SlideShare a Scribd company logo
1 of 75
Download to read offline
Design and
Construction of
Auger Cast Piles
101th Annual Road School 2015
3/11/2015
Malek Smadi, Ph.D., P.E.
Principal Engineer - GEOTILL - Fishers, IN
msmadi@geotill.com - www.geotill.com
CONTENTS
1. Auger Cast Pile Types
2. Construction Sequence
3. Applications For
Transportation Projects
4. Common Materials
5. Construction Equipment
6. Procedures Used In This
Technology
7. Static Axial Capacity,
Case History
8. Group Effects For Axial
Capacity Lateral Load And
Settlement, Case History
9. Quality Control (QC)/
Quality Assurance (QA)
Example of Foundations Failure
1
Example of Foundations Failure
2
Example of Foundations Failure
3
Example of Foundations Failure
4
Auger Cast Pile Types
Auger Cast Pile (ACP)
Continuous Flight Auger (CFA) Piles
Augered-Cast-in-Place (ACIP)
Auger Pressure Grout
Screw Piles
Drilled Displacement (DD) Piles
Auger Cast Pile Types
Auger cast piles are a type of
drilled foundation in which the
pile is drilled to the final depth
in one continuous process using
a continuous flight auger.
Auger
Cast Piles
Auger Cast Pile Types
A) During drilling the flights of the auger are filled with soil, providing lateral support and maintaining the
stability of the hole. B) At the same time the auger is withdrawn from the hole, concrete or a sand/cement
grout is placed by pumping the concrete/grout mix through the hollow center of the auger pipe to the base of
the auger that provides continuous support of the hole. C) Then Steel-reinforcement is placed into the hole.
Auger Cast Pile Types
Drilled Displacement (DD) Piles
Auger Cast Pile Types
Auger Cast Pile Types
Auger Cast Piles
Auger cast piles are typically installed with
diameters ranging from 12 to 36 in. and lengths
of up to 100 ft. In Europe with more recent
powerful rigs, diameters could go up to 60 in.
The reinforcement is in the upper portion of the
pile for ease of installation and low bending
stresses are transferred below these depths. In
some cases, full-length reinforcement is used, as
is most common with drilled shaft foundations.
Auger cast piles can be constructed as single
piles like for soundwall or light pole foundations
For bridges or other large structural foundations,
auger cast piles are most commonly installed as
part of a pile group in a manner similar to that of
driven pile foundations
Auger Cast Pile Types
Drilled Shaft vs. CFA Foundation
Auger Cast Piles
Use of casing or slurry to temporarily support the
hole is avoided.
Drilling the hole in one continuous process is faster
than drilling a shaft excavation.
Because of torque requirement the diameter and
length of CFA piles are generally less than drilled
shafts.
Continuous auger for installation also limits CFA
piles to soil or very weak rock profiles.
Auger Cast Pile Types
Drilled Shaft vs. CFA Foundation
Auger Cast Piles
Auger Cast Pile Types
Driven Piles vs. CFA Foundation
Auger Cast Piles
Noise and vibration due to pile driving are
minimized.
CFA piles eliminate splices and cutoffs.
Soil heave due to driving can be eliminated when
non-displacement CFA piles are used.
A disadvantage of CFA piles compared to driven
piles is that the available QA methods to verify the
structural integrity and pile bearing capacity for CFA
piles are less reliable than those for driven piles.
CFA piles generate soil spoils that require collection
and disposal especially if it is contaminated.
Construction Sequence - Drilling
Effect of Over- Excavation using CFA Piles
Balanced auger rotation and
penetration rates
The auger having an
excessively slow penetration
rate and an insufficient base
feed to keep the auger flights
full
Construction Sequence - Drilling
When a soil profile
being drilled has mixed
soil conditions (e.g.,
weak and strong
layers), difficulties
may arise. If the rig
cannot penetrate the
strong soil stratum at
the proper rate, the
augers can “mine” the
overlying weak soil to
the surface and cause
subsidence.
One solution to properly balance soil removal and
penetration rate is to use Drilled Displacement (DD) piles.
Construction Sequence - Grouting
When the drilling stage
is complete and the
auger has penetrated to
the required depth, the
grouting stage must
begin immediately.
Grout or concrete is
pumped under pressure
through a hose to the
top of the rig and
delivered to the base of
the auger via the
hollow center of the
auger stem.Grout Delivered to Pump
Construction Sequence - Grouting
Hole at Base of Auger for Concrete
