SlideShare a Scribd company logo
1 of 13
Design of Sprinkler System and CO2 Total Flooding
System of Given Plan
Gaurav Singh Rajput
B. Tech Safety & Fire Engineering, CUSAT
Assistant Manager- HSEF, at NAYARA ENERGY LTD
DEPARTMENT OF SAFETY AND FIRE & ENGINEERING
SCHOOL OF ENGINEERING, CUSAT.
NOVEMBER 2017
2
INDEX
1. Introduction …3
2. Sprinkler system design …5
3. CO2 Total flooding system design …9
4. Reference …13
3
This project includes two parts
1. Sprinkler System Design
2. CO2 Total Flooding System Design
In sprinkler system design first given plan were studied and its area divided on the
basic of hazardous classification of building as per NBC Part- 4 and number of
sprinklers required in area were calculated. Then pressure and flow rate of water at
externa inlet valve were calculated. Number of hangers, range pipe and distribution
pipes were calculated.
In CO2 Total Flooding System Design number of co2 cylinder required for the given
compartment for total flooding system were calculated.
4
SPRINKLER SYSTEM DESIGN
Civil Station
5
Occupancy type - Group E, Business building
Area of compartment = 141.9 m2
Hazard classification - Moderate hazard
Sprinkler type - standard
Maximum spacing of sprinklers along range pipe and between adjustment rows
For standard (sand D) - 4.0m
Minimum spacing of sprinklers - 2m
Distance between sprinklers and boundary
For standard spacing = 0.5s
Distance between range pipe and boundary - 0.5D
Maximum area of coverage of a sprinkler
Amax = 2m
Range pipes are to be laid parallel to the side of compartment
For standard spacing layout =6.6/4 =1.65
= 2(say)
Spacing of range required = 6.6/2 =3.3m
Providing a spacing of 3.6 m (D) with outer range pipes at 1.5m away from the wall
(<0.5D) now,
No of sprinklers along the range pipe = 21.5/4 =5.375 = 6(Say)
Spacing of sprinklers along range pipe =21.5/6 =3.58 m
Maximum spacing of sprinklers along the range pipe considering the average of
single sprinklers =12/3.6= 3.33m
6
So,
Proving a spacing of 3.2m (S) with extreme sprinkler at 1.5m away from the side wall
(<0.5 s)
So,
Number of sprinklers in range pipe =7
Total number of sprinklers = 14
HYDRAULIC CALCULATION OF PRESSURE AND FLOW AT
AMAO LOCATED AT THE MOST REMOTE AREA
Pressure calculation between sprinkler 1 and top of riser:
Sprin
kler
start
node
Sprin
kler
end
node
Descripti
on
Diamet
er of
pipe
(mm)
Length
of pipe
betwee
n
nodes
(m)
Pipe
fittings
and
devices
Equivalen
t pipe
length
(mm)
Pressure
required at
start node
(bar)
Water flow in
sprinkler at
start node
(l/min)
Friction
loss per
m length
(bar/m)
Static
head
loss
(bar)
Total
pressure
loss in
pipe
(bar)
Total discharge
just before the
end node
(l/min)
1 2 Most
remotest
sprinkler
25 3.2 Nil - 0.51 37.6 0.024 0 0.076 57.6
2 3 - 32 3.2 Nil - 0.58 61.24 0.008 0 0.026 118.8
3 4 - 32 3.2 Nil - 0.606 62.27 0.0084 0 0.0269 180.64
4 Top
of
riser
- 50 1.6 Tee 2.91 0.6329 63.94 0.001 0 0.004 244.58
Design Density = 5 lpm/m2
Minimum discharge required for each sprinkler = 5*3.2*3.6
= 57.6 l/min
Selecting 15mm nominal orifice size sprinkler with a k value of 80
Minimum pressure required at entry point of sprinkler = (57.6/80)2
=0.51 bar
As per table 29 of IS 15105:2002 minimum pressure for moderate hazard is
0.35 bar <0.51 bar, hence ok
7
Pressure calculation between 7 and top of riser:
Sprinkl
er start
node
Sprinkl
er end
node
Des
cripti
on
Diamete
r of pipe
(mm)
Length of
pipe
between
nodes (m)
Pipe
fittings
and
devise
s
Equiv
alent
pipe
lenth
(m)
Pressur
e require
at start
node
(bar)
Water
flow in
sprinkler
at start
node
(l/min)
Frictio
n loss
per m
length
(bar/m
)
Static
head
loss
(bar)
Total
pressure
loss in
pipe
(bar)
Total
discharge just
before the end
node (l/min)
7 6 - 32 3.2 Nil - 0.51 57.6 0.007
2
0 0.023 57.6
6 5 - 32 3.2 - - 0.53 58.24 0.007
4
0 0.0236 115.84
5 Top of
riser
- 50 1.6 - - 0.55 59.32 0.008
7
0 0.0139 175.16
Minimum pressure required at top of riser for sprinkler 1 to 4, Ph = 0.6329+0.004
= 0.6369 bar
Water discharge to sprinkler 1 to 4 at top of riser, Qh = 244.58 l/min
Minimum pressure required at top of riser for sprinkler 7 to 5 (Pl) = 0.55+0.0139
= 0.5639 bar
Water discharge to sprinkler 7 to 5 at top of riser, (QL) =175.16 l/min
Adjustment of water flow to sprinklers 6 and 7 due to pressure
difference:
Qad j= QL*√(𝑃h/PL)
=175.16*√0.6369/0.5639
=186.15 l/min
Total water flow required at top of riser to sprinkler to sprinkler 1 to
7=244.58+186.15
=430.73 l/min
Pressure calculation between sprinklers top of riser to bottom
of riser at next range pipe:
Sprink
ler
start
node
Sprink
ler end
node
Desc
ripti
on
Diame
ter of
pipe
(mm)
Length
of pipe
between
nodes
(m)
Pipe
fittings
and
devises
Equivale
nt pipe
length
(m)
Pressure
require
at start
node
(bar)
Water
flow in
sprinkler
at start
node
(l/min)
Friction
loss per
m length
(bar/m)
Static
head
loss
(bar)
Total
pressure loss
in pipe (bar)
Total
discharge
just before
the end
node
(l/min)
Top of
riser
Botto
m of
riser
- 50 0.5 Tee 2.91 0.636 430.73 0.034 0.05 0.185 430.73
Botto Botto Dist 65 3.6 Nill 0 0.801 430.73 0.009 0 0.0324 430.73
8
m of
riser
to
extre
me
range
pipe
m of
next
riser
ribut
ion
pipe
Adjustment of water flow to sprinklers 8 and 14 due to
pressure difference:
Pressure required at bottom of riser for sprinkler 1 to 7, Pi=0.636+0.165
=0.801 bar
Water discharge to sprinkler 1 to 7 at bottom of riser , Qi =430.73 l/min
Branch line K factor, Kbr = Qi/√ 𝑃𝑖 =430.73/√(0.801)
= 481.27
Pressure required at bottom of next riser for sprinkler for sprinkler 8 to 14,
P = 0.80+0.0324
=0.8334 bar
Water discharge required to sprinkler 8 to 14 at bottom of riser
Q= kbr*√ 𝑃 = 481.27*√0.8334
= 439.354 l/min
Total discharge required at bottom of riser for sprinkler 1 to 14
=430.73+439.354
= 870.084 l/min
Sprinkler
start
node
Sprinkle
r end
node
Desc
riptio
n
Diame
ter of
pipe
(mm)
Length
of pipe
betwe
en
nodes
(m)
Pipe
fittings
&
devise
s
Equivale
nt pipe
length
(m)
Pressure
required
at start
node
(bar)
Water
flow in
sprinkler
at start
node
(l/min)
Friction
loss per
m length
(bar/m)
Static
head
loss
(bar)
Total
pressure
loss IN
pipe (bar)
Total
discharge
just before
the end
node
(l/min)
Bottom
of riser 8
to 14
End of
distribut
ion pipe
Distri
butio
n
pipe
65 2 Tee 3.81 0.8334 870 0.035 0 0.07 870
End of
distributi
on pipe
Top of
alarm
valve
Main
riser
100 8 Nill 0 0.9 870 0.0042 0.8 0.84 870
Top of
alarm
valve
Bottom
of
control
valve
Contr
ol
valve
100 0.5 Alarm
valve,
gate
valve
5.88 1.74 870 0.0042 0.05 0.076 870
9
We need 870 l/min water discharge with minimum pressure of 1.86 bar at the
bottom of control valve to have the required discharge and pressure at AMAO.
Hanger for sprinkler pipe:
Distribution/range pipes should not be supported from celling sheathing or cladding
or from any other associated suspended system systems.
Hanger should not be welded or fastened directly to the pipe work.
The supports on which the pipe work rests should be secured firmly in position.
The thickness of all parts of pipe supports should not be less than 3mm.
Whenever possible, pipes should be supported from non-combustible building
elements.
Pipe work in corrosive areas should be of either stainless steel or or suitably
protected against corrosion.
The distance between pipe supports measured along the line of connected pipes,
shall not be less than
• 4.0 m for pipe diameter up to 65mm
• 6 m for pipe diameter from 65 to 100mm
Distribution Pipes:
1. The first support on a normally horizontal distribution pipe shall not be more than
2m from the main distribution pipe; the last support shall not be more than 450
mm from the end
2. The drop of riser pipes shall be secured to the building structure either directly or
indirectly at the adjacent nominally horizontal part of the pipe within 300 mm of
the drop or riser.
Range Pipe:
1. The first support on range pipe shall not be more than 2 m from the distribution
pipe; the last support shall not be more than 1.5 m from the range pipe end.
2. At least one support shall be provided for each pipe run connecting adjacent
sprinkler, and the pipe run connecting the distribution pipe and the first sprinkler
on the range pipe.
3. Pipe support shall not be closer than 150 mm to any sprinkler axial central line.
10
DESIGNING CO2 TOTAL FLOODING SYSTEM FOR MARKET
AREA IN GIVEN PLAN
All doors and windows are closable during the application of the carbon dioxide.
Volume of the whole compartment = 21.5*6.6*3.4
= 482.46 m3
Assume volume of pedestal = 100m3
Net volume of compartment,
V= 482.46-100
= 382.46 m3
Minimum design concentration of CO2 required for the combustible material-
Hydrocarbon (IS-15528, Table 3) = 75%
Volume factor based on space to be protected and for a design concentration 34%
(Table 3, IS-15526)
=0.8 kg of CO2/m3
The basic concentration of CO2 required at 34% concentration
11
Qbasic = V*volume factor
=382.46*0.8
Qbasic=305.96 kg
Minimum concentration of CO2 required at 34% concentration,
Qmin = 113.5 kg
i.e, 305.6 > 113.5
So, the basic quantity of CO2 required at 34% concentration,
Qbasic=305.96 kg.
Basic quantity of CO2 required at 75% concentration,
Q=Qbasic*(material conversion factor)
=305.96*1.2
=367.15 kg
Total amount of CO2 required =367.15kg
Pressure inside cylinder =55 bar
Density =
Mass
volume
Volume =
367.15
1.98
= 185.42 m3
Now, P1V1 = P2V2
55*v1 = 1*185.42
V1=3.371m3 =3371.27L
Assume one cylinder of capacity 80L.
Number of cylinders =
3371.25
80
= 42.14
The filling ratio of co2 is 0.67 so, the number of cylinders required is 43
Number of total cylinders required = 43
We can store these cylinders in main bank, and same amount of co2 should be stored
for standby. The minimum effective discharge time for use in calculating the quantity
shall be 60 s.
12
13
REFERENCE
1. IS 15105: Design and Installation of Fixed Automatic Sprinkler Fire Extinguishing
Systems--Code of Practice.
2. IS 15528: Gaseous Fire Extinguishing Systems— Carbon Dioxide Total Flooding
and Local Application (Subfloor and In-Cabinet), High and Low Pressure
(Refrigerated) Systems.

More Related Content

What's hot

Fire Protection Training_QPS_26DEC20_Final.pptx
Fire Protection Training_QPS_26DEC20_Final.pptxFire Protection Training_QPS_26DEC20_Final.pptx
Fire Protection Training_QPS_26DEC20_Final.pptxVirenPatel528405
 
Inspection, Testing and Maintenance of fire pump
Inspection, Testing and Maintenance of fire pumpInspection, Testing and Maintenance of fire pump
Inspection, Testing and Maintenance of fire pumpklsmani
 
Fire sprinkler systems
Fire sprinkler systemsFire sprinkler systems
Fire sprinkler systemsjosebolis
 
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptBASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptRajeshKannan579711
 
Fire hydrant system
Fire hydrant systemFire hydrant system
Fire hydrant systemFarahNaz96
 
Fire protection system...
Fire protection system...Fire protection system...
Fire protection system...AnkitaGorhe
 
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTFIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTMEP ENGINEER'S SERVICES
 
Clean Agent & Inert Gas Fire Suppression
Clean Agent & Inert Gas Fire SuppressionClean Agent & Inert Gas Fire Suppression
Clean Agent & Inert Gas Fire SuppressionBen Adams
 
Fire Protection System Design
Fire Protection System DesignFire Protection System Design
Fire Protection System DesignMostafa Al Wakeel
 
Fire and safety equipment madh
Fire and safety equipment madhFire and safety equipment madh
Fire and safety equipment madhDeepak Thapa
 
Nfpa20 standard for the installation of stationary pumps for fire protection ...
Nfpa20 standard for the installation of stationary pumps for fire protection ...Nfpa20 standard for the installation of stationary pumps for fire protection ...
Nfpa20 standard for the installation of stationary pumps for fire protection ...Bowen Ngo
 
Basic Guide to NFPA 13 Occupancy and Commodity Classifications
Basic Guide to NFPA 13 Occupancy and Commodity ClassificationsBasic Guide to NFPA 13 Occupancy and Commodity Classifications
Basic Guide to NFPA 13 Occupancy and Commodity ClassificationsAaron Johnson
 
Fire water netowrk presentation
Fire water netowrk presentationFire water netowrk presentation
Fire water netowrk presentationakbar_ali
 
Introductory training on fire water pumping system
Introductory training  on fire water pumping systemIntroductory training  on fire water pumping system
Introductory training on fire water pumping systemSabrul Jamil
 
Fire Detection and Alarm Systems
Fire Detection and Alarm SystemsFire Detection and Alarm Systems
Fire Detection and Alarm SystemsJ.T.A.JONES
 
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016John Newquist
 

What's hot (20)

Fire Protection Training_QPS_26DEC20_Final.pptx
Fire Protection Training_QPS_26DEC20_Final.pptxFire Protection Training_QPS_26DEC20_Final.pptx
Fire Protection Training_QPS_26DEC20_Final.pptx
 
Inspection, Testing and Maintenance of fire pump
Inspection, Testing and Maintenance of fire pumpInspection, Testing and Maintenance of fire pump
Inspection, Testing and Maintenance of fire pump
 
Fire sprinkler systems
Fire sprinkler systemsFire sprinkler systems
Fire sprinkler systems
 
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptBASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
 
Everything about Elite Fire.
Everything about Elite Fire. Everything about Elite Fire.
Everything about Elite Fire.
 
fire protection
fire protectionfire protection
fire protection
 
Fire hydrant system
Fire hydrant systemFire hydrant system
Fire hydrant system
 
Fire protection system...
Fire protection system...Fire protection system...
Fire protection system...
 
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTFIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
 
Clean Agent & Inert Gas Fire Suppression
Clean Agent & Inert Gas Fire SuppressionClean Agent & Inert Gas Fire Suppression
Clean Agent & Inert Gas Fire Suppression
 
Fire Protection System Design
Fire Protection System DesignFire Protection System Design
Fire Protection System Design
 
Fire and safety equipment madh
Fire and safety equipment madhFire and safety equipment madh
Fire and safety equipment madh
 
Nfpa20 standard for the installation of stationary pumps for fire protection ...
Nfpa20 standard for the installation of stationary pumps for fire protection ...Nfpa20 standard for the installation of stationary pumps for fire protection ...
Nfpa20 standard for the installation of stationary pumps for fire protection ...
 
Basic Guide to NFPA 13 Occupancy and Commodity Classifications
Basic Guide to NFPA 13 Occupancy and Commodity ClassificationsBasic Guide to NFPA 13 Occupancy and Commodity Classifications
Basic Guide to NFPA 13 Occupancy and Commodity Classifications
 
Fire water netowrk presentation
Fire water netowrk presentationFire water netowrk presentation
Fire water netowrk presentation
 
Fire pumps in brief
Fire pumps in briefFire pumps in brief
Fire pumps in brief
 
Introductory training on fire water pumping system
Introductory training  on fire water pumping systemIntroductory training  on fire water pumping system
Introductory training on fire water pumping system
 
Fire Detection and Alarm Systems
Fire Detection and Alarm SystemsFire Detection and Alarm Systems
Fire Detection and Alarm Systems
 
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
 
Chapter 05
Chapter 05Chapter 05
Chapter 05
 

Similar to Design of Sprinkler System and CO2 Total Flooding System of Given Plan I Gaurav Singh Rajput

Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Nikhilesh Mane
 
DUCT FORMULA Design-2006.pptx
DUCT FORMULA Design-2006.pptxDUCT FORMULA Design-2006.pptx
DUCT FORMULA Design-2006.pptxPraveenMGowdru
 
final presentation edit.pptx
final presentation edit.pptxfinal presentation edit.pptx
final presentation edit.pptxssuser0ee912
 
anaesthesia machine-140810030802-pptx.pptx
anaesthesia machine-140810030802-pptx.pptxanaesthesia machine-140810030802-pptx.pptx
anaesthesia machine-140810030802-pptx.pptxRaj Kumar
 
Improvement of ventilation system in a mining site
Improvement of ventilation system in a mining siteImprovement of ventilation system in a mining site
Improvement of ventilation system in a mining sitesaadamatola
 
Effect of Arresters on Erosion in Economizer Zone and its Analysis
Effect of Arresters on Erosion in Economizer Zone and its AnalysisEffect of Arresters on Erosion in Economizer Zone and its Analysis
Effect of Arresters on Erosion in Economizer Zone and its AnalysisIDES Editor
 
Turbimax cus31 endress+hauser datasheet-turbidity sensor
Turbimax cus31 endress+hauser datasheet-turbidity sensorTurbimax cus31 endress+hauser datasheet-turbidity sensor
Turbimax cus31 endress+hauser datasheet-turbidity sensorENVIMART
 
Air-5 final - Copy.pptx
Air-5 final - Copy.pptxAir-5 final - Copy.pptx
Air-5 final - Copy.pptxdejene1234567
 
Water distribution system design report
Water distribution system design reportWater distribution system design report
Water distribution system design reportMuhammad Magsi
 
Design of sprinkler laterals, design of main line, selection of pumps,
Design of sprinkler laterals, design of main line,  selection of pumps,Design of sprinkler laterals, design of main line,  selection of pumps,
Design of sprinkler laterals, design of main line, selection of pumps,Suyog Khose
 
Flow through orifice meter
Flow through orifice meterFlow through orifice meter
Flow through orifice meterPulkit Shukla
 

Similar to Design of Sprinkler System and CO2 Total Flooding System of Given Plan I Gaurav Singh Rajput (20)

tushar is - 13488.pptx
tushar is - 13488.pptxtushar is - 13488.pptx
tushar is - 13488.pptx
 
Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)
 
Drainage design
Drainage designDrainage design
Drainage design
 
DUCT FORMULA Design-2006.pptx
DUCT FORMULA Design-2006.pptxDUCT FORMULA Design-2006.pptx
DUCT FORMULA Design-2006.pptx
 
Tp+manual
Tp+manualTp+manual
Tp+manual
 
final presentation edit.pptx
final presentation edit.pptxfinal presentation edit.pptx
final presentation edit.pptx
 
anaesthesia machine-140810030802-pptx.pptx
anaesthesia machine-140810030802-pptx.pptxanaesthesia machine-140810030802-pptx.pptx
anaesthesia machine-140810030802-pptx.pptx
 
Improvement of ventilation system in a mining site
Improvement of ventilation system in a mining siteImprovement of ventilation system in a mining site
Improvement of ventilation system in a mining site
 
Chapter4.pdf
Chapter4.pdfChapter4.pdf
Chapter4.pdf
 
Effect of Arresters on Erosion in Economizer Zone and its Analysis
Effect of Arresters on Erosion in Economizer Zone and its AnalysisEffect of Arresters on Erosion in Economizer Zone and its Analysis
Effect of Arresters on Erosion in Economizer Zone and its Analysis
 
Turbimax cus31 endress+hauser datasheet-turbidity sensor
Turbimax cus31 endress+hauser datasheet-turbidity sensorTurbimax cus31 endress+hauser datasheet-turbidity sensor
Turbimax cus31 endress+hauser datasheet-turbidity sensor
 
Steam Blow
Steam BlowSteam Blow
Steam Blow
 
Turbidity sensor-Turbimax CUS31
Turbidity sensor-Turbimax CUS31Turbidity sensor-Turbimax CUS31
Turbidity sensor-Turbimax CUS31
 
Air-5 final - Copy.pptx
Air-5 final - Copy.pptxAir-5 final - Copy.pptx
Air-5 final - Copy.pptx
 
Water distribution system design report
Water distribution system design reportWater distribution system design report
Water distribution system design report
 
Design of sprinkler laterals, design of main line, selection of pumps,
Design of sprinkler laterals, design of main line,  selection of pumps,Design of sprinkler laterals, design of main line,  selection of pumps,
Design of sprinkler laterals, design of main line, selection of pumps,
 
Process Piping.pdf
Process Piping.pdfProcess Piping.pdf
Process Piping.pdf
 
AMAN PPT 4985 Assignment-1.pptx
AMAN PPT 4985 Assignment-1.pptxAMAN PPT 4985 Assignment-1.pptx
AMAN PPT 4985 Assignment-1.pptx
 
Venturi
VenturiVenturi
Venturi
 
Flow through orifice meter
Flow through orifice meterFlow through orifice meter
Flow through orifice meter
 

More from Gaurav Singh Rajput

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputGaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputGaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputGaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Gaurav Singh Rajput
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputGaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputGaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputGaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputGaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputGaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputGaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputGaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...Gaurav Singh Rajput
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputGaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputGaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Gaurav Singh Rajput
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputGaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputGaurav Singh Rajput
 

More from Gaurav Singh Rajput (20)

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 

Design of Sprinkler System and CO2 Total Flooding System of Given Plan I Gaurav Singh Rajput

