 Procedures
Design of Machine Elements- Unit 2 ProceduresDesign of Machine Elements- Unit 2 Procedures
Design of Machine Elements- Unit 2 Proceduress Kumaravel
 
Finite Element Analysis - Part 5
Finite Element Analysis - Part 5Finite Element Analysis - Part 5
Finite Element Analysis - Part 5s Kumaravel
 

More from s Kumaravel (20)

TOTAL QUALITY MANAGEMENT-UNIT III TQM TOOLS
TOTAL QUALITY MANAGEMENT-UNIT III TQM TOOLS TOTAL QUALITY MANAGEMENT-UNIT III TQM TOOLS
TOTAL QUALITY MANAGEMENT-UNIT III TQM TOOLS
 
TOTAL QUALITY MANAGEMENT-UNIT II TQM PRINCIPLES
TOTAL QUALITY MANAGEMENT-UNIT II TQM PRINCIPLES TOTAL QUALITY MANAGEMENT-UNIT II TQM PRINCIPLES
TOTAL QUALITY MANAGEMENT-UNIT II TQM PRINCIPLES
 
TOTAL QUALITY MANAGEMENT-UNIT IV TQM TECHNIQUES
TOTAL QUALITY MANAGEMENT-UNIT IV TQM TECHNIQUES TOTAL QUALITY MANAGEMENT-UNIT IV TQM TECHNIQUES
TOTAL QUALITY MANAGEMENT-UNIT IV TQM TECHNIQUES
 
TOTAL QUALITY MANAGEMENT-UNIT I INTRODUCTION
TOTAL QUALITY MANAGEMENT-UNIT I INTRODUCTIONTOTAL QUALITY MANAGEMENT-UNIT I INTRODUCTION
TOTAL QUALITY MANAGEMENT-UNIT I INTRODUCTION
 
TOTAL QUALITY MANAGEMENT-UNIT V QUALITY SYSTEMS
TOTAL QUALITY MANAGEMENT-UNIT V QUALITY SYSTEMS TOTAL QUALITY MANAGEMENT-UNIT V QUALITY SYSTEMS
TOTAL QUALITY MANAGEMENT-UNIT V QUALITY SYSTEMS
 
Unit I Introduction to Indian constitution
Unit I Introduction to Indian constitutionUnit I Introduction to Indian constitution
Unit I Introduction to Indian constitution
 
Unit III Governments of the States and Local Government
Unit III Governments of the States and Local GovernmentUnit III Governments of the States and Local Government
Unit III Governments of the States and Local Government
 
Unit IV The Judicature
Unit IV The Judicature Unit IV The Judicature
Unit IV The Judicature
 
Unit V The Federal System
Unit V The Federal System Unit V The Federal System
Unit V The Federal System
 
Unit II Government of the Union
Unit II Government of the UnionUnit II Government of the Union
Unit II Government of the Union
 
TQM - QUESTION BANK.pdf
TQM - QUESTION BANK.pdfTQM - QUESTION BANK.pdf
TQM - QUESTION BANK.pdf
 
COI UNITWISE QUESTION BANK.pdf
COI UNITWISE QUESTION BANK.pdfCOI UNITWISE QUESTION BANK.pdf
COI UNITWISE QUESTION BANK.pdf
 
Process planning and cost estimation unit ii
Process planning and cost estimation  unit   iiProcess planning and cost estimation  unit   ii
Process planning and cost estimation unit ii
 
Process planning and cost estimation unit v
Process planning and cost estimation  unit   vProcess planning and cost estimation  unit   v
Process planning and cost estimation unit v
 
Process planning and cost estimation unit iv
Process planning and cost estimation  unit   ivProcess planning and cost estimation  unit   iv
Process planning and cost estimation unit iv
 
Design of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 ProcedureDesign of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 Procedure
 
Design of Machine Elements - Unit 4 Procedures
 Design of Machine Elements - Unit 4 Procedures Design of Machine Elements - Unit 4 Procedures
Design of Machine Elements - Unit 4 Procedures
 
Design of Machine Elements - Unit 3 Procedures
 Design of Machine Elements - Unit 3 Procedures Design of Machine Elements - Unit 3 Procedures
Design of Machine Elements - Unit 3 Procedures
 
Design of Machine Elements- Unit 2 Procedures
Design of Machine Elements- Unit 2 ProceduresDesign of Machine Elements- Unit 2 Procedures
Design of Machine Elements- Unit 2 Procedures
 
