SlideShare a Scribd company logo
1 of 210
INSPECTION OF FIRE FIGHTING
EQUIPMENT, TOOLS, DEVICES,
VEHICLES & APPARATUS
(NFPA REGULATIONS)
Introduction to Fire Hazards and Fire
Risk Assessment
 Occidental's Piper Alpha platform was destroyed
by explosion and fire in 1988. 167 workers were
killed in the blaze.
 A support vessel collided with Mumbai High North in
2005, rupturing a riser and causing a major fire
that destroyed the platform.
 BP, Texas 2005
 The April 2010 BP “Deepwater Horizon” blow-out
disaster
Principles of fire and explosion
The fire triangle
Stages of combustion
Classifications of dangerous substances
Flammable & Combustible Substance
Flammable liquids
Combustible liquids
Fire growth rates
Examples
Fire
growth
rate
Category
Open plan office – with limited combustible
materials, stored or used
Slow
1
Warehouse – which is likely to have stacked
cardboard boxes, wooden pallets
Medium
2
Production unit/warehouse – baled thermoplastic
chips for packaging, stacked plasticproducts, baled
clothing awaiting delivery
Fast
3
Production unit/warehouse – flammable liquids,
expanded cellular plastics and foam
Manufacturing, processing, repairing, cleaning or
otherwise treating any hazardous goods or materials
Ultra-
fast
4
Factors affecting the growth rate
 Construction and layout of the building
 Ventilation into, throughout and out of the building
 Use of the building (including the types of activity
being undertaken)
 Fire loading within the building.
Types of fire accidents
Explosion
 An abrupt oxidation, or decomposition reaction,
that produces an increase in temperature, or
pressure, or in both temperature and pressure
simultaneously.
Explosive atmosphere
 flammable substances in the form of gases, vapors,
mists or dusts mixed with air under atmospheric
conditions, which, after ignition has occurred,
combustion spreads to the entire unburned mixture.
Deflagration
 Combustion wave propagating from an explosion
at subsonic velocity relative to the unburnt gas
immediately ahead of the flame (flame front).
Detonation
 A combustion wave propagating from an explosion
at supersonic velocity relative to the unburnt gas
immediately ahead of the flame (flame front).
BLEVE – boiling liquid expanding
vapor explosion
 An explosion due to the flashing of liquids when a
vessel with a high vapor pressure substance fails.
CGE – confined gas explosion
 Explosion within tanks, process equipment, sewage
systems, underground installations, closed rooms,
etc.
UVCE – Unconfined Vapor Cloud
Explosion
 A vapor/gas explosion (deflagration or
detonation) in an unconfined, unobstructed cloud.
The mechanism of explosion
 A dust explosion occurs when a combustible
material is dispersed within the air forming a
flammable cloud, this allows the flame to
propagate through it.
 A gas explosion follows a very similar principle
when gas and oxygen are premixed within
explosive limits
Explosive limits and the flammable/explosion
range
Deflagration, detonation and explosive
atmospheres
 When a cloud is ignited the flame can propagate
in two different modes through it. These modes are:
 ➤ Deflagration
 ➤ Detonation.
Lower explosion limit (LEL
 The minimum concentration of vapour in air below
which the propagation of flame will not occur in
the presence of an ignition source. Also referred to
as the lower flammable limit or the lower explosive
limit.
Upper explosion limit (UEL)
 The maximum concentration of vapor in air above
which the propagation of flame will not occur in
the presence of an ignition source. Also referred to
as the upper flammable limit or the upper
explosive limit.
Explosive conditions
 The types of materials that often cause dust
explosions include:
 ➤ Coal and peat
 ➤ Metals such as iron, zinc, aluminium
 ➤ Natural organic materials such as grain,
linen,sugar, etc.
 ➤ Processed materials such as plastics, organic
pigments (paint), pesticides, etc.
