SlideShare a Scribd company logo
1 of 11
Project Management Process Groups and Knowledge Areas
Knowledge
Areas
Initiation
Process
Planning
Process
Execution
Process
Monitoring
Process
Closing
Process
4. Project
Integration
Management (7)
4.1 Develop
Project
Charter
4.2 Develop Project
Management Plan
4.3 Direct and
Manage Project
Work
4.4 Manage Project
Knowledge
4.5 Monitor and
Control Project
Work
4.6 Perform
Integrated Change
Control
4.7 Close
Project or
Phase
5. Project Scope
Management (6)
5.1 Plan Scope
Management
5.2 Collect
Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project
Schedule
Management (6)
6.1 Plan Schedule
Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity
Durations
6.5 Develop Schedule
6.6 Control
Schedule
7. Project Cost
Management (4)
7.1 Plan Cost
Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Cost
8. Project Quality
Management (3)
8.1 Plan Quality
Management
8.2 Manage Quality 8.3 Control Quality
9. Project
Resource
Management (6)
9.1 Plan Resource
Management
9.2 Estimate Activity
Resources
9.3 Acquire
Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control
Resources
10. Project
Communication
Management (3)
10.1 Plan
Communications
Management
10.2 Manage
Communications
10.3 Monitor
Communications
11. Project Risk
Management (7)
11.1 Plan Risk
Management
11.2 Identify Risks
11.3 Perform
Qualitative Risk
Analysis
11.4 Perform
Quantitative Risk
Analysis
11.5 Plan Risk
Responses
11.6 Implement Risk
responses
11.7 Monitor Risks
12. Project
Procurement
Management (3)
12.1 Plan Procurement
Management
12.2 Conduct
Procurements
12.3 Control
Procurements
13. Project
Stakeholder
Management (4)
13.1 Identify
Stakeholders
13.2 Plan Stakeholder
Engagement
13.3 Manage
Stakeholder
Engagement
13.4 Monitor
Stakeholder
Engagement
TOTAL (49) 2 24 10 12 1
PMBOK GUIDE SIXTH EDITION (ITTO)
Project Integration Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
INTEGRATION
Develop
Project Charter
A project charter is
developed that
authorizes the project
and links it with the
strategic objectives of
the organization.
1. Business Documents
2. Agreements
3. Enterprise Environmental
Factors
4. Organizational Process
Asset
1. Expert Judgment
2. Data Gathering
3. Interpersonal and Team
Skills
4. Meetings
1. Project Charter
2. Assumption Log
Develop
Project
Management
Plan
The content and goal
of this process are
defining, preparing
and coordinating all
plan components.
1. Project Charter
2. Outputs from Other
Processes
3. Enterprise Environmental
Factors
4. Organizational Process
Assets
1. Expert Judgment
2. Data Gathering
3. Interpersonal and Team
Skills
4. Meetings
1. Project Management
Plan
Direct and
Manage
Project
Execution
This process comprises
leading and
performing the work
that was defined in
the project
management plan as
well as implementing
approved changes,
1. Project Management Plan
2. Project Documents
3. Approved Changed
Requests
4. Enterprise Environmental
Factors
5 Organizational Process
Assets
1. Expert Judgment
2. Project Management
Information System
3 .Meetings
1. Deliverables
2. Work Performance Data
Issue Log
2. Change Requests
4. Project Management
Plan Updates
5. Project Document
Updates
6. Organizational Process
Assets Updates
Manage
Project
Knowledge
This process describes
the use of existing and
the creation of new
pieces of knowledge
in order to achieve
the project objectives
and support
organizational
learning
1. Project Management Plan
2. Project Documents
3. Deliverables
4. Enterprise Environmental
Factors
5. Organizational Process
Assets
1. Expert Judgment
2. Knowledge
Management
3. Information
Management
4. Interpersonal And Team
Skills
1. Lessons Learned Register
2. Project Management
Plan Updates
3. Organizational Process
Assets Updates
Monitor and
Control Project
Work
Ensure the overall
progress is tracked,
reviewed and
reported to meet the
performance
objectives defined in
the project
management plan.
1 Project Management Plan
2 Project Documents
3 Work Performance
Information
4 Agreements
5 Enterprise Environmental
Factors
6 Organizational Process
Assets
1 Expert Judgment
2 Data Analysis
3 Decision Making
Meetings
1 Work Performance
Reports
2 Change Requests
3 Project Management
Plan Updates
4 Project Document
Updates
Perform
Integrated
Change
Control
The content of this
process is reviewing all
change requests,
getting approval for
changes, and
managing changes to
deliverables,
documents and plans
1 Project Management Plan
2 Project Documents
3 Work Performance Reports
4 Change Requests
5 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Expert Judgment
2 Change Control Tools
3 Data Analysis
4 Decision Making
Meetings
1 Approved Change
Requests
2 Project Management
Plan Updates
3 Project Document
Updates
Close Project
or Phase
In the ‘close’ process,
all activities of a
project, a phase or a
contract are finalized.
This includes archiving
project or phase
information as well as
releasing team
resources
1 Project Charter
2 Project Management Plan
3 Project Documents
4 Accepted Deliverables
5 Business Documents
Agreements
6 Procurement
Documentation
7 Organizational Process
Assets
1 Expert Judgment
2 Data Analysis
3 Meetings
1 Project Documents
Updates
2 Final Product, Service, or
Result Transition
3 Final Report
4 Organizational Process
Assets Updates
Project Scope Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
SCOPE
Plan Scope
Management
The goal of this
process is to create a
scope management
plan that sets out the
framework of the
definition, validation
and controlling of the
project and product
scope
1Project Charter
2Project Management Plan
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Expert Judgment
2 Data Analysis
3 Meetings
1 Scope Management
Plan
2 Requirements
Management Plan
Collect
Requirements
Determines,
documents, and
manages stakeholder
needs and
requirements which
are performed in
order to meet the
project objectives. This
process helps create
the foundation of the
project and product
scope.
1 Project Charter
2 Project Management Plan
3 Project Documents
4 Business Documents
Agreements
5 Enterprise Environmental
Factors
6 Organizational Process
Assets
1 Expert Judgment
2 Data Gathering
3 Data Analysis
4 Decision Making
5 Data Representations
6 Interpersonal and Team
Skills
7 Context Diagrams
Prototypes
1 Requirements
Documentation
2 Requirements
Traceability Matrix
Define Scope This process is about
developing a detailed
description of the
project and product,
incl. the result
boundaries and
acceptance criteria.
1 Project Charter
2 Project Management Plan
3 Project Documents
4 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Expert Judgment
2 Data Analysis
3 Decision Making
4 Interpersonal and Team
Skills
5 Product Analysis
1 Project Scope
Statement
2 Project Document
Updates
Create Work
Breakdown
Structure
Creating the work
breakdown structure
means breaking down
project deliverables
and project work into
relatively small and
manageable
components.
1 Project Management Plan
2 Project Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Expert Judgment
2 Decomposition
1 Scope Baseline
2 Project Document
Updates
Validate
Scope
This process formalizes
the acceptance of
the completed
project deliverables. It
sets out the objectivity
and the procedure of
acceptance of the
final product based
on the acceptance of
each deliverable
1 Project Management Plan
2 Project Documents
3 Verified Deliverables
4 Work Performance Data
1 Inspection
2 Decision Making
1 Accepted Deliverables
2 Work Performance
Information
3 Change Requests
4 Project Document
Updates
Control Scope This process sets out
the monitoring of the
project status and
product scope as well
as the management
of changes to the
scope baseline. It also
ensures that the
scope baseline is
accurately
maintained and
updated ongoing
1 Project Management Plan
2 Project Documents
3 Work Performance Data
4 Organizational Process
Assets
1 Data Analysis 1 Work Performance
Information
2 Change Requests
3 Project Management
Plan Updates
4 Project Documents
Updates
Project Time Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
TIME
Plan Schedule
Management
This process contains
the establishment of
policies, procedures,
and documentation
of the project
schedule
management.
1 Project Charter
2 Project Management Plan
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Expert Judgment
2 Data Analysis
3 Meetings
1 Schedule Management
Plan
Define
Activities
In this process, the
actions needed to
produce the project
deliverables are
identified and
defined.
1 Project Management Plan
2 Enterprise Environmental
Factors
3 Organizational Process
Assets
1 Expert Judgment
2 Decomposition
3 Rolling Wave Planning
4 Meetings
1 Activity List
2 Activity Attributes
3 Milestone List
4 Change Requests
5 Project Management
Plan Updates
Sequence
Activities
This process comprises
the identification and
documentation of the
relationships among
the project activities.
1Project Management Plan
2 Project Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Precedence
Diagramming Method
(PDM)
2 Dependency
Determination And
Integration
3 Leads & Lags
4 Project Management
Information System
1 Project Schedule
2 Network Diagrams
3 Project Document
Updates
Estimate
Activity
Durations
In this process, the
durations to perform
each activity are
estimated.
1 Project Management Plan
2 Project Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Expert Judgment
2 Analogous Estimating
3 Parametric Estimating
4 Three-Point Estimating
5 Bottom-Up Estimating
6 Data Analysis
7 Decision Making
8 Meetings
1. Duration Estimates
2. Basis Of Estimates
3. Project Documents
Updates
Develop
Schedule
When developing the
project schedule,
activity sequences,
durations, resource
requirements, and
schedule constraints
are taken into
consideration.
1. Project Management Plan
2. Project Documents
3. Agreements
4. Enterprise Environmental
Factors
5. Organizational Process
Assets
1. Schedule Network
Analysis
2. Critical Path Method
3. Resource Optimization
4. Data Analysis
5. Leads and Lags
6. Schedule Compression
7. Project Management
8. information System
9. Agile Release Planning
1 Schedule Baseline
2 Project Schedule
3 Schedule Data
4. Project Calendars
5. Change Requests
6. Project Management
7. Plan Updates
8. Project Documents
Updates
Control
Schedule
This process defines
the monitoring of the
project status in order
to update the project
schedule as well as
the management of
changes to the
schedule baseline
1 Project Management Plan
2 Project Documents
3 Work Performance Data
4 Organizational Process
Assets
1 Data Analysis
2 Critical Path Method
3 Project Management
4 Information System
5 Resource Optimization
6 Leads and Lags
7 Schedule Compression
1 Work Performance
Information
2 Schedule Forecasts
3 Change Requests
4 Project Management
5 Plan Updates
6 Project Documents
Updates
Project Cost Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
COST
Plan Cost
Management
This process is about
defining the
approaches and
procedures to
estimate, budget,
manage, monitor and
control project costs.
1. Project charter
2. Project management
plan
3. Enterprise environmental
factors
4. Organizational process
assets
1. Expert judgment
2. Data Analysis
3. Meetings
1. Cost Management Plan
Estimate Costs In this process, an
approximation of the
cost of required
resources is estimated.
1. Project management
plan
2. Project documents
3. Enterprise environmental
factors
4. Organizational process
assets
1. Expert Judgement
2. Analogous estimating
3. Parametric estimating
4. Three Point estimating
5. Bottom-up estimating
6. Data Analysis
7. Decision marking
8. PMIS
1. Cost estimates
2. Basis of estimates
3. Project document
updates
Determine
Budget
Aggregation of the
estimated cost of all
activities and work
packages which is the
foundation of the
authorized cost
baseline.
1. Project management
plan
2. Project documents
3. Business documents
4. Agreements
5. Enterprise enviromental
factors
6. Organizational process
assets
1. Expert judgment
2. Cost aggregation
3. Reserve analysis
4. Historical information
review
5. Funding limit
reconciliation
6. Financing
1. Cost baseline
2. Project funding
requirements
3. Project document
updates
Control Costs This process is about
monitoring, managing
and updating actual
and planned project
costs as well as the
cost baseline
1. Project management
plan
2. Project documents
3. Project funding
requirements
4. Work performance data
5. Organizational process
assets
1. Expert judgment
2. Data Analysis
3. To complete
performance index (TCPI)
4. Project management
information system (PMIS)
1. Work Performance
Information
2. Cost forecasts
3. Change requests
4. Project management
plan updates
5. Project documents
updates
Project Quality Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
QUALITY
Plan Quality
Management
In this process, quality
requirements and
standards are
identified. One of the
outputs is the
documentation of
how they are
maintained ongoing.
1 Project Charter
2 Project Management Plan
3 Project Documents
4 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Expert Judgement
2 Data Gathering
3 Data Analysis
4 Decision Making
5 Data Representation
6 Test and Inspection
Planning
7 Meetings
1 Quality Management
Plan
2 Quality Metrics
3 Project Management
Plan Updates
4 Project Documents
Updates
Manage
Quality
This process is the
transformation of the
quality management
plan into individual
activities that
incorporate the
quality
requirements/standar
ds into the project.
Thus, it facilitates
achieving the quality
goals and identifying
ineffective processes
and causes of poor
quality
1 Project Management Plan
