2. A project manager needs to submit a project management plan to be approved. Which of
the following should not be included in the submission?
A. Change management plan
B. Schedule baseline
C. Configuration management plan
D. Risk register
HINT: Which are components of the project plan vs. other project documents?
QUESTION:
3. The correct answer is D.
The project management plan describes how the project is to be executed, as well as
monitored and controlled. It consists of many subsidiary plans, which need to be baselined.
The risk register is the only one among the choices, which is not part of the project
management plan.
ANSWER: