SlideShare a Scribd company logo
1 of 5
Download to read offline
PMP EXAM
SAMPLE Q & A
You are part of a cross-functional development team piloting an adaptive approach to project
management in an organization that has traditionally used a predictive approach. You realize that you
have to tailor the template of the schedule management plan.
Which of the following components of the template are you likely to tailor the most?
A. The rules of performance measurement, the summary milestones, and the key deliverables
B. The organizational procedures links, the units of measure, and the project organization charts
C. The schedule model development, the release and iteration length, and the reporting formats
D. The project schedule model maintenance, the level of accuracy, and the level of precision
HINT: To eliminate some choices, look for items that are not components of the schedule management
plan.
Question
Answer and Explanation:
The correct answer is C.
The question suggests you are carrying out the Plan Schedule Management process.
The schedule management plan is the primary output of this process. The schedule management plan
establishes the criteria and the activities for developing, monitoring, and controlling the schedule. Of the
choices presented, only the schedule model development, the release and iteration length, and the
reporting formats are components of the schedule management plan.
All three of these components would merit significant tailoring to reflect an adaptive approach to project
management. The project schedule model development specifies the scheduling methodology and the
scheduling tool used to develop the schedule model.
Answer
For an adaptive approach, the schedule model will be a selected series of activities needed to complete a
high-priority subset of the project scope that can deliver value quickly.
The release and iteration length determine the time-boxed events that must be completed and how long
it will take to release the iteration. The reporting formats will be driven by the adaptive schedule model
and the iteration length.
The other answer choices contain components that are not part of the schedule management plan.
Answer
All our questions are updated to the latest 
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.


Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.


We are a trusted and experienced education provider.

More Related Content

Similar to Free PMP Exam Q & A

SAP Organization Change Management
SAP Organization Change ManagementSAP Organization Change Management
SAP Organization Change Management
Fred Asher, Ph.D.
 
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change TutorialSanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
guesta83e9d
 
Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...
PMILebanonChapter
 
Requirement NumberRequirement DescriptionPriority (High, Mediu.docx
Requirement NumberRequirement DescriptionPriority (High, Mediu.docxRequirement NumberRequirement DescriptionPriority (High, Mediu.docx
Requirement NumberRequirement DescriptionPriority (High, Mediu.docx
heunice
 
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxProject Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
briancrawford30935
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
smumbahelp
 
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docxWeek_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
philipnelson29183
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
Cheryl Burcham
 

Similar to Free PMP Exam Q & A (20)

Pm 0010 introduction to project management
Pm 0010   introduction to project managementPm 0010   introduction to project management
Pm 0010 introduction to project management
 
PMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study GuidePMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study Guide
 
SAP Organization Change Management
SAP Organization Change ManagementSAP Organization Change Management
SAP Organization Change Management
 
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change TutorialSanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
 
Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...
 
Requirement NumberRequirement DescriptionPriority (High, Mediu.docx
Requirement NumberRequirement DescriptionPriority (High, Mediu.docxRequirement NumberRequirement DescriptionPriority (High, Mediu.docx
Requirement NumberRequirement DescriptionPriority (High, Mediu.docx
 
ASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptxASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptx
 
PgMP Panel Review (3/3)
PgMP Panel Review (3/3)PgMP Panel Review (3/3)
PgMP Panel Review (3/3)
 
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxProject Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
ALM Assessment Program
ALM Assessment ProgramALM Assessment Program
ALM Assessment Program
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
 
A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability framework
 
Test management
Test managementTest management
Test management
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
Ch23
Ch23Ch23
Ch23
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docxWeek_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
Critical success factors in effective project implementation
Critical success factors in effective project implementationCritical success factors in effective project implementation
Critical success factors in effective project implementation
 

More from OSP International LLC

More from OSP International LLC (20)

Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorFree PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam Simulator
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam Simulator
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from The PM Exam Simulator
Free PMP Exam Sample Question from The PM Exam SimulatorFree PMP Exam Sample Question from The PM Exam Simulator
Free PMP Exam Sample Question from The PM Exam Simulator
 

Recently uploaded

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 

Recently uploaded (20)

Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 

Free PMP Exam Q & A

  • 2. You are part of a cross-functional development team piloting an adaptive approach to project management in an organization that has traditionally used a predictive approach. You realize that you have to tailor the template of the schedule management plan. Which of the following components of the template are you likely to tailor the most? A. The rules of performance measurement, the summary milestones, and the key deliverables B. The organizational procedures links, the units of measure, and the project organization charts C. The schedule model development, the release and iteration length, and the reporting formats D. The project schedule model maintenance, the level of accuracy, and the level of precision HINT: To eliminate some choices, look for items that are not components of the schedule management plan. Question
  • 3. Answer and Explanation: The correct answer is C. The question suggests you are carrying out the Plan Schedule Management process. The schedule management plan is the primary output of this process. The schedule management plan establishes the criteria and the activities for developing, monitoring, and controlling the schedule. Of the choices presented, only the schedule model development, the release and iteration length, and the reporting formats are components of the schedule management plan. All three of these components would merit significant tailoring to reflect an adaptive approach to project management. The project schedule model development specifies the scheduling methodology and the scheduling tool used to develop the schedule model. Answer
  • 4. For an adaptive approach, the schedule model will be a selected series of activities needed to complete a high-priority subset of the project scope that can deliver value quickly. The release and iteration length determine the time-boxed events that must be completed and how long it will take to release the iteration. The reporting formats will be driven by the adaptive schedule model and the iteration length. The other answer choices contain components that are not part of the schedule management plan. Answer
  • 5. All our questions are updated to the latest  A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.