2 Project Documents
3 Organizational Process
Assets
1 Data Gathering
2 Data Analysis
3 Decision Making
4 Data Representation
Audits
5 Design for X
6 Problem Solving
7 Quality Improvement
Methods
1 Quality Reports
2 Test and Evaluation
Documents
3 Change Requests
4 Project Management
Plan Updates
5 Project Documents
Updates
Control Quality The content of this
process is the
monitoring and
controlling of the
results of quality
management
activities. This also
includes verifying that
project deliverables
and the project work
are in line with the
requirements for final
acceptance
1 Project Management Plan
2 Project Documents
3 Approved Change
Requests
4 Deliverables
5 Work Performance Data
6 Enterprise Environmental
Factors
7 Organizational Process
Assets
1Data Gathering
2 Data Analysis
3 Inspection
4 Testing/Product
Evaluation
5 Data Representation
Meetings
1 Quality Control
Measurements
2 Verified Deliverables
3 Work Performance
Information
4 Change Requests
5 Project Management
Plan Updates
6 Project Document
Updates
Project Resource Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
HUMAN RESOURCE
Plan Resource
Management
This process is about
defining how the
team and physical
resources will be
estimated, acquired,
managed, and used
during the project.
1 Project Charter
2 Project Management
Plan
3 Project Documents
4 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Expert Judgement
2 Data Representation
3 Organizational Theory
Meetings
1 Resource Management
Plan
2 Team Charter
3 Project Documents
Updates
Estimate Activity
Resources
This process contains
the estimation of the
team headcount
and physical
resources that are
needed to perform
project work.
1 Project Management
Plan
2 Project Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Expert Judgement
2 Bottom-Up Estimating
3 Analogous Estimating
4 Parametric Estimating
5 Data Analysis
6 Project Management
Information System
7 Meetings
1 Resource Requirements
2 Basis of Estimates
3 Resource Breakdown
Structure
4 Project Documents
Updates
Acquire
Resources
In this process, team
members are hired
and on-boarded and
physical resources
are acquired. This
includes the
selection of sources
as well as the
assignment of
resources to specific
activities
1 Project Management
Plan
2 Project Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Decision Making
2 Interpersonal and Team
Skills
3 Pre-Assignment
4 Virtual Teams
1 Physical Resource
Assignments
2 Project Team
Assignments
3 Resource Calendars
4 Change Requests
5 Project Management
Plan Updates
6 Project Documents
Updates
7 Enterprise Environmental
Factors Updates
8 Organizational Process
Assets Updates
Develop Team This process aims to
improve skills and
competencies,
interactions and the
environment of
project teams in
order to enhance
the overall project
performance
1 Project Management
Plan
2 Project Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Colocation
2 Virtual Teams
3 Communication
Technology
4 Interpersonal and Team
Skills
5 Recognition and
Rewards
6 Training
7 Individual and Team
Assessments
8 Meetings
1 Team Performance
Assessments
2 Change Requests
3 Project Management
Plan Updates
4 Project Documents
Updates
5 Enterprise Environmental
Factors Updates
6 Organizational Process
Assets Updates
Manage Team This process includes
performance
tracking, feedback,
and management of
changes and
adjustments to the
project team.
1 Project Management
Plan
2 Project Documents
3 Work Performance
Reports
3 Team Performance
Assessments
4 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Interpersonal and Team
Skills
2 Project Management
Information System
1 Change Requests
2 Project Management
Plan Updates
3 Project Documents
Updates
4 Enterprise Environmental
Factors Updates
Control
Resources
This process helps
ensure that the
physical resources
are available and
utilized as planned.
This may also include
corrective actions if
required.
1 Project Management
Plan
2 Project Documents
3 Work Performance Data
Agreements
4 Organizational Process
Assets
1 Data Analysis
2 Problem Solving
3 Interpersonal and Team
Skills
4 Project Management
Information System
1 Work Performance
Information
2 Change Requests
3 Project Management
Plan Updates
4 Project Documents
Updates
Project Communications Management
Major Processes Primary Inputs Tools & Techniques Primary Outputs
COMMUNICATIONS
Plan
Communication
s Management
In this process, the
approach and plan
for project
communications
are developed.
Thereby,
stakeholders’ and
the project’s
information needs
as well as available
organizational
assets are taken
into account
1 Project Charter
2 Project Management Plan
3 Project Documents
4 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Expert Judgement
2 Communication
Requirements Analysis
3 Communication
Technology
4 Communication Models
5 Communication Methods
6 Interpersonal And Team
Skills
7 Data Representation
Meetings
1. Communications
Management Plan
2. Project Management
Plan Updates
3. Project Documents
Update
Manage
Communication
s
Manage
communications is
the ongoing
process of ensuring
timely and
appropriate
communication in
order to facilitate
an efficient and
effective
information flow
between the
project team and
stakeholders.
1 Project Management Plan
2 Project Documents
3 Work Performance Reports
4 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Communication
Technology
2 Communication Methods
3 Communication Skills
4 Project Management
Information System
5 Project Reporting
Interpersonal and Team
Skills
6 Meetings
1 Project
Communications
2 Project Management
Plan Updates
3 Project Document
Updates
4 Organizational Process
Assets Updates
Monitor
Communication
s
This process makes
sure that the
information needs
of the project and
the stakeholders are
met properly and
timely
1 Project Management Plan
2 Project Documents
3 Work Performance Data
4 Enterprise Environment
Factors
5 Organizational Process
Assets
1 Expert Judgement
2 Project Management
Information System
3 Data Representation
Interpersonal and Team
Skills
4 Meetings
1 Work Performance
Information
2 Change Requests
3 Project Management
Plan Updates
4Project Documents
Updates
Project Risk Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
RISK
Plan Risk
Responses
This process comprises the
planning of risk
management activities for
the project which includes
tailoring of risk
management
considerations to the
individual situation
1 Project Management
Plan
2 Projects Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Expert Judgment
2 Data Gathering
3 Interpersonal and
Team Skills
4 Strategies for Threats
5 Contingent Response
Strategies
6 Strategies for Overall
Project Risk
7 Data Analysis
8 Decision Making
1 Change Requests
2 Project Management
Plan Updates
3 Project Documents
Updates
Identify Risks This process focuses on
identifying and