Construction Sequence – Grouting Sequence
Upon achieving the design pile tip elevation, the auger is lifted a short
distance typically 6 to 12 in. and grout is pumped under pressure to
expel the plug at the base of the internal pipe and commence the flow.
The auger is then screwed back down to the original pile tip elevation
to establish a small head of grout or concrete on the auger and to
achieve a good bearing contact at the pile tip.
The grout is pumped continuously under pressure typically up to 150 to
300 psi measured at the top of the auger while the auger is lifted
smoothly in one continuous operation.
Simultaneously, as the auger is lifted, the soil is removed from the
flights at the ground surface so that soil cuttings are not lifted high into
the air (potential safety hazard).
After the auger has cleared the ground surface and the
grouting/concrete procedure is completed, any remaining soil cuttings
are removed from the area at the top of the pile and the top of the pile
is cleared of debris and contamination.
The reinforcement cage is lowered into the fluid grout/concrete to
the required depth and tied off at the ground surface to maintain
the proper reinforcement elevation.
Construction Sequence
Construction Sequence
Sometime the top
of the pile can be
difficult to find
among the surface
disturbance.
Attention to detail
in the final
preparation of the
surface is critical
to ensure that
structural integrity
is maintained.
Grout at Surface after Auger
Withdrawal
Construction Sequence
Finishing Pile and Reinforcement Placement
Construction Sequence - Grout vs. Concrete
Concrete
Majority of work is using a
sand/cement grout mixture
because of the fluidity and ease of
installation of reinforcement. The
typical range of compressive
strength of grout (4,000 to 5,000
psi).
In the grout mix, fly ash and slag
are often substituted for a portion
of the cement for 24% to 30% to
produce mixes with higher
workability and pumpability,
reduced bleeding, and reduced
shrinkage.
Grout is so fluid that the
workability is typically measured
using a flow cone.
For concrete a pea-gravel size
aggregate with around 42% sand
used in the mix. Concrete is cited
as being less costly than grout,
less prone to overrun volume, and
is considered to be more stable in
the hole when constructing piles
through soft ground. Concrete
slump for CFA construction is
similar to that of wet-hole drilled
shaft construction, with target
slump values in the 8 in. ± 1 in.
range.
Grout
Applications For Transportation Projects
Bridge Piers and
Abutments.
Soundwalls.
Earth Retaining
Structures.
Pile-Supported
Embankments.
Advantages And Limitations of CFA Piles
Speed of installation of CFA piles and
lower cost over other pile types.
Increased requirements to minimize
noise and vibrations from pile
installation in heavily populated areas.
A reluctance by many owners to utilize
CFA piles because of concerns about
quality control and structural integrity.
Demand on bridges for uplift and
lateral load capacity, scour
considerations, and/or seismic
considerations, require pile diameters
and possibly lengths
Advantages And Limitations of CFA Piles
Medium to very stiff clay soils.
Cemented sands or weak limestone.
Medium dense to dense silty sands
and well-graded sands.
Rock overlain by stiff or cemented
deposits.
Favorable Geotechnical Conditions
Very soft soils.
Loose sands under groundwater.
Geologic formations containing voids.
Hard soil or rock overlain by soft soil
or loose, granular soil.
Unfavorable Geotechnical Conditions
Applications For Transportation Projects
Favorable geotechnical conditions available.
Projects where speed of installation is important.
Batter Piles Required.
Projects where large numbers of piles are required.
Low headroom conditions.
When to Select and Use the CFA Piles
Applications For Transportation Projects
Bridge Piers and Abutments
Types of bridge most suited for
the use of CFA
Interchange structures (where
scour is not a major issue).
Approach structures.
Or those involving bridge widening.
Applications For Transportation Projects
Bridge Piers and Abutments
Crosby, Texas
Applications For Transportation Projects
Bridge Piers and Abutments
Crosby, Texas Twelve production
piles were
instrumented and
monitored during
construction and load
testing using trucks.
The results from the
pile instrumentation
suggest that the piles
supported the fully
loaded bridge entirely
by mobilizing side
friction alone and with
very small around 0.1
