SlideShare a Scribd company logo
1 of 3
Event-based Risk and Non-Event Risks
The risk is future uncertain event or condition that, if it occurs, has a positive or negative
effect on one or more project objectives. [PMBOK6]
The risk is the effect of uncertainty on objectives, and an effect is a positive or negative
deviation from what is expected. [ISO31000]
Event-Based Risk
Event-Based Risks or are future possible events known as stochastic uncertainty or event risk. An
event risk refers to something that has not happened yet and it might not happen at all. In case the
situation does happen, it will influence one or more objectives. Many risks are identified in the
representative project risk register as event risks. Below are some examples of event-based risks
including both threats and opportunities.
 An important supplier may go out of business while the project is on-going
 The client may change the requirements after completion of design
 New regulatory limitations might be enforced
 You may lose a prominent resource during the critical phase of the project
 The client may permit incremental deliveries
Event-Based Risk Management (EBRM) is an approach to help the project manager in overcoming
this issue. Typically, traditional risk management processes use the bottom-up methodology to
identify individual project risks. Investing a lot of time in evaluating and managing the wrong risks
can divert means that could be used more efficiently. Event-Based Risk Management facilitates a
top-down approach for analyzing project risks and complements the typically bottom-up technique.
The outcomes help in understanding the relevant details along with the key risks. This is an
imperative element of any project. It is correspondingly applicable during the project planning and
the implementation phases. EBRM comes with the following discriminators:
 It follows a top-down approach to offer a bigger view in contrast to the bottom-up approach.
 Event-centric interpretation focuses on key events or deliverables.
 Intrinsic schedule evaluation to improve the probability of project success.
 Key artifacts that significantly facilitate comprehending important risks to the project. These
artifacts are quite effective for communicating essential project information to both the project
team and to other stakeholders.
 Review inputs from others who have somewhat similar experiences.
Non-Event Risks
Some risks arise from uncertainty when some aspects of a planned task or situation are not known.
They are more subtle in nature. For instance, suppose a situation from the project arena where you
might be planning to run a 15-day trial, while the actual duration is somewhere between 10-25 days.
The likelihood of running the trial is 100% through the duration is uncertain. Other unknown
parameters include budget, resource requirement, output, deficiency rate, performance, etc. Below, I
have listed some examples of non-event risks:
 Efficiency may be above or below the target
 The number of miscalculations found during testing may be high or low than expected
 Unseasonal weather circumstances may arise during the building phase
 Exchange rates can vary beyond the range used to finalize quote
Example
*A simplified hypothetical example of driving from Paris to Frankfurt and tries to figure out how
long it should take. He collects data points: 5 hours is the ideal time, 6 hours is more likely, and it
could be upward of 25 hours if the car breaks down. That provides an estimated range of 5 to 25
hours wide.
The range 8 hours to 25 hours comprises ‘event’ risk as understood traditionally by the PMBOK. In
order to refine this estimate, we must take a conventional risk approach: identify risks, analyse,
prioritise, and develop responses to the high priority risks.
Further Readings
1. Risk and Issues
2. How Do You Handle Event Risk versus Non-Event Risk?*
3. When is a Risk not a Risk? by Dr David Hillson

More Related Content

What's hot

What Is Six Sigma? An Introduction for Technical Writers
What Is Six Sigma? An Introduction for Technical WritersWhat Is Six Sigma? An Introduction for Technical Writers
What Is Six Sigma? An Introduction for Technical WritersSTC-Philadelphia Metro Chapter
 
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre..."Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...SN Panigrahi, PMP
 
Derivatives and Pakistani Market
Derivatives and Pakistani MarketDerivatives and Pakistani Market
Derivatives and Pakistani Markethadishaikh2
 
Slides-Meezan-Bank.ppt
Slides-Meezan-Bank.pptSlides-Meezan-Bank.ppt
Slides-Meezan-Bank.pptSalman Khan
 
Project Management Report
Project Management ReportProject Management Report
Project Management ReportSANKET SENAPATI
 

What's hot (7)

What Is Six Sigma? An Introduction for Technical Writers
What Is Six Sigma? An Introduction for Technical WritersWhat Is Six Sigma? An Introduction for Technical Writers
What Is Six Sigma? An Introduction for Technical Writers
 
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre..."Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
 
Bank Alfalah
Bank AlfalahBank Alfalah
Bank Alfalah
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Derivatives and Pakistani Market
Derivatives and Pakistani MarketDerivatives and Pakistani Market
Derivatives and Pakistani Market
 
Slides-Meezan-Bank.ppt
Slides-Meezan-Bank.pptSlides-Meezan-Bank.ppt
Slides-Meezan-Bank.ppt
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
 

Similar to Event and Non-Event Risk - PMP/CAPM from PMI

Integrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost RiskIntegrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost RiskHKA
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxMehediHasan636262
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managmentMalan Bothma
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdfNmnKmr2
 
5 Project Risk Managementadrian825iStockThinkstockLe.docx
5 Project Risk Managementadrian825iStockThinkstockLe.docx5 Project Risk Managementadrian825iStockThinkstockLe.docx
5 Project Risk Managementadrian825iStockThinkstockLe.docxgilbertkpeters11344
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareLiberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareSong Love
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual EssayPrince Bertrand
 
Risky Business
Risky BusinessRisky Business
Risky Business3gamma
 
Risk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxRisk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxSUBHI7
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleGlen Alleman
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk ManagementGlen Alleman
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazMohamed Saeed
 

Similar to Event and Non-Event Risk - PMP/CAPM from PMI (20)

Project risk management
Project risk managementProject risk management
Project risk management
 
Risk management
Risk managementRisk management
Risk management
 
Integrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost RiskIntegrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost Risk
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managment
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdf
 
5 Project Risk Managementadrian825iStockThinkstockLe.docx
5 Project Risk Managementadrian825iStockThinkstockLe.docx5 Project Risk Managementadrian825iStockThinkstockLe.docx
5 Project Risk Managementadrian825iStockThinkstockLe.docx
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareLiberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual Essay
 
Risky Business
Risky BusinessRisky Business
Risky Business
 
Risk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxRisk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docx
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbaz
 
Project/Program Risk management
Project/Program Risk managementProject/Program Risk management
Project/Program Risk management
 

More from Mudassir Iqbal

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIMudassir Iqbal
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIMudassir Iqbal
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIMudassir Iqbal
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIMudassir Iqbal
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIMudassir Iqbal
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIMudassir Iqbal
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPMMudassir Iqbal
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMMudassir Iqbal
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMMudassir Iqbal
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPMMudassir Iqbal
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
Executing process group
Executing process groupExecuting process group
Executing process groupMudassir Iqbal
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone scheduleMudassir Iqbal
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budgetMudassir Iqbal
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko Mudassir Iqbal
 

More from Mudassir Iqbal (17)

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMI
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMI
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMI
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMI
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMI
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPM
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPM
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
Executing process group
Executing process groupExecuting process group
Executing process group
 
Closing process group
Closing process groupClosing process group
Closing process group
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
 
Quality and Grade
Quality and GradeQuality and Grade
Quality and Grade
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budget
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko
 

Recently uploaded

Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 

Recently uploaded (20)

Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 

Event and Non-Event Risk - PMP/CAPM from PMI

  • 1. Event-based Risk and Non-Event Risks The risk is future uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives. [PMBOK6] The risk is the effect of uncertainty on objectives, and an effect is a positive or negative deviation from what is expected. [ISO31000] Event-Based Risk Event-Based Risks or are future possible events known as stochastic uncertainty or event risk. An event risk refers to something that has not happened yet and it might not happen at all. In case the situation does happen, it will influence one or more objectives. Many risks are identified in the representative project risk register as event risks. Below are some examples of event-based risks including both threats and opportunities.  An important supplier may go out of business while the project is on-going  The client may change the requirements after completion of design  New regulatory limitations might be enforced
  • 2.  You may lose a prominent resource during the critical phase of the project  The client may permit incremental deliveries Event-Based Risk Management (EBRM) is an approach to help the project manager in overcoming this issue. Typically, traditional risk management processes use the bottom-up methodology to identify individual project risks. Investing a lot of time in evaluating and managing the wrong risks can divert means that could be used more efficiently. Event-Based Risk Management facilitates a top-down approach for analyzing project risks and complements the typically bottom-up technique. The outcomes help in understanding the relevant details along with the key risks. This is an imperative element of any project. It is correspondingly applicable during the project planning and the implementation phases. EBRM comes with the following discriminators:  It follows a top-down approach to offer a bigger view in contrast to the bottom-up approach.  Event-centric interpretation focuses on key events or deliverables.  Intrinsic schedule evaluation to improve the probability of project success.  Key artifacts that significantly facilitate comprehending important risks to the project. These artifacts are quite effective for communicating essential project information to both the project team and to other stakeholders.  Review inputs from others who have somewhat similar experiences. Non-Event Risks Some risks arise from uncertainty when some aspects of a planned task or situation are not known. They are more subtle in nature. For instance, suppose a situation from the project arena where you might be planning to run a 15-day trial, while the actual duration is somewhere between 10-25 days. The likelihood of running the trial is 100% through the duration is uncertain. Other unknown parameters include budget, resource requirement, output, deficiency rate, performance, etc. Below, I have listed some examples of non-event risks:  Efficiency may be above or below the target
  • 3.  The number of miscalculations found during testing may be high or low than expected  Unseasonal weather circumstances may arise during the building phase  Exchange rates can vary beyond the range used to finalize quote Example *A simplified hypothetical example of driving from Paris to Frankfurt and tries to figure out how long it should take. He collects data points: 5 hours is the ideal time, 6 hours is more likely, and it could be upward of 25 hours if the car breaks down. That provides an estimated range of 5 to 25 hours wide. The range 8 hours to 25 hours comprises ‘event’ risk as understood traditionally by the PMBOK. In order to refine this estimate, we must take a conventional risk approach: identify risks, analyse, prioritise, and develop responses to the high priority risks. Further Readings 1. Risk and Issues 2. How Do You Handle Event Risk versus Non-Event Risk?* 3. When is a Risk not a Risk? by Dr David Hillson