SlideShare a Scribd company logo
1 of 4
Download to read offline
Example risk check list (based on a Risk Breakdown Structure)
RBS LEVEL 0 RBS LEVEL 1 RBS LEVEL 2 EXAMPLE RISKS
Could this risk
affect our project?
Yes
No
Don’t know
Not applicable
1.1 Scope definition Scope changes may arise during project.
Redundant scope may be discovered.
1.2 Requirements
definition
Client may introduce significant change during project (positive or negative).
Internal inconsistencies may exist within requirements.
Key requirements may be missing from formal requirement specification.
1.3 Estimates,
assumptions and
constraints
Basis of estimating may be wrong.
Planning assumptions may be invalidated during project.
Imposed constraints may be relieved or removed.
1.4 Technical processes Standard processes may not meet requirements of specific solution.
New processes may be required.
Processes may be improved and made more effective.
1.5 Technology New technology may be developed during project lifetime.
Technology changes may invalidate design.
1.6 Technical interfaces Unexpected interactions may occur at key interfaces.
Data inconsistencies across interfaces may require rework.
Key interfaces may be reduced.
1.7 Design It may prove impossible to meet some requirements within design limitations.
Reuse of existing design elements may be possible.
1.8 Performance Final solution may not meet performance requirements.
Some performance requirements may be mutually exclusive.
1.9 Reliability &
maintainability
Target reliability criteria may be unattainable with chosen solution.
The use of innovative technology may improve reliability.
Maintainability requirements may impose unacceptable design constraints.
1.10 Safety ALARP solution may impose additional cost.
Changes in safety regulations may require significant redesign.
1.11 Security Security implications may be overlooked during design.
Government regulations may change during project.
0. PROJECT RISK
1. TECHNICAL RISK
1.12 Test & acceptance Test protocols may reveal significant design error requiring rework.
Client may withhold final acceptance for reasons outside contract.
© David Hillson and Peter Simon - 2007.
RBS LEVEL 0 RBS LEVEL 1 RBS LEVEL 2 EXAMPLE RISKS
Could this risk
affect our project?
Yes
No
Don’t know
Not applicable
2.1 Project management Project management systems may not be adequate to support project
requirements.
Poor decision-making may result in inappropriate task allocation.
Adoption of best practice risk process may improve project performance.
2.2 Programme/portfolio
management
Project may be given inappropriate priority within the programme.
Other projects may divert key resources.
Other projects may be cancelled and release resources.
2.3 Operations
management
Design may expose weaknesses in existing products or processes.
Business-as-usual demands may reduce project funding or contingency.
2.4 Organisation Reorganisation may impact project organisation (negatively or positively).
Changes in corporate structure may affect project (negatively or positively).
2.5 Resourcing Key resources may be unavailable when required.
Specific skills may not be available when required.
It may be possible to recruit existing subcontract staff permanently.
2.6 Communication The client’s requirement may be misunderstood.
Project reporting needs may change during project.
Key stakeholder interests may change (positively or negatively).
2.7 Information Client may fail to provide required information on time.
Client-supplied information may be inadequate to support project.
2.8 HS&E Health & safety legislation may change during the project.
An accident or incident may occur delaying the project.
2.9 Quality The number of defects found during integration may not match expectations
(higher or lower).
Quality circles may result in significant effort reduction.
Effective quality management may reduce rework.
2. MANAGEMENT RISK
2.10 Reputation Corporate reputation incident may damage support for the project.
Senior management may lose confidence in project team.
Improved reputation may increase availability of funds and resources.
3. COMMERCIAL RISK
3.1 Contractual terms &
conditions
Client standard terms may prove unacceptably onerous.
Contractual terms may contain internal inconsistencies.
Harmonised client/subcontractor terms may reduce risk exposure.
© David Hillson and Peter Simon - 2007.
RBS LEVEL 0 RBS LEVEL 1 RBS LEVEL 2 EXAMPLE RISKS
Could this risk
affect our project?
Yes
No
Don’t know
Not applicable
3.2 Internal procurement Other departments may not deliver as expected.
Required skills may not be available from other departments.
Internal support may increase as the project progresses.
3.3 Suppliers & vendors A key supplier may go out of business.
Mergers between suppliers may erode competitiveness.
Vendors may be able to deliver ahead of schedule.
3.4 Subcontracts Key subcontractors may refuse to work together.
Subcontract staff may take industrial action (strike).
Partnering with selected subcontractors may improve working relationships.
3.5 Client/customer
stability
Client may change business focus and withdraw support for project.
Changes in client personnel may require additional project management
effort.
Client may be bought out or merge with a more supportive company.
3.6 Partnerships & joint
ventures
Our partner may have competing commercial interests.
The joint venture may break up.
4.1 Legislation Changes in legislation may impose changes in the solution (positive or
negative).
Legal requirements may add unforeseen design requirements.
4.2 Exchange rates Exchange rates may change during the project (favourably or unfavourably).
Key suppliers may invoice in foreign currency.
4.3 Site/facilities Site access may prove more difficult than expected.
Required facilities may not be available on site.
New transport arrangements may ease project logistics.
4.4 Environmental/
weather
Weather may be unseasonable (better or worse than expected).
Unexpected environmental conditions may affect progress (positively or
negatively).
4.5 Competition A key competitor may launch a competing product and invalidate the project.
Key staff may be poached by competitors.
Key competitor may withdraw from the market.
4. EXTERNAL RISK
4.6 Regulatory Regulatory requirements may impose unexpected design constraints.
Significant changes in regulation may occur during the project (positive or
negative).
© David Hillson and Peter Simon - 2007.
RBS LEVEL 0 RBS LEVEL 1 RBS LEVEL 2 EXAMPLE RISKS
Could this risk
affect our project?
Yes
No
Don’t know
Not applicable
4.7 Political Political factors may influence senior management support for the project.
A change in government may result in changed priorities or legislation
(positively or negatively).
4.8 Country Local resources may lack the required skills.
Currency instability may undermine the business case for the project.
Local government interest in the project may change (positively or negatively).
4.9 Social/demographic Changing social imperatives may impose additional requirements.
Public perception of the project may change (positively or negatively).
4.10 Pressure groups Extremists may disrupt project progress.
Lobby groups may promote the cause of the project.
4.11 Force majeure Force majeure event may occur, disrupting the project.
Occurrence of force majeure may create an opportunity to address underlying
issues.
© David Hillson and Peter Simon - 2007.