documenting individual
risks as well as sources of
overall project risks.
1. Project management
plan
2. Project documents
3. Agreements
4. Procurement
documentation
5. Enterprise enviromental
factors
6. Organizational process
assets
1. Expert judgment
2. Data Gathering
3. Data Analysis
4. Interpersonal and
team skills
5. Prompt Lists
6. Meetings
1. Risk register
2. Risk report
3. Project documents
updates
Perform
Qualitative
Risk Analysis
In the process of
qualitative risk analysis, the
probability and the
potential impact of
individual project risks are
assessed, which is the basis
for their prioritization
1. Project management
plan
2. Project documents
3. Enterprise enviromental
factors
4. Organizational process
assets
1. Expert judgment
2. Data Gathering
3. Data Analysis
4. Interpersonal and
team skills
5. Risk categorization
6. Data representation
7. Meetings
1. Project Documents
Update
Perform
Quantitative
Risk Analysis
This process consists of
statistical analyses (e.g.
Monte Carlo simulation) of
identified individual project
risks and other sources of
ambiguity or uncertainty.
This is typically not applied
to small or less critical
projects
1. Project management
plan
2. Project documents
3. Enterprise enviromental
factors
4. Organizational process
assets
1. Expert judgment
2. Data Gathering
3. Interpersonal and
team skills
4. Representations of
uncertainty
5. Data Analysis
1. Project Document
Update
Plan Risk
Responses
In this process, the ways to
address overall and
individual project risks are
identified and assessed,
incl. definition of activities
as potential risk responses.
1. Project mangement
plan
2. Project documents
3. Enterprise enviromental
factors
4. Organizational process
assets
1. Expert judgment
2. Data Gathering
3. Interpersonal and
team skills
4. Strategies for threats
5. Strategies for
Opportunities
6. Contingent response
strategies
7. Strategies for overall
project risks
8. Data Analysis
9. Decision making
1. Change requests
2. Project management
plan updates
3. Project document
updates
Implement
Risk Responses
This process is conducted
when risks require a
response, i.e. the previously
selected risk responses
(activities) are
implemented
1 Project Management
Plan
2 Project Documents
3 Organizational Process
Assets
1 Expert Judgement
2 Interpersonal and
Team Skills
3 Project Management
Information System
1 Change Requests
2 Project Documents
Updates
Monitor Risks In this process, risk
responses and identified
risks are monitored and
tracked. In addition, new
risks are identified and
assessed.
1 Project Management
Plan
2 Project Documents
3 Work Performance Data
4 Work Performance
Reports
1 Data Analysis
2 Audits
3 Meetings
1 Work Performance
Information
2 Change Requests
3 Project Management
Plan Updates
4 Project Documents
Updates
5 Organizational Process
Assets Updates
Project Procurement Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
PROCUREMENT
Plan
Procurement
Management
Planning procurement
management
includes documenting
the way project
procurement
decisions are made,
specifying the
approach and
identifying potential
sellers.
1 Project Management Plan
2 Projects Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Expert Judgment
2 Data Gathering
3 Interpersonal and Team
Skills
4 Strategies for Threats
5 Contingent Response
Strategies
6 Strategies for Overall
Project Risk
7 Data Analysis
8 Decision Making
1 Change Requests
2 Project Management
Plan Updates
3 Project Documents
Updates
Conduct
Procurements
This process comprises
selecting a seller and
implementing the
agreements and
contracts for delivery.
1 Project Management Plan
2 Project Documents
3 Organizational Process
Assets
1 Expert Judgement
2 Interpersonal and Team
Skills
3 Project Management
Information System
1 Change Requests
2 Project Documents
Updates
Control
Procurements
In this process,
procurement
relationships are
managed and
contract performance
is monitored. This may
also extend to
changes and
corrections as well as
closing out contracts.
1 Project Management Plan
2 Project Documents
Agreements
3 Procurement
Documentation
4 Approved Change
Requests
5 Work Performance Data
6 Enterprise Environmental
Factors
7 Organizational Process
Assets
1 Expert Judgment
2 Claims Administration
3 Data Analysis
4 Inspection
5 Audits
1 Closed Procurements
2 Work Performance
Information
3 Procurement
Documentation Updates
4 Change Requests
5 Project Management
Plan Updates
6 Project Documents
Updates
7 Organizational Process
Assets Updates
Project Stakeholder Management
Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs
STAKEHOLDER
Identify
Stakeholders
This process implies
identifying
stakeholders and their
respective interests,
involvement, power,
and potential impact
on the project
1 Project Charter
2 Business Documents
3 Project Management Plan
4 Project Documents
Agreements
5 Enterprise Environmental
Factors
6 Organizational Process
Assets
1 Expert Judgment
2 Data Gathering
3 Data Analysis
3 Data Representation
Meetings
1 Stakeholder Register
2 Change Requests
3 Project Management
Plan Updates
4 Project Documents
Updates
Plan
Stakeholder
Engagement
This planning process
is about developing
how to involve
stakeholders and how
to interact effectively
with them during the
project.
1 Project Charter
2 Project Management Plan
3 Project Documents
Agreements
4 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Expert Judgment
2 Data Gathering
3 Data Analysis
4 Decision Making
5 Data Representation
6 Meetings
1 Stakeholder
Engagement Plan
Manage
Stakeholder
Engagement
The management of
stakeholder
engagement includes
communicating and
working with
stakeholders to meet
their needs and
expectations. The
goal of this process is
to ensure their support
and reduce resistance
from stakeholders.
1 Project Management Plan
2 Project Documents
3 Enterprise Environmental
Factors
4 Organizational Process
Assets
1 Expert Judgment
2 Communication Skills
3 Interpersonal and Team
Skills
4 Ground Rules
Meetings
1 Change Requests
2 Project Management
Plan Updates
3 Project Documents
Updates
Monitor
Stakeholder
Engagement
This process describes
the monitoring of
relationships and the
adjustment of
strategies in order to
engage stakeholders
in an optimal way.
1 Project Management Plan
2 Project Documents
3 Work Performance Data
4 Enterprise Environmental
Factors
5 Organizational Process
Assets
1 Data Analysis
2 Decision Making
3 Data Representation
4 Communication Skills
5 Interpersonal and Team
Skills
6 Meetings
1 Work Performance
Information
2 Change Requests
3 Project Management
Plan Updates
4 Project Documents
Updates
Adapted from PMBOK™ guide 6th
Edition
Copyright and all rights reserved. Permission to reproduce granted for individual use only.
Issah Abdul-Wahab, PMP, PgMP, PfMP (WhatsApp - +233202225560)
Last update: Feb 19, 2021