Creating an explosive atmosphere
 The presence of a flammable substance
 The degree of dispersion of the flammable
substance (this will vary dependent upon its state –
dusts, gases, vapours and mists)
 ➤The concentration of the flammable substance in
air within the explosive range
Confined explosion within a tank
Ignition sources
 Hot surfaces
 ➤ Naked fl ames and other hot gases
 ➤ Mechanically generated sparks
 ➤ Electrical equipment
 ➤ Static electricity
 ➤ Lightning
 ➤ Radio frequency (RF) – electromagnetic waves
 ➤ Ionising radiation.
unconfined vapor cloud
explosions,
Principles of explosion management
 Control
 Design and construction – equipment, protective
systems and system components
 Dilution by ventilation
 Mitigation (Explosion venting)
Plant layout and classification of
zones
Plant layout and classification of
zones
Fire hazard identification
 Combustion of Gases
 Explosive Risk
 Flammable Gas Risk
 Toxic Gas Risk
Fire Explosion Mitigation
 Passive fire protection (barriers and special
coatings)
 Containment and spill control
- Isolation valves
- Blowdown/ Depressurization
- fire divisions
- limiting and controlling spills and releases
 Water deluge and pray systems
 Water monitor system
Fire Explosion Mitigation
 Foam system
 Dry chemicals
 Water mist system
 Gas dispersion with water spray
 Portable firefighting equipment
- Extinguishers
- Hand hold nozzles
- Monitors/ Cameras
- breathing apparatus
Firefighting (FIFI) tugs
Alarm Levels
 Workers are often under risk of gas exposure in
situations where atmospheres cannot be controlled,
such as in confined space entry applications where
alarming at TWA values would be inappropriate.
Gas Detection Systems
 Catalytic gas detection
 Infra red gas detection
 Smoke detection
 Incipient fire detection
 Flame detection
Gas Detection Systems
 Fixed gas detectors can be positioned in strategic
zones, for example in confined spaces or ‘hot work’
areas
 Most gas detectors should be calibrated every six
months to ensure optimum operation. However, a
new range of IR (infrared) detectors allow users to
extend maintenance checks to once every 12 months
Future Trends
 It is likely that both portable and fixed hydrocarbon
gas detectors will use IR sensors rather than the
traditional catalytic bead (pellistor) sensors
currently used in most detectors.
 Sensor technologies such as PID (photo-ionisation)
are being used more commonly as requirements for
monitoring levels of VOCs (volatile organic
compounds) in industry increase.
Future Trends
 Optical sensing developments and solid-electrolyte
sensors will provide solutions in toxic gas and
oxygen sensing applications where traditional
electrochemical cells have operating limitations
 Fixed detection systems will also continue to utilize a
variety of technologies (such as point-type
detectors, open-path detectors, acoustic sensors and
even gas cameras) for the most comprehensive
coverage. Wireless connectivity will replace cables
in some applications.
The five steps of Fire and Explosion
Hazard Management FEHM
 Step 1: Reviewing fire and explosion scenarios that
can occur
 Step 2: Reviewing different policies to reduce fire
and explosion risk
 Step 3: Decide which policy is the most appropriate
 Step 4: Implement and maintain policy
 Step 5: Update policy according to change in
facilities or operating environment
Fire Risk Assessment Process
 Look for the hazards
 Decide who might be harmed and how
 Evaluate the risks and decide whether the existing
precautions are adequate or whether more should
be done
 Record your findings
 Review your assessment and revise if necessary.
Fire Risk Assessment Process
Gaseous Extinguishing Agent Systems
Gaseous Extinguishing Agent Systems
 A gas extinguishing system is a fire extinguishing
system that extinguishes fire with the help of a
gaseous extinguishing agent either through oxygen
displacement (reduction of oxygen content) or
physical effects (heat extraction).
 In contrast to a sprinkler system, a gas extinguishing
system is designed to extinguish and not only
suppress fire.
AREAS OF USE
 IT systems and computer rooms
 Archive rooms, document safes
 Emergency call centres, flight navigation and control towers,
mobile phone transmitter stations.
 Art galleries, libraries, film projector rooms, museums
 Medical sector: imaging systems, operating rooms, mobile
stations
 Industrial facilities such as laboratories, control rooms, offshore
drilling platforms, robotic equipment
 Emergency power generators, battery compartments, low-
voltage compartments, cable compartments, etc.
 Flight simulators, ships, military vehicles
EXTINGUISHING AGENT
Oxygen-displacing extinguishing gases - inert gases and
carbon dioxide (CO2)
 Carbon dioxide (CO2)
 Argon - IG-01
 Nitrogen - IG-100
 Argonite® - IG-55
 Inergen® - IG-541
Chemically-acting extinguishing gases
 Novec 1230 ® (Keton)
 FM 200 (HFC227ea)
 HFC-125
 FE-13
Dry Chemical Systems
NFPA 17
Introduction
 Dry chemical is an excellent extinguishing agent due
to its rapid flame suppressing capability on
hydrocarbon, three-dimensional and natural gas
pressure fires.
Applications for DC Units and
Systems
 Compressor Stations
 Oil and Gas Well Servicing
 Drilling Operations
 Off-Shore Platforms
 Fuel Loading Racks
 Storage Tank Vents
 Electrical Transformers
 Chemical and Petro-Chemical Plants
 Storage Facilities
 Airports and Heliports
 Manufacturing Facilities
DETERMINING REQUIREMENTS
 The first steps in determining the requirements for a
Dry Chemical System is to identify the hazard, size
of hazard and any conditions requiring special
consideration such as wind exposure or objects
blocking discharge of agent to the hazard.
COMMON TYPES OF FIRE HAZARDS
 Spill Fires
 Liquid in Depth
 Three Dimensional Fires
 Pressure Fires
 Class “A” Fires
TYPE OF EQUIPMENT AND
APPLICATION
 The type of system required (handline application, total
flooding, manual, semi automatic or full automatic) is
normally a judgment call based on the following:
 Is the facility manned full time?
 Are experienced fire-fighting personnel available at all
times?
 Visibility of hazard in the event of fire.
 Power source available for automatic system?
 Hazard to personnel that might be in area during?
 Discharge of equipment?
 Obstacles which would prevent extinguishment using
handlines.
When Hand line Protection is Used
 The unit must have the capacity to maintain flow
through the hand lines for a minimum of 30 seconds.
 A fixed system providing total flooding must
maintain flow for a minimum time of 30 seconds
Types of dry chemical powder
 PK Potassium Bicarbonate Based is a premium
powder suitable for use in high-risk areas
 BC Dry Chemical Powder Mixture of sodium
bicarbonate, silicates and stearates.
Data for dry chemical unit method of figuring
dry chemical agent requirements for specific
hazards
Unit Size Capacity (lbs.) BC Capacity (lbs.)
PK/ABC
Max Flow Rate
(lbs./sec.) BC
Max Flow Rate (lbs./sec.)
PK/ABC
DISCHARGE
OPENING Inch.
CDC200 230 200 7.5 6.5 1-1/2
CDC500 600 500 20 16 2
CDC1000 1200 1050 40 35 2-1/2
CDC1500 1550 1400 50 45 2-1/2
CDC2000 2100 1850 70 60 3
CDC2500 2600 2300 85 75 3
CDC3000 3000 2750 100 90 3
CDC3500 3500 3100 115 100 3
CDC4000 4000 3750 140 125 4
CDC4500 4500 4050 150 135 4
CDC5000 5000 4500 170 150 4
Dry Chemical Units System Performance On
Hydrocarbon Fires
NFPA 17 Requires minimum of discharge time
The types of hazards
 Flammable or combustible liquids
 Flammable or combustible gases
 Combustible solids including plastics, which melt when
involved in fire
 Electrical hazards such as oil-filled transformers or
circuit breakers
 Textile operations subject to flash surface fires
 Ordinary combustibles such as wood, paper, or cloth
 Restaurant and commercial hoods, ducts, and
associated cooking appliance hazards such as deep-fat
fryers
5.1.2 Limitations
DC extinguishing systems shall not be considered satisfactory
protection for the following:
 Chemicals containing their own oxygen supply, such as cellulose
nitrate
 Combustible metals such as sodium, potassium, magnesium,
titanium, and zirconium
 Deep-seated or burrowing fires in ordinary combustibles where
the dry chemical cannot reach the point of combustion
 Delicate electrical equipment
 The minimum temperature limitation shall be at most 32°F (0°C).
 The maximum temperature limitation shall be at least 120°F
(48.9°C)
Multiple Systems Protecting a
Common Hazard.
 two or more systems are used to protect a common
hazard, they shall be arranged for simultaneous
operation.
 Operation of a single actuator shall cause all
systems to operate.
Systems Protecting Two or More
Hazards.
 Where two or more hazards could be
simultaneously involved in fire by reason of their
proximity, the hazards shall be protected by either
of the following:
 (1) Individual systems installed to operate
simultaneously
 (2) A single system designed to protect all hazards
that could be simultaneously involved
Dry Chemical Requirements and
Distribution.