in. movements.
Applications For Transportation Projects
Low Headroom Conditions
Applications For Transportation Projects
Secant or Tangent Pile Walls
CFA piles can be a
viable alternative to
drilled shafts or
slurry walls.
A structural steel
section may be used
for pile reinforcement
rather than a
reinforcing cage.
Needs heavy drilling
equipment.
Applications For Transportation Projects
Secant or Tangent Pile Walls
Applications For Transportation Projects
Drilling CFA Piles for Secant
Wall
Applications For Transportation Projects
Secant or Tangent Pile Walls
New Haven, Connecticut
Applications For Transportation Projects
Secant or Tangent Pile Walls
New Haven, Connecticut
Applications For Transportation Projects
Soundwalls in Favorable Soil
Applications For Transportation Projects
Pilecaps on CFA Piles for a Pile-Supported Embankment
The use of CFA piles for a pile-supported embankment may
represent a cost-effective alternative to ground modification
Applications For Transportation Projects
Pilecaps on CFA Piles for a Pile-Supported Embankment
Foundation strata consist
of weak and compressible
subsoils, which would take
a long time to consolidate.
Accelerating construction.
fill supporting a
transportation facility that is
particularly sensitive to
settlements (such as a
high-speed rail).
Accelerated construction is
required for projects where
additional cost due to
traffic shifts, geotechnical
instrumentation, and
related time delays present
an unacceptable situation
to project owners
Construction Cost
($20 to $28 per linear foot
Costs relating to performance and integrity testing are likely to
be higher on transportation projects.
Length, diameter, reinforcement, and grout strength.
Size of the project.
Mobilization cost
Many Variables Affect Pile Costs
Construction Equipment
Crane-Attached CFA System Hydraulic CFA System
Construction Equipment
Augers for Different Soil Conditions: Auger for CFA Piles in
Sandy Soil (Top) and Augers for DD Piles (Bottom)
Construction Equipment
Auger for Use in Clay, with Auger Cleaner Attachment
Construction Equipment
Cutter Heads for Hard Material (left) and Soil (right)
Construction Equipment
Double Rotary CFA Piles
Construction Equipment
Trucks Discharging into Pump Close up View of Grout Pump
Construction Equipment
In-Line Flowmeter
Construction Equipment
Sensor for Concrete Pressure at Auger Tip
Reinforcement
Machine-Welded Reinforcement Cage on Project Site
Reinforcement
Use of Steel Pipe to Reinforce a CFA Pile for a Wall
Reinforcement
Installation of Reinforcement Cage into Battered CFA Pile
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
12 Floors Building in Downtown Fort Wayne, Indiana
Static Axial Capacity and Group Effects, Case History
14 Floors Tower in Downtown Indianapolis, Indiana
Static Axial Capacity and Group Effects, Case History
14 Floors Tower in Downtown Indianapolis, Indiana
Static Axial Capacity and Group Effects, Case History
14 Floors Tower in Downtown Indianapolis, Indiana
Quality Control (QC) / Quality Assurance (QA)
Operator with Cab Mounted Display Used to Control Drilling
Monitoring and Control of the Drilling Phase
The operator and
inspector should
observe and record
the depth of the
auger, the speed of
the auger, the rate
at which the auger
penetrates into the
ground, and the
torque with which
the auger is rotated.
Quality Control (QC) / Quality Assurance (QA)
In-line Flowmeter
Monitoring and Control of the Grouting/Concreting Phase
Control of the
grouting /
concreting phase
of construction
may be the most
important aspect
of QA/QC for
CFA piles.
Quality Control (QC) / Quality Assurance (QA)
Display Panel for Observation by Inspector
Monitoring and Control of the Grouting/Concreting Phase
Quality Control (QC) / Quality Assurance (QA)
Example Data Sheet from Project
Quality Control (QC) / Quality Assurance (QA)
Cubes for Grout Testing
Quality Control (QC) / Quality Assurance (QA)
Integrity Testing by Surface Methods -Sonic Echo Testing
Use of Integrity Testing
Quality Control (QC) / Quality Assurance (QA)
Integrity Testing using Downhole Techniques
Downhole Single-Hole Sonic Logging (SSL) Concept
Use of Integrity Testing
Quality Control (QC) / Quality Assurance (QA)
Static Load Test Setup on CFA Piles
Load Testing
Quality Control (QC) / Quality Assurance (QA)
Proof Testing of Production Piles with Statnamic
Load Testing
Questions ?
Malek Smadi, Ph.D., P.E.
Principal Engineer - GEOTILL - Fishers, IN
msmadi@geotill.com - www.geotill.com