More Related Content

What's hot

Project communication management
Project communication managementProject communication management
Project communication managementSaad Al Jabri
 
10.2 Manage Communication
10.2 Manage Communication10.2 Manage Communication
10.2 Manage CommunicationDavidMcLachlan1
 
PMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOPMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOAnthony Natoli
 
Project Management 101 Primer
Project Management 101   PrimerProject Management 101   Primer
Project Management 101 PrimerGary Drumm
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingJustAcademy
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishRicardo Viana Vargas
 
IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)jimmcdonaldpmp
 
Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008ITVAMP, LLC
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementMohamed Loey
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication ManagementBhuWan Khadka
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guiderobsonnasc
 
projec kickoff presentation template
 projec kickoff presentation template projec kickoff presentation template
projec kickoff presentation templatedadiiskandar4
 
Project communication management
Project communication managementProject communication management
Project communication managementTakudzwa Chatora
 

What's hot (20)

Project communication management
Project communication managementProject communication management
Project communication management
 
Project Management
Project ManagementProject Management
Project Management
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
10.2 Manage Communication
10.2 Manage Communication10.2 Manage Communication
10.2 Manage Communication
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
PMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOPMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMO
 
Project Management 101 Primer
Project Management 101   PrimerProject Management 101   Primer
Project Management 101 Primer
 
PM process groups and processes
PM process groups and processesPM process groups and processes
PM process groups and processes
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
 
Real example of PMO deployment
Real example of PMO deploymentReal example of PMO deployment
Real example of PMO deployment
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in English
 
IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)
 
Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication Management
 
Pmp integration management
Pmp integration managementPmp integration management
Pmp integration management
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guide
 
projec kickoff presentation template
 projec kickoff presentation template projec kickoff presentation template
projec kickoff presentation template
 
Project communication management
Project communication managementProject communication management
Project communication management
 

Similar to Itto pmbok guide 6th edition

PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management FrameworkAarti Dahiya PMP
 
PMI knowledge areas and processes
PMI knowledge areas and processesPMI knowledge areas and processes
PMI knowledge areas and processesWiktor Kabatc
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementMohamed Loey
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...Arlene Smith
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope ManagementDavidMcLachlan1
 
PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionRicardo Viana Vargas
 
Proses Manajemen Proyek - PMBOK Guide Fifth Edition Chapter 3
Proses Manajemen Proyek - PMBOK Guide Fifth Edition Chapter 3 Proses Manajemen Proyek - PMBOK Guide Fifth Edition Chapter 3
Proses Manajemen Proyek - PMBOK Guide Fifth Edition Chapter 3 Primaaasue
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management OverviewDavidMcLachlan1
 
Mapa procesos pmbok 5
Mapa procesos pmbok 5Mapa procesos pmbok 5
Mapa procesos pmbok 5Pedro Arcas
 
Pm bok 5 ittos ok - pmbok5-ittos
Pm bok 5 ittos   ok - pmbok5-ittosPm bok 5 ittos   ok - pmbok5-ittos
Pm bok 5 ittos ok - pmbok5-ittosMauricio Campuzano
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
projectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfprojectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfAbdiqadirOsman
 
Project Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxProject Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxKareemBullard1
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management areaZaur Ahmadov, PMP
 

Similar to Itto pmbok guide 6th edition (20)

PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
 
PMI knowledge areas and processes
PMI knowledge areas and processesPMI knowledge areas and processes
PMI knowledge areas and processes
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
PMBOK processes schema by Ricardo Vargas
PMBOK processes schema by Ricardo VargasPMBOK processes schema by Ricardo Vargas
PMBOK processes schema by Ricardo Vargas
 
PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th Edition
 
Proses Manajemen Proyek - PMBOK Guide Fifth Edition Chapter 3
Proses Manajemen Proyek - PMBOK Guide Fifth Edition Chapter 3 Proses Manajemen Proyek - PMBOK Guide Fifth Edition Chapter 3
Proses Manajemen Proyek - PMBOK Guide Fifth Edition Chapter 3
 
Itto slide share
Itto slide shareItto slide share
Itto slide share
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 
Project managment 3
Project managment 3Project managment 3
Project managment 3
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
Mapa procesos pmbok 5
Mapa procesos pmbok 5Mapa procesos pmbok 5
Mapa procesos pmbok 5
 
Pm bok 5 ittos ok - pmbok5-ittos
Pm bok 5 ittos   ok - pmbok5-ittosPm bok 5 ittos   ok - pmbok5-ittos
Pm bok 5 ittos ok - pmbok5-ittos
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
8.2 Manage Quality
8.2 Manage Quality8.2 Manage Quality
8.2 Manage Quality
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
projectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfprojectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdf
 
Project Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxProject Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptx
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management area
 

Recently uploaded

Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxLigayaBacuel1
 

Recently uploaded (20)

Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptx
 

Itto pmbok guide 6th edition

  • 1. Project Management Process Groups and Knowledge Areas Knowledge Areas Initiation Process Planning Process Execution Process Monitoring Process Closing Process 4. Project Integration Management (7) 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management (6) 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management (6) 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management (4) 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Cost 8. Project Quality Management (3) 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management (6) 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communication Management (3) 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management (7) 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk responses 11.7 Monitor Risks 12. Project Procurement Management (3) 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management (4) 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement TOTAL (49) 2 24 10 12 1 PMBOK GUIDE SIXTH EDITION (ITTO)
  • 2. Project Integration Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs INTEGRATION Develop Project Charter A project charter is developed that authorizes the project and links it with the strategic objectives of the organization. 1. Business Documents 2. Agreements 3. Enterprise Environmental Factors 4. Organizational Process Asset 1. Expert Judgment 2. Data Gathering 3. Interpersonal and Team Skills 4. Meetings 1. Project Charter 2. Assumption Log Develop Project Management Plan The content and goal of this process are defining, preparing and coordinating all plan components. 1. Project Charter 2. Outputs from Other Processes 3. Enterprise Environmental Factors 4. Organizational Process Assets 1. Expert Judgment 2. Data Gathering 3. Interpersonal and Team Skills 4. Meetings 1. Project Management Plan Direct and Manage Project Execution This process comprises leading and performing the work that was defined in the project management plan as well as implementing approved changes, 1. Project Management Plan 2. Project Documents 3. Approved Changed Requests 4. Enterprise Environmental Factors 5 Organizational Process Assets 1. Expert Judgment 2. Project Management Information System 3 .Meetings 1. Deliverables 2. Work Performance Data Issue Log 2. Change Requests 4. Project Management Plan Updates 5. Project Document Updates 6. Organizational Process Assets Updates Manage Project Knowledge This process describes the use of existing and the creation of new pieces of knowledge in order to achieve the project objectives and support organizational learning 1. Project Management Plan 2. Project Documents 3. Deliverables 4. Enterprise Environmental Factors 5. Organizational Process Assets 1. Expert Judgment 2. Knowledge Management 3. Information Management 4. Interpersonal And Team Skills 1. Lessons Learned Register 2. Project Management Plan Updates 3. Organizational Process Assets Updates Monitor and Control Project Work Ensure the overall progress is tracked, reviewed and reported to meet the performance objectives defined in the project management plan. 1 Project Management Plan 2 Project Documents 3 Work Performance Information 4 Agreements 5 Enterprise Environmental Factors 6 Organizational Process Assets 1 Expert Judgment 2 Data Analysis 3 Decision Making Meetings 1 Work Performance Reports 2 Change Requests 3 Project Management Plan Updates 4 Project Document Updates Perform Integrated Change Control The content of this process is reviewing all change requests, getting approval for changes, and managing changes to deliverables, documents and plans 1 Project Management Plan 2 Project Documents 3 Work Performance Reports 4 Change Requests 5 Enterprise Environmental Factors 5 Organizational Process Assets 1 Expert Judgment 2 Change Control Tools 3 Data Analysis 4 Decision Making Meetings 1 Approved Change Requests 2 Project Management Plan Updates 3 Project Document Updates Close Project or Phase In the ‘close’ process, all activities of a project, a phase or a contract are finalized. This includes archiving project or phase information as well as releasing team resources 1 Project Charter 2 Project Management Plan 3 Project Documents 4 Accepted Deliverables 5 Business Documents Agreements 6 Procurement Documentation 7 Organizational Process Assets 1 Expert Judgment 2 Data Analysis 3 Meetings 1 Project Documents Updates 2 Final Product, Service, or Result Transition 3 Final Report 4 Organizational Process Assets Updates
  • 3. Project Scope Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs SCOPE Plan Scope Management The goal of this process is to create a scope management plan that sets out the framework of the definition, validation and controlling of the project and product scope 1Project Charter 2Project Management Plan 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Expert Judgment 2 Data Analysis 3 Meetings 1 Scope Management Plan 2 Requirements Management Plan Collect Requirements Determines, documents, and manages stakeholder needs and requirements which are performed in order to meet the project objectives. This process helps create the foundation of the project and product scope. 1 Project Charter 2 Project Management Plan 3 Project Documents 4 Business Documents Agreements 5 Enterprise Environmental Factors 6 Organizational Process Assets 1 Expert Judgment 2 Data Gathering 3 Data Analysis 4 Decision Making 5 Data Representations 6 Interpersonal and Team Skills 7 Context Diagrams Prototypes 1 Requirements Documentation 2 Requirements Traceability Matrix Define Scope This process is about developing a detailed description of the project and product, incl. the result boundaries and acceptance criteria. 1 Project Charter 2 Project Management Plan 3 Project Documents 4 Enterprise Environmental Factors 5 Organizational Process Assets 1 Expert Judgment 2 Data Analysis 3 Decision Making 4 Interpersonal and Team Skills 5 Product Analysis 1 Project Scope Statement 2 Project Document Updates Create Work Breakdown Structure Creating the work breakdown structure means breaking down project deliverables and project work into relatively small and manageable components. 1 Project Management Plan 2 Project Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Expert Judgment 2 Decomposition 1 Scope Baseline 2 Project Document Updates Validate Scope This process formalizes the acceptance of the completed project deliverables. It sets out the objectivity and the procedure of acceptance of the final product based on the acceptance of each deliverable 1 Project Management Plan 2 Project Documents 3 Verified Deliverables 4 Work Performance Data 1 Inspection 2 Decision Making 1 Accepted Deliverables 2 Work Performance Information 3 Change Requests 4 Project Document Updates Control Scope This process sets out the monitoring of the project status and product scope as well as the management of changes to the scope baseline. It also ensures that the scope baseline is accurately maintained and updated ongoing 1 Project Management Plan 2 Project Documents 3 Work Performance Data 4 Organizational Process Assets 1 Data Analysis 1 Work Performance Information 2 Change Requests 3 Project Management Plan Updates 4 Project Documents Updates
  • 4. Project Time Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs TIME Plan Schedule Management This process contains the establishment of policies, procedures, and documentation of the project schedule management. 1 Project Charter 2 Project Management Plan 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Expert Judgment 2 Data Analysis 3 Meetings 1 Schedule Management Plan Define Activities In this process, the actions needed to produce the project deliverables are identified and defined. 1 Project Management Plan 2 Enterprise Environmental Factors 3 Organizational Process Assets 1 Expert Judgment 2 Decomposition 3 Rolling Wave Planning 4 Meetings 1 Activity List 2 Activity Attributes 3 Milestone List 4 Change Requests 5 Project Management Plan Updates Sequence Activities This process comprises the identification and documentation of the relationships among the project activities. 1Project Management Plan 2 Project Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Precedence Diagramming Method (PDM) 2 Dependency Determination And Integration 3 Leads & Lags 4 Project Management Information System 1 Project Schedule 2 Network Diagrams 3 Project Document Updates Estimate Activity Durations In this process, the durations to perform each activity are estimated. 1 Project Management Plan 2 Project Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Expert Judgment 2 Analogous Estimating 3 Parametric Estimating 4 Three-Point Estimating 5 Bottom-Up Estimating 6 Data Analysis 7 Decision Making 8 Meetings 1. Duration Estimates 2. Basis Of Estimates 3. Project Documents Updates Develop Schedule When developing the project schedule, activity sequences, durations, resource requirements, and schedule constraints are taken into consideration. 1. Project Management Plan 2. Project Documents 3. Agreements 4. Enterprise Environmental Factors 5. Organizational Process Assets 1. Schedule Network Analysis 2. Critical Path Method 3. Resource Optimization 4. Data Analysis 5. Leads and Lags 6. Schedule Compression 7. Project Management 8. information System 9. Agile Release Planning 1 Schedule Baseline 2 Project Schedule 3 Schedule Data 4. Project Calendars 5. Change Requests 6. Project Management 7. Plan Updates 8. Project Documents Updates Control Schedule This process defines the monitoring of the project status in order to update the project schedule as well as the management of changes to the schedule baseline 1 Project Management Plan 2 Project Documents 3 Work Performance Data 4 Organizational Process Assets 1 Data Analysis 2 Critical Path Method 3 Project Management 4 Information System 5 Resource Optimization 6 Leads and Lags 7 Schedule Compression 1 Work Performance Information 2 Schedule Forecasts 3 Change Requests 4 Project Management 5 Plan Updates 6 Project Documents Updates
