SlideShare a Scribd company logo
1 of 3
Residual Risk and Secondary Risk
The PMBOK® Guide ver 6 defines risk as “An uncertain event or condition that, if it
occurs, has a positive or negative effect upon at least one project objective.”
Residual Risks
The risks that might remain after the planned response of risk and those that have
been purposely accepted. PMBOK Guide ver 6.
Residual risks are referred to as leftover risks. These are accepted to the corporate risk tolerance
level. In certain cases, a residual risk doesn’t have a reasonable response. Project manager merely
accepts them the way they are since there is not much do about it. The risks are recognized during the
process of planning. Usually, a contingency reserve is set up to cope with such risks. As a project
manager, you will make sure that every residual risk is assessed properly. If there is no action
required, you will probably keep them on the watch list. Though if they need any action, you should
perhaps minimize the probability or influence of the risk through mitigation plan. For Residual Risk,
we might not always act.
Example:
Imagine you have identified a risk about the occurrence of rain for an hour or two. Subsequently, you
have developed a contingency plan to manage the risk. You might think that what if the rain
continues to fall even after two hours. You will further evaluate the situation and create a fallback
plan referred to as residual risk.
Secondary Risks
The risks that come up as a direct result of executing a risk response. PMBOK Guide
ver 6.
For secondary risks, the project management team need to identify the risk and formulate a response
plan to deal with the situation. As soon as the plan is executed, it may lead to a new risk that’s known
as secondary risk. A response plan is developed primarily depending on the influence of these risks
on the project. Typically, a high impact risk requires a response plan. On the contrary, if the risk
appears negligible, it will be only looked after by the project manager. Subsequently, the secondary
risks are evaluated for their severity and that may or may not need a response plan to achieve the
ultimate project objectives. For Secondary Risk, we will have response plan.
Example:
Suppose you are a project manager for construction tasks. According to your experience, you are
well aware of the fact that one major risk that you might face is when the sand supplier doesn’t
deliver on time. Accordingly, in the risk management plan, you will consider this risk and the
required action in case of such an event. Even after the implementation of the risk response plan,
there is another potential risk that’s the difference in the sand provided by two suppliers which were
to be referred to as a secondary risk.
The difference between Residual Risk and Secondary Risk
Assume you are planning the study schedule for your upcoming exam, the primary risks affecting the
schedule may include:
 You may not find enough time to study due to professional commitment. There might an
unexpected project comes up during the exam preparation as residual risk. Consequently, you
need to set a plan to postpone your exam commonly known as a known unknown from
contingency reserve.
 In another situation, you may fall ill during exam prep. There will be mainly a secondary risk for
the risk response i.e. what if the vaccines cause side effects such as prolonged fatigue or
infection. You will perhaps require a risk response plan for this secondary risk.
It is important for Project Manager or for Project management Team that all types of risks must be
identified, analyzed, monitored and taken care of throughout the project.
Further Readings
1. Project Risk Management
2. Risk Definitions
3. Residual Risk

More Related Content

What's hot

Project Management Uncertainty, Presented by upul chanaka from Sri Lanka
Project Management Uncertainty, Presented by upul chanaka from Sri Lanka Project Management Uncertainty, Presented by upul chanaka from Sri Lanka
Project Management Uncertainty, Presented by upul chanaka from Sri Lanka Upul Chanaka
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsAcumen
 
Project risk management workshops
Project risk management workshopsProject risk management workshops
Project risk management workshopsshippers1000
 
Risk management program oregon sql
Risk management program oregon sqlRisk management program oregon sql
Risk management program oregon sqlRehr Consulting
 
Emergency & Disaster Management for SME's
Emergency & Disaster Management for SME'sEmergency & Disaster Management for SME's
Emergency & Disaster Management for SME'sDavid Nixon
 
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd Healthcare consultant
 
Risk Management Process Steps PowerPoint Presentation Slides
Risk Management Process Steps PowerPoint Presentation Slides Risk Management Process Steps PowerPoint Presentation Slides
Risk Management Process Steps PowerPoint Presentation Slides SlideTeam
 
A Risk Analysis and Management in Software Engineering
A Risk Analysis and Management in Software Engineering A Risk Analysis and Management in Software Engineering
A Risk Analysis and Management in Software Engineering MuhammadTalha436
 
Risk Identification Process PowerPoint Presentation Slides
Risk Identification Process PowerPoint Presentation SlidesRisk Identification Process PowerPoint Presentation Slides
Risk Identification Process PowerPoint Presentation SlidesSlideTeam
 
Risk Management Lifecycle PowerPoint Presentation Slides
Risk Management Lifecycle PowerPoint Presentation Slides Risk Management Lifecycle PowerPoint Presentation Slides
Risk Management Lifecycle PowerPoint Presentation Slides SlideTeam
 
Business Continuity Planning
Business Continuity PlanningBusiness Continuity Planning
Business Continuity PlanningPete DiSantis
 
IT Disaster Recovery Plan
IT Disaster Recovery PlanIT Disaster Recovery Plan
IT Disaster Recovery PlanCallOneTel
 
Risk Mitigation Strategy Powerpoint Presentation Slides
Risk Mitigation Strategy Powerpoint Presentation SlidesRisk Mitigation Strategy Powerpoint Presentation Slides
Risk Mitigation Strategy Powerpoint Presentation SlidesSlideTeam
 
Risk Management: A Key Success Factor
Risk Management: A Key Success FactorRisk Management: A Key Success Factor
Risk Management: A Key Success FactorERAUWebinars
 

What's hot (20)

Project Management Uncertainty, Presented by upul chanaka from Sri Lanka
Project Management Uncertainty, Presented by upul chanaka from Sri Lanka Project Management Uncertainty, Presented by upul chanaka from Sri Lanka
Project Management Uncertainty, Presented by upul chanaka from Sri Lanka
 
Risk management
Risk managementRisk management
Risk management
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk Workshops
 
Project risk management workshops
Project risk management workshopsProject risk management workshops
Project risk management workshops
 
Risk management program oregon sql
Risk management program oregon sqlRisk management program oregon sql
Risk management program oregon sql
 
Risk Assessment And Risk Treatment
Risk Assessment And Risk TreatmentRisk Assessment And Risk Treatment
Risk Assessment And Risk Treatment
 
Emergency & Disaster Management for SME's
Emergency & Disaster Management for SME'sEmergency & Disaster Management for SME's
Emergency & Disaster Management for SME's
 
Risk management
Risk managementRisk management
Risk management
 
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
 
Risk Management Process Steps PowerPoint Presentation Slides
Risk Management Process Steps PowerPoint Presentation Slides Risk Management Process Steps PowerPoint Presentation Slides
Risk Management Process Steps PowerPoint Presentation Slides
 
A Risk Analysis and Management in Software Engineering
A Risk Analysis and Management in Software Engineering A Risk Analysis and Management in Software Engineering
A Risk Analysis and Management in Software Engineering
 
Risk Identification Process PowerPoint Presentation Slides
Risk Identification Process PowerPoint Presentation SlidesRisk Identification Process PowerPoint Presentation Slides
Risk Identification Process PowerPoint Presentation Slides
 
Risk Management Lifecycle PowerPoint Presentation Slides
Risk Management Lifecycle PowerPoint Presentation Slides Risk Management Lifecycle PowerPoint Presentation Slides
Risk Management Lifecycle PowerPoint Presentation Slides
 
Risk avoidance
Risk avoidanceRisk avoidance
Risk avoidance
 
Business Continuity Planning
Business Continuity PlanningBusiness Continuity Planning
Business Continuity Planning
 
IT Disaster Recovery Plan
IT Disaster Recovery PlanIT Disaster Recovery Plan
IT Disaster Recovery Plan
 
The Basics of a Business Continuity Plan
The Basics of a Business Continuity PlanThe Basics of a Business Continuity Plan
The Basics of a Business Continuity Plan
 
Risk Mitigation Strategy Powerpoint Presentation Slides
Risk Mitigation Strategy Powerpoint Presentation SlidesRisk Mitigation Strategy Powerpoint Presentation Slides
Risk Mitigation Strategy Powerpoint Presentation Slides
 
Risk Management: A Key Success Factor
Risk Management: A Key Success FactorRisk Management: A Key Success Factor
Risk Management: A Key Success Factor
 
SunGard Risk Assessment Module
SunGard Risk Assessment ModuleSunGard Risk Assessment Module
SunGard Risk Assessment Module
 

Similar to Residual risk and secondary risk - PMP/CAPM from PMI

Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxMehediHasan636262
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk managementPMC Mentor
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docxaryan532920
 
NEGATIVE_RESPONSE_STRATEGIES_V1.1
NEGATIVE_RESPONSE_STRATEGIES_V1.1NEGATIVE_RESPONSE_STRATEGIES_V1.1
NEGATIVE_RESPONSE_STRATEGIES_V1.1Fahad Saleem
 
Risk 9-pm study project risk management-test
Risk 9-pm study project risk management-testRisk 9-pm study project risk management-test
Risk 9-pm study project risk management-testMohamed Saeed
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docxalinainglis
 
Risk 8- pm study question risk management
Risk 8- pm study question risk managementRisk 8- pm study question risk management
Risk 8- pm study question risk managementMohamed Saeed
 
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docxjesusamckone
 
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docxRAJU852744
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship AliAbbas390458
 
Ten rules of project risk management
Ten rules of project risk managementTen rules of project risk management
Ten rules of project risk managementTony
 

Similar to Residual risk and secondary risk - PMP/CAPM from PMI (20)

Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
NEGATIVE_RESPONSE_STRATEGIES_V1.1
NEGATIVE_RESPONSE_STRATEGIES_V1.1NEGATIVE_RESPONSE_STRATEGIES_V1.1
NEGATIVE_RESPONSE_STRATEGIES_V1.1
 
Risk guideline
Risk guidelineRisk guideline
Risk guideline
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Risk 9-pm study project risk management-test
Risk 9-pm study project risk management-testRisk 9-pm study project risk management-test
Risk 9-pm study project risk management-test
 
Risk based thinking
Risk based thinkingRisk based thinking
Risk based thinking
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx
 
Risk management
Risk managementRisk management
Risk management
 
Risk 8- pm study question risk management
Risk 8- pm study question risk managementRisk 8- pm study question risk management
Risk 8- pm study question risk management
 
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
 
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Ten rules of project risk management
Ten rules of project risk managementTen rules of project risk management
Ten rules of project risk management
 

More from Mudassir Iqbal

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIMudassir Iqbal
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIMudassir Iqbal
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMIMudassir Iqbal
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIMudassir Iqbal
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIMudassir Iqbal
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIMudassir Iqbal
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPMMudassir Iqbal
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMMudassir Iqbal
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMMudassir Iqbal
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPMMudassir Iqbal
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
Executing process group
Executing process groupExecuting process group
Executing process groupMudassir Iqbal
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone scheduleMudassir Iqbal
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budgetMudassir Iqbal
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko Mudassir Iqbal
 

More from Mudassir Iqbal (17)

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMI
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMI
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMI
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMI
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPM
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPM
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
Executing process group
Executing process groupExecuting process group
Executing process group
 
Closing process group
Closing process groupClosing process group
Closing process group
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
 
Quality and Grade
Quality and GradeQuality and Grade
Quality and Grade
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budget
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko
 

Recently uploaded

(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756dollysharma2066
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFOrient Homes
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 

Recently uploaded (20)

(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 

Residual risk and secondary risk - PMP/CAPM from PMI

  • 1. Residual Risk and Secondary Risk The PMBOK® Guide ver 6 defines risk as “An uncertain event or condition that, if it occurs, has a positive or negative effect upon at least one project objective.” Residual Risks The risks that might remain after the planned response of risk and those that have been purposely accepted. PMBOK Guide ver 6. Residual risks are referred to as leftover risks. These are accepted to the corporate risk tolerance level. In certain cases, a residual risk doesn’t have a reasonable response. Project manager merely accepts them the way they are since there is not much do about it. The risks are recognized during the process of planning. Usually, a contingency reserve is set up to cope with such risks. As a project manager, you will make sure that every residual risk is assessed properly. If there is no action required, you will probably keep them on the watch list. Though if they need any action, you should perhaps minimize the probability or influence of the risk through mitigation plan. For Residual Risk, we might not always act. Example: Imagine you have identified a risk about the occurrence of rain for an hour or two. Subsequently, you have developed a contingency plan to manage the risk. You might think that what if the rain continues to fall even after two hours. You will further evaluate the situation and create a fallback plan referred to as residual risk. Secondary Risks The risks that come up as a direct result of executing a risk response. PMBOK Guide ver 6. For secondary risks, the project management team need to identify the risk and formulate a response plan to deal with the situation. As soon as the plan is executed, it may lead to a new risk that’s known as secondary risk. A response plan is developed primarily depending on the influence of these risks
  • 2. on the project. Typically, a high impact risk requires a response plan. On the contrary, if the risk appears negligible, it will be only looked after by the project manager. Subsequently, the secondary risks are evaluated for their severity and that may or may not need a response plan to achieve the ultimate project objectives. For Secondary Risk, we will have response plan. Example: Suppose you are a project manager for construction tasks. According to your experience, you are well aware of the fact that one major risk that you might face is when the sand supplier doesn’t deliver on time. Accordingly, in the risk management plan, you will consider this risk and the required action in case of such an event. Even after the implementation of the risk response plan, there is another potential risk that’s the difference in the sand provided by two suppliers which were to be referred to as a secondary risk. The difference between Residual Risk and Secondary Risk Assume you are planning the study schedule for your upcoming exam, the primary risks affecting the schedule may include:  You may not find enough time to study due to professional commitment. There might an unexpected project comes up during the exam preparation as residual risk. Consequently, you need to set a plan to postpone your exam commonly known as a known unknown from contingency reserve.  In another situation, you may fall ill during exam prep. There will be mainly a secondary risk for the risk response i.e. what if the vaccines cause side effects such as prolonged fatigue or infection. You will perhaps require a risk response plan for this secondary risk. It is important for Project Manager or for Project management Team that all types of risks must be identified, analyzed, monitored and taken care of throughout the project. Further Readings 1. Project Risk Management 2. Risk Definitions