More Related Content

What's hot (20)

Lecture 2 bearing capacity
Lecture 2 bearing capacityLecture 2 bearing capacity
Lecture 2 bearing capacity
 
Deep foundation ppt my final tos work
Deep foundation ppt  my final tos workDeep foundation ppt  my final tos work
Deep foundation ppt my final tos work
 
Standard penetration test
Standard penetration testStandard penetration test
Standard penetration test
 
Granular subbase and equipments used for its construction
Granular subbase and equipments used for its constructionGranular subbase and equipments used for its construction
Granular subbase and equipments used for its construction
 
Pavement materials in Road Construction
Pavement materials in Road ConstructionPavement materials in Road Construction
Pavement materials in Road Construction
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Settlement of soil/foundation
Settlement of soil/foundationSettlement of soil/foundation
Settlement of soil/foundation
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
2
22
2
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
 
Grading of bitumen by SURAJ KUMAR
Grading of bitumen by SURAJ KUMARGrading of bitumen by SURAJ KUMAR
Grading of bitumen by SURAJ KUMAR
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
EXCAVATIONS
EXCAVATIONSEXCAVATIONS
EXCAVATIONS
 
Earthwork
EarthworkEarthwork
Earthwork
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
Piles, Piers and Caissons
Piles, Piers and CaissonsPiles, Piers and Caissons
Piles, Piers and Caissons
 
Lec 7 pile foundation
Lec 7 pile foundationLec 7 pile foundation
Lec 7 pile foundation
 
Field Compaction
Field CompactionField Compaction
Field Compaction
 
Dewatering by well point system
Dewatering by well point systemDewatering by well point system
Dewatering by well point system
 

Viewers also liked

Mantenimiento Correctivo
Mantenimiento CorrectivoMantenimiento Correctivo
Mantenimiento CorrectivoOrtega98
 
Mantenimiento Correctivo
Mantenimiento CorrectivoMantenimiento Correctivo
Mantenimiento CorrectivoAngel Medina
 
Mantenimiento Correctivo
Mantenimiento CorrectivoMantenimiento Correctivo
Mantenimiento Correctivokarig28
 
Mantenimiento Correctivo
Mantenimiento CorrectivoMantenimiento Correctivo
Mantenimiento Correctivocasa
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSjagrutib22
 
Mantenimiento correctivo
Mantenimiento correctivoMantenimiento correctivo
Mantenimiento correctivoJuan Manuel
 
Mantenimiento correctivo
Mantenimiento correctivoMantenimiento correctivo
Mantenimiento correctivofranportus
 
PILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAPILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAaditya singh
 
Statistical Quality Control.
Statistical Quality Control.Statistical Quality Control.
Statistical Quality Control.Raviraj Jadeja
 
Mantenimiento correctivo
Mantenimiento correctivo Mantenimiento correctivo
Mantenimiento correctivo saritaseminario
 

Viewers also liked (16)

Cmh bp profile 2013
Cmh bp profile 2013Cmh bp profile 2013
Cmh bp profile 2013
 
Microtunel Construction / Secant Pile
Microtunel Construction / Secant PileMicrotunel Construction / Secant Pile
Microtunel Construction / Secant Pile
 
Mantenimiento Correctivo
Mantenimiento CorrectivoMantenimiento Correctivo
Mantenimiento Correctivo
 
Mantenimiento Correctivo
Mantenimiento CorrectivoMantenimiento Correctivo
Mantenimiento Correctivo
 