  • 5. Project Cost Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs COST Plan Cost Management This process is about defining the approaches and procedures to estimate, budget, manage, monitor and control project costs. 1. Project charter 2. Project management plan 3. Enterprise environmental factors 4. Organizational process assets 1. Expert judgment 2. Data Analysis 3. Meetings 1. Cost Management Plan Estimate Costs In this process, an approximation of the cost of required resources is estimated. 1. Project management plan 2. Project documents 3. Enterprise environmental factors 4. Organizational process assets 1. Expert Judgement 2. Analogous estimating 3. Parametric estimating 4. Three Point estimating 5. Bottom-up estimating 6. Data Analysis 7. Decision marking 8. PMIS 1. Cost estimates 2. Basis of estimates 3. Project document updates Determine Budget Aggregation of the estimated cost of all activities and work packages which is the foundation of the authorized cost baseline. 1. Project management plan 2. Project documents 3. Business documents 4. Agreements 5. Enterprise enviromental factors 6. Organizational process assets 1. Expert judgment 2. Cost aggregation 3. Reserve analysis 4. Historical information review 5. Funding limit reconciliation 6. Financing 1. Cost baseline 2. Project funding requirements 3. Project document updates Control Costs This process is about monitoring, managing and updating actual and planned project costs as well as the cost baseline 1. Project management plan 2. Project documents 3. Project funding requirements 4. Work performance data 5. Organizational process assets 1. Expert judgment 2. Data Analysis 3. To complete performance index (TCPI) 4. Project management information system (PMIS) 1. Work Performance Information 2. Cost forecasts 3. Change requests 4. Project management plan updates 5. Project documents updates
  • 6. Project Quality Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs QUALITY Plan Quality Management In this process, quality requirements and standards are identified. One of the outputs is the documentation of how they are maintained ongoing. 1 Project Charter 2 Project Management Plan 3 Project Documents 4 Enterprise Environmental Factors 5 Organizational Process Assets 1 Expert Judgement 2 Data Gathering 3 Data Analysis 4 Decision Making 5 Data Representation 6 Test and Inspection Planning 7 Meetings 1 Quality Management Plan 2 Quality Metrics 3 Project Management Plan Updates 4 Project Documents Updates Manage Quality This process is the transformation of the quality management plan into individual activities that incorporate the quality requirements/standar ds into the project. Thus, it facilitates achieving the quality goals and identifying ineffective processes and causes of poor quality 1 Project Management Plan 2 Project Documents 3 Organizational Process Assets 1 Data Gathering 2 Data Analysis 3 Decision Making 4 Data Representation Audits 5 Design for X 6 Problem Solving 7 Quality Improvement Methods 1 Quality Reports 2 Test and Evaluation Documents 3 Change Requests 4 Project Management Plan Updates 5 Project Documents Updates Control Quality The content of this process is the monitoring and controlling of the results of quality management activities. This also includes verifying that project deliverables and the project work are in line with the requirements for final acceptance 1 Project Management Plan 2 Project Documents 3 Approved Change Requests 4 Deliverables 5 Work Performance Data 6 Enterprise Environmental Factors 7 Organizational Process Assets 1Data Gathering 2 Data Analysis 3 Inspection 4 Testing/Product Evaluation 5 Data Representation Meetings 1 Quality Control Measurements 2 Verified Deliverables 3 Work Performance Information 4 Change Requests 5 Project Management Plan Updates 6 Project Document Updates
  • 7. Project Resource Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs HUMAN RESOURCE Plan Resource Management This process is about defining how the team and physical resources will be estimated, acquired, managed, and used during the project. 1 Project Charter 2 Project Management Plan 3 Project Documents 4 Enterprise Environmental Factors 5 Organizational Process Assets 1 Expert Judgement 2 Data Representation 3 Organizational Theory Meetings 1 Resource Management Plan 2 Team Charter 3 Project Documents Updates Estimate Activity Resources This process contains the estimation of the team headcount and physical resources that are needed to perform project work. 1 Project Management Plan 2 Project Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Expert Judgement 2 Bottom-Up Estimating 3 Analogous Estimating 4 Parametric Estimating 5 Data Analysis 6 Project Management Information System 7 Meetings 1 Resource Requirements 2 Basis of Estimates 3 Resource Breakdown Structure 4 Project Documents Updates Acquire Resources In this process, team members are hired and on-boarded and physical resources are acquired. This includes the selection of sources as well as the assignment of resources to specific activities 1 Project Management Plan 2 Project Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Decision Making 2 Interpersonal and Team Skills 3 Pre-Assignment 4 Virtual Teams 1 Physical Resource Assignments 2 Project Team Assignments 3 Resource Calendars 4 Change Requests 5 Project Management Plan Updates 6 Project Documents Updates 7 Enterprise Environmental Factors Updates 8 Organizational Process Assets Updates Develop Team This process aims to improve skills and competencies, interactions and the environment of project teams in order to enhance the overall project performance 1 Project Management Plan 2 Project Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Colocation 2 Virtual Teams 3 Communication Technology 4 Interpersonal and Team Skills 5 Recognition and Rewards 6 Training 7 Individual and Team Assessments 8 Meetings 1 Team Performance Assessments 2 Change Requests 3 Project Management Plan Updates 4 Project Documents Updates 5 Enterprise Environmental Factors Updates 6 Organizational Process Assets Updates Manage Team This process includes performance tracking, feedback, and management of changes and adjustments to the project team. 1 Project Management Plan 2 Project Documents 3 Work Performance Reports 3 Team Performance Assessments 4 Enterprise Environmental Factors 5 Organizational Process Assets 1 Interpersonal and Team Skills 2 Project Management Information System 1 Change Requests 2 Project Management Plan Updates 3 Project Documents Updates 4 Enterprise Environmental Factors Updates Control Resources This process helps ensure that the physical resources are available and utilized as planned. This may also include corrective actions if required. 1 Project Management Plan 2 Project Documents 3 Work Performance Data Agreements 4 Organizational Process Assets 1 Data Analysis 2 Problem Solving 3 Interpersonal and Team Skills 4 Project Management Information System 1 Work Performance Information 2 Change Requests 3 Project Management Plan Updates 4 Project Documents Updates
