SlideShare a Scribd company logo
1 of 13
Download to read offline
PIPING GUIDE
A.1 CHECK LIST FOR ISOMETRICS
1) Line Nos.
2) Line Specs
3) Start Point Location
4) End Point Location
5) Branch Connection
6) Valve Accecibility
7) Support
8) Insulation (For Insulated Line Only)
9) Instrument Connection
10) Flow Arrow
11) High Point Vent, Low Point Drain
12) Hydro Test Vent And Drain
13) Nozzle Connection
14) Nozzle Nos.
15) Equipment Nos.
16) Coordinates And Elevations
17) Iso North
18) Bill Of Material
19) Valve Tag Nos.
20) Instruments Tag Nos.
21) Contination Sheets Or Iso. Nos.
22) Grid Location And Nos.
A.2 DOCUMENTS FOR ISOMETRICS CHECKING
1) Piping And Instrument Diagrames
2) Piping Layouts
3) Sectional Drawings
4) Equipment Drawings
5) Nozzle Orientations
6) Piping Specification
7) Suppotrs Standard
8) Special Items Drawings
9) Sress Analysis Report
A.3 POINTS TO REMEMBERS IN ISOMETRICS CHECKING
1) Pump Suction Is Bigger Than Discharge Line
2) Eccentric Reducer (Flat Side Top) Using For Pump Suction Line This Is Using For Avoid The Air
Block In Pump Suction.
3) Pump Suction Line And Compresser Suction Line Keep Always Downword Position, No Loops
Permitted To Pump Suction.
4) Psv Outlet Always Rising Position.
5) Check The Valve Accesibility For Maitainance Purpose. Valve Operating Height Min 250mm To
1200mm From Floor Level.
6) Lift Check Valve Always Horizontally Using. Swing Check Valve Verticaly And Horiontaly Using.
7) Control Station Operating Height 500mm To 750mm From Floor Level.
8) Shoe Not Required For Trunion. (Insulated Lines)
9) Headroom Clearance Minimum 2.2m From Ground/Floor Level.
10) Dripleg Required For Steam Line Header.
11) Shoe Required For Insulated Lines (Steam ,Chilled Water,Brine,Steam Condasate).
12) Shoe Not Required For Condansate Line When Line Will Be On Pipe Rack.
13) Nozzle Orientations Should Be Keep As Per Piping Requirement.
14) Avoid The Obstucles. Keep A Piping Routing Neat And Clearly.
15) Control Stations Locates Side Of Near The Walls Or Columns
16) Give A Trunion Supports To Control Station Both Side Of Control Valves.
17) Use A Dike Wall Around The Equipments For Avoid The Liquid To Spread In The Plant Area. The
Volume Of Dike Wall Is 1.5 Times More Than Total Capacity Of Equipments.
18) Use Weldneck Flange For Pressure Piping.
B.1 TYPES OF CONTROL VALVE
1) Pcv Pressure control Valve
2) Tcv Temperature Control Valve
3) Fcv Flow Control Valve
4) Lcv Level Control Valve
5) Xv Isolation Valve
6) Xcv High Pressure Control Valve
B.2 TYPES OF PUMPS
1) Reciprocating Pump
2) Rotary Pump
3) Centrifugal Pump
4) Vacuum Pump
5) Metering Pump
B.3 TYPES OF EXCHANGER
1) Air Cooler Exchanger
2) Plate Type Exchanger
3) Shell & Tube Exchanger
4) 2 Pipe Exchanger
5) Spiral Exchanger
B.4 TYPES OF COMPRESSOR
1) Elevated Centrifugal Compressor
2) Grade-Mounted Centrifugal Compressor
3) Reciprocating Compressor
B.5 TYPES OF TOWER
1) Tray Tower
2) Packed Tower
3) Vacuume Tower
B.6 TYPES OF VALVE
1) Gate Valve
2) Globe Valve
3) Check Valve (Non Return Valve)
4) Ball Valve
5) Butterfly Valve
6) Diaframe Valve
7) Plug Valve
B.7 TYPE OF FLANGES
1) Weldneck Flange (Flat Face,Race Face)
2) Slipon Flange Do
3) Lap Joint Flange (Flat Face)
4) Reducing Flange (Flat Face,Race Face)
5) Screwed Flange
6) Blind Flange
7) Socketweld Flange
B.7A PRESSURE TEMPERATURE RATTING
150#, 300#, 400#, 600#, 900#, 1500#, 2500#.
B.7B FLANGES FACING
1) Ff Flat Face
2) Rf Raise Face
3) T/G Tongue And Groove Face
4) M/F Male And Female Faces
5) Rtj Ring Type Joint Faces
B.8 TYPES OF FITTINGS
1) 90 Elbow, 45 Elbow (Butt Welded, Socket Welded, Threded)
2) Equal Tee, Reducing Tee Do
3) Cap,Union,Plug, Half Coupling, Full Coupling, Lateral.
B.9 TYPES OF OLETS
1) Laterolet
2) Elbowlet
3) Weldolet
4) Sockolet
5) Threadolet
6) Sweepolet
7) Nippolet
B.10 TYPES OF REDUCER
1) Eccentric Reducer (Butt Welded)
2) Concentric Reducer (Butt Welded)
3) Swages (Socket Weld, Threded)
B.11 TYPES OF INSTRUMENTS
1) Psv Pressure Safety Valve
2) Lg Level Guage
3) Li Level Indicator
3) Pg Pressure Guage
4) Pi Pressure Indicator
4) Cv Control Valve
5) Ti Temperature Indicator
6) Tw Thermowell
7) Fe Flow Elements
8) Fi Flow Indicators
9) Fo Flow Orifice Flanges
A GENERAL PURPOSE
1) Control Valves (Globe, Ball, Butterfly)
2) On/Off Valves (Ball, Butterfly)
3) Relief Valves (Pressure, Thermal)
4) Rapture Disc
5) Restriction Orifice
B FLOW MESSURING INSTRUMENTS
1) Orifice Plate
2) Variable Aria Flow Meter
3) Magnetic Flow Meter
4) Turbine Flow Meter
5) Positive Displacement Meter
C TEMPERATURE MEASURING INSTRUMENTS
1) Thermocouples
2) Resistance Temperature Detactors
3) Filled System
4) Bimetallic Thermometres
5) Thermowells
D PRESSURE MESSURING INSTRUMENTS
1) Manometer
2) Bourden Type
3) Bellow Type
4) Diaphragm Type
E LEVEL MEASURING INSTRUMENTS
1) Level Guage (Direct Type)
2) Hydrostatic Head (Inferential)
3) Buoyancy
4) Conductance
5) Capacitance
6) Radiation
7) Float
B.12 SPECIAL ITEMS
1) Steam Trap (Float Type, Thermodynamic,Bucket)
2) Orifice Flange
3) Flow Elements
4) Strainner (Y Type Srainner, Bucket Type Strainner)
B.13 TYPES OF PIPE ENDS
1) Pbe Plain Both End
2) Ple Plain Large End
3) Pse Plain Small End
4) Ble Bevelled Large End
5) Tse Threaded Small End
B.14 TYPES OF GASKETS
1) Full Face
2) Inside Bolt Circle
3) Spiral Wound Mettalic
4) Ring Type
5) Metal Jacketed
C.1 SERVICE CODE FOR UTILITY LINES
1) Lps Low Pressure Steam
2) Hps High Pressure Steam
3) Mps Medium Pressure Steam
4) Cws Cooling Water Supply
5) Cwr Cooling Water Return
6) Chws Chilled Water Supply
7) Chwr Chilled Water Return
8) Bs Brine Supply
9) Br Brine Return
10) Ia Instrument Air
11) Ca Compress Air
12) Dmw Potable Water35
13) Ps Process Water
C.2 SERVICE CODE FOR PROCESS LINE
1) Fg = Fuel Gas
2) Pa = General Hydrocarbon
3) Pb = Hydrocarbon With Sulfer
4) Pc = Hydrocarbon With Hydrogen
5) Pd = Hydrocarbon With Hydrogen & H2s
6) Pe = Hydrocarbon With Sour Water
7) Cb = High Strenght Caustic
8) Va = Sulphuric Acid
9) Ha = Hydrocloric Acid
10) Cc = Low Strenght Caustic
11) Ct = Catalyst
12) Hy = Hydrogen
13) Ch = Chemicals
14) Ni = Nitrogen
15) Ca = Amines
16) Su = Molten Sulphur
17) Ga = Gaseus Extinguishant
18) Dl = Diesel
19) Fg = Fuel Gas
20) Fs = Fuel Gas (Sour)
21) Fo = Fuel Oil
22) Rt = Refrigerant
23) Lg = Flue Gas
24) Lo = Lube Oil
25) Ba = General Hydrocarbon
26) Bb = Hydrocarbon With Sulphur
27) Bc = Hydrocarbon With Hydrogen
28) Bd = Hydrocarbon With Hydrogen & H2s
29) Be = Hydrocarbon With Sour Water
D.1 SHORT CODE
1) Ibr Indian Boiler Regulation Act
2) Astm American Society Of Testing Material
3) Ansi American National Standard Institute
4) Smls Seamless
5) Thd Threded
6) Bw Butt Welded
8) Sw Socket Welded
9) Ecc. Red. Eccentric Reducer
10) Conc.Red. Concentric Reducer
11) Eq.Tee Equal Tee
12) Red. Tee Reducing Tee
13) Clpg Coupling
14) Vlv Valve
15) Str Strainner
16) T Trap
17) Elb Elbow
18) Fof.El. Finish Floor Elevation
19) Ptfl.El. Platform Elevation
20) Gr.El Ground Elevation
21) Sch Schedule
22) Thk Thickness
23) Eqpt Equipment
24) Sorf Slipon Rase Face
25) Soff Slipon Flat Face
26) Wnrf Weldneck Rase Face
27) Wnff Weldneck Flat Face
28) Bop.El. Bottom Of Elevation
29) Cl.El. Center Line Elevation
30) Pcd Pitch Circle Dia.
31) Nb Nominal Bore
32) Ns Nominal Size
33) Be Beveled End
34) Isi Indian Standard Institute
35) Fst Flat Side Top
36) Fsd Flat Side Down
37) Suc. Suction
38) Disch. Discharge
39) Wp.El. Work Point Elevation
40) Ga General Arrangement
41) P&Id Piping And Instrument Diagrames
D.2 AMERICAN STANDARD
42) Astm The American Society Of Testing Materials
43) Api The Americal Petroleum Institute
44) Aisi The American Iron And Steel Institute
45) Ansi The American National Standard Institute
46) Aws The American Welding Society
47) Awwa The American Water Works Association
48) Asme The American Society Of Mechanical Engineers
D.3 API STANDARDS
1) Api5l Specification For Pipe Line
2) Api6d Pipe Line Valves, End Closers, Connectors, And Swivels
3) Api600 Steel Gate Valve
4) Api 605 Large Diametre Carbon Steel Flanges
D.4 ANSI STANDARDS
1) Ansi/Asme 31.1 Power Piping-1995
2) Ansi/Asme 31.2 Fuel Gas Piping-1968
3) Ansi/Asme-31.3 Chemical Petroleum Refinery Piping-1993
D.5 BRITISH STANDARD
1) BS10 FLANGES
2) BS806 PIPES AND FITTINGS FOR BOILER
3) BS916 BLACK BOLTS,NUTS AND SCREWS
4) BS1560 STEEL PIPE FLANGES
5) BS1414 GATE VALVES FOR PETROLEUM INDUSTRIES
6) BS1600 DIMENSIONS OF STEEL PIPES
7) BS1965 BUTT WELDING PIPE FITTINGS
8) BS2080 FACE TO FACE /END TO END DIMENSIONS OF VALVES
9) BS2598 GLASS PIPE LINES AND FITTINGS.
10) BS3351 PIPING SYSTEM FOR PETROLEUM REFINERIES
E.1 DRAWINGS
1) Study Layout
2) General Arrangement Drawings
3) Piping And Instrument Diagrames
4) Sectional Layouts
5) Civil Layouts
6) Equipment Layouts
7) Fabrication Details Drawing
8) Foudation Details Drawings
9) Structural Layout
10) Isometrics
11) Piping Details Layout
12) Nozzle Orientations
13) Plot Plan
14) Flow Diagrame
F1 PROCESS DESIGN CODE FOR SERVICE
1) Sulfer Asme B31.3
2)
F2.PIPING MATERIAL CODE
1) Buttwelded Fittings A234-Wp5, Sch.40, B16.9
Buttweld, 5crom ½ Molydenum Alloysteel Per Astm Grade
Wp5,Schedule 40, Per Ansi B16.9
2) Spectacle Blind A240-304h 600lb Rf Smth
Stainless Steel, Per Astm A240 Grade 321, Class 600, Per Api
590
3) Piping Cs. A106 Gr. B
4) Valve Cs A216 Wcb
5) Flange Asme B16.5, Class 150 Ratting
6) Small Fittings As A182 F5
7) Gasket Spiral Wound
G.1 PIPE ENDS
1) Bevelled Ends
2) Plain Ends
3) Screwed Ends
4) Flanged Ends
5) Spigot/Socket Ends
6) Buttress End
H.1 PIPE MATERIALS
1) Astm A53 Welded And Seamless Pipe
2) Astm A106 Seamless Cs Pipe For High Temp. Services
3) Api 5l Line Pipe
4) Is 1239 Steel Pipes For General Pupose
5) Is 3589 Steel Pipes For General Services
H.2 DIMENSIONAL STANDARD
1) Ansi B16.1 Cast Iron Flanged End Fittings
2) Ansi B16.3 Malleable Iron Threded Fittings
3) Ansi B16.4 Cast Iron Threded Fittings
4) Ansi B16.5 Steel Flanged End Fittings
5) Ansi B16.9 Buttwelding End Fittings
6) Ansi B16.11 Socketweld And Screwed End Fittings
H.3 SW/SCRD FITTING MATERIALS
1) Astm 105 Forged Carbon Steel
2) Astm A181 Forged Carbon Steel For General Purposes
3) Astm A182 Forged Alloy Steel And Stainless Steel
4) Astm A234 Wrought Carbon Steel And Elevated Alloy Steel Pipe
Fitting For Moderate And Elevated Temperatures
5) Astm A350 Forged Alloy Steel For Low Temperature Services
H.3 BUTTWELDED END FITTINGS
1) Astm A234 Carbon Steel Fittings
2) Astm A403 Austenitic Stainless Steel Fittings
3) Astm A420 Alloy Steel For Low Temperature Services.
H.4 FLANGED END FITTINGS
1) Astm 216 Carbon Steel Castings
2) Astm 351 Stainless Steel Castings
3) Astm A352 Alloy Steel Castings
4) Astm F 1545 Plasting Lined Fittings
5) Is 1538 Ci Fittings
H.5 PIPING PACKAGES
1) Exchanger Piping
2) Reactor Piping
3) Tower Piping
4) Column Piping
5) Pump Suction Discharge Piping
6) Pipe Rack Piping
7) Boiler Piping
8) Cooling Tower Piping
9) Chiller Piping
10) Steam Trap Assembly
11) Control Valve Assembly
12) Steam Manifold Assembly
13) Utility Manifold Assembly
14) Offsite Area Piping
15) Tank Farm Area Piping
16) Trench Piping
17) Under Ground Piping
18) Domestic Piping
19) Diesel Engine Piping
20) Compressor Piping
Piping Concepts
Piping Concepts
Site Plan
Site Plan
Considerations
All aspects of safety, operability, maintenance, constructability and economics.
All aspects of safety, operability, maintenance, constructability and economics.
Layout and spacing of the roads, process plants, tanks and piperacks.
Layout and spacing of the roads, process plants, tanks and piperacks.
Equipment location & spacing, associated piping, controls & maintenance & constructability
Equipment location & spacing, associated piping, controls & maintenance & constructability
Good accessibility to valves and instruments, avoiding hazardous obstructions like misplaced manifolds,
Good accessibility to valves and instruments, avoiding hazardous obstructions like misplaced manifolds,
valve stems & support columns.
valve stems & support columns.
Constructability to ensure no obstruction to transportation, lifting & erection of equipment due to adjacent
Constructability to ensure no obstruction to transportation, lifting & erection of equipment due to adjacent
plant, structures or equipment and compliance to sequenced construction plan.
plant, structures or equipment and compliance to sequenced construction plan.
Potential late delivery of large equipment items to avoid serious impact on construction schedule.
Potential late delivery of large equipment items to avoid serious impact on construction schedule.
One overall site plan for the entire complex, interconnecting piperacks and their relative locations to be
One overall site plan for the entire complex, interconnecting piperacks and their relative locations to be
made.
made.
Process units and offplot facilities, to be constructed to common schedule to be grouped and located to
Process units and offplot facilities, to be constructed to common schedule to be grouped and located to
ensure minimum impact from and to the operating plant during construction for later phases.
ensure minimum impact from and to the operating plant during construction for later phases.
Prevailing wind direction to be considered for special cases.
Prevailing wind direction to be considered for special cases.
For e.g., Flares for the refinery to be located upwind of the process units.
For e.g., Flares for the refinery to be located upwind of the process units.
Layout of the tankage area to suit the flow of products and feed stocks with the pumps stations located
Layout of the tankage area to suit the flow of products and feed stocks with the pumps stations located
outside of the bunded area.
outside of the bunded area.
Roads to be provided around the tanks for access to all areas for maintenance & fire fighting.
Roads to be provided around the tanks for access to all areas for maintenance & fire fighting.
Unit Plot Plan
One unit plot plan for each process unit.
One unit plot plan for each process unit.
Equipment layout & spacing to allow for maintenance & constructability
Equipment layout & spacing to allow for maintenance & constructability
Air coolers to be on top of a pipe rack. No equipment is to be located above or below coolers to facilitate
Air coolers to be on top of a pipe rack. No equipment is to be located above or below coolers to facilitate
access to place the air coolers and remove the tube bundle for maintenance.
access to place the air coolers and remove the tube bundle for maintenance.
Furnaces and boilers to be located at plot boundaries for ease of access. Adequate dropout and swinging
Furnaces and boilers to be located at plot boundaries for ease of access. Adequate dropout and swinging
space for tube pulling by mobile crane.
space for tube pulling by mobile crane.
Fired heaters to be located upwind of process units. In congested process areas, heater locations to provide
Fired heaters to be located upwind of process units. In congested process areas, heater locations to provide
the lowest risk of fire or explosion.
the lowest risk of fire or explosion.
Exchangers to be with channel end away from piperacks to facilitate tube bundle removal
Exchangers to be with channel end away from piperacks to facilitate tube bundle removal
Pumps handling flammable materials not to be located below piperacks but to be placed with centreline of
Pumps handling flammable materials not to be located below piperacks but to be placed with centreline of
discharge at min. 1.5 m from the centre line of pipework column.
discharge at min. 1.5 m from the centre line of pipework column.
Compressors to be located adjacent to roadway and downwind from heaters & to be in shelters to provide
Compressors to be located adjacent to roadway and downwind from heaters & to be in shelters to provide
protection for equipment & personnel. Bridge or gantry crane for removal of compressor components.
protection for equipment & personnel. Bridge or gantry crane for removal of compressor components.
Vertical vessels to be placed on a common centreline parallel to the main piperack USO.
Vertical vessels to be placed on a common centreline parallel to the main piperack USO.
Horizontal vessels to be located to minimise piping runs & to be lined up with their tangents on a common
Horizontal vessels to be located to minimise piping runs & to be lined up with their tangents on a common
locating line.
locating line.
Reactors to be located for ease of access during catalyst unloading and loading operations. Space to be
Reactors to be located for ease of access during catalyst unloading and loading operations. Space to be
provided for cranes and storage of spent and new catalyst.
provided for cranes and storage of spent and new catalyst.
Pipe Stress Analysis
Purpose
To ensure that piping is routed and supported so that no damage occurs to either the pipe or
To ensure that piping is routed and supported so that no damage occurs to either the pipe or
associated equipment due to the effects of thermal expansion or contraction, or loads resulting from
associated equipment due to the effects of thermal expansion or contraction, or loads resulting from
weight, pressure, wind earthquake, pulsation, shock, foundation settlement, etc.
weight, pressure, wind earthquake, pulsation, shock, foundation settlement, etc.
Procedure
Ensuring compliance to all Code, Client and Inspection Authority requirements pertaining to Piping
Ensuring compliance to all Code, Client and Inspection Authority requirements pertaining to Piping
Stress Analysis.
Stress Analysis.
Establishing all operating functions including start-up,
Establishing all operating functions including start-up,
shutdown, steam-out, various combinations of equipment working and idle, bypasses in and out of
shutdown, steam-out, various combinations of equipment working and idle, bypasses in and out of
use, de-coking, etc., for lines to be analyzed.
use, de-coking, etc., for lines to be analyzed.
Stress Critical Line List Review.
Stress Critical Line List Review.
Nozzle loads calculations.
Nozzle loads calculations.
Check for flange leakage where bending moments are large, including flanged connections at
Check for flange leakage where bending moments are large, including flanged connections at
equipment.
equipment.
Anchor loads on structures and/or foundations.
Anchor loads on structures and/or foundations.
Finalising the location of spring supports with required loads and movements on the Stress sketch.
Finalising the location of spring supports with required loads and movements on the Stress sketch.
Analysing requirement of reinforcement at branch connections, (other than for internal/external
Analysing requirement of reinforcement at branch connections, (other than for internal/external
pressure considerations covered by the Piping Material Specification), or at concentrated loading
pressure considerations covered by the Piping Material Specification), or at concentrated loading
points.
points.
Considering expansion joints in stress analysis
Considering expansion joints in stress analysis
Checking position of fixed and sliding supports of heat exchangers, horizontal drums, etc.
Checking position of fixed and sliding supports of heat exchangers, horizontal drums, etc.
Review of vendor drawings for equipment nozzle loadings.
Review of vendor drawings for equipment nozzle loadings.
Piping Layout (GA)
Piping Layout (GA)
Purpose
For piping installation within a construction area.
For piping installation within a construction area.
Information for construction planning.
Information for construction planning.
Information for testing and pre-commissioning.
Information for testing and pre-commissioning.
Information for Plant Operators
Information for Plant Operators.
.
Methodology
Piping arrangement drawings produced in two stages:
Piping arrangement drawings produced in two stages:
–
– Planning drawing (study sketches / 2D CAD )
Planning drawing (study sketches / 2D CAD )
To solve major design problems, transmit information & co-ordinate activities of the
To solve major design problems, transmit information & co-ordinate activities of the
different design departments.
different design departments.
Preliminary piping arrangement for inter-discipline review & comment.
Preliminary piping arrangement for inter-discipline review & comment.
–
– Final drawings (3D CAD model or Non-CAD manual drawing)
Final drawings (3D CAD model or Non-CAD manual drawing)
For 2" and larger lines with dimensions and labelling
For 2" and larger lines with dimensions and labelling
GA Using 3D CAD Model
GA Using 3D CAD Model
–
– G.A. drawings to be extracted from 3D CAD model.
G.A. drawings to be extracted from 3D CAD model.
–
– All verification, geometric & clash checks to be completed (including equipment checks to
All verification, geometric & clash checks to be completed (including equipment checks to
vendor data) before IFC GA extraction.
vendor data) before IFC GA extraction.
Non-CAD GAs
Non-CAD GAs
–
– Additional Pipe support GA’s issued for construction to reflect pipe support requirements
Additional Pipe support GA’s issued for construction to reflect pipe support requirements
only.
only.
Design Data
Design Data
High point of grade.
High point of grade.
Column and vessel orientation
Column and vessel orientation design sketches
design sketches including:
including:
–
– nozzles and manways
nozzles and manways
–
– column and vessel piping
column and vessel piping
–
– platform and ladder size
platform and ladder size
–
– instrument orientation and location
instrument orientation and location
–
– height of tower and vessel skirts
height of tower and vessel skirts
Orientation of major equipment nozzles, i.e. pumps, exchangers, compressors, etc.
Orientation of major equipment nozzles, i.e. pumps, exchangers, compressors, etc.
Top of grout for all equipment foundations & pads.
Top of grout for all equipment foundations & pads.
Pipe rack widths, bent spacing and top of support elevation of main pipe racks.
Pipe rack widths, bent spacing and top of support elevation of main pipe racks.
Allocation of space for electrical, instrument racks, analyser houses, switchgear, and utility hose
Allocation of space for electrical, instrument racks, analyser houses, switchgear, and utility hose
stations.
stations.
Location of all main structural columns.
Location of all main structural columns.
Elevations of structural levels and extent of platforms, ladders and stairs required.
Elevations of structural levels and extent of platforms, ladders and stairs required.
Contents of Piping Layout
Equipment co-ordinates.
Equipment co-ordinates.
Elevations (Piping, Equipment, Platforms, etc.).
Elevations (Piping, Equipment, Platforms, etc.).
Line No. Identification and Flow Arrow.
Line No. Identification and Flow Arrow.
Instrument Identification
Instrument Identification
Match lines.
Match lines.
Drawing Continuation References.
Drawing Continuation References.
Key Plan Identification.
Key Plan Identification.
Complete "Holds" List.
Complete "Holds" List.
Reference Drawings.
Reference Drawings.
Structural Column Identification
Structural Column Identification.
.
Piping Layout - Checkpoints
Conformance with P&ID's for
Conformance with P&ID's for
Line number, size, classification, direction of flow.
Line number, size, classification, direction of flow.
Instrument connections and numbers (long form).
Instrument connections and numbers (long form).
Piping material classification changes.
Piping material classification changes.
Drawing "Holds" list.
Drawing "Holds" list.
Drawing title block & Drawing key plan.
Drawing title block & Drawing key plan.
Compliance with standard drawings and plot plan.
Compliance with standard drawings and plot plan.
Adjacent drawings & key plans for correct co-ordinates & drawing references.
Adjacent drawings & key plans for correct co-ordinates & drawing references.
Fire & Safety requirements & location of fire fighting equipment.
Fire & Safety requirements & location of fire fighting equipment.
Location of Drain hubs, Utility stations, safety showers, eyewashes, drinking fountains & ladders.
Location of Drain hubs, Utility stations, safety showers, eyewashes, drinking fountains & ladders.
No fouling of piping with structures, equipment and other lines.
No fouling of piping with structures, equipment and other lines.
Requirements for operating aisles, headway and roadway clearances and other mandatory
Requirements for operating aisles, headway and roadway clearances and other mandatory
dimensional clearances
dimensional clearances.
.
Piping Isometrics
Piping Isometrics
Purpose
Adequate information to fabricate shop pipework.
Adequate information to fabricate shop pipework.
Adequate information to field run small bore piping.
Adequate information to field run small bore piping.
Adequate information to erect the pre-fabricated pipe spools.
Adequate information to erect the pre-fabricated pipe spools.
Adequate means of identifying materials for above mentioned isometrics.
Adequate means of identifying materials for above mentioned isometrics.
Adequate information for locating & identifying pipe supports welded to shop fabricated pipework.
Adequate information for locating & identifying pipe supports welded to shop fabricated pipework.
Methodology
Shop and field isometrics to be extracted/drawn & self-contained within a model base, plant or unit as
Shop and field isometrics to be extracted/drawn & self-contained within a model base, plant or unit as
defined at start of job.
defined at start of job.
Shop isometrics to be adequately dimensioned to enable spooling and/or shop fabrication.
Shop isometrics to be adequately dimensioned to enable spooling and/or shop fabrication.
Field isometrics to be extracted/drawn with overall dimensions only for material purposes & to
Field isometrics to be extracted/drawn with overall dimensions only for material purposes & to
assist field erection.
assist field erection.
Isometrics using 3D CAD Model
Isometrics using 3D CAD Model
–
– Isometrics to be extracted from 3D CAD model.
Isometrics to be extracted from 3D CAD model.
–
– Isometrics need not be fully checked dimensionally.
Isometrics need not be fully checked dimensionally.
–
– P & ID check of the isometric and yellow off to be done.
P & ID check of the isometric and yellow off to be done.
–
– Material to be downloaded from model.
Material to be downloaded from model.
–
– Isometric to be downloaded for piping spool drawings.
Isometric to be downloaded for piping spool drawings.
Non-CAD Isometrics
Non-CAD Isometrics
–
– Manually prepared on Isometric Sheet.
Manually prepared on Isometric Sheet.
–
– Both dimensional and P&ID checks to be done.
Both dimensional and P&ID checks to be done.
–
– Material to be manually entered.
Material to be manually entered.
Contents of Piping Isometrics
 Line Number & Size
 Pipe Classification
 Direction of Flow
 Equipment Reference & Nozzle Identification
 Structural Number Identification
 Isometric Drawing Continuation References
 All Valving (except vent and drain valves)
 Strainers, Traps & Flexible Hoses
 Break with Shop and Field
 Field Welds (but not shop welds)
 Vents (as V) & Drains (as D)
 Orifice Assemblies
 Spectacle Blinds and Spacers
 Instrument Numbers, such as PI, TIs, TWs, etc.
 Instrument Connections
 Out of Specification Items
 Sample Points
 Special Shop Attachment of Pipe Support
 Dummy Legs
 Cold Pull
 Special Line Features, such as Fall, Reinforcing Pads, Weep Holes, Welded Lugs, etc.
 Spool Identification (suffix letter only)
 Insulation (include limit)
Piping Material
Piping Material
Scope
Scope
Material take-off
Material take-off
Updating & control of material quantities with design
Updating & control of material quantities with design
Monitoring of material requisitions.
Monitoring of material requisitions.
Method
Method
Automated
Automated Material Control
Material Control
–
– MTO download from 3D CAD Model
MTO download from 3D CAD Model
–
– Manual Material Entry (for non-modelled items).
Manual Material Entry (for non-modelled items).
Link to Procurement Tracking System
Link to Procurement Tracking System
Piping Stock Code
Piping Stock Code
Project Stock Code Index generated by Piping Material Classes to be issued as a project
Project Stock Code Index generated by Piping Material Classes to be issued as a project
specification.
specification.
Responsibility
Responsibility
Lead Piping Engineer to schedule and co-ordinate all piping material take-off activities and material
Lead Piping Engineer to schedule and co-ordinate all piping material take-off activities and material
requisitioning.
requisitioning.
Civil Group to give take-off of underground carbon steel non-pressure piping using the appropriate
Civil Group to give take-off of underground carbon steel non-pressure piping using the appropriate
piping class.
piping class.
Instrument Group to give take-off of all instrument piping beyond the primary (root) block valve
Instrument Group to give take-off of all instrument piping beyond the primary (root) block valve
(except at level instruments).
(except at level instruments).
Electrical Group to give take-off of all electrical cable duct piping.
Electrical Group to give take-off of all electrical cable duct piping.
Piping Materials Engineer to transmit a summary of all tubing and tubing fittings requirements to
Piping Materials Engineer to transmit a summary of all tubing and tubing fittings requirements to
Instrument Group for requisitioning.
Instrument Group for requisitioning.
Material Control
Material Control
Initial material take off from :
Initial material take off from :
–
– Completed preliminary line routings in the CAD model
Completed preliminary line routings in the CAD model
–
– Manual take off from P&IDs
Manual take off from P&IDs
Total forecast material requirements including working surplus and contingency form the basis of
Total forecast material requirements including working surplus and contingency form the basis of
the Bulk Material Requisitions.
the Bulk Material Requisitions.
Frequency & timing of material extractions from CAD model & manual MTO ensure that bulk
Frequency & timing of material extractions from CAD model & manual MTO ensure that bulk
material status is concurrent with design.
material status is concurrent with design.
Field material control is possible as the data within the piping material control programme is
Field material control is possible as the data within the piping material control programme is
downloaded to Procurement Tracking System.
downloaded to Procurement Tracking System.
Material requisitions issued to procurement for enquiry/ purchase.
Material requisitions issued to procurement for enquiry/ purchase.
MR quantities issued for purchase (initial & at each revision) are downloaded to Procurement
MR quantities issued for purchase (initial & at each revision) are downloaded to Procurement
Tracking System.
Tracking System.
Statutory Requirements
Statutory Requirements
Applicable Codes
Applicable Codes
International piping codes and standards accepted in India
International piping codes and standards accepted in India
–
– ASME/ANSI B31.1, “Power Piping”
ASME/ANSI B31.1, “Power Piping”
–
– ASME/ANSI B31.3, “Chemical Plant and Petroleum Refinery Piping”
ASME/ANSI B31.3, “Chemical Plant and Petroleum Refinery Piping”
Oil Industry Safety Directorate,Standard 118.
Oil Industry Safety Directorate,Standard 118.
–
– Layout & spacing of roads,buildings,storage tanks and all equipment
Layout & spacing of roads,buildings,storage tanks and all equipment
Authority Approval
Authority Approval
Indian Boiler Regulations (IBR)
Indian Boiler Regulations (IBR)
–
– Materials and fabrication associated with steam and boiler feed systems.
Materials and fabrication associated with steam and boiler feed systems.
Chief Controller of Explosives. (CCOE)
Chief Controller of Explosives. (CCOE)
–
– All Plot Plans for approval together with safety radii from various sources. (Hazardous Area
All Plot Plans for approval together with safety radii from various sources. (Hazardous Area
Drawings).
Drawings).
Tariff Advisory Committee (TAC)
Tariff Advisory Committee (TAC)
–
– Fire protection system & material selection
Fire protection system & material selection.
.

