SlideShare a Scribd company logo
1 of 6
1
1 Project profile GNSS Package No: 7 Investigation, Design and
Earth work Excavation of GNSS Main Canal
from Km. 209.025 to KM 240.000 including
Construction of CM & CD works and Excavation
of Chitvel Branch Canal including construction
of CM & CD works for distributory system and
field Channels to feed an ayacut of 40,000 Acres
under Package -07/2006 of GNSS Phase-II in
Kadapa District
2 Utilization of water in TMC Nil
3 Administrative Sanction :
Rs. ECV value Rs. 155.46 Crores.
4 No of Packages 1
5 Agreement value of Package
(Pkgs 6 to 14)
: RsRs. 117.99 Crs
6 Expenditure (Pkgs 6 to 14)
as on 31.03.2019
: RsRs. 23.99 Crs
GNSS PROJECT (PHASE-II)
2
3
7 Progress of Work Total Completed % Balance
Qty of Earth work (L.Cum) : 1 17.40 13.04 Work is pre
closed
Qty of Concrete (L.Cum) : 0.35 000 0 work is pre closed
8 Land Acquisition (Ph-II 6 to 14)
(Acres)
Required Requisitioned Acquired Balance
1230.80 1230.80 292.94 938.56
9 Forest (Ph-II 6 to 14) (Ha) Required Requisitioned Alienated Balance
0 0.000 0.00 0
10 IP Contemplated : 40000 acres
11 IP created as on 31.03.2019 : Nil-Acres (New), Nil- Acres (Stab)
4
12 Status of Land Acquisition 1. L.A is pending due to stiff resistance from the
formers as the canal is running in costly
horticulture lands.
(13)Canal alignment is not passing through forest
13 Status of Forest
14 Structures (Nos) (6 to 14)
(including Distributory
System)
:
Total Completed Progress Balance
(Revised Estimate is prepared and submitted for
Rs.552.81 Crores to the Government for approval)
15 Main Canal length (Km)
Branch Canal length (Km)
: 30.975 9.00 0 21.975
67.00 0 0 67.00
Total Completed Progress Balance
16
National Highways (Nos)
State Highways (Nos)
Railway Crossings (Nos)
:
:
0 0 0 0
9 - -- 9
3 0 0 3
Tentative
17 R&R (for 6 to 14)
No. of villages affected Fully (Nos) : -----
No. of Housing units Shifted (Nos) : ------
No. of R & R Centers contemplated
(Nos)
Exp. incurred
:
:
:
------
-----
18 Irrigation Potential 40000
19
Districts benefited Kadapa - 40000
20 Percentage of work done
(Physical) (6to14)
: 20.33(work is pre closed)
21 No of Lifts & Its details (if any) Nil
22 Target date of completion : (subjected to approval of already submitted estimate)
5
23. Bottlenecks in detail : L.A is pending due to stiff resistance from the formers as the canal is running
in costly horticulture lands. Accouts are to be settled for the previous agency
for closure of contract. At present Peg marking from Ch.220.225KM to
Ch.220.825KM, 223.025KM to 223.925KM and 223.925KM to 225.025KM is in
Progress.
24 Any additional information (if any): The work is pre closed. Settlement of accounts is in progress. And
Estimate for balance quantities with current SSR 2018-19 is prepared and submitted to the Government
for approval for Rs.552.81 Crores.Total Land acquisition required is 1230.80 acres. Already acquired land
is 292.24 acres and the balance LA is 938.56 acres. Revised L.P schedules to an extent of 908.503 acres
submitted to the Spl. Collector, GNSS kadapa on 16.05.2018. Field survey for LA is in progress. Survey
and peg marking completed for 176.45 acres. At present Peg marking from Ch.220.225KM to
Ch.220.825KM, 223.025KM to 223.925KM and 223.925KM to 225.025KM is in Progress.
6