  • 8. Project Communications Management Major Processes Primary Inputs Tools & Techniques Primary Outputs COMMUNICATIONS Plan Communication s Management In this process, the approach and plan for project communications are developed. Thereby, stakeholders’ and the project’s information needs as well as available organizational assets are taken into account 1 Project Charter 2 Project Management Plan 3 Project Documents 4 Enterprise Environmental Factors 5 Organizational Process Assets 1 Expert Judgement 2 Communication Requirements Analysis 3 Communication Technology 4 Communication Models 5 Communication Methods 6 Interpersonal And Team Skills 7 Data Representation Meetings 1. Communications Management Plan 2. Project Management Plan Updates 3. Project Documents Update Manage Communication s Manage communications is the ongoing process of ensuring timely and appropriate communication in order to facilitate an efficient and effective information flow between the project team and stakeholders. 1 Project Management Plan 2 Project Documents 3 Work Performance Reports 4 Enterprise Environmental Factors 5 Organizational Process Assets 1 Communication Technology 2 Communication Methods 3 Communication Skills 4 Project Management Information System 5 Project Reporting Interpersonal and Team Skills 6 Meetings 1 Project Communications 2 Project Management Plan Updates 3 Project Document Updates 4 Organizational Process Assets Updates Monitor Communication s This process makes sure that the information needs of the project and the stakeholders are met properly and timely 1 Project Management Plan 2 Project Documents 3 Work Performance Data 4 Enterprise Environment Factors 5 Organizational Process Assets 1 Expert Judgement 2 Project Management Information System 3 Data Representation Interpersonal and Team Skills 4 Meetings 1 Work Performance Information 2 Change Requests 3 Project Management Plan Updates 4Project Documents Updates
  • 9. Project Risk Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs RISK Plan Risk Responses This process comprises the planning of risk management activities for the project which includes tailoring of risk management considerations to the individual situation 1 Project Management Plan 2 Projects Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Expert Judgment 2 Data Gathering 3 Interpersonal and Team Skills 4 Strategies for Threats 5 Contingent Response Strategies 6 Strategies for Overall Project Risk 7 Data Analysis 8 Decision Making 1 Change Requests 2 Project Management Plan Updates 3 Project Documents Updates Identify Risks This process focuses on identifying and documenting individual risks as well as sources of overall project risks. 1. Project management plan 2. Project documents 3. Agreements 4. Procurement documentation 5. Enterprise enviromental factors 6. Organizational process assets 1. Expert judgment 2. Data Gathering 3. Data Analysis 4. Interpersonal and team skills 5. Prompt Lists 6. Meetings 1. Risk register 2. Risk report 3. Project documents updates Perform Qualitative Risk Analysis In the process of qualitative risk analysis, the probability and the potential impact of individual project risks are assessed, which is the basis for their prioritization 1. Project management plan 2. Project documents 3. Enterprise enviromental factors 4. Organizational process assets 1. Expert judgment 2. Data Gathering 3. Data Analysis 4. Interpersonal and team skills 5. Risk categorization 6. Data representation 7. Meetings 1. Project Documents Update Perform Quantitative Risk Analysis This process consists of statistical analyses (e.g. Monte Carlo simulation) of identified individual project risks and other sources of ambiguity or uncertainty. This is typically not applied to small or less critical projects 1. Project management plan 2. Project documents 3. Enterprise enviromental factors 4. Organizational process assets 1. Expert judgment 2. Data Gathering 3. Interpersonal and team skills 4. Representations of uncertainty 5. Data Analysis 1. Project Document Update Plan Risk Responses In this process, the ways to address overall and individual project risks are identified and assessed, incl. definition of activities as potential risk responses. 1. Project mangement plan 2. Project documents 3. Enterprise enviromental factors 4. Organizational process assets 1. Expert judgment 2. Data Gathering 3. Interpersonal and team skills 4. Strategies for threats 5. Strategies for Opportunities 6. Contingent response strategies 7. Strategies for overall project risks 8. Data Analysis 9. Decision making 1. Change requests 2. Project management plan updates 3. Project document updates Implement Risk Responses This process is conducted when risks require a response, i.e. the previously selected risk responses (activities) are implemented 1 Project Management Plan 2 Project Documents 3 Organizational Process Assets 1 Expert Judgement 2 Interpersonal and Team Skills 3 Project Management Information System 1 Change Requests 2 Project Documents Updates Monitor Risks In this process, risk responses and identified risks are monitored and tracked. In addition, new risks are identified and assessed. 1 Project Management Plan 2 Project Documents 3 Work Performance Data 4 Work Performance Reports 1 Data Analysis 2 Audits 3 Meetings 1 Work Performance Information 2 Change Requests 3 Project Management Plan Updates 4 Project Documents Updates 5 Organizational Process Assets Updates
  • 10. Project Procurement Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs PROCUREMENT Plan Procurement Management Planning procurement management includes documenting the way project procurement decisions are made, specifying the approach and identifying potential sellers. 1 Project Management Plan 2 Projects Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Expert Judgment 2 Data Gathering 3 Interpersonal and Team Skills 4 Strategies for Threats 5 Contingent Response Strategies 6 Strategies for Overall Project Risk 7 Data Analysis 8 Decision Making 1 Change Requests 2 Project Management Plan Updates 3 Project Documents Updates Conduct Procurements This process comprises selecting a seller and implementing the agreements and contracts for delivery. 1 Project Management Plan 2 Project Documents 3 Organizational Process Assets 1 Expert Judgement 2 Interpersonal and Team Skills 3 Project Management Information System 1 Change Requests 2 Project Documents Updates Control Procurements In this process, procurement relationships are managed and contract performance is monitored. This may also extend to changes and corrections as well as closing out contracts. 1 Project Management Plan 2 Project Documents Agreements 3 Procurement Documentation 4 Approved Change Requests 5 Work Performance Data 6 Enterprise Environmental Factors 7 Organizational Process Assets 1 Expert Judgment 2 Claims Administration 3 Data Analysis 4 Inspection 5 Audits 1 Closed Procurements 2 Work Performance Information 3 Procurement Documentation Updates 4 Change Requests 5 Project Management Plan Updates 6 Project Documents Updates 7 Organizational Process Assets Updates
  • 11. Project Stakeholder Management Knowledge Areas Major Processes Primary Inputs Tools & Techniques Primary Outputs STAKEHOLDER Identify Stakeholders This process implies identifying stakeholders and their respective interests, involvement, power, and potential impact on the project 1 Project Charter 2 Business Documents 3 Project Management Plan 4 Project Documents Agreements 5 Enterprise Environmental Factors 6 Organizational Process Assets 1 Expert Judgment 2 Data Gathering 3 Data Analysis 3 Data Representation Meetings 1 Stakeholder Register 2 Change Requests 3 Project Management Plan Updates 4 Project Documents Updates Plan Stakeholder Engagement This planning process is about developing how to involve stakeholders and how to interact effectively with them during the project. 1 Project Charter 2 Project Management Plan 3 Project Documents Agreements 4 Enterprise Environmental Factors 5 Organizational Process Assets 1 Expert Judgment 2 Data Gathering 3 Data Analysis 4 Decision Making 5 Data Representation 6 Meetings 1 Stakeholder Engagement Plan Manage Stakeholder Engagement The management of stakeholder engagement includes communicating and working with stakeholders to meet their needs and expectations. The goal of this process is to ensure their support and reduce resistance from stakeholders. 1 Project Management Plan 2 Project Documents 3 Enterprise Environmental Factors 4 Organizational Process Assets 1 Expert Judgment 2 Communication Skills 3 Interpersonal and Team Skills 4 Ground Rules Meetings 1 Change Requests 2 Project Management Plan Updates 3 Project Documents Updates Monitor Stakeholder Engagement This process describes the monitoring of relationships and the adjustment of strategies in order to engage stakeholders in an optimal way. 1 Project Management Plan 2 Project Documents 3 Work Performance Data 4 Enterprise Environmental Factors 5 Organizational Process Assets 1 Data Analysis 2 Decision Making 3 Data Representation 4 Communication Skills 5 Interpersonal and Team Skills 6 Meetings 1 Work Performance Information 2 Change Requests 3 Project Management Plan Updates 4 Project Documents Updates Adapted from PMBOK™ guide 6th Edition Copyright and all rights reserved. Permission to reproduce granted for individual use only. Issah Abdul-Wahab, PMP, PgMP, PfMP (WhatsApp - +233202225560) Last update: Feb 19, 2021