More Related Content

What's hot

Simple Piping design
Simple Piping designSimple Piping design
Simple Piping design
Musa Sabri
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
Mario Fonseca
 
35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope
jubin
 

What's hot (20)

Line sizing
Line sizingLine sizing
Line sizing
 
Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressure
 
B31.3 process piping course 02 metallic pipe & fitting selection
B31.3 process piping course   02 metallic pipe & fitting selectionB31.3 process piping course   02 metallic pipe & fitting selection
B31.3 process piping course 02 metallic pipe & fitting selection
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Simple Piping design
Simple Piping designSimple Piping design
Simple Piping design
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
 
Piping interview
Piping interviewPiping interview
Piping interview
 
Basic piping for freshers Engineer
Basic piping for freshers EngineerBasic piping for freshers Engineer
Basic piping for freshers Engineer
 
Piping and Instrumentation Diagram Development.pdf
Piping and Instrumentation Diagram Development.pdfPiping and Instrumentation Diagram Development.pdf
Piping and Instrumentation Diagram Development.pdf
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
 
P and Id
P and IdP and Id
P and Id
 
Process piping fundamentals, codes and standards module 1
Process piping fundamentals, codes and standards    module 1Process piping fundamentals, codes and standards    module 1
Process piping fundamentals, codes and standards module 1
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
 
Refinery mechanical piping systems a fundamental overview
Refinery mechanical piping systems   a fundamental overviewRefinery mechanical piping systems   a fundamental overview
Refinery mechanical piping systems a fundamental overview
 
35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope
 
Inspection of Heat exchanger .pdf
Inspection of Heat exchanger .pdfInspection of Heat exchanger .pdf
Inspection of Heat exchanger .pdf
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
QC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdfQC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdf
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
 
Introduction to piping design
Introduction to piping designIntroduction to piping design
Introduction to piping design
 