More Related Content

Similar to Status of GNSS Phase II of Package.7 Kadapa.ppt

PMDP Presentation Sep-22_Final dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final  dt 27.10.2022.pptxPMDP Presentation Sep-22_Final  dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final dt 27.10.2022.pptxssuserea04ef1
 
T13 Work Plan for Extension of time with financial target
T13 Work Plan for Extension of time  with financial targetT13 Work Plan for Extension of time  with financial target
T13 Work Plan for Extension of time with financial targetdivyanshudahayat
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptAkdDeshmukh
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)jamsheer p
 
MPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptxMPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptxSuyogJungare
 
Detailed Project Report-BAVLA-Green Eminent 2010 GUDM
Detailed Project Report-BAVLA-Green Eminent 2010 GUDMDetailed Project Report-BAVLA-Green Eminent 2010 GUDM
Detailed Project Report-BAVLA-Green Eminent 2010 GUDMShashikant Kumar, Ph.D
 
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation  for NCC-FFP Meeting -Keyal HPP.pptxupdated Presentation  for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptxhurain5
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15Ptpg Stuc
 
EMCRP Draft ISR Mission_Presentation_August, 2022.pptx
EMCRP Draft   ISR  Mission_Presentation_August, 2022.pptxEMCRP Draft   ISR  Mission_Presentation_August, 2022.pptx
EMCRP Draft ISR Mission_Presentation_August, 2022.pptxappoloes971
 
Yhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxYhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxKheljitSingh
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Munir Hussain
 
Fairgrounds Permit Application Amend Phase 1 11-15-2010
Fairgrounds Permit Application Amend Phase 1 11-15-2010Fairgrounds Permit Application Amend Phase 1 11-15-2010
Fairgrounds Permit Application Amend Phase 1 11-15-2010Adam Cohen
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptSrikanthTirluka1
 
ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxssuser3797b9
 
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptxBhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptxssuser8ee2f9
 

Similar to Status of GNSS Phase II of Package.7 Kadapa.ppt (20)

Nagpur csr
Nagpur csrNagpur csr
Nagpur csr
 
exp_sewage.pptx
exp_sewage.pptxexp_sewage.pptx
exp_sewage.pptx
 
PMDP Presentation Sep-22_Final dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final  dt 27.10.2022.pptxPMDP Presentation Sep-22_Final  dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final dt 27.10.2022.pptx
 
T13 Work Plan for Extension of time with financial target
T13 Work Plan for Extension of time  with financial targetT13 Work Plan for Extension of time  with financial target
T13 Work Plan for Extension of time with financial target
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
 
MPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptxMPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptx
 
Detailed Project Report-BAVLA-Green Eminent 2010 GUDM
Detailed Project Report-BAVLA-Green Eminent 2010 GUDMDetailed Project Report-BAVLA-Green Eminent 2010 GUDM
Detailed Project Report-BAVLA-Green Eminent 2010 GUDM
 
Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017
 
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation  for NCC-FFP Meeting -Keyal HPP.pptxupdated Presentation  for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
EMCRP Draft ISR Mission_Presentation_August, 2022.pptx
EMCRP Draft   ISR  Mission_Presentation_August, 2022.pptxEMCRP Draft   ISR  Mission_Presentation_August, 2022.pptx
EMCRP Draft ISR Mission_Presentation_August, 2022.pptx
 
Yhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxYhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptx
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019
 
Fairgrounds Permit Application Amend Phase 1 11-15-2010
Fairgrounds Permit Application Amend Phase 1 11-15-2010Fairgrounds Permit Application Amend Phase 1 11-15-2010
Fairgrounds Permit Application Amend Phase 1 11-15-2010
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.ppt
 
ONGC Offshore Projects
ONGC Offshore ProjectsONGC Offshore Projects
ONGC Offshore Projects
 
Wb final presentation
Wb final presentationWb final presentation
Wb final presentation
 
ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptx
 
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptxBhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
 