More Related Content

What's hot

Build vs. Buy: A New Look at the Classic IT Dilemma
Build vs. Buy: A New Look at the Classic IT DilemmaBuild vs. Buy: A New Look at the Classic IT Dilemma
Build vs. Buy: A New Look at the Classic IT DilemmaZuora, Inc.
 
PMO Managed Service Introduction
PMO Managed Service IntroductionPMO Managed Service Introduction
PMO Managed Service IntroductionKeith Rackley
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
APMP Foundation: Preparing for the APMP Foundation Exam
APMP Foundation: Preparing for the APMP Foundation ExamAPMP Foundation: Preparing for the APMP Foundation Exam
APMP Foundation: Preparing for the APMP Foundation ExamBid to Win Ltd
 
Change Management Proposal
Change Management ProposalChange Management Proposal
Change Management ProposalRoy Hoppe
 
Business Proposal Powerpoint Presentation Slides
Business Proposal Powerpoint Presentation SlidesBusiness Proposal Powerpoint Presentation Slides
Business Proposal Powerpoint Presentation SlidesSlideTeam
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...Shamil Habet
 
The Changing Landscape of Project Management in 2018
The Changing Landscape of Project Management in 2018The Changing Landscape of Project Management in 2018
The Changing Landscape of Project Management in 2018Richard Kok
 
Infrastructure Project Manager
Infrastructure Project ManagerInfrastructure Project Manager
Infrastructure Project Managergaryclough
 
Team Capability Assessment PowerPoint Presentation Slides
Team Capability Assessment PowerPoint Presentation Slides Team Capability Assessment PowerPoint Presentation Slides
Team Capability Assessment PowerPoint Presentation Slides SlideTeam
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
PMO View Interactive Dashboard
PMO View Interactive DashboardPMO View Interactive Dashboard
PMO View Interactive DashboardMatt Angerer
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkHossam Maghrabi
 
Project management
Project managementProject management
Project managementNihal Ranjan
 
APMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process ManagementAPMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process ManagementBid to Win Ltd
 

What's hot (20)

Build vs. Buy: A New Look at the Classic IT Dilemma
Build vs. Buy: A New Look at the Classic IT DilemmaBuild vs. Buy: A New Look at the Classic IT Dilemma
Build vs. Buy: A New Look at the Classic IT Dilemma
 
PMO Managed Service Introduction
PMO Managed Service IntroductionPMO Managed Service Introduction
PMO Managed Service Introduction
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
APMP Foundation: Preparing for the APMP Foundation Exam
APMP Foundation: Preparing for the APMP Foundation ExamAPMP Foundation: Preparing for the APMP Foundation Exam
APMP Foundation: Preparing for the APMP Foundation Exam
 
Change Management Proposal
Change Management ProposalChange Management Proposal
Change Management Proposal
 
Project governance
Project governanceProject governance
Project governance
 
Business Proposal Powerpoint Presentation Slides
Business Proposal Powerpoint Presentation SlidesBusiness Proposal Powerpoint Presentation Slides
Business Proposal Powerpoint Presentation Slides
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
The Changing Landscape of Project Management in 2018
The Changing Landscape of Project Management in 2018The Changing Landscape of Project Management in 2018
The Changing Landscape of Project Management in 2018
 
Infrastructure Project Manager
Infrastructure Project ManagerInfrastructure Project Manager
Infrastructure Project Manager
 
Project governanc
Project governancProject governanc
Project governanc
 
Team Capability Assessment PowerPoint Presentation Slides
Team Capability Assessment PowerPoint Presentation Slides Team Capability Assessment PowerPoint Presentation Slides
Team Capability Assessment PowerPoint Presentation Slides
 
Project management
Project managementProject management
Project management
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
PMO View Interactive Dashboard
PMO View Interactive DashboardPMO View Interactive Dashboard
PMO View Interactive Dashboard
 
Change Management
Change ManagementChange Management
Change Management
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management Framework
 
Project management
Project managementProject management
Project management
 
APMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process ManagementAPMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process Management
 

Similar to Example risk check list based on a risk breakdown structure

PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE S. Sathishkumar
 
challenges of highway projects in India
challenges of highway projects in Indiachallenges of highway projects in India
challenges of highway projects in IndiaSanjay Kedia
 
An admittedly incomplete list of business components and possible risks
An admittedly incomplete list of business components and possible risksAn admittedly incomplete list of business components and possible risks
An admittedly incomplete list of business components and possible risksSalt Marsh Solutions, Inc.
 
Project management risks.pptx for college
Project management risks.pptx for collegeProject management risks.pptx for college
Project management risks.pptx for collegessuser829171
 
Pre-opening interior snagging services for luxury hotels
Pre-opening interior snagging services for luxury hotelsPre-opening interior snagging services for luxury hotels
Pre-opening interior snagging services for luxury hotelsSamir Khosla
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfreddyramesh2024
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfShaikNasir10
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfsaikumarmba2023
 
Impact of eLearning Scope Creep_ A Project Manager's Guide
Impact of eLearning Scope Creep_ A Project Manager's GuideImpact of eLearning Scope Creep_ A Project Manager's Guide
Impact of eLearning Scope Creep_ A Project Manager's Guidevinaybommena900
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)Rintu Das
 
GER_Project_Management_Ch22_summary.pdf
GER_Project_Management_Ch22_summary.pdfGER_Project_Management_Ch22_summary.pdf
GER_Project_Management_Ch22_summary.pdfTigabu Yaya
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train WrecksPete Luan
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industryAngad Partap Singh Bali
 
Top 5 Pitfalls to Avoid Implemeting COSO 2013
Top 5 Pitfalls to Avoid Implemeting COSO 2013Top 5 Pitfalls to Avoid Implemeting COSO 2013
Top 5 Pitfalls to Avoid Implemeting COSO 2013Aviva Spectrum™
 
Scope cerrp vs golden plating
Scope cerrp vs golden platingScope cerrp vs golden plating
Scope cerrp vs golden platingmohamed fawzy
 
Top 10 project mgt. problems
Top 10 project mgt. problemsTop 10 project mgt. problems
Top 10 project mgt. problemsMaksudul Munna
 

