2. A team member submits a draft of the requirements management plan to the project manager for a review.
The project manager notices that one of the components included in the plan does not belong there.
Which of the following components did the project manager most likely notice?
A. A process that describes how the project requirements will be prioritized
B. The metrics that will be used and the rationale for using them
C. A process that specifies how a project scope statement will be prepared
D. How requirement activities will be planned, tracked, and reported
HINT: Which element should be included in the scope management plan and not the requirements
management plan?
Question
3. The correct answer is C.
The requirements management plan is a component of the project or program management plan that
describes how requirements will be analyzed, documented, and managed.
A process that specifies how a project scope statement will be prepared is an element of the scope
management plan and should be excluded from the requirements management plan.
The incorrect answer choices represent components that should be included in the requirements
management plan.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.