Similar to 428190111-Piping-Guide.pdf

244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf
moumo1
 
Manifold Bulletin - SVM1014
Manifold Bulletin - SVM1014Manifold Bulletin - SVM1014
Manifold Bulletin - SVM1014
Peter White
 

Similar to 428190111-Piping-Guide.pdf (20)

Sz3000
 Sz3000 Sz3000
Sz3000
 
244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf
 
Akai2200amp
Akai2200ampAkai2200amp
Akai2200amp
 
Guia gestra
Guia gestraGuia gestra
Guia gestra
 
Marine System Design
Marine System DesignMarine System Design
Marine System Design
 
GWC Valve International Trunnion Mounted Ball Valves
GWC Valve International Trunnion Mounted Ball ValvesGWC Valve International Trunnion Mounted Ball Valves
GWC Valve International Trunnion Mounted Ball Valves
 
17426 fluid flow operation
17426 fluid flow operation17426 fluid flow operation
17426 fluid flow operation
 
406808075-Piping-questonary.pdf
406808075-Piping-questonary.pdf406808075-Piping-questonary.pdf
406808075-Piping-questonary.pdf
 
Trunnion Mount Ball Valves For Industrial Pipelines
Trunnion Mount Ball Valves For Industrial PipelinesTrunnion Mount Ball Valves For Industrial Pipelines
Trunnion Mount Ball Valves For Industrial Pipelines
 
419471094-PIPING-HANDBOOK-pdf.pdf
419471094-PIPING-HANDBOOK-pdf.pdf419471094-PIPING-HANDBOOK-pdf.pdf
419471094-PIPING-HANDBOOK-pdf.pdf
 
Ss 2-4222
Ss 2-4222Ss 2-4222
Ss 2-4222
 
Air & flue gas system
Air & flue gas system Air & flue gas system
Air & flue gas system
 
Manifold Bulletin - SVM1014
Manifold Bulletin - SVM1014Manifold Bulletin - SVM1014
Manifold Bulletin - SVM1014
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube Design
 
Summer traning on Power Transformer Construction
Summer traning on Power Transformer ConstructionSummer traning on Power Transformer Construction
Summer traning on Power Transformer Construction
 
Pump suction piping rules
Pump suction piping rulesPump suction piping rules
Pump suction piping rules
 
Catalog flow straighner
Catalog flow straighnerCatalog flow straighner
Catalog flow straighner
 
Control Valves (THINKTANK®️)
Control Valves (THINKTANK®️)Control Valves (THINKTANK®️)
Control Valves (THINKTANK®️)
 
1 Hoja especificaciones.pdf
1 Hoja especificaciones.pdf1 Hoja especificaciones.pdf
1 Hoja especificaciones.pdf
 
Vpa4000
  Vpa4000  Vpa4000
Vpa4000
 

Recently uploaded

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 

Recently uploaded (20)

Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 

428190111-Piping-Guide.pdf

  • 1. PIPING GUIDE A.1 CHECK LIST FOR ISOMETRICS 1) Line Nos. 2) Line Specs 3) Start Point Location 4) End Point Location 5) Branch Connection 6) Valve Accecibility 7) Support 8) Insulation (For Insulated Line Only) 9) Instrument Connection 10) Flow Arrow 11) High Point Vent, Low Point Drain 12) Hydro Test Vent And Drain 13) Nozzle Connection 14) Nozzle Nos. 15) Equipment Nos. 16) Coordinates And Elevations 17) Iso North 18) Bill Of Material 19) Valve Tag Nos. 20) Instruments Tag Nos. 21) Contination Sheets Or Iso. Nos. 22) Grid Location And Nos. A.2 DOCUMENTS FOR ISOMETRICS CHECKING 1) Piping And Instrument Diagrames 2) Piping Layouts 3) Sectional Drawings 4) Equipment Drawings 5) Nozzle Orientations 6) Piping Specification 7) Suppotrs Standard 8) Special Items Drawings 9) Sress Analysis Report A.3 POINTS TO REMEMBERS IN ISOMETRICS CHECKING 1) Pump Suction Is Bigger Than Discharge Line 2) Eccentric Reducer (Flat Side Top) Using For Pump Suction Line This Is Using For Avoid The Air Block In Pump Suction. 3) Pump Suction Line And Compresser Suction Line Keep Always Downword Position, No Loops Permitted To Pump Suction. 4) Psv Outlet Always Rising Position. 5) Check The Valve Accesibility For Maitainance Purpose. Valve Operating Height Min 250mm To 1200mm From Floor Level. 6) Lift Check Valve Always Horizontally Using. Swing Check Valve Verticaly And Horiontaly Using. 7) Control Station Operating Height 500mm To 750mm From Floor Level. 8) Shoe Not Required For Trunion. (Insulated Lines) 9) Headroom Clearance Minimum 2.2m From Ground/Floor Level. 10) Dripleg Required For Steam Line Header. 11) Shoe Required For Insulated Lines (Steam ,Chilled Water,Brine,Steam Condasate). 12) Shoe Not Required For Condansate Line When Line Will Be On Pipe Rack. 13) Nozzle Orientations Should Be Keep As Per Piping Requirement. 14) Avoid The Obstucles. Keep A Piping Routing Neat And Clearly. 15) Control Stations Locates Side Of Near The Walls Or Columns 16) Give A Trunion Supports To Control Station Both Side Of Control Valves. 17) Use A Dike Wall Around The Equipments For Avoid The Liquid To Spread In The Plant Area. The Volume Of Dike Wall Is 1.5 Times More Than Total Capacity Of Equipments. 18) Use Weldneck Flange For Pressure Piping.
  • 2. B.1 TYPES OF CONTROL VALVE 1) Pcv Pressure control Valve 2) Tcv Temperature Control Valve 3) Fcv Flow Control Valve 4) Lcv Level Control Valve 5) Xv Isolation Valve 6) Xcv High Pressure Control Valve B.2 TYPES OF PUMPS 1) Reciprocating Pump 2) Rotary Pump 3) Centrifugal Pump 4) Vacuum Pump 5) Metering Pump B.3 TYPES OF EXCHANGER 1) Air Cooler Exchanger 2) Plate Type Exchanger 3) Shell & Tube Exchanger 4) 2 Pipe Exchanger 5) Spiral Exchanger B.4 TYPES OF COMPRESSOR 1) Elevated Centrifugal Compressor 2) Grade-Mounted Centrifugal Compressor 3) Reciprocating Compressor B.5 TYPES OF TOWER 1) Tray Tower 2) Packed Tower 3) Vacuume Tower B.6 TYPES OF VALVE 1) Gate Valve 2) Globe Valve
  • 3. 3) Check Valve (Non Return Valve) 4) Ball Valve 5) Butterfly Valve 6) Diaframe Valve 7) Plug Valve B.7 TYPE OF FLANGES 1) Weldneck Flange (Flat Face,Race Face) 2) Slipon Flange Do 3) Lap Joint Flange (Flat Face) 4) Reducing Flange (Flat Face,Race Face) 5) Screwed Flange 6) Blind Flange 7) Socketweld Flange B.7A PRESSURE TEMPERATURE RATTING 150#, 300#, 400#, 600#, 900#, 1500#, 2500#. B.7B FLANGES FACING 1) Ff Flat Face 2) Rf Raise Face 3) T/G Tongue And Groove Face 4) M/F Male And Female Faces 5) Rtj Ring Type Joint Faces B.8 TYPES OF FITTINGS 1) 90 Elbow, 45 Elbow (Butt Welded, Socket Welded, Threded) 2) Equal Tee, Reducing Tee Do 3) Cap,Union,Plug, Half Coupling, Full Coupling, Lateral. B.9 TYPES OF OLETS 1) Laterolet 2) Elbowlet 3) Weldolet 4) Sockolet
  • 4. 5) Threadolet 6) Sweepolet 7) Nippolet B.10 TYPES OF REDUCER 1) Eccentric Reducer (Butt Welded) 2) Concentric Reducer (Butt Welded) 3) Swages (Socket Weld, Threded) B.11 TYPES OF INSTRUMENTS 1) Psv Pressure Safety Valve 2) Lg Level Guage 3) Li Level Indicator 3) Pg Pressure Guage 4) Pi Pressure Indicator 4) Cv Control Valve 5) Ti Temperature Indicator 6) Tw Thermowell 7) Fe Flow Elements 8) Fi Flow Indicators 9) Fo Flow Orifice Flanges A GENERAL PURPOSE 1) Control Valves (Globe, Ball, Butterfly) 2) On/Off Valves (Ball, Butterfly) 3) Relief Valves (Pressure, Thermal) 4) Rapture Disc 5) Restriction Orifice B FLOW MESSURING INSTRUMENTS 1) Orifice Plate 2) Variable Aria Flow Meter 3) Magnetic Flow Meter 4) Turbine Flow Meter 5) Positive Displacement Meter C TEMPERATURE MEASURING INSTRUMENTS 1) Thermocouples 2) Resistance Temperature Detactors 3) Filled System 4) Bimetallic Thermometres 5) Thermowells D PRESSURE MESSURING INSTRUMENTS 1) Manometer 2) Bourden Type 3) Bellow Type 4) Diaphragm Type E LEVEL MEASURING INSTRUMENTS 1) Level Guage (Direct Type) 2) Hydrostatic Head (Inferential) 3) Buoyancy 4) Conductance 5) Capacitance 6) Radiation 7) Float B.12 SPECIAL ITEMS 1) Steam Trap (Float Type, Thermodynamic,Bucket) 2) Orifice Flange 3) Flow Elements 4) Strainner (Y Type Srainner, Bucket Type Strainner)
  • 5. B.13 TYPES OF PIPE ENDS 1) Pbe Plain Both End 2) Ple Plain Large End 3) Pse Plain Small End 4) Ble Bevelled Large End 5) Tse Threaded Small End B.14 TYPES OF GASKETS 1) Full Face 2) Inside Bolt Circle 3) Spiral Wound Mettalic 4) Ring Type 5) Metal Jacketed C.1 SERVICE CODE FOR UTILITY LINES 1) Lps Low Pressure Steam 2) Hps High Pressure Steam 3) Mps Medium Pressure Steam 4) Cws Cooling Water Supply 5) Cwr Cooling Water Return 6) Chws Chilled Water Supply 7) Chwr Chilled Water Return 8) Bs Brine Supply 9) Br Brine Return 10) Ia Instrument Air 11) Ca Compress Air 12) Dmw Potable Water35 13) Ps Process Water C.2 SERVICE CODE FOR PROCESS LINE 1) Fg = Fuel Gas 2) Pa = General Hydrocarbon 3) Pb = Hydrocarbon With Sulfer 4) Pc = Hydrocarbon With Hydrogen 5) Pd = Hydrocarbon With Hydrogen & H2s 6) Pe = Hydrocarbon With Sour Water 7) Cb = High Strenght Caustic 8) Va = Sulphuric Acid 9) Ha = Hydrocloric Acid 10) Cc = Low Strenght Caustic 11) Ct = Catalyst 12) Hy = Hydrogen 13) Ch = Chemicals 14) Ni = Nitrogen 15) Ca = Amines 16) Su = Molten Sulphur 17) Ga = Gaseus Extinguishant 18) Dl = Diesel 19) Fg = Fuel Gas 20) Fs = Fuel Gas (Sour) 21) Fo = Fuel Oil 22) Rt = Refrigerant 23) Lg = Flue Gas 24) Lo = Lube Oil 25) Ba = General Hydrocarbon 26) Bb = Hydrocarbon With Sulphur 27) Bc = Hydrocarbon With Hydrogen 28) Bd = Hydrocarbon With Hydrogen & H2s 29) Be = Hydrocarbon With Sour Water
  • 6. D.1 SHORT CODE 1) Ibr Indian Boiler Regulation Act 2) Astm American Society Of Testing Material 3) Ansi American National Standard Institute 4) Smls Seamless 5) Thd Threded 6) Bw Butt Welded 8) Sw Socket Welded 9) Ecc. Red. Eccentric Reducer 10) Conc.Red. Concentric Reducer 11) Eq.Tee Equal Tee 12) Red. Tee Reducing Tee 13) Clpg Coupling 14) Vlv Valve 15) Str Strainner 16) T Trap 17) Elb Elbow 18) Fof.El. Finish Floor Elevation 19) Ptfl.El. Platform Elevation 20) Gr.El Ground Elevation 21) Sch Schedule 22) Thk Thickness 23) Eqpt Equipment 24) Sorf Slipon Rase Face 25) Soff Slipon Flat Face 26) Wnrf Weldneck Rase Face 27) Wnff Weldneck Flat Face 28) Bop.El. Bottom Of Elevation 29) Cl.El. Center Line Elevation 30) Pcd Pitch Circle Dia. 31) Nb Nominal Bore 32) Ns Nominal Size 33) Be Beveled End 34) Isi Indian Standard Institute 35) Fst Flat Side Top 36) Fsd Flat Side Down 37) Suc. Suction 38) Disch. Discharge 39) Wp.El. Work Point Elevation 40) Ga General Arrangement 41) P&Id Piping And Instrument Diagrames D.2 AMERICAN STANDARD 42) Astm The American Society Of Testing Materials 43) Api The Americal Petroleum Institute 44) Aisi The American Iron And Steel Institute 45) Ansi The American National Standard Institute 46) Aws The American Welding Society 47) Awwa The American Water Works Association 48) Asme The American Society Of Mechanical Engineers D.3 API STANDARDS 1) Api5l Specification For Pipe Line 2) Api6d Pipe Line Valves, End Closers, Connectors, And Swivels 3) Api600 Steel Gate Valve 4) Api 605 Large Diametre Carbon Steel Flanges D.4 ANSI STANDARDS 1) Ansi/Asme 31.1 Power Piping-1995 2) Ansi/Asme 31.2 Fuel Gas Piping-1968 3) Ansi/Asme-31.3 Chemical Petroleum Refinery Piping-1993
  • 7. D.5 BRITISH STANDARD 1) BS10 FLANGES 2) BS806 PIPES AND FITTINGS FOR BOILER 3) BS916 BLACK BOLTS,NUTS AND SCREWS 4) BS1560 STEEL PIPE FLANGES 5) BS1414 GATE VALVES FOR PETROLEUM INDUSTRIES 6) BS1600 DIMENSIONS OF STEEL PIPES 7) BS1965 BUTT WELDING PIPE FITTINGS 8) BS2080 FACE TO FACE /END TO END DIMENSIONS OF VALVES 9) BS2598 GLASS PIPE LINES AND FITTINGS. 10) BS3351 PIPING SYSTEM FOR PETROLEUM REFINERIES E.1 DRAWINGS 1) Study Layout 2) General Arrangement Drawings 3) Piping And Instrument Diagrames 4) Sectional Layouts 5) Civil Layouts 6) Equipment Layouts 7) Fabrication Details Drawing 8) Foudation Details Drawings 9) Structural Layout 10) Isometrics 11) Piping Details Layout 12) Nozzle Orientations 13) Plot Plan 14) Flow Diagrame F1 PROCESS DESIGN CODE FOR SERVICE 1) Sulfer Asme B31.3 2) F2.PIPING MATERIAL CODE 1) Buttwelded Fittings A234-Wp5, Sch.40, B16.9 Buttweld, 5crom ½ Molydenum Alloysteel Per Astm Grade Wp5,Schedule 40, Per Ansi B16.9 2) Spectacle Blind A240-304h 600lb Rf Smth Stainless Steel, Per Astm A240 Grade 321, Class 600, Per Api 590 3) Piping Cs. A106 Gr. B 4) Valve Cs A216 Wcb 5) Flange Asme B16.5, Class 150 Ratting 6) Small Fittings As A182 F5 7) Gasket Spiral Wound G.1 PIPE ENDS 1) Bevelled Ends 2) Plain Ends 3) Screwed Ends 4) Flanged Ends 5) Spigot/Socket Ends 6) Buttress End H.1 PIPE MATERIALS 1) Astm A53 Welded And Seamless Pipe 2) Astm A106 Seamless Cs Pipe For High Temp. Services 3) Api 5l Line Pipe 4) Is 1239 Steel Pipes For General Pupose 5) Is 3589 Steel Pipes For General Services
  • 8. H.2 DIMENSIONAL STANDARD 1) Ansi B16.1 Cast Iron Flanged End Fittings 2) Ansi B16.3 Malleable Iron Threded Fittings 3) Ansi B16.4 Cast Iron Threded Fittings 4) Ansi B16.5 Steel Flanged End Fittings 5) Ansi B16.9 Buttwelding End Fittings 6) Ansi B16.11 Socketweld And Screwed End Fittings H.3 SW/SCRD FITTING MATERIALS 1) Astm 105 Forged Carbon Steel 2) Astm A181 Forged Carbon Steel For General Purposes 3) Astm A182 Forged Alloy Steel And Stainless Steel 4) Astm A234 Wrought Carbon Steel And Elevated Alloy Steel Pipe Fitting For Moderate And Elevated Temperatures 5) Astm A350 Forged Alloy Steel For Low Temperature Services H.3 BUTTWELDED END FITTINGS 1) Astm A234 Carbon Steel Fittings 2) Astm A403 Austenitic Stainless Steel Fittings 3) Astm A420 Alloy Steel For Low Temperature Services. H.4 FLANGED END FITTINGS 1) Astm 216 Carbon Steel Castings 2) Astm 351 Stainless Steel Castings 3) Astm A352 Alloy Steel Castings 4) Astm F 1545 Plasting Lined Fittings 5) Is 1538 Ci Fittings H.5 PIPING PACKAGES 1) Exchanger Piping 2) Reactor Piping 3) Tower Piping 4) Column Piping 5) Pump Suction Discharge Piping 6) Pipe Rack Piping 7) Boiler Piping 8) Cooling Tower Piping 9) Chiller Piping 10) Steam Trap Assembly 11) Control Valve Assembly 12) Steam Manifold Assembly 13) Utility Manifold Assembly 14) Offsite Area Piping 15) Tank Farm Area Piping 16) Trench Piping 17) Under Ground Piping 18) Domestic Piping 19) Diesel Engine Piping 20) Compressor Piping
