1. Event-based Risk and Non-Event Risks
The risk is future uncertain event or condition that, if it occurs, has a positive or negative
effect on one or more project objectives. [PMBOK6]
The risk is the effect of uncertainty on objectives, and an effect is a positive or negative
deviation from what is expected. [ISO31000]
Event-Based Risk
Event-Based Risks or are future possible events known as stochastic uncertainty or event risk. An
event risk refers to something that has not happened yet and it might not happen at all. In case the
situation does happen, it will influence one or more objectives. Many risks are identified in the
representative project risk register as event risks. Below are some examples of event-based risks
including both threats and opportunities.
An important supplier may go out of business while the project is on-going
The client may change the requirements after completion of design
New regulatory limitations might be enforced
2. You may lose a prominent resource during the critical phase of the project
The client may permit incremental deliveries
Event-Based Risk Management (EBRM) is an approach to help the project manager in overcoming
this issue. Typically, traditional risk management processes use the bottom-up methodology to
identify individual project risks. Investing a lot of time in evaluating and managing the wrong risks
can divert means that could be used more efficiently. Event-Based Risk Management facilitates a
top-down approach for analyzing project risks and complements the typically bottom-up technique.
The outcomes help in understanding the relevant details along with the key risks. This is an
imperative element of any project. It is correspondingly applicable during the project planning and
the implementation phases. EBRM comes with the following discriminators:
It follows a top-down approach to offer a bigger view in contrast to the bottom-up approach.
Event-centric interpretation focuses on key events or deliverables.
Intrinsic schedule evaluation to improve the probability of project success.
Key artifacts that significantly facilitate comprehending important risks to the project. These
artifacts are quite effective for communicating essential project information to both the project
team and to other stakeholders.
Review inputs from others who have somewhat similar experiences.
Non-Event Risks
Some risks arise from uncertainty when some aspects of a planned task or situation are not known.
They are more subtle in nature. For instance, suppose a situation from the project arena where you
might be planning to run a 15-day trial, while the actual duration is somewhere between 10-25 days.
The likelihood of running the trial is 100% through the duration is uncertain. Other unknown
parameters include budget, resource requirement, output, deficiency rate, performance, etc. Below, I
have listed some examples of non-event risks:
Efficiency may be above or below the target
3. The number of miscalculations found during testing may be high or low than expected
Unseasonal weather circumstances may arise during the building phase
Exchange rates can vary beyond the range used to finalize quote
Example
*A simplified hypothetical example of driving from Paris to Frankfurt and tries to figure out how
long it should take. He collects data points: 5 hours is the ideal time, 6 hours is more likely, and it
could be upward of 25 hours if the car breaks down. That provides an estimated range of 5 to 25
hours wide.
The range 8 hours to 25 hours comprises ‘event’ risk as understood traditionally by the PMBOK. In
order to refine this estimate, we must take a conventional risk approach: identify risks, analyse,
prioritise, and develop responses to the high priority risks.
Further Readings
1. Risk and Issues
2. How Do You Handle Event Risk versus Non-Event Risk?*
3. When is a Risk not a Risk? by Dr David Hillson