Quantity Take-off
What is Quantity Take-off
• Quantity take-offs (QTO) is an in-depth construction estimation of
materials and labor required to complete a construction project.
• Developed during the pre-construction phase. These measurements are
used to format a bid on the scope of construction. Estimators
review drawings, specifications, and models to find these quantities.
Preparing a quantity takeoff required a high degree of skill, as well as
good judgment and critical thinking skills. The term “takeoff” refers to
this process of “taking off” all of the materials for a project from a design
drawing or blueprint.
• .
SIGNIFICANCE
Quantity takeoffs fulfill an important function for construction projects of
nearly any size. Quantity takeoffs are an integral part of the cost estimation
process. The information from a quantity takeoff is incorporated into a final
detailed estimate, along with things like labor costs, office overhead costs,
subcontractor costs, and equipment rentals. Given that material costs
represent a sizeable portion of total construction costs, the quantity takeoff
must be accurate and up-to-date.
• Quantity takeoffs are generally performed early on during the bidding
process.
Significance
• During the estimation process, an estimator may have to make frequent
adjustments to there quantity takeoff. This may be due to design changes,
additional engineering requirements, or changes in what the client wants.
• The quantity takeoff is often a living document that undergoes many
changes until a design is decided upon and a bid is secured.
Components of a Quantity take-off
• The first part of a quantity takeoff involves putting together a list of all of
the materials required for a project. This will include all raw materials,
like lumber, concrete, asphalt, and steel. In addition to raw materials, the
quantity takeoff will include any prefabrication in construction that are
necessary for the project.
• Example: materials like lumber, the quantity takeoff would include
what specific type of lumber the job requires, the length and width of the
lumber, and may include the total weight of the required lumber for
shipping considerations.
Quantity takeoffs fulfill two basic functions in a construction
cost estimate
• First, they detail what materials need to be purchased to complete a
project. Second, they provide a total material cost for a project, which is
then incorporated into a detailed cost estimate.
• Determining the price of materials can be accomplished in a number of
ways. For large projects, the estimator would seek a bid from a material
supplier. For other projects, estimators may use a personal database of
material costs, or draw information from a third-party construction costs
database.
 Subcontractors may routinely prepare quantity takeoffs that include the
same materials. If the cost of those materials is known and stable, the
subcontractor can simply plug in their known prices into their quantity
takeoff.
Once prices for each material have been determined, the estimator will
then produce a total material cost estimate. Most often, the person
preparing the quantity takeoff will markup the total material costs. How
much or little of a markup occurs will depend on a number of factors,
and can be a key determinant of whether a bid is accepted or rejected. A
markup for material costs is necessary for most projects to ensure a
project remains profitable for the contractor.
Types of Quantity Takeoffs
Quantity takeoffs are prepared by a wide range of people and organizations
within the construction industry, and each quantity takeoff can be unique.
Each individual or organization may find a method of preparation for their
quantity takeoffs that they prefer and may format their final quantity takeoff
cost analysis in different ways. Despite the unique nature of each quantity
takeoff and the various ways they are approached, there are two broad types
of quantity takeoffs.
(1) Manual Quantity Takeoff (2) Digital Quantity Takeoff
Manual Quantity Takeoff
• A manual quantity takeoff is simply a takeoff that is completed without the
assistance of digital takeoff software.
• An estimator would examine physical drawings or blueprints and
painstakingly create a list of materials. Many people still complete
quantity takeoffs manually, but do so with the assistance of computer
software that information is entered into by hand. Although still aided by a
computer, the process is still largely manual. If done by hand, the
estimator must make complex calculations. If done with a computer,
software such as Excel can be used to perform certain calculations.
Digital Quantity Takeoff
• Digital quantity takeoffs are completed using a construction cost
estimation program that contains digital takeoff capability. As you could
assume, there are many benefits of using construction estimating software
to run your calculations.
• the basic process of creating a digital quantity takeoff is roughly the same.
First, a blueprint is uploaded or scanned into the program. From there, the
program analyzes the blueprint or drawings and generates a list of all of
the required materials. At this point, the estimator can make any
adjustments to the material requirements that they see.
 Any complex calculations required for assigning quantities to materials are
embedded into the program, making this process vastly easier than a manual
quantity takeoff. From there, the estimator can apply prices to each material.
 Some software has the capability, price information can be drawn from a
database of current prices populated by the contractor. Alternatively, some
takeoff software can draw cost data from online construction cost
databases such as RS Means. Once prices are applied to each material, the
estimator can dynamically adjust the price to account for material cost
increases.
Benefits of Digital take-offs
• Digital takeoffs help reduce errors associated with quantity takeoffs.
• digital takeoffs take much less time to produce.
• Quantity takeoffs don’t just save time when creating a takeoff, but they also
save time when a quantity takeoff has to be adjusted. This happens
frequently during projects. Digital takeoff software allows for a rapid
turnaround time if adjustments are necessary.
• Digital quantity takeoffs require less specialization to complete than a
manual takeoff.
References
1. Book Fundamentals of Construction estimating.
2. https://proest.com/what-is-a-quantity-takeoff-in-construction/
3. https://www.quora.com/What-is-quantity-takeoff.

More Related Content

What's hot

What's hot (20)

Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
An introduction to taking off building quantities
An introduction to taking off building quantities An introduction to taking off building quantities
An introduction to taking off building quantities
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDF
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost Planning
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
Contracts
ContractsContracts
Contracts
 
Taking off qs
Taking off qsTaking off qs
Taking off qs
 

Similar to Quantity take off

Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
bjohn46
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
Aravind NC
 

Similar to Quantity take off (20)

ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
3D Models for Construction Estimating
3D Models for Construction Estimating3D Models for Construction Estimating
3D Models for Construction Estimating
 
Estimation
EstimationEstimation
Estimation
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
 
Project cost management
Project cost management Project cost management
Project cost management
 
Estimation
EstimationEstimation
Estimation
 
QSS
QSSQSS
QSS
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Total-Project-Cost.pptx
Total-Project-Cost.pptxTotal-Project-Cost.pptx
Total-Project-Cost.pptx
 
Software application finalized group report
Software application finalized group reportSoftware application finalized group report
Software application finalized group report
 
Project_cost_managment definition and tools
Project_cost_managment definition and toolsProject_cost_managment definition and tools
Project_cost_managment definition and tools
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total Cost
 
Qsx
QsxQsx
Qsx
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 

Recently uploaded

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 

Quantity take off

  • 2. What is Quantity Take-off • Quantity take-offs (QTO) is an in-depth construction estimation of materials and labor required to complete a construction project. • Developed during the pre-construction phase. These measurements are used to format a bid on the scope of construction. Estimators review drawings, specifications, and models to find these quantities. Preparing a quantity takeoff required a high degree of skill, as well as good judgment and critical thinking skills. The term “takeoff” refers to this process of “taking off” all of the materials for a project from a design drawing or blueprint. • .
  • 3. SIGNIFICANCE Quantity takeoffs fulfill an important function for construction projects of nearly any size. Quantity takeoffs are an integral part of the cost estimation process. The information from a quantity takeoff is incorporated into a final detailed estimate, along with things like labor costs, office overhead costs, subcontractor costs, and equipment rentals. Given that material costs represent a sizeable portion of total construction costs, the quantity takeoff must be accurate and up-to-date. • Quantity takeoffs are generally performed early on during the bidding process.
  • 4. Significance • During the estimation process, an estimator may have to make frequent adjustments to there quantity takeoff. This may be due to design changes, additional engineering requirements, or changes in what the client wants. • The quantity takeoff is often a living document that undergoes many changes until a design is decided upon and a bid is secured.
  • 5. Components of a Quantity take-off • The first part of a quantity takeoff involves putting together a list of all of the materials required for a project. This will include all raw materials, like lumber, concrete, asphalt, and steel. In addition to raw materials, the quantity takeoff will include any prefabrication in construction that are necessary for the project. • Example: materials like lumber, the quantity takeoff would include what specific type of lumber the job requires, the length and width of the lumber, and may include the total weight of the required lumber for shipping considerations.
  • 6. Quantity takeoffs fulfill two basic functions in a construction cost estimate • First, they detail what materials need to be purchased to complete a project. Second, they provide a total material cost for a project, which is then incorporated into a detailed cost estimate. • Determining the price of materials can be accomplished in a number of ways. For large projects, the estimator would seek a bid from a material supplier. For other projects, estimators may use a personal database of material costs, or draw information from a third-party construction costs database.
  • 7.  Subcontractors may routinely prepare quantity takeoffs that include the same materials. If the cost of those materials is known and stable, the subcontractor can simply plug in their known prices into their quantity takeoff. Once prices for each material have been determined, the estimator will then produce a total material cost estimate. Most often, the person preparing the quantity takeoff will markup the total material costs. How much or little of a markup occurs will depend on a number of factors, and can be a key determinant of whether a bid is accepted or rejected. A markup for material costs is necessary for most projects to ensure a project remains profitable for the contractor.
  • 8. Types of Quantity Takeoffs Quantity takeoffs are prepared by a wide range of people and organizations within the construction industry, and each quantity takeoff can be unique. Each individual or organization may find a method of preparation for their quantity takeoffs that they prefer and may format their final quantity takeoff cost analysis in different ways. Despite the unique nature of each quantity takeoff and the various ways they are approached, there are two broad types of quantity takeoffs. (1) Manual Quantity Takeoff (2) Digital Quantity Takeoff
  • 9. Manual Quantity Takeoff • A manual quantity takeoff is simply a takeoff that is completed without the assistance of digital takeoff software. • An estimator would examine physical drawings or blueprints and painstakingly create a list of materials. Many people still complete quantity takeoffs manually, but do so with the assistance of computer software that information is entered into by hand. Although still aided by a computer, the process is still largely manual. If done by hand, the estimator must make complex calculations. If done with a computer, software such as Excel can be used to perform certain calculations.
  • 10. Digital Quantity Takeoff • Digital quantity takeoffs are completed using a construction cost estimation program that contains digital takeoff capability. As you could assume, there are many benefits of using construction estimating software to run your calculations. • the basic process of creating a digital quantity takeoff is roughly the same. First, a blueprint is uploaded or scanned into the program. From there, the program analyzes the blueprint or drawings and generates a list of all of the required materials. At this point, the estimator can make any adjustments to the material requirements that they see.
  • 11.  Any complex calculations required for assigning quantities to materials are embedded into the program, making this process vastly easier than a manual quantity takeoff. From there, the estimator can apply prices to each material.  Some software has the capability, price information can be drawn from a database of current prices populated by the contractor. Alternatively, some takeoff software can draw cost data from online construction cost databases such as RS Means. Once prices are applied to each material, the estimator can dynamically adjust the price to account for material cost increases.
  • 12. Benefits of Digital take-offs • Digital takeoffs help reduce errors associated with quantity takeoffs. • digital takeoffs take much less time to produce. • Quantity takeoffs don’t just save time when creating a takeoff, but they also save time when a quantity takeoff has to be adjusted. This happens frequently during projects. Digital takeoff software allows for a rapid turnaround time if adjustments are necessary. • Digital quantity takeoffs require less specialization to complete than a manual takeoff.
  • 13. References 1. Book Fundamentals of Construction estimating. 2. https://proest.com/what-is-a-quantity-takeoff-in-construction/ 3. https://www.quora.com/What-is-quantity-takeoff.