  • 9. Piping Concepts Piping Concepts Site Plan Site Plan Considerations All aspects of safety, operability, maintenance, constructability and economics. All aspects of safety, operability, maintenance, constructability and economics. Layout and spacing of the roads, process plants, tanks and piperacks. Layout and spacing of the roads, process plants, tanks and piperacks. Equipment location & spacing, associated piping, controls & maintenance & constructability Equipment location & spacing, associated piping, controls & maintenance & constructability Good accessibility to valves and instruments, avoiding hazardous obstructions like misplaced manifolds, Good accessibility to valves and instruments, avoiding hazardous obstructions like misplaced manifolds, valve stems & support columns. valve stems & support columns. Constructability to ensure no obstruction to transportation, lifting & erection of equipment due to adjacent Constructability to ensure no obstruction to transportation, lifting & erection of equipment due to adjacent plant, structures or equipment and compliance to sequenced construction plan. plant, structures or equipment and compliance to sequenced construction plan. Potential late delivery of large equipment items to avoid serious impact on construction schedule. Potential late delivery of large equipment items to avoid serious impact on construction schedule. One overall site plan for the entire complex, interconnecting piperacks and their relative locations to be One overall site plan for the entire complex, interconnecting piperacks and their relative locations to be made. made. Process units and offplot facilities, to be constructed to common schedule to be grouped and located to Process units and offplot facilities, to be constructed to common schedule to be grouped and located to ensure minimum impact from and to the operating plant during construction for later phases. ensure minimum impact from and to the operating plant during construction for later phases. Prevailing wind direction to be considered for special cases. Prevailing wind direction to be considered for special cases. For e.g., Flares for the refinery to be located upwind of the process units. For e.g., Flares for the refinery to be located upwind of the process units. Layout of the tankage area to suit the flow of products and feed stocks with the pumps stations located Layout of the tankage area to suit the flow of products and feed stocks with the pumps stations located outside of the bunded area. outside of the bunded area. Roads to be provided around the tanks for access to all areas for maintenance & fire fighting. Roads to be provided around the tanks for access to all areas for maintenance & fire fighting. Unit Plot Plan One unit plot plan for each process unit. One unit plot plan for each process unit. Equipment layout & spacing to allow for maintenance & constructability Equipment layout & spacing to allow for maintenance & constructability Air coolers to be on top of a pipe rack. No equipment is to be located above or below coolers to facilitate Air coolers to be on top of a pipe rack. No equipment is to be located above or below coolers to facilitate access to place the air coolers and remove the tube bundle for maintenance. access to place the air coolers and remove the tube bundle for maintenance. Furnaces and boilers to be located at plot boundaries for ease of access. Adequate dropout and swinging Furnaces and boilers to be located at plot boundaries for ease of access. Adequate dropout and swinging space for tube pulling by mobile crane. space for tube pulling by mobile crane. Fired heaters to be located upwind of process units. In congested process areas, heater locations to provide Fired heaters to be located upwind of process units. In congested process areas, heater locations to provide the lowest risk of fire or explosion. the lowest risk of fire or explosion. Exchangers to be with channel end away from piperacks to facilitate tube bundle removal Exchangers to be with channel end away from piperacks to facilitate tube bundle removal Pumps handling flammable materials not to be located below piperacks but to be placed with centreline of Pumps handling flammable materials not to be located below piperacks but to be placed with centreline of discharge at min. 1.5 m from the centre line of pipework column. discharge at min. 1.5 m from the centre line of pipework column. Compressors to be located adjacent to roadway and downwind from heaters & to be in shelters to provide Compressors to be located adjacent to roadway and downwind from heaters & to be in shelters to provide protection for equipment & personnel. Bridge or gantry crane for removal of compressor components. protection for equipment & personnel. Bridge or gantry crane for removal of compressor components. Vertical vessels to be placed on a common centreline parallel to the main piperack USO. Vertical vessels to be placed on a common centreline parallel to the main piperack USO. Horizontal vessels to be located to minimise piping runs & to be lined up with their tangents on a common Horizontal vessels to be located to minimise piping runs & to be lined up with their tangents on a common locating line. locating line. Reactors to be located for ease of access during catalyst unloading and loading operations. Space to be Reactors to be located for ease of access during catalyst unloading and loading operations. Space to be provided for cranes and storage of spent and new catalyst. provided for cranes and storage of spent and new catalyst. Pipe Stress Analysis Purpose To ensure that piping is routed and supported so that no damage occurs to either the pipe or To ensure that piping is routed and supported so that no damage occurs to either the pipe or associated equipment due to the effects of thermal expansion or contraction, or loads resulting from associated equipment due to the effects of thermal expansion or contraction, or loads resulting from weight, pressure, wind earthquake, pulsation, shock, foundation settlement, etc. weight, pressure, wind earthquake, pulsation, shock, foundation settlement, etc. Procedure Ensuring compliance to all Code, Client and Inspection Authority requirements pertaining to Piping Ensuring compliance to all Code, Client and Inspection Authority requirements pertaining to Piping Stress Analysis. Stress Analysis.
  • 10. Establishing all operating functions including start-up, Establishing all operating functions including start-up, shutdown, steam-out, various combinations of equipment working and idle, bypasses in and out of shutdown, steam-out, various combinations of equipment working and idle, bypasses in and out of use, de-coking, etc., for lines to be analyzed. use, de-coking, etc., for lines to be analyzed. Stress Critical Line List Review. Stress Critical Line List Review. Nozzle loads calculations. Nozzle loads calculations. Check for flange leakage where bending moments are large, including flanged connections at Check for flange leakage where bending moments are large, including flanged connections at equipment. equipment. Anchor loads on structures and/or foundations. Anchor loads on structures and/or foundations. Finalising the location of spring supports with required loads and movements on the Stress sketch. Finalising the location of spring supports with required loads and movements on the Stress sketch. Analysing requirement of reinforcement at branch connections, (other than for internal/external Analysing requirement of reinforcement at branch connections, (other than for internal/external pressure considerations covered by the Piping Material Specification), or at concentrated loading pressure considerations covered by the Piping Material Specification), or at concentrated loading points. points. Considering expansion joints in stress analysis Considering expansion joints in stress analysis Checking position of fixed and sliding supports of heat exchangers, horizontal drums, etc. Checking position of fixed and sliding supports of heat exchangers, horizontal drums, etc. Review of vendor drawings for equipment nozzle loadings. Review of vendor drawings for equipment nozzle loadings. Piping Layout (GA) Piping Layout (GA) Purpose For piping installation within a construction area. For piping installation within a construction area. Information for construction planning. Information for construction planning. Information for testing and pre-commissioning. Information for testing and pre-commissioning. Information for Plant Operators Information for Plant Operators. . Methodology Piping arrangement drawings produced in two stages: Piping arrangement drawings produced in two stages: – – Planning drawing (study sketches / 2D CAD ) Planning drawing (study sketches / 2D CAD ) To solve major design problems, transmit information & co-ordinate activities of the To solve major design problems, transmit information & co-ordinate activities of the different design departments. different design departments. Preliminary piping arrangement for inter-discipline review & comment. Preliminary piping arrangement for inter-discipline review & comment. – – Final drawings (3D CAD model or Non-CAD manual drawing) Final drawings (3D CAD model or Non-CAD manual drawing) For 2" and larger lines with dimensions and labelling For 2" and larger lines with dimensions and labelling GA Using 3D CAD Model GA Using 3D CAD Model – – G.A. drawings to be extracted from 3D CAD model. G.A. drawings to be extracted from 3D CAD model. – – All verification, geometric & clash checks to be completed (including equipment checks to All verification, geometric & clash checks to be completed (including equipment checks to vendor data) before IFC GA extraction. vendor data) before IFC GA extraction. Non-CAD GAs Non-CAD GAs – – Additional Pipe support GA’s issued for construction to reflect pipe support requirements Additional Pipe support GA’s issued for construction to reflect pipe support requirements only. only. Design Data Design Data High point of grade. High point of grade. Column and vessel orientation Column and vessel orientation design sketches design sketches including: including: – – nozzles and manways nozzles and manways – – column and vessel piping column and vessel piping – – platform and ladder size platform and ladder size – – instrument orientation and location instrument orientation and location – – height of tower and vessel skirts height of tower and vessel skirts Orientation of major equipment nozzles, i.e. pumps, exchangers, compressors, etc. Orientation of major equipment nozzles, i.e. pumps, exchangers, compressors, etc. Top of grout for all equipment foundations & pads. Top of grout for all equipment foundations & pads. Pipe rack widths, bent spacing and top of support elevation of main pipe racks. Pipe rack widths, bent spacing and top of support elevation of main pipe racks.