Finite Element Analysis - Part 5
Finite Element Analysis - Part 5Finite Element Analysis - Part 5
Finite Element Analysis - Part 5
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 

Process planning and cost estimation unit iii

  • 2. UNIT III INTRODUCTION TO COST ESTIMATION  Importance of costing and estimation  Methods of costing-elements of cost estimation  Types of estimates  Estimating procedure  Estimation labor cost, material cost  Allocation of over head charges  Calculation of depreciation cost
  • 3. WHAT IS MEAN BY COST ESTIMATION? WHAT IS MEAN BY COST ESTIMATION?  Estimation of the expected cost of producing a job  Executing a manufacturing order before the actual production is taken up  Predicting what new products will cost before they are made
  • 4. DEFINITION DEFINITION Costing or cost accounting means classifying, recording and allocating the appropriate expenditure for determining the cost of production and achieved by keeping a continuous record of all the costs involved in manufacturing
  • 5. REASONS FOR DOING ESTIMATES REASONS FOR DOING ESTIMATES  Should the product be produced?  When a company designs a new product  To assist management in making an intelligent decision about producing the product.
  • 6. GENERAL PROCEDURE GENERAL PROCEDURE  A cost estimate must be developed for jigs, fixtures, tools, dies and gauges  Also, the cost of any capital equipment must be entered into the estimate  These figures are usually supplied through quotation by vendors  An estimate of this nature will include a vast amount of details, because if management approves the project, the estimate now becomes the budget
  • 7. OBJECTIVES (OR) PURPOSE OF ESTIMATING OBJECTIVES (OR) PURPOSE OF ESTIMATING  To establish the selling price of a product  To ascertain whether a proposed product can be manufactured and marketed profitably  To determine how much must be invested in equipment  To find whether parts or assemblies can be more cheaply fabricated or purchased from outside (make or buy decision)  To determine the most economical process, tooling or material for making a product
  • 8. FUNCTIONS OF ESTIMATING FUNCTIONS OF ESTIMATING  To calculate the cost of new material needed to manufacture a product  To find the cost of parts to be purchased from outside vendors  To find the cost of equipment, machinery, tools, jigs and fixtures etc. required to be purchased to make the product  To calculate the direct and indirect labour cost associated with the manufacture of the product, based upon work study.  To calculate various overhead charges associated with the product.
  • 9.  To decide about the profit to be charged, taking into consideration other manufacturers of same product in the market  To calculate the selling price of the product  To maintain records of previous estimating activities of the company for future references  To decide the most economical method of making the product  To submit cost estimates with the competent authority for further action FUNCTIONS OF ESTIMATING FUNCTIONS OF ESTIMATING Contd.,
  • 10. COMPONENTS OF A COST ESTIMATE OR JOB ESTIMATE COMPONENTS OF A COST ESTIMATE OR JOB ESTIMATE 1. Cost of design 2. Cost of drafting 3. Cost of research and development 4. Cost of raw materials 5. Cost of labour 6. Cost of inspection 7. Cost of tools, jigs and fixtures 8. Overhead cost
  • 11. 1. COST OF DESIGN 1. COST OF DESIGN  The cost of design of a component or product is estimated by ascertaining the expected time for the design of that component  The estimate design time multiplied by the salary of designer per unit time gives the estimated cost of design  If the design of the component is done by some outside agency, the total amount paid to outside agency gives the cost of design.
  • 12. 2. COST OF DRAFTING 2. COST OF DRAFTING  Once the design of the component is complete, its drawings have to be prepared by draftsman  The expected time to be spent in drawing or drafting is estimated and is then multiplied by the standard drafting rate or by the salary of the draftsman per unit time to get estimated cost of drafting
  • 13. 3. COST OF RESEARCH AND DEVELOPMENT WORK 3. COST OF RESEARCH AND DEVELOPMENT WORK  Before taking up the manufacturing of actual components/parts considerable time and money has to be spent on research and development  The research may be theoretical, experimental or developmental research.  The cost of R and D can be estimated by considering various items of expenditure incurred during R and D work
  • 14. 4. COST OF RAW MATERIAL 4. COST OF RAW MATERIAL  A list of all the materials used in the manufacture of the product is made which includes the direct as well as indirect materials  The quantity (weight or volume) of all the material expected to be used in the manufacture of the product is estimated.  The allowance for material wastage, spoilage and scarp are also added for each component/part.
