https://www.mudassiriqbal.net/project-management-terms-and-concepts
There are many concepts and definitions which require special attention by all PMP Aspirants as the terminologies are largely used interchangeably in the real world.
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Residual risk and secondary risk - PMP/CAPM from PMI
1. Residual Risk and Secondary Risk
The PMBOK® Guide ver 6 defines risk as “An uncertain event or condition that, if it
occurs, has a positive or negative effect upon at least one project objective.”
Residual Risks
The risks that might remain after the planned response of risk and those that have
been purposely accepted. PMBOK Guide ver 6.
Residual risks are referred to as leftover risks. These are accepted to the corporate risk tolerance
level. In certain cases, a residual risk doesn’t have a reasonable response. Project manager merely
accepts them the way they are since there is not much do about it. The risks are recognized during the
process of planning. Usually, a contingency reserve is set up to cope with such risks. As a project
manager, you will make sure that every residual risk is assessed properly. If there is no action
required, you will probably keep them on the watch list. Though if they need any action, you should
perhaps minimize the probability or influence of the risk through mitigation plan. For Residual Risk,
we might not always act.
Example:
Imagine you have identified a risk about the occurrence of rain for an hour or two. Subsequently, you
have developed a contingency plan to manage the risk. You might think that what if the rain
continues to fall even after two hours. You will further evaluate the situation and create a fallback
plan referred to as residual risk.
Secondary Risks
The risks that come up as a direct result of executing a risk response. PMBOK Guide
ver 6.
For secondary risks, the project management team need to identify the risk and formulate a response
plan to deal with the situation. As soon as the plan is executed, it may lead to a new risk that’s known
as secondary risk. A response plan is developed primarily depending on the influence of these risks
2. on the project. Typically, a high impact risk requires a response plan. On the contrary, if the risk
appears negligible, it will be only looked after by the project manager. Subsequently, the secondary
risks are evaluated for their severity and that may or may not need a response plan to achieve the
ultimate project objectives. For Secondary Risk, we will have response plan.
Example:
Suppose you are a project manager for construction tasks. According to your experience, you are
well aware of the fact that one major risk that you might face is when the sand supplier doesn’t
deliver on time. Accordingly, in the risk management plan, you will consider this risk and the
required action in case of such an event. Even after the implementation of the risk response plan,
there is another potential risk that’s the difference in the sand provided by two suppliers which were
to be referred to as a secondary risk.
The difference between Residual Risk and Secondary Risk
Assume you are planning the study schedule for your upcoming exam, the primary risks affecting the
schedule may include:
You may not find enough time to study due to professional commitment. There might an
unexpected project comes up during the exam preparation as residual risk. Consequently, you
need to set a plan to postpone your exam commonly known as a known unknown from
contingency reserve.
In another situation, you may fall ill during exam prep. There will be mainly a secondary risk for
the risk response i.e. what if the vaccines cause side effects such as prolonged fatigue or
infection. You will perhaps require a risk response plan for this secondary risk.
It is important for Project Manager or for Project management Team that all types of risks must be
identified, analyzed, monitored and taken care of throughout the project.
Further Readings
1. Project Risk Management
2. Risk Definitions