  • 11. Allocation of space for electrical, instrument racks, analyser houses, switchgear, and utility hose Allocation of space for electrical, instrument racks, analyser houses, switchgear, and utility hose stations. stations. Location of all main structural columns. Location of all main structural columns. Elevations of structural levels and extent of platforms, ladders and stairs required. Elevations of structural levels and extent of platforms, ladders and stairs required. Contents of Piping Layout Equipment co-ordinates. Equipment co-ordinates. Elevations (Piping, Equipment, Platforms, etc.). Elevations (Piping, Equipment, Platforms, etc.). Line No. Identification and Flow Arrow. Line No. Identification and Flow Arrow. Instrument Identification Instrument Identification Match lines. Match lines. Drawing Continuation References. Drawing Continuation References. Key Plan Identification. Key Plan Identification. Complete "Holds" List. Complete "Holds" List. Reference Drawings. Reference Drawings. Structural Column Identification Structural Column Identification. . Piping Layout - Checkpoints Conformance with P&ID's for Conformance with P&ID's for Line number, size, classification, direction of flow. Line number, size, classification, direction of flow. Instrument connections and numbers (long form). Instrument connections and numbers (long form). Piping material classification changes. Piping material classification changes. Drawing "Holds" list. Drawing "Holds" list. Drawing title block & Drawing key plan. Drawing title block & Drawing key plan. Compliance with standard drawings and plot plan. Compliance with standard drawings and plot plan. Adjacent drawings & key plans for correct co-ordinates & drawing references. Adjacent drawings & key plans for correct co-ordinates & drawing references. Fire & Safety requirements & location of fire fighting equipment. Fire & Safety requirements & location of fire fighting equipment. Location of Drain hubs, Utility stations, safety showers, eyewashes, drinking fountains & ladders. Location of Drain hubs, Utility stations, safety showers, eyewashes, drinking fountains & ladders. No fouling of piping with structures, equipment and other lines. No fouling of piping with structures, equipment and other lines. Requirements for operating aisles, headway and roadway clearances and other mandatory Requirements for operating aisles, headway and roadway clearances and other mandatory dimensional clearances dimensional clearances. . Piping Isometrics Piping Isometrics Purpose Adequate information to fabricate shop pipework. Adequate information to fabricate shop pipework. Adequate information to field run small bore piping. Adequate information to field run small bore piping. Adequate information to erect the pre-fabricated pipe spools. Adequate information to erect the pre-fabricated pipe spools. Adequate means of identifying materials for above mentioned isometrics. Adequate means of identifying materials for above mentioned isometrics. Adequate information for locating & identifying pipe supports welded to shop fabricated pipework. Adequate information for locating & identifying pipe supports welded to shop fabricated pipework. Methodology Shop and field isometrics to be extracted/drawn & self-contained within a model base, plant or unit as Shop and field isometrics to be extracted/drawn & self-contained within a model base, plant or unit as defined at start of job. defined at start of job. Shop isometrics to be adequately dimensioned to enable spooling and/or shop fabrication. Shop isometrics to be adequately dimensioned to enable spooling and/or shop fabrication. Field isometrics to be extracted/drawn with overall dimensions only for material purposes & to Field isometrics to be extracted/drawn with overall dimensions only for material purposes & to assist field erection. assist field erection. Isometrics using 3D CAD Model Isometrics using 3D CAD Model – – Isometrics to be extracted from 3D CAD model. Isometrics to be extracted from 3D CAD model. – – Isometrics need not be fully checked dimensionally. Isometrics need not be fully checked dimensionally. – – P & ID check of the isometric and yellow off to be done. P & ID check of the isometric and yellow off to be done. – – Material to be downloaded from model. Material to be downloaded from model. – – Isometric to be downloaded for piping spool drawings. Isometric to be downloaded for piping spool drawings.
  • 12. Non-CAD Isometrics Non-CAD Isometrics – – Manually prepared on Isometric Sheet. Manually prepared on Isometric Sheet. – – Both dimensional and P&ID checks to be done. Both dimensional and P&ID checks to be done. – – Material to be manually entered. Material to be manually entered. Contents of Piping Isometrics  Line Number & Size  Pipe Classification  Direction of Flow  Equipment Reference & Nozzle Identification  Structural Number Identification  Isometric Drawing Continuation References  All Valving (except vent and drain valves)  Strainers, Traps & Flexible Hoses  Break with Shop and Field  Field Welds (but not shop welds)  Vents (as V) & Drains (as D)  Orifice Assemblies  Spectacle Blinds and Spacers  Instrument Numbers, such as PI, TIs, TWs, etc.  Instrument Connections  Out of Specification Items  Sample Points  Special Shop Attachment of Pipe Support  Dummy Legs  Cold Pull  Special Line Features, such as Fall, Reinforcing Pads, Weep Holes, Welded Lugs, etc.  Spool Identification (suffix letter only)  Insulation (include limit) Piping Material Piping Material Scope Scope Material take-off Material take-off Updating & control of material quantities with design Updating & control of material quantities with design Monitoring of material requisitions. Monitoring of material requisitions. Method Method Automated Automated Material Control Material Control – – MTO download from 3D CAD Model MTO download from 3D CAD Model – – Manual Material Entry (for non-modelled items). Manual Material Entry (for non-modelled items). Link to Procurement Tracking System Link to Procurement Tracking System
  • 13. Piping Stock Code Piping Stock Code Project Stock Code Index generated by Piping Material Classes to be issued as a project Project Stock Code Index generated by Piping Material Classes to be issued as a project specification. specification. Responsibility Responsibility Lead Piping Engineer to schedule and co-ordinate all piping material take-off activities and material Lead Piping Engineer to schedule and co-ordinate all piping material take-off activities and material requisitioning. requisitioning. Civil Group to give take-off of underground carbon steel non-pressure piping using the appropriate Civil Group to give take-off of underground carbon steel non-pressure piping using the appropriate piping class. piping class. Instrument Group to give take-off of all instrument piping beyond the primary (root) block valve Instrument Group to give take-off of all instrument piping beyond the primary (root) block valve (except at level instruments). (except at level instruments). Electrical Group to give take-off of all electrical cable duct piping. Electrical Group to give take-off of all electrical cable duct piping. Piping Materials Engineer to transmit a summary of all tubing and tubing fittings requirements to Piping Materials Engineer to transmit a summary of all tubing and tubing fittings requirements to Instrument Group for requisitioning. Instrument Group for requisitioning. Material Control Material Control Initial material take off from : Initial material take off from : – – Completed preliminary line routings in the CAD model Completed preliminary line routings in the CAD model – – Manual take off from P&IDs Manual take off from P&IDs Total forecast material requirements including working surplus and contingency form the basis of Total forecast material requirements including working surplus and contingency form the basis of the Bulk Material Requisitions. the Bulk Material Requisitions. Frequency & timing of material extractions from CAD model & manual MTO ensure that bulk Frequency & timing of material extractions from CAD model & manual MTO ensure that bulk material status is concurrent with design. material status is concurrent with design. Field material control is possible as the data within the piping material control programme is Field material control is possible as the data within the piping material control programme is downloaded to Procurement Tracking System. downloaded to Procurement Tracking System. Material requisitions issued to procurement for enquiry/ purchase. Material requisitions issued to procurement for enquiry/ purchase. MR quantities issued for purchase (initial & at each revision) are downloaded to Procurement MR quantities issued for purchase (initial & at each revision) are downloaded to Procurement Tracking System. Tracking System. Statutory Requirements Statutory Requirements Applicable Codes Applicable Codes International piping codes and standards accepted in India International piping codes and standards accepted in India – – ASME/ANSI B31.1, “Power Piping” ASME/ANSI B31.1, “Power Piping” – – ASME/ANSI B31.3, “Chemical Plant and Petroleum Refinery Piping” ASME/ANSI B31.3, “Chemical Plant and Petroleum Refinery Piping” Oil Industry Safety Directorate,Standard 118. Oil Industry Safety Directorate,Standard 118. – – Layout & spacing of roads,buildings,storage tanks and all equipment Layout & spacing of roads,buildings,storage tanks and all equipment Authority Approval Authority Approval Indian Boiler Regulations (IBR) Indian Boiler Regulations (IBR) – – Materials and fabrication associated with steam and boiler feed systems. Materials and fabrication associated with steam and boiler feed systems. Chief Controller of Explosives. (CCOE) Chief Controller of Explosives. (CCOE) – – All Plot Plans for approval together with safety radii from various sources. (Hazardous Area All Plot Plans for approval together with safety radii from various sources. (Hazardous Area Drawings). Drawings). Tariff Advisory Committee (TAC) Tariff Advisory Committee (TAC) – – Fire protection system & material selection Fire protection system & material selection. .