  • 15. 4. COST OF RAW MATERIAL 4. COST OF RAW MATERIAL Cost of each material is estimated by multiplying the estimated quantity of each material with its estimated future price The estimate of future price of a material is made keeping in view of present prices and general trends and variations Estimated cost of all the materials is added to get the overall estimated material cost Contd.,
  • 16. 5. COST OF LABOUR 5. COST OF LABOUR  The cost of labour involved in the manufacture of a product is estimated by estimating the labour time needed to manufacture the product and multiplying it by cost of labour per hour.  In order to estimate the labour time expected to be spent on a job, one must have thorough knowledge of the various operations to be performed, machines to be used, sequence of operations, tools to be used and labour rates
  • 17. 6. COST OF INSPECTION 6. COST OF INSPECTION  A product being manufactured is inspected at various stages during its manufacture  It may be inspection of raw material or in-process inspection or inspection of finished goods
  • 18. 7. COST AND MAINTENANCE CHARGES OF TOOLS, JIGS AND FIXTURES 7. COST AND MAINTENANCE CHARGES OF TOOLS, JIGS AND FIXTURES  The cost of tools, jigs, fixtures etc., is estimated considering their present prices, market trend and the number of times a particular tool can be used during its life-time.  The estimated cost divided by the number of jobs it can make, gives the tool cost per unit produced
  • 19. 8. OVERHEAD COSTS 8. OVERHEAD COSTS  Overhead or indirect costs are those which are not incurred specifically for any one order or product and these can not be charged directly to a specific order or product  The overhead costs may be estimated by referring to the records of overhead costs in similar items produced in past
  • 20. BASIC STEPS IN COST ESTIMATION BASIC STEPS IN COST ESTIMATION 1. Make thorough study of cost estimation request to understand it fully. 2. Make an analysis of the product and prepare a bill of materials. 3. Make separate lists of parts to be purchased from the market and parts to be manufactured in plant. 4. Determine the cost of parts to be purchased from outside. 5. Estimate the material cost for the parts/components to be manufactured in plant.
  • 21. BASIC STEPS IN COST ESTIMATION BASIC STEPS IN COST ESTIMATION 6. Make manufacturing process plan for the parts to be manufactured in plant. 7. Estimate the machining time for each operation listed in the manufacturing process plan. 8. Multiply each operation time by the labour wage rate and add them up to find direct labour cost 9. Add the estimate of step 4, 5, and 8 to get prime cost of component. 10. Apply overhead costs to get the total cost of the component. The selling price of the component is estimated by adding profit to the total cost obtained in step 10.
  • 22. TYPES OF COST ESTIMATES TYPES OF COST ESTIMATES (a) Factor Method of Cost Estimation (b) Material Cost Method of Estimation (c) Function Method of Cost Estimation Other types (i) Product comparison (ii) Data base calculations
  • 23. FACTOR METHOD OF COST ESTIMATION FACTOR METHOD OF COST ESTIMATION Estimated cost of an item = Factor for total cost estimate × Amount of major cost item Example: (i) Cost of construction per km of highway (ii) Cost of fabricated component per kg of casting (iii) Cost of house construction per Sq.m. of livable space
  • 24. Example Problem: If a casting weighed 15 kg, and the factor of the cost of casting per kg of casting is Rs. 75, what is the estimated cost of the casting ? Estimated cost of the casting = Rs. 75 per kg of casting × wt. of the casting (15 kg) = Rs. 1125 per casting
  • 25. MATERIAL COST METHOD OF ESTIMATION MATERIAL COST METHOD OF ESTIMATION Material cost method predicts the total cost of the product based on the ratio of the material cost of the product to the material cost share of the total cost. Estimated cost of an item = Material cost of the item being estimated Material cost share of item being estimated (in %)
  • 26. Examples of material cost share : Product Material cost share (%) Passenger car 65% Diesel engine 50% Clocks, watches 25% Glass product 10% Example Problem: If the material cost of an automobile was Rs. 2.50 Lakhs, what would be the total cost of the automobile ? Use the table above. Estimated total cost of automobile = Rs. 2.50 Lakhs / 0.65 = Rs. 3.85 Lakhs
  • 27.  This method is similar to the factor method, but more variables are used.  Function method uses a mathematical expression with constants and parameters derived for specific process, such as casting or machining or for specific classes of parts based on material, size, weight or other cost parameters. Function Method of Estimation Function Method of Estimation