ADSC Presentation - 11.30.12
ADSC Presentation - 11.30.12ADSC Presentation - 11.30.12
ADSC Presentation - 11.30.12
 
Mantenimiento Correctivo
Mantenimiento CorrectivoMantenimiento Correctivo
Mantenimiento Correctivo
 
Mantenimiento Correctivo
Mantenimiento CorrectivoMantenimiento Correctivo
Mantenimiento Correctivo
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONS
 
Mantenimiento correctivo
Mantenimiento correctivoMantenimiento correctivo
Mantenimiento correctivo
 
Mantenimiento correctivo
Mantenimiento correctivoMantenimiento correctivo
Mantenimiento correctivo
 
PILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAPILE FOUNDATION-INDIA
PILE FOUNDATION-INDIA
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
Statistical Quality Control.
Statistical Quality Control.Statistical Quality Control.
Statistical Quality Control.
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Mantenimiento correctivo
Mantenimiento correctivo Mantenimiento correctivo
Mantenimiento correctivo
 

Similar to Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL

deep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptxdeep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptxvalter gentile
 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundationashishcivil098
 
Soil Nailing (1) [Autosaved] (1).pptx
Soil Nailing (1) [Autosaved] (1).pptxSoil Nailing (1) [Autosaved] (1).pptx
Soil Nailing (1) [Autosaved] (1).pptxHariAinala
 
Pile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraPile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraSUNIL KUMAR MOHAPATRA
 
Influence of deep foundation installation methods morgan nesmith
Influence of deep foundation installation methods   morgan nesmithInfluence of deep foundation installation methods   morgan nesmith
Influence of deep foundation installation methods morgan nesmithcfpbolivia
 
EP- August 2015.PDF
EP- August 2015.PDFEP- August 2015.PDF
EP- August 2015.PDFMoises Nava
 
1206765 634528654292080000
1206765 6345286542920800001206765 634528654292080000
1206765 634528654292080000Civil Engineers
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement techniqueSatish Kambaliya
 
Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)Daphne Tan
 
pdfslide.net_ppt-stone-columns.pptx
pdfslide.net_ppt-stone-columns.pptxpdfslide.net_ppt-stone-columns.pptx
pdfslide.net_ppt-stone-columns.pptxSAYANSAHA963163
 
Pre fabricated vertical drain and stone columns
Pre fabricated vertical drain and stone columnsPre fabricated vertical drain and stone columns
Pre fabricated vertical drain and stone columnsRavi Bhadani
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Controlnik kin
 

Similar to Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL (20)

deep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptxdeep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundation
 
pile wall
pile wallpile wall
pile wall
 
Soil Nailing (1) [Autosaved] (1).pptx
Soil Nailing (1) [Autosaved] (1).pptxSoil Nailing (1) [Autosaved] (1).pptx
Soil Nailing (1) [Autosaved] (1).pptx
 
6.1 Grouting.pptx
6.1 Grouting.pptx6.1 Grouting.pptx
6.1 Grouting.pptx
 
Compaction grouting hassan
Compaction  grouting hassanCompaction  grouting hassan
Compaction grouting hassan
 
Pile Foundation
Pile FoundationPile Foundation
Pile Foundation
 
Pile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraPile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatra
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
 
Influence of deep foundation installation methods morgan nesmith
Influence of deep foundation installation methods   morgan nesmithInfluence of deep foundation installation methods   morgan nesmith
Influence of deep foundation installation methods morgan nesmith
 
EP- August 2015.PDF
EP- August 2015.PDFEP- August 2015.PDF
EP- August 2015.PDF
 
1206765 634528654292080000
1206765 6345286542920800001206765 634528654292080000
1206765 634528654292080000
 
Soil nailing
Soil nailing Soil nailing
Soil nailing
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)
 
pdfslide.net_ppt-stone-columns.pptx
pdfslide.net_ppt-stone-columns.pptxpdfslide.net_ppt-stone-columns.pptx
pdfslide.net_ppt-stone-columns.pptx
 
Pre fabricated vertical drain and stone columns
Pre fabricated vertical drain and stone columnsPre fabricated vertical drain and stone columns
Pre fabricated vertical drain and stone columns
 