Recently uploaded

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 

Recently uploaded (20)

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 

Status of GNSS Phase II of Package.7 Kadapa.ppt

  • 1. 1
  • 2. 1 Project profile GNSS Package No: 7 Investigation, Design and Earth work Excavation of GNSS Main Canal from Km. 209.025 to KM 240.000 including Construction of CM & CD works and Excavation of Chitvel Branch Canal including construction of CM & CD works for distributory system and field Channels to feed an ayacut of 40,000 Acres under Package -07/2006 of GNSS Phase-II in Kadapa District 2 Utilization of water in TMC Nil 3 Administrative Sanction : Rs. ECV value Rs. 155.46 Crores. 4 No of Packages 1 5 Agreement value of Package (Pkgs 6 to 14) : RsRs. 117.99 Crs 6 Expenditure (Pkgs 6 to 14) as on 31.03.2019 : RsRs. 23.99 Crs GNSS PROJECT (PHASE-II) 2
  • 3. 3 7 Progress of Work Total Completed % Balance Qty of Earth work (L.Cum) : 1 17.40 13.04 Work is pre closed Qty of Concrete (L.Cum) : 0.35 000 0 work is pre closed 8 Land Acquisition (Ph-II 6 to 14) (Acres) Required Requisitioned Acquired Balance 1230.80 1230.80 292.94 938.56 9 Forest (Ph-II 6 to 14) (Ha) Required Requisitioned Alienated Balance 0 0.000 0.00 0 10 IP Contemplated : 40000 acres 11 IP created as on 31.03.2019 : Nil-Acres (New), Nil- Acres (Stab)
  • 4. 4 12 Status of Land Acquisition 1. L.A is pending due to stiff resistance from the formers as the canal is running in costly horticulture lands. (13)Canal alignment is not passing through forest 13 Status of Forest 14 Structures (Nos) (6 to 14) (including Distributory System) : Total Completed Progress Balance (Revised Estimate is prepared and submitted for Rs.552.81 Crores to the Government for approval) 15 Main Canal length (Km) Branch Canal length (Km) : 30.975 9.00 0 21.975 67.00 0 0 67.00
  • 5. Total Completed Progress Balance 16 National Highways (Nos) State Highways (Nos) Railway Crossings (Nos) : : 0 0 0 0 9 - -- 9 3 0 0 3 Tentative 17 R&R (for 6 to 14) No. of villages affected Fully (Nos) : ----- No. of Housing units Shifted (Nos) : ------ No. of R & R Centers contemplated (Nos) Exp. incurred : : : ------ ----- 18 Irrigation Potential 40000 19 Districts benefited Kadapa - 40000 20 Percentage of work done (Physical) (6to14) : 20.33(work is pre closed) 21 No of Lifts & Its details (if any) Nil 22 Target date of completion : (subjected to approval of already submitted estimate) 5
  • 6. 23. Bottlenecks in detail : L.A is pending due to stiff resistance from the formers as the canal is running in costly horticulture lands. Accouts are to be settled for the previous agency for closure of contract. At present Peg marking from Ch.220.225KM to Ch.220.825KM, 223.025KM to 223.925KM and 223.925KM to 225.025KM is in Progress. 24 Any additional information (if any): The work is pre closed. Settlement of accounts is in progress. And Estimate for balance quantities with current SSR 2018-19 is prepared and submitted to the Government for approval for Rs.552.81 Crores.Total Land acquisition required is 1230.80 acres. Already acquired land is 292.24 acres and the balance LA is 938.56 acres. Revised L.P schedules to an extent of 908.503 acres submitted to the Spl. Collector, GNSS kadapa on 16.05.2018. Field survey for LA is in progress. Survey and peg marking completed for 176.45 acres. At present Peg marking from Ch.220.225KM to Ch.220.825KM, 223.025KM to 223.925KM and 223.925KM to 225.025KM is in Progress. 6