  • 28. According to this method : Estimated cost of an item = G × (a + b) + (R × c) + (N × d) where G = Weight of the item, kg a = Material cost per kg b = Tolerance cost per, kg R = Weight of material Removed, kg c = Cost per kg of material removed N = No. of dimensions of a product surface d = Cost per dimension Function Method of Estimation Function Method of Estimation Contd.,
  • 29. (i) Product comparison : The new product is compared with existing products (of similar function, design etc.) and adjustments/modifications are made for the differences. (ii) Data base calculations : The product cost estimate is determined from cost data bases which a company is expected to maintain over a period of time (Historical Cost Data Base).
  • 30. ELEMENTS OF COST ELEMENTS OF COST  Material cost (a) Direct material cost (b) Indirect material cost  Labour cost (a) Direct labour cost (b) Indirect labour cost  Other expenses (a) Direct expenses (b) Indirect expenses (i) Factory expenses (ii) Administrative expenses (iii) Selling and distribution expenses
  • 31. MATERIAL COST MATERIAL COST Direct material cost (i) From the product drawing, make a list of all the components required to make the final product. (ii) Calculate the volume of each component from the drawing dimensions after adding machining allowances, wherever necessary. (iii) The volume of component multiplied by the density of material used gives the weight of the material per component.
  • 32. MATERIAL COST MATERIAL COST Direct material cost (iv) Add process rejection and other allowances like cutting allowance to get the gross weight per component. (v) Multiply the gross weight by the cost of material per unit weight to get the cost of raw material per component. (vi) The cost of raw material for all the components is, similarly, calculated and added up which gives the cost of direct material for the product. Contd.,
  • 33. MATERIAL COST MATERIAL COST Indirect material cost  The indirect materials include oils, general tools, grease, sand papers, coolants, cotton waste etc.  The cost associated with indirect materials is called indirect material cost.
  • 34. LABOUR COST LABOUR COST Direct labour cost  Direct labourer is one who actually works and processes the materials to convert it into the final shape.  The cost associated with direct labour is called direct labour cost.  The direct labour are the workers operating lathes, milling machines or welders, or assemblers in assembly shop.
  • 35. LABOUR COST LABOUR COST Indirect labour cost  Indirect labourer is one who is not directly employed in the manufacturing of the product but his services are used in some indirect manner.  The cost associated with indirect labour is called indirect labour cost.  The indirect labour includes supervisors, inspectors, foreman, storekeeper, gatekeeper, maintenance staff, crane driver etc.
  • 36. OTHER EXPENSES OTHER EXPENSES Direct expenses  Direct expenses include all that expenditure which can be directly allocated and charged to a particular job.  The direct expenses include cost of special jigs or fixtures, patterns, toolings made for job, or cost of research and development work done for that specific job.
  • 37. OTHER EXPENSES OTHER EXPENSES Indirect expenses  Except direct expenses, all other indirect expenditure incurred by the manufacturer is called indirect expenses  The indirect expenses are also called overhead expenses or on-cost The indirect expenses are further classified as (i) Factory expenses (ii) Administrative expenses (iii) Selling and distribution expenses
  • 38. OTHER EXPENSES OTHER EXPENSES Indirect expenses - Factory expenses  Factory expenses comprise of the indirect expenses incurred from the receipt of the order to the completion of production.  Includes rent of factory building, licence fee, electricity and telephone bills of factory, insurance charges etc.
  • 39. OTHER EXPENSES OTHER EXPENSES Indirect expenses - Administrative expenses  Administrative expenses or office expenses include the expenditure incurred on control and administration of the factory  It includes the salaries of office and administrative staff, rent of office building, postage and telephone charges, water and electricity charges for office, Director’s fee, legal and audit charges etc.
  • 40. OTHER EXPENSES OTHER EXPENSES Indirect expenses - Selling and distribution expenses  his is the expenditure incurred on Sales Department for selling the product  It includes the wages, salaries, commission and travelling allowances of salesmen and officers in Sales Department, cost of advertisement, packing, delivery and distribution expenses, rent of warehouses etc.
  • 41. METHODS OF ESTIMATING METHODS OF ESTIMATING  Conference method  Comparison method  Detailed analysis method