Chapter 09
Chapter 09Chapter 09
Chapter 09
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 

Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL

  • 1. Design and Construction of Auger Cast Piles 101th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com
  • 2. CONTENTS 1. Auger Cast Pile Types 2. Construction Sequence 3. Applications For Transportation Projects 4. Common Materials 5. Construction Equipment 6. Procedures Used In This Technology 7. Static Axial Capacity, Case History 8. Group Effects For Axial Capacity Lateral Load And Settlement, Case History 9. Quality Control (QC)/ Quality Assurance (QA)
  • 7. Auger Cast Pile Types Auger Cast Pile (ACP) Continuous Flight Auger (CFA) Piles Augered-Cast-in-Place (ACIP) Auger Pressure Grout Screw Piles Drilled Displacement (DD) Piles
  • 8. Auger Cast Pile Types Auger cast piles are a type of drilled foundation in which the pile is drilled to the final depth in one continuous process using a continuous flight auger. Auger Cast Piles
  • 9. Auger Cast Pile Types A) During drilling the flights of the auger are filled with soil, providing lateral support and maintaining the stability of the hole. B) At the same time the auger is withdrawn from the hole, concrete or a sand/cement grout is placed by pumping the concrete/grout mix through the hollow center of the auger pipe to the base of the auger that provides continuous support of the hole. C) Then Steel-reinforcement is placed into the hole.
  • 10. Auger Cast Pile Types Drilled Displacement (DD) Piles
  • 12. Auger Cast Pile Types Auger Cast Piles Auger cast piles are typically installed with diameters ranging from 12 to 36 in. and lengths of up to 100 ft. In Europe with more recent powerful rigs, diameters could go up to 60 in. The reinforcement is in the upper portion of the pile for ease of installation and low bending stresses are transferred below these depths. In some cases, full-length reinforcement is used, as is most common with drilled shaft foundations. Auger cast piles can be constructed as single piles like for soundwall or light pole foundations For bridges or other large structural foundations, auger cast piles are most commonly installed as part of a pile group in a manner similar to that of driven pile foundations
  • 13. Auger Cast Pile Types Drilled Shaft vs. CFA Foundation Auger Cast Piles Use of casing or slurry to temporarily support the hole is avoided. Drilling the hole in one continuous process is faster than drilling a shaft excavation. Because of torque requirement the diameter and length of CFA piles are generally less than drilled shafts. Continuous auger for installation also limits CFA piles to soil or very weak rock profiles.
  • 14. Auger Cast Pile Types Drilled Shaft vs. CFA Foundation Auger Cast Piles
  • 15. Auger Cast Pile Types Driven Piles vs. CFA Foundation Auger Cast Piles Noise and vibration due to pile driving are minimized. CFA piles eliminate splices and cutoffs. Soil heave due to driving can be eliminated when non-displacement CFA piles are used. A disadvantage of CFA piles compared to driven piles is that the available QA methods to verify the structural integrity and pile bearing capacity for CFA piles are less reliable than those for driven piles. CFA piles generate soil spoils that require collection and disposal especially if it is contaminated.
  • 16. Construction Sequence - Drilling Effect of Over- Excavation using CFA Piles Balanced auger rotation and penetration rates The auger having an excessively slow penetration rate and an insufficient base feed to keep the auger flights full
  • 17. Construction Sequence - Drilling When a soil profile being drilled has mixed soil conditions (e.g., weak and strong layers), difficulties may arise. If the rig cannot penetrate the strong soil stratum at the proper rate, the augers can “mine” the overlying weak soil to the surface and cause subsidence. One solution to properly balance soil removal and penetration rate is to use Drilled Displacement (DD) piles.
  • 18. Construction Sequence - Grouting When the drilling stage is complete and the auger has penetrated to the required depth, the grouting stage must begin immediately. Grout or concrete is pumped under pressure through a hose to the top of the rig and delivered to the base of the auger via the hollow center of the auger stem.Grout Delivered to Pump
  • 19. Construction Sequence - Grouting Hole at Base of Auger for Concrete