 The following factors shall be considered in
determining the amount of dry chemical required:
 (1) Minimum quantity of dry chemical
 (2) Minimum flow rate of dry chemical
 (3) Nozzle placement limitations, including spacing,
distribution, and obstructions
 (4) High ventilation rates, if applicable
 (5) Prevailing wind conditions, if applicable
5.5 Special Considerations
 Ensuring shutoff of power and fuel valves upon
operation of the extinguishing systems.
 Conveyors moving flammable or combustible materials
or commodities, shall be automatically shut off upon
operation of the extinguishing systems.
 All shutoff systems shall be fail-safe.
 All shutoff systems shall require manual resetting prior
to restoration of the operating conditions existing
before operation of the extinguishing systems.
 All shutoff devices shall function with the system
operation
5.6* Personnel Safety
 (1) Personnel training
 (2) Warning signs
 (3) Predischarge alarms
 (4) Discharge alarms
 (5) Respiratory protection
5.6.2 Electrical Clearances
 The following references shall be considered as the
minimum electrical clearance requirements for the
installation of dry chemical systems:
 (1) ANSI C-2, National Electrical Safety Code
 (2) NFPA 70, National Electrical Code
 (3) 29 CFR 1910 S
5.7* Operation and Control of
Systems
5.7.1 Methods of Actuation
 Systems shall be provided with both automatic and
manual independent means of operation
 All operating devices shall be designed, located,
installed, or protected so that they are not subject
to mechanical, environmental, or other conditions
that could render them inoperative
 the manual actuation device shall be installed no
more than 48 in. and no less than 42 in. above the
floor.
5.7.3* Notification
 An audible or visual indicator shall be provided to
show that the system has operated, that personnel
response might be needed, and that the system is in
need of recharge.
Connection to the Alarm System
 The extinguishing system shall be connected to the
fire alarm system, if provided, in accordance with
the requirements of NFPA 72
Piping & Nozzles
 For engineered systems, pipe sizes and nozzles shall be
selected, on the basis of calculations, to deliver the
required dry chemical flow rate at each nozzle.
 For pre-engineered systems, pipe sizes and nozzles
shall be selected in accordance with the manufacturer’s
listed installation and maintenance manual
 All discharge nozzles shall be designed and
subsequently located, installed, and protected so that
they are not subject to mechanical, environmental, or
other conditions that could render them inoperative.
Hand Hose Line Systems
 Dry chemical hand hose line systems shall be
provided with turrets, skid-mounted hose reels,
remote hose reels, or combinations thereof.
 If multiple cylinders are used to pressurize the dry
chemical agent containers, each cylinder shall be
provided with a pressure gauge and a manual
means of operation.
System Operational Tests
 System operational tests shall be performed in
accordance with the manufacturer’s design,
installation, and maintenance manual and shall
include functional tests of the automatic detection
system, the manual release devices, and
shutdown devices, where provided.
 The installing contractor shall complete and sign an
acceptance test report acceptable to the authority
having jurisdiction.
Inspection, Maintenance, and
Recharging
 Storage shall be in a constantly dry area, and the
dry chemical shall be contained in metal drums .
 A service technician who performs maintenance on
an extinguishing system shall be certified after
passing a written test.
 A service technician shall service the dry chemical
fire-extinguishing system at intervals no more than 6
months apart
Recharge Agents
 Dry chemical provided for the system shall be
listed for the system.
 Expellant gas for stored pressure cylinders shall be
standard industrial-grade nitrogen with a dew point
of −60°F (−51°C) or lower (CGA nitrogen
specification G10.1).
 Where carbon dioxide or nitrogen is used as the
expellant gas, it shall be of good commercial grade
and free of water and other contaminants that
might cause container corrosion.
Owner’s Inspection
 On a monthly basis, inspection shall be conducted in
accordance with the manufacturer’s design, installation,
and maintenance manual or the owner’s manual.
 As a minimum, inspection shall include verification of the
following:
 (1) The extinguishing system is in its proper location. (2)
The manual actuators are unobstructed.
 (3) The tamper indicators and seals are intact.
 (4) The maintenance tag or certificate is in place.
 (5) The system shows no physical damage or condition
that might prevent operation.
Owner’s Inspection
 (6) The pressure gauge(s), if provided, is inspected
physically or electrically to ensure it is in the operable
range.
 (7) The nozzle blowoff caps, where provided, are intact and
undamaged.
 (8) Neither the protected equipment nor the hazard has
been replaced, modified, or relocated.