  • 42. CONFERENCE METHOD CONFERENCE METHOD  A co-ordinator from either accounting or estimating collect costs and applies overhead factors to develop a total manufacturing cost for the product  If vague or only verbal information is available, then the total product material, labour and tooling will be estimated as one lump sum for each  The degree of accuracy of this method depends upon the availability of specificaitions, samples and drawings
  • 43. COMPARISON METHOD COMPARISON METHOD  In this method of estimating the costs of similar parts are applied to the product and are adjusted to suit variations in the workpiece, material and labour costs.  It is based on the accumulation of past experience data
  • 44. DETAILED ANALYSIS METHOD DETAILED ANALYSIS METHOD This method involves I. Calculation of raw material usage including scrap allowance and salvage material II. Processing each individual component (writing the operation sheet) III. Determining the production time (direct labour) for each operation IV. The equipment required (new, network, or on hand) V. Tools, gauges, and special fixtures or dies, VI. Inspection and testing equipment VII. Packaging and shipping requirements
  • 45. COST ESTIMATING PROCEDURE COST ESTIMATING PROCEDURE Step 1: Study the cost estimation request thoroughly and understand it completely Step 2: Analyse the product and decide the requirements and specifications of the product Step 3: Prepare the list of all the parts of the product and their bill of materials Step 4: Take make or buy decisions and prepare separate lists of parts to be manufactured within the plant and parts to be purchased outside the plant
  • 46. COST ESTIMATING PROCEDURE COST ESTIMATING PROCEDURE Step 5: Estimate the materials cost for the parts to be manufactured in the plant Material cost = Weight of the material × Material cost per unit weight Step 6 : Determine the cost of parts to be purchased from outside Step 7: Make a manufacturing process plan for the parts to be manufactured in the plant Contd.,
  • 47. COST ESTIMATING PROCEDURE COST ESTIMATING PROCEDURE Step 8: Estimate the machining time for each operations listed in the manufacturing process plan Step 9: Determine the direct labour cost Direct labour cost = Total operation time × Labour wage rate Step 10: Determine the prime cost by adding direct expenses, direct material cost, and direct labour cost ∴ Prime cost = Direct labour cost + Direct material cost + Direct expenses Contd.,
  • 48. COST ESTIMATING PROCEDURE COST ESTIMATING PROCEDURE Step 11: Estimate the factory overheads, which include all indirect expenditure incurred during production such as indirect material cost, indirect labour cost, depreciation and expenditure on maintenance of the plant, machinery, power, etc. Step 12: Estimate the administrative expenses Contd.,
  • 49. COST ESTIMATING PROCEDURE COST ESTIMATING PROCEDURE Step 13: Estimate the selling and distribution expenses which include packing and delivery charges, advertisement charges, etc. Step 14: Now calculate the total cost of the product Total Cost = Prime Cost + Factory overheads + Administrative expenses + Selling and distribution expenses Contd.,
  • 50. COST ESTIMATING PROCEDURE COST ESTIMATING PROCEDURE Step 15: Decide the profit and add the profit to the total cost to fix the selling price of the part Selling Price = Total cost + Profit Step 16: Finally estimate the time of delivery in consultation with the production and sales department Contd.,
  • 51. ESTIMATE FORM ESTIMATE FORM After estimating all the elements of cost estimate, these estimated datas are entered into an estimate form
  • 52. COST OF PRODUCT (LADDER OF COSTS) COST OF PRODUCT (LADDER OF COSTS) 1. Prime cost = Direct material cost + Direct labour cost + Direct expenses 2. Factory cost = Prime cost + Factory expenses 3. Production cost = Factory cost + Administrative expenses 4. Total or Ultimate cost = Production cost + Selling and distribution expenses. 5. Selling price = Ultimate cost + Profit
  • 54. Example: Calculate prime cost, factory cost, production cost, total cost and selling price per item from the data given below for the year 2003-04.
  • 55.
  • 56.
  • 57. Example : From the following data for a sewing machine manufacturer, prepare a statement showing prime cost, Works/factory cost, production cost, total cost and profit.
  • 58.
  • 59.
  • 60. Example : From the following data for a sewing machine manufacturer, prepare a statement showing prime cost, Works/factory cost, production cost, total cost and profit.
  • 61.
  • 62.
  • 63.
  • 64.
  • 65.
  • 66.
  • 67.
  • 68.
  • 69.
  • 70. ESTIMATION OF MATERIALS COST ESTIMATION OF MATERIALS COST Procedure  Study the given drawing carefully. Then break up the product into simple geometrical shapes such as cubes, prisms, cylinders, etc.,  Calculate the volume of each parts using formulae  Add volumes to get total volume  Calculate the weight of material by Volume × Density  Material cost = Weight of the material × Material cost per unit weight