  • 20. Construction Sequence – Grouting Sequence Upon achieving the design pile tip elevation, the auger is lifted a short distance typically 6 to 12 in. and grout is pumped under pressure to expel the plug at the base of the internal pipe and commence the flow. The auger is then screwed back down to the original pile tip elevation to establish a small head of grout or concrete on the auger and to achieve a good bearing contact at the pile tip. The grout is pumped continuously under pressure typically up to 150 to 300 psi measured at the top of the auger while the auger is lifted smoothly in one continuous operation. Simultaneously, as the auger is lifted, the soil is removed from the flights at the ground surface so that soil cuttings are not lifted high into the air (potential safety hazard). After the auger has cleared the ground surface and the grouting/concrete procedure is completed, any remaining soil cuttings are removed from the area at the top of the pile and the top of the pile is cleared of debris and contamination. The reinforcement cage is lowered into the fluid grout/concrete to the required depth and tied off at the ground surface to maintain the proper reinforcement elevation.
  • 22. Construction Sequence Sometime the top of the pile can be difficult to find among the surface disturbance. Attention to detail in the final preparation of the surface is critical to ensure that structural integrity is maintained. Grout at Surface after Auger Withdrawal
  • 23. Construction Sequence Finishing Pile and Reinforcement Placement
  • 24. Construction Sequence - Grout vs. Concrete Concrete Majority of work is using a sand/cement grout mixture because of the fluidity and ease of installation of reinforcement. The typical range of compressive strength of grout (4,000 to 5,000 psi). In the grout mix, fly ash and slag are often substituted for a portion of the cement for 24% to 30% to produce mixes with higher workability and pumpability, reduced bleeding, and reduced shrinkage. Grout is so fluid that the workability is typically measured using a flow cone. For concrete a pea-gravel size aggregate with around 42% sand used in the mix. Concrete is cited as being less costly than grout, less prone to overrun volume, and is considered to be more stable in the hole when constructing piles through soft ground. Concrete slump for CFA construction is similar to that of wet-hole drilled shaft construction, with target slump values in the 8 in. ± 1 in. range. Grout
  • 25. Applications For Transportation Projects Bridge Piers and Abutments. Soundwalls. Earth Retaining Structures. Pile-Supported Embankments.
  • 26. Advantages And Limitations of CFA Piles Speed of installation of CFA piles and lower cost over other pile types. Increased requirements to minimize noise and vibrations from pile installation in heavily populated areas. A reluctance by many owners to utilize CFA piles because of concerns about quality control and structural integrity. Demand on bridges for uplift and lateral load capacity, scour considerations, and/or seismic considerations, require pile diameters and possibly lengths
  • 27. Advantages And Limitations of CFA Piles Medium to very stiff clay soils. Cemented sands or weak limestone. Medium dense to dense silty sands and well-graded sands. Rock overlain by stiff or cemented deposits. Favorable Geotechnical Conditions Very soft soils. Loose sands under groundwater. Geologic formations containing voids. Hard soil or rock overlain by soft soil or loose, granular soil. Unfavorable Geotechnical Conditions
  • 28. Applications For Transportation Projects Favorable geotechnical conditions available. Projects where speed of installation is important. Batter Piles Required. Projects where large numbers of piles are required. Low headroom conditions. When to Select and Use the CFA Piles
  • 29. Applications For Transportation Projects Bridge Piers and Abutments Types of bridge most suited for the use of CFA Interchange structures (where scour is not a major issue). Approach structures. Or those involving bridge widening.
  • 30. Applications For Transportation Projects Bridge Piers and Abutments Crosby, Texas
  • 31. Applications For Transportation Projects Bridge Piers and Abutments Crosby, Texas Twelve production piles were instrumented and monitored during construction and load testing using trucks. The results from the pile instrumentation suggest that the piles supported the fully loaded bridge entirely by mobilizing side friction alone and with very small around 0.1 in. movements.
  • 32. Applications For Transportation Projects Low Headroom Conditions
  • 33. Applications For Transportation Projects Secant or Tangent Pile Walls CFA piles can be a viable alternative to drilled shafts or slurry walls. A structural steel section may be used for pile reinforcement rather than a reinforcing cage. Needs heavy drilling equipment.