 Personnel making inspections shall keep records for those
extinguishing systems that were found to require corrective
actions.
 The records shall be retained until the next semiannual
maintenance.
Maintenance
 At least semiannually and after any system activation, maintenance
shall be conducted in accordance with the manufacturer’s design,
installation, and maintenance manual.
 As a minimum, such maintenance shall include thefollowing:
 (1) A check to see that the hazard has not changed
 (2) An examination of all detectors, expellant gas container( s),
agent container(s), releasing devices, piping, hose assemblies,
nozzles, signals, and all auxiliary equipment
 (3)*Verification that the agent distribution piping is not obstructed
 (4) Examination of the dry chemical (If there is evidence of caking,
the dry chemical shall be discarded and the system shall be
recharged in accordance with the manufacturer’s instructions.)
Maintenance
 Dry chemical in stored pressure systems shall not require
semiannual examination but shall be examined at least
every 6 years.
 Dry chemical containers that pass the applicable 6-year
requirement of 11.3.1.2 shall have the maintenance
information recorded on a durable weatherproof label that
is a minimum size of 2 in. × 31⁄2 in. (51 mm × 89 mm)
 The label shall include the following information:
 (1) Month and year the maintenance was performed,
indicated by a perforation such as done by a hand punch
 (2) Name or initials of the person performing the
maintenance and the name of the agency performing the
maintenance
Maintenance
 Each system container that has undergone maintenance
that includes internal examination or has been
recharged shall have a verification-of-service collar
located around the neck of the container.
 The collar shall include the following information:
 (1) Month and year the service was performed,
indicated by a perforation such as done by a hand
 punch
 (2) Name of the agency performing the maintenance or
recharge
Maintenance
 Where maintenance of any dry chemical containers
or any system components reveals conditions such
as, but not limited to, corrosion or pitting in excess
of the manufacturer’s limits; structural damage; fire
damage; or repairs by soldering, welding, or
brazing, the affected container shall be replaced or
hydrostatically
 Until such repairs are accomplished, the system(s)
shall be tagged as noncompliant, and after repair
parties shall be informed.
Maintenance
 Pressure regulators shall be operationally checked at
least annually.
 Defective regulator(s) shall not be adjusted but shall be
replaced
 The maintenance report, including any
recommendations, shall be filed with the owner or with
the owner’s representative.
 The owner or owner’s representative shall retain all
maintenance reports for a period of 1 year after the
next maintenance of that type required by this
standard.
Maintenance
 Fixed temperature-sensing elements of the fusible
metal alloy type shall be replaced at least
semiannually from the date of installation.
 Heat detectors other than metal alloy–type fusible
links shall be permitted to remain continuously in
service, provided they are inspected, cleaned, and
tested,
Recharging
 All extinguishing systems shall be recharged after use
or as indicated by an inspection or a maintenance check
in accordance with the manufacturer’s design,
installation, and maintenance manual.
 The following parts of dry chemical extinguishing
systems shall be subjected to a hydrostatic pressure test
at intervals not exceeding 12 years:
 (1) Dry chemical containers
 (2) Auxiliary pressure containers
 (3) Hose assemblies
Recharging
 No leakage, rupture, or movement of hose couplings
shall be permitted.
 The pressure in a hydrostatic test of a cylinder shall
be maintained for a minimum of 30 seconds but for
no less time than is required for complete expansion
of the cylinder and to complete the visual
examination of the cylinder.
Firewater Systems
General Requirements
 The building owner shall ensure that all areas of the
building containing water-filled piping shall be
maintained at a minimum temperature of 40°F (4.4°C)
and not exposed to freezing conditions.
 Inspection, testing, and maintenance shall be performed
by personnel who have developed competence through
training and experience.
 Accessibility..
 Notification of System Shutdown.
 Changes in Occupancy, Use, Process, or Materials.
Re-evaluation
 (1) Occupancy changes such as converting office or
production space into warehousing
 (2) Process or material changes such as metal
stamping to molded plastics
 (3) Building revisions such as relocated walls, added
mezzanines, and ceilings added below sprinklers
 (4) Removal of heating systems in spaces with
piping subject to freezing
Addressing Changes in Hazard
 In case of any change, the owner or his
representative shall promptly take steps to evaluate
the adequacy of the installed system in order to
protect the building or hazard in question.
 Corrections shall be approved
Valve Location.
 The location of shutoff valves shall be identified.