  • 1. Design of Sprinkler System and CO2 Total Flooding System of Given Plan Gaurav Singh Rajput B. Tech Safety & Fire Engineering, CUSAT Assistant Manager- HSEF, at NAYARA ENERGY LTD DEPARTMENT OF SAFETY AND FIRE & ENGINEERING SCHOOL OF ENGINEERING, CUSAT. NOVEMBER 2017
  • 2. 2 INDEX 1. Introduction …3 2. Sprinkler system design …5 3. CO2 Total flooding system design …9 4. Reference …13
  • 3. 3 This project includes two parts 1. Sprinkler System Design 2. CO2 Total Flooding System Design In sprinkler system design first given plan were studied and its area divided on the basic of hazardous classification of building as per NBC Part- 4 and number of sprinklers required in area were calculated. Then pressure and flow rate of water at externa inlet valve were calculated. Number of hangers, range pipe and distribution pipes were calculated. In CO2 Total Flooding System Design number of co2 cylinder required for the given compartment for total flooding system were calculated.
  • 5. 5 Occupancy type - Group E, Business building Area of compartment = 141.9 m2 Hazard classification - Moderate hazard Sprinkler type - standard Maximum spacing of sprinklers along range pipe and between adjustment rows For standard (sand D) - 4.0m Minimum spacing of sprinklers - 2m Distance between sprinklers and boundary For standard spacing = 0.5s Distance between range pipe and boundary - 0.5D Maximum area of coverage of a sprinkler Amax = 2m Range pipes are to be laid parallel to the side of compartment For standard spacing layout =6.6/4 =1.65 = 2(say) Spacing of range required = 6.6/2 =3.3m Providing a spacing of 3.6 m (D) with outer range pipes at 1.5m away from the wall (<0.5D) now, No of sprinklers along the range pipe = 21.5/4 =5.375 = 6(Say) Spacing of sprinklers along range pipe =21.5/6 =3.58 m Maximum spacing of sprinklers along the range pipe considering the average of single sprinklers =12/3.6= 3.33m
  • 6. 6 So, Proving a spacing of 3.2m (S) with extreme sprinkler at 1.5m away from the side wall (<0.5 s) So, Number of sprinklers in range pipe =7 Total number of sprinklers = 14 HYDRAULIC CALCULATION OF PRESSURE AND FLOW AT AMAO LOCATED AT THE MOST REMOTE AREA Pressure calculation between sprinkler 1 and top of riser: Sprin kler start node Sprin kler end node Descripti on Diamet er of pipe (mm) Length of pipe betwee n nodes (m) Pipe fittings and devices Equivalen t pipe length (mm) Pressure required at start node (bar) Water flow in sprinkler at start node (l/min) Friction loss per m length (bar/m) Static head loss (bar) Total pressure loss in pipe (bar) Total discharge just before the end node (l/min) 1 2 Most remotest sprinkler 25 3.2 Nil - 0.51 37.6 0.024 0 0.076 57.6 2 3 - 32 3.2 Nil - 0.58 61.24 0.008 0 0.026 118.8 3 4 - 32 3.2 Nil - 0.606 62.27 0.0084 0 0.0269 180.64 4 Top of riser - 50 1.6 Tee 2.91 0.6329 63.94 0.001 0 0.004 244.58 Design Density = 5 lpm/m2 Minimum discharge required for each sprinkler = 5*3.2*3.6 = 57.6 l/min Selecting 15mm nominal orifice size sprinkler with a k value of 80 Minimum pressure required at entry point of sprinkler = (57.6/80)2 =0.51 bar As per table 29 of IS 15105:2002 minimum pressure for moderate hazard is 0.35 bar <0.51 bar, hence ok
  • 7. 7 Pressure calculation between 7 and top of riser: Sprinkl er start node Sprinkl er end node Des cripti on Diamete r of pipe (mm) Length of pipe between nodes (m) Pipe fittings and devise s Equiv alent pipe lenth (m) Pressur e require at start node (bar) Water flow in sprinkler at start node (l/min) Frictio n loss per m length (bar/m ) Static head loss (bar) Total pressure loss in pipe (bar) Total discharge just before the end node (l/min) 7 6 - 32 3.2 Nil - 0.51 57.6 0.007 2 0 0.023 57.6 6 5 - 32 3.2 - - 0.53 58.24 0.007 4 0 0.0236 115.84 5 Top of riser - 50 1.6 - - 0.55 59.32 0.008 7 0 0.0139 175.16 Minimum pressure required at top of riser for sprinkler 1 to 4, Ph = 0.6329+0.004 = 0.6369 bar Water discharge to sprinkler 1 to 4 at top of riser, Qh = 244.58 l/min Minimum pressure required at top of riser for sprinkler 7 to 5 (Pl) = 0.55+0.0139 = 0.5639 bar Water discharge to sprinkler 7 to 5 at top of riser, (QL) =175.16 l/min Adjustment of water flow to sprinklers 6 and 7 due to pressure difference: Qad j= QL*√(𝑃h/PL) =175.16*√0.6369/0.5639 =186.15 l/min Total water flow required at top of riser to sprinkler to sprinkler 1 to 7=244.58+186.15 =430.73 l/min Pressure calculation between sprinklers top of riser to bottom of riser at next range pipe: Sprink ler start node Sprink ler end node Desc ripti on Diame ter of pipe (mm) Length of pipe between nodes (m) Pipe fittings and devises Equivale nt pipe length (m) Pressure require at start node (bar) Water flow in sprinkler at start node (l/min) Friction loss per m length (bar/m) Static head loss (bar) Total pressure loss in pipe (bar) Total discharge just before the end node (l/min) Top of riser Botto m of riser - 50 0.5 Tee 2.91 0.636 430.73 0.034 0.05 0.185 430.73 Botto Botto Dist 65 3.6 Nill 0 0.801 430.73 0.009 0 0.0324 430.73
  • 8. 8 m of riser to extre me range pipe m of next riser ribut ion pipe Adjustment of water flow to sprinklers 8 and 14 due to pressure difference: Pressure required at bottom of riser for sprinkler 1 to 7, Pi=0.636+0.165 =0.801 bar Water discharge to sprinkler 1 to 7 at bottom of riser , Qi =430.73 l/min Branch line K factor, Kbr = Qi/√ 𝑃𝑖 =430.73/√(0.801) = 481.27 Pressure required at bottom of next riser for sprinkler for sprinkler 8 to 14, P = 0.80+0.0324 =0.8334 bar Water discharge required to sprinkler 8 to 14 at bottom of riser Q= kbr*√ 𝑃 = 481.27*√0.8334 = 439.354 l/min Total discharge required at bottom of riser for sprinkler 1 to 14 =430.73+439.354 = 870.084 l/min Sprinkler start node Sprinkle r end node Desc riptio n Diame ter of pipe (mm) Length of pipe betwe en nodes (m) Pipe fittings & devise s Equivale nt pipe length (m) Pressure required at start node (bar) Water flow in sprinkler at start node (l/min) Friction loss per m length (bar/m) Static head loss (bar) Total pressure loss IN pipe (bar) Total discharge just before the end node (l/min) Bottom of riser 8 to 14 End of distribut ion pipe Distri butio n pipe 65 2 Tee 3.81 0.8334 870 0.035 0 0.07 870 End of distributi on pipe Top of alarm valve Main riser 100 8 Nill 0 0.9 870 0.0042 0.8 0.84 870 Top of alarm valve Bottom of control valve Contr ol valve 100 0.5 Alarm valve, gate valve 5.88 1.74 870 0.0042 0.05 0.076 870
  • 9. 9 We need 870 l/min water discharge with minimum pressure of 1.86 bar at the bottom of control valve to have the required discharge and pressure at AMAO. Hanger for sprinkler pipe: Distribution/range pipes should not be supported from celling sheathing or cladding or from any other associated suspended system systems. Hanger should not be welded or fastened directly to the pipe work. The supports on which the pipe work rests should be secured firmly in position. The thickness of all parts of pipe supports should not be less than 3mm. Whenever possible, pipes should be supported from non-combustible building elements. Pipe work in corrosive areas should be of either stainless steel or or suitably protected against corrosion. The distance between pipe supports measured along the line of connected pipes, shall not be less than • 4.0 m for pipe diameter up to 65mm • 6 m for pipe diameter from 65 to 100mm Distribution Pipes: 1. The first support on a normally horizontal distribution pipe shall not be more than 2m from the main distribution pipe; the last support shall not be more than 450 mm from the end 2. The drop of riser pipes shall be secured to the building structure either directly or indirectly at the adjacent nominally horizontal part of the pipe within 300 mm of the drop or riser. Range Pipe: 1. The first support on range pipe shall not be more than 2 m from the distribution pipe; the last support shall not be more than 1.5 m from the range pipe end. 2. At least one support shall be provided for each pipe run connecting adjacent sprinkler, and the pipe run connecting the distribution pipe and the first sprinkler on the range pipe. 3. Pipe support shall not be closer than 150 mm to any sprinkler axial central line.
  • 10. 10 DESIGNING CO2 TOTAL FLOODING SYSTEM FOR MARKET AREA IN GIVEN PLAN All doors and windows are closable during the application of the carbon dioxide. Volume of the whole compartment = 21.5*6.6*3.4 = 482.46 m3 Assume volume of pedestal = 100m3 Net volume of compartment, V= 482.46-100 = 382.46 m3 Minimum design concentration of CO2 required for the combustible material- Hydrocarbon (IS-15528, Table 3) = 75% Volume factor based on space to be protected and for a design concentration 34% (Table 3, IS-15526) =0.8 kg of CO2/m3 The basic concentration of CO2 required at 34% concentration
  • 11. 11 Qbasic = V*volume factor =382.46*0.8 Qbasic=305.96 kg Minimum concentration of CO2 required at 34% concentration, Qmin = 113.5 kg i.e, 305.6 > 113.5 So, the basic quantity of CO2 required at 34% concentration, Qbasic=305.96 kg. Basic quantity of CO2 required at 75% concentration, Q=Qbasic*(material conversion factor) =305.96*1.2 =367.15 kg Total amount of CO2 required =367.15kg Pressure inside cylinder =55 bar Density = Mass volume Volume = 367.15 1.98 = 185.42 m3 Now, P1V1 = P2V2 55*v1 = 1*185.42 V1=3.371m3 =3371.27L Assume one cylinder of capacity 80L. Number of cylinders = 3371.25 80 = 42.14 The filling ratio of co2 is 0.67 so, the number of cylinders required is 43 Number of total cylinders required = 43 We can store these cylinders in main bank, and same amount of co2 should be stored for standby. The minimum effective discharge time for use in calculating the quantity shall be 60 s.
  • 12. 12
  • 13. 13 REFERENCE 1. IS 15105: Design and Installation of Fixed Automatic Sprinkler Fire Extinguishing Systems--Code of Practice. 2. IS 15528: Gaseous Fire Extinguishing Systems— Carbon Dioxide Total Flooding and Local Application (Subfloor and In-Cabinet), High and Low Pressure (Refrigerated) Systems.