  • 34. Applications For Transportation Projects Secant or Tangent Pile Walls
  • 35. Applications For Transportation Projects Drilling CFA Piles for Secant Wall
  • 36. Applications For Transportation Projects Secant or Tangent Pile Walls New Haven, Connecticut
  • 37. Applications For Transportation Projects Secant or Tangent Pile Walls New Haven, Connecticut
  • 38. Applications For Transportation Projects Soundwalls in Favorable Soil
  • 39. Applications For Transportation Projects Pilecaps on CFA Piles for a Pile-Supported Embankment The use of CFA piles for a pile-supported embankment may represent a cost-effective alternative to ground modification
  • 40. Applications For Transportation Projects Pilecaps on CFA Piles for a Pile-Supported Embankment Foundation strata consist of weak and compressible subsoils, which would take a long time to consolidate. Accelerating construction. fill supporting a transportation facility that is particularly sensitive to settlements (such as a high-speed rail). Accelerated construction is required for projects where additional cost due to traffic shifts, geotechnical instrumentation, and related time delays present an unacceptable situation to project owners
  • 41. Construction Cost ($20 to $28 per linear foot Costs relating to performance and integrity testing are likely to be higher on transportation projects. Length, diameter, reinforcement, and grout strength. Size of the project. Mobilization cost Many Variables Affect Pile Costs
  • 42. Construction Equipment Crane-Attached CFA System Hydraulic CFA System
  • 43. Construction Equipment Augers for Different Soil Conditions: Auger for CFA Piles in Sandy Soil (Top) and Augers for DD Piles (Bottom)
  • 44. Construction Equipment Auger for Use in Clay, with Auger Cleaner Attachment
  • 45. Construction Equipment Cutter Heads for Hard Material (left) and Soil (right)
  • 47. Construction Equipment Trucks Discharging into Pump Close up View of Grout Pump
  • 49. Construction Equipment Sensor for Concrete Pressure at Auger Tip
  • 51. Reinforcement Use of Steel Pipe to Reinforce a CFA Pile for a Wall
  • 52. Reinforcement Installation of Reinforcement Cage into Battered CFA Pile
  • 53. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 54. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 55. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 56. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 57. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 58. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 59. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 60. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 61. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 62. Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana
  • 63. Static Axial Capacity and Group Effects, Case History 14 Floors Tower in Downtown Indianapolis, Indiana
  • 64. Static Axial Capacity and Group Effects, Case History 14 Floors Tower in Downtown Indianapolis, Indiana
  • 65. Static Axial Capacity and Group Effects, Case History 14 Floors Tower in Downtown Indianapolis, Indiana
  • 66. Quality Control (QC) / Quality Assurance (QA) Operator with Cab Mounted Display Used to Control Drilling Monitoring and Control of the Drilling Phase The operator and inspector should observe and record the depth of the auger, the speed of the auger, the rate at which the auger penetrates into the ground, and the torque with which the auger is rotated.
  • 67. Quality Control (QC) / Quality Assurance (QA) In-line Flowmeter Monitoring and Control of the Grouting/Concreting Phase Control of the grouting / concreting phase of construction may be the most important aspect of QA/QC for CFA piles.
  • 68. Quality Control (QC) / Quality Assurance (QA) Display Panel for Observation by Inspector Monitoring and Control of the Grouting/Concreting Phase
  • 69. Quality Control (QC) / Quality Assurance (QA) Example Data Sheet from Project
  • 70. Quality Control (QC) / Quality Assurance (QA) Cubes for Grout Testing
  • 71. Quality Control (QC) / Quality Assurance (QA) Integrity Testing by Surface Methods -Sonic Echo Testing Use of Integrity Testing
  • 72. Quality Control (QC) / Quality Assurance (QA) Integrity Testing using Downhole Techniques Downhole Single-Hole Sonic Logging (SSL) Concept Use of Integrity Testing
  • 73. Quality Control (QC) / Quality Assurance (QA) Static Load Test Setup on CFA Piles Load Testing
  • 74. Quality Control (QC) / Quality Assurance (QA) Proof Testing of Production Piles with Statnamic Load Testing
  • 75. Questions ? Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com