Information Sign.
 The sign shall indicate at least the following
information:
 (1) Location of the area served by the system
 (2) Location of auxiliary drains and low-point drains
for dry pipe and preaction systems
 (3) The presence and location of antifreeze or other
auxiliary systems
 (4) The presence and location(s) of heat tape
Records
 Records shall indicate the procedure performed
(e.g., inspection, test, or maintenance), the
organization that performed the work, the results,
and the date.
 Records shall be maintained by the property owner.
Testing
 All components and systems shall be tested to verify
that they function as intended.
 Test results shall be compared with those of the
original acceptance test (if available) and with the
most recent test results.
Foam System
System Components and System
Types
 All components shall be listed for their intended use.
Water Supplies
 Quality & Quantity
 Pressure.(the minimum pressure for which the
system has been designed)
 Temperature (water at temperatures between 4°C
(40°F) and 37.8°C (100°F).
 Design. The water system shall be designed and
installed in accordance with NFPA 24.
 Storage Water supply or premixed solution shall be
protected against freezing
Water and Foam Concentrate Pumps.
 When water or foam concentrate pumps are
required for automatic foam system operation, they
shall be designed and installed in accordance with
NFPA 20.
 Controllers in accordance with NFPA 20 shall not be
required for manual systems.
Foam Concentrates
 Foam concentrate shall be listed and be one of the
following types:
 1. Protein
 2. Fluoroprotein
 3. Aqueous film-forming foam (AFFF)
 4. Film-forming fluoroprotein (FFFP)
 5. Alcohol-resistant
 6. High-expansion
 7. Medium-expansion
 8. Others listed for this purpose
Concentrate Storage.
 shall be stored in a location not exposed to the
hazard they protect and in a noncombustible
structure.
 Bulk liquid storage tanks shall be fabricated from or
be lined with materials compatible with the
concentrate.
 The storage tank shall be designed to minimize
evaporation of foam concentrate.
Foam Proportioning
 The method of foam proportioning shall conform to one
of the following:
 1. Self-educting nozzle
 2. In-line eductor
 3. Pressure proportioners (with or without bladder)
 4. Around-the-pump proportioners
 5. Direct injection variable output foam pump system
 6. Coupled-water motor pump
 7. Balanced pressure pump-type proportioners
Foam Concentrate Pumps.
 The design and materials of construction for foam
concentrate pumps shall be in accordance with
NFPA 20.
Piping.
 Pipe Materials. Pipe within the hazard area shall be of
steel or other alloy rated for the pressure and
temperature involved.
 Shall conform to one of the following standards:
 1. ASTM (American Society for Testing Matwerial) A
135
 2. ASTM A 53
 3. ASTM A 795
 Galvanized pipe shall be used for noncorrosive
atmospheres.
Fittings.
 All pipe fittings shall be in accordance with one of the
 following:
 (1) ANSI B16.1
 (2) ANSI B16.3
 (3) ANSI B16.4
 (4) ANSI B16.5
 (5) ANSI B16.9
 (6) ANSI B16.11
 (7) ANSI B16.25
 (8) ASTM A 234
Valves.
 All valves shall be of the indicator type, such as OS&Y
or post indicator.
 Inside the hazard or diked area, automatic control
valves and shutoff valves shall be of steel or other alloy
capable of withstanding exposure to fire temperatures.
 All valves required for automatic foam systems shall be
supervised in their normal operating position by one of
the following methods:
 (1) Electrical, in accordance with NFPA 72
 (2) Locked
 (3) Sealed
System Types
 The following four types of systems shall be
 permitted:
 (1) Fixed
 (2) Semifixed
 (3) Mobile
 (4) Portable
Operation and Control of Systems
 Systems shall be permitted to be actuated
automatically or manually.
 All systems shall have provisions for manual
actuation.
Low-Expansion System Design
 Types of Hazards. (protect outdoor storage tanks,
interior flammable liquid hazards, loading racks,
diked areas, and nondiked spill areas)
Outdoor Fixed Roof (Cone) Tanks.