Similar to Example risk check list based on a risk breakdown structure (20)

PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Why Software Estimations Fail.pptx
Why Software Estimations Fail.pptxWhy Software Estimations Fail.pptx
Why Software Estimations Fail.pptx
 
challenges of highway projects in India
challenges of highway projects in Indiachallenges of highway projects in India
challenges of highway projects in India
 
An admittedly incomplete list of business components and possible risks
An admittedly incomplete list of business components and possible risksAn admittedly incomplete list of business components and possible risks
An admittedly incomplete list of business components and possible risks
 
Project management risks.pptx for college
Project management risks.pptx for collegeProject management risks.pptx for college
Project management risks.pptx for college
 
Pre-opening interior snagging services for luxury hotels
Pre-opening interior snagging services for luxury hotelsPre-opening interior snagging services for luxury hotels
Pre-opening interior snagging services for luxury hotels
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
 
Impact of eLearning Scope Creep_ A Project Manager's Guide
Impact of eLearning Scope Creep_ A Project Manager's GuideImpact of eLearning Scope Creep_ A Project Manager's Guide
Impact of eLearning Scope Creep_ A Project Manager's Guide
 
Oscpa webinar sox change readiness
Oscpa webinar sox change readinessOscpa webinar sox change readiness
Oscpa webinar sox change readiness
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
GER_Project_Management_Ch22_summary.pdf
GER_Project_Management_Ch22_summary.pdfGER_Project_Management_Ch22_summary.pdf
GER_Project_Management_Ch22_summary.pdf
 
Iss 03
Iss 03Iss 03
Iss 03
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
 
Top 5 Pitfalls to Avoid Implemeting COSO 2013
Top 5 Pitfalls to Avoid Implemeting COSO 2013Top 5 Pitfalls to Avoid Implemeting COSO 2013
Top 5 Pitfalls to Avoid Implemeting COSO 2013
 
Scope cerrp vs golden plating
Scope cerrp vs golden platingScope cerrp vs golden plating
Scope cerrp vs golden plating
 
Top 10 project mgt. problems
Top 10 project mgt. problemsTop 10 project mgt. problems
Top 10 project mgt. problems
 
Ch22
Ch22Ch22
Ch22
 

Recently uploaded

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 

Recently uploaded (20)

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 

Example risk check list based on a risk breakdown structure

  • 1. Example risk check list (based on a Risk Breakdown Structure) RBS LEVEL 0 RBS LEVEL 1 RBS LEVEL 2 EXAMPLE RISKS Could this risk affect our project? Yes No Don’t know Not applicable 1.1 Scope definition Scope changes may arise during project. Redundant scope may be discovered. 1.2 Requirements definition Client may introduce significant change during project (positive or negative). Internal inconsistencies may exist within requirements. Key requirements may be missing from formal requirement specification. 1.3 Estimates, assumptions and constraints Basis of estimating may be wrong. Planning assumptions may be invalidated during project. Imposed constraints may be relieved or removed. 1.4 Technical processes Standard processes may not meet requirements of specific solution. New processes may be required. Processes may be improved and made more effective. 1.5 Technology New technology may be developed during project lifetime. Technology changes may invalidate design. 1.6 Technical interfaces Unexpected interactions may occur at key interfaces. Data inconsistencies across interfaces may require rework. Key interfaces may be reduced. 1.7 Design It may prove impossible to meet some requirements within design limitations. Reuse of existing design elements may be possible. 1.8 Performance Final solution may not meet performance requirements. Some performance requirements may be mutually exclusive. 1.9 Reliability & maintainability Target reliability criteria may be unattainable with chosen solution. The use of innovative technology may improve reliability. Maintainability requirements may impose unacceptable design constraints. 1.10 Safety ALARP solution may impose additional cost. Changes in safety regulations may require significant redesign. 1.11 Security Security implications may be overlooked during design. Government regulations may change during project. 0. PROJECT RISK 1. TECHNICAL RISK 1.12 Test & acceptance Test protocols may reveal significant design error requiring rework. Client may withhold final acceptance for reasons outside contract. © David Hillson and Peter Simon - 2007.
  • 2. RBS LEVEL 0 RBS LEVEL 1 RBS LEVEL 2 EXAMPLE RISKS Could this risk affect our project? Yes No Don’t know Not applicable 2.1 Project management Project management systems may not be adequate to support project requirements. Poor decision-making may result in inappropriate task allocation. Adoption of best practice risk process may improve project performance. 2.2 Programme/portfolio management Project may be given inappropriate priority within the programme. Other projects may divert key resources. Other projects may be cancelled and release resources. 2.3 Operations management Design may expose weaknesses in existing products or processes. Business-as-usual demands may reduce project funding or contingency. 2.4 Organisation Reorganisation may impact project organisation (negatively or positively). Changes in corporate structure may affect project (negatively or positively). 2.5 Resourcing Key resources may be unavailable when required. Specific skills may not be available when required. It may be possible to recruit existing subcontract staff permanently. 2.6 Communication The client’s requirement may be misunderstood. Project reporting needs may change during project. Key stakeholder interests may change (positively or negatively). 2.7 Information Client may fail to provide required information on time. Client-supplied information may be inadequate to support project. 2.8 HS&E Health & safety legislation may change during the project. An accident or incident may occur delaying the project. 2.9 Quality The number of defects found during integration may not match expectations (higher or lower). Quality circles may result in significant effort reduction. Effective quality management may reduce rework. 2. MANAGEMENT RISK 2.10 Reputation Corporate reputation incident may damage support for the project. Senior management may lose confidence in project team. Improved reputation may increase availability of funds and resources. 3. COMMERCIAL RISK 3.1 Contractual terms & conditions Client standard terms may prove unacceptably onerous. Contractual terms may contain internal inconsistencies. Harmonised client/subcontractor terms may reduce risk exposure. © David Hillson and Peter Simon - 2007.
  • 3. RBS LEVEL 0 RBS LEVEL 1 RBS LEVEL 2 EXAMPLE RISKS Could this risk affect our project? Yes No Don’t know Not applicable 3.2 Internal procurement Other departments may not deliver as expected. Required skills may not be available from other departments. Internal support may increase as the project progresses. 3.3 Suppliers & vendors A key supplier may go out of business. Mergers between suppliers may erode competitiveness. Vendors may be able to deliver ahead of schedule. 3.4 Subcontracts Key subcontractors may refuse to work together. Subcontract staff may take industrial action (strike). Partnering with selected subcontractors may improve working relationships. 3.5 Client/customer stability Client may change business focus and withdraw support for project. Changes in client personnel may require additional project management effort. Client may be bought out or merge with a more supportive company. 3.6 Partnerships & joint ventures Our partner may have competing commercial interests. The joint venture may break up. 4.1 Legislation Changes in legislation may impose changes in the solution (positive or negative). Legal requirements may add unforeseen design requirements. 4.2 Exchange rates Exchange rates may change during the project (favourably or unfavourably). Key suppliers may invoice in foreign currency. 4.3 Site/facilities Site access may prove more difficult than expected. Required facilities may not be available on site. New transport arrangements may ease project logistics. 4.4 Environmental/ weather Weather may be unseasonable (better or worse than expected). Unexpected environmental conditions may affect progress (positively or negatively). 4.5 Competition A key competitor may launch a competing product and invalidate the project. Key staff may be poached by competitors. Key competitor may withdraw from the market. 4. EXTERNAL RISK 4.6 Regulatory Regulatory requirements may impose unexpected design constraints. Significant changes in regulation may occur during the project (positive or negative). © David Hillson and Peter Simon - 2007.
  • 4. RBS LEVEL 0 RBS LEVEL 1 RBS LEVEL 2 EXAMPLE RISKS Could this risk affect our project? Yes No Don’t know Not applicable 4.7 Political Political factors may influence senior management support for the project. A change in government may result in changed priorities or legislation (positively or negatively). 4.8 Country Local resources may lack the required skills. Currency instability may undermine the business case for the project. Local government interest in the project may change (positively or negatively). 4.9 Social/demographic Changing social imperatives may impose additional requirements. Public perception of the project may change (positively or negatively). 4.10 Pressure groups Extremists may disrupt project progress. Lobby groups may promote the cause of the project. 4.11 Force majeure Force majeure event may occur, disrupting the project. Occurrence of force majeure may create an opportunity to address underlying issues. © David Hillson and Peter Simon - 2007.