 The following methods for protecting exterior fixed-
roof tanks shall be included within this section:
 (1) Foam monitors and handlines
 (2) Surface application with fixed foam discharge
outlets
 (3) Subsurface application
 (4) Semisubsurface injection methods
Foam Handline and Monitor Protection for
Fixed-Roof Storage Tanks Containing
Hydrocarbons
Number of Fixed Foam Discharge Outlets for
Fixed-Roof Tanks Containing Hydrocarbons or
Flammable and Combustible Liquids Requiring
Alcohol-Resistant Foams
Minimum Discharge Times and Application
Rate for Type I and Type II Fixed Foam
Discharge Outlets on Fixed-Roof (Cone)
Storage Tanks Containing Hydrocarbons
Application Rate and Discharge Times for
Fixed-Roof (Cone) Tanks Containing
Flammable and Combustible Liquids Requiring
Alcohol-Resistant Foams
Minimum Number of Subsurface Foam
Discharge Outlets for Fixed-Roof
Minimum Discharge Times and Application
Rates for Subsurface Application on Fixed-
Roof Storage Tanks
Medium- and High-Expansion
Systems
Hazards Protected
 (1) Ordinary combustibles
 (2) Flammable and combustible liquids
 (3) Combinations of (1) and (2)
 (4) Liquefied natural gas (high-expansion foam
only)
Medium- and high-expansion foam
systems
 Medium- and high-expansion foam systems shall not be used
on fires in the following hazards:
 (1) Chemicals, such as cellulose nitrate, that release sufficient
oxygen or other oxidizing agents to sustain combustion
 (2) Energized unenclosed electrical equipment
 (3) Water-reactive metals such as sodium, potassium, and
NaK (sodium-potassium alloys)
 (4) Hazardous water-reactive materials, such as triethyl
aluminum and phosphorus pentoxide
 (5) Liquefied flammable gas
 (6) Hazards listed in (1)–(5) where competent evaluation,
including tests, indicates acceptability
Types of Systems
 (1) Total flooding systems
 (2) Local application systems
 (3) Portable foam-generating devices
Electrical Clearances.
Operation and Control of Systems
 Detection of Fires
 Supervision
 Alarms (operation – failure )
 Operating Devices (power - foam generators, valves,
proportioners, eductors, discharge controls, and shutdown
equipment)
 window closers, vent openers, and electrical equipment
shutdown devices shall be considered integral parts of the
system and shall function simultaneously with the system
operation.
 All manual operating devices shall be identified with signs
as to the hazards they protect.
Foam-Generating Apparatus Location
 Foam generating apparatus shall be located and
arranged so that inspection, testing, recharging, and
other maintenance is facilitated and interruption of
protection is held to a minimum.
Ducts.
 Ducts shall be protected from undue mechanical,
chemical, or other damage.
Total Flooding Systems General
Information
 A total flooding system shall consist of fixed foam-
generating apparatus complete with a piped
supply of foam concentrate and water, arranged to
discharge into an enclosed space or enclosure
around the hazard
Inspection and Visual Examination
 Foam systems shall be examined visually to
determine that they have been properly installed.
 Foam systems shall be inspected for such items as
conformity with installation plans; continuity of
piping; removal of temporary blinds; accessibility
of valves, controls, and gauges; and proper
installation of vapor seals, where applicable.
Flushing after Installation
 The water supply mains shall be flushed thoroughly
at the maximum practicable rate of flow before
connection is made to system piping.
Pressure Tests
 All piping shall be subjected to a 2-hour hydrostatic
pressure gauge test at 1379 kPa (200 psi) or 345
kPa (50 psi) in excess of the maximum pressure
anticipated, whichever is greater, in accordance
with NFPA 13.
Operating Tests
 Tests for total flooding systems shall establish that
all automatic closing devices for doors, windows,
and conveyor openings, and automatic equipment
interlocks, as well as automatic opening of heat and
smoke vents or ventilators, will function upon system
operation.
Discharge Tests
 The following data shall be required:
 (1) Static water pressure
 (2) Residual water pressure at the control valve and at
a remote reference point in the system
 (3) Actual discharge rate
 (4) Consumption rate of foam-producing material
 (5) Concentration of the foam solution
 (6) Foam quality (expansion and one-quarter drain
time) or foam discharge shall be conducted, or the foam
discharge shall be visually inspected to ensure that it is
satisfactory for the purpose intended.
Periodic Inspection
 At least annually, all foam systems shall be
thoroughly inspected and checked for correct
operation.
 inspection report, with recommendations, shall be
filed with the owner.
Water Spray Fixed Systems
NFPA 25
 This chapter shall provide the minimum requirements
for the routine inspection, testing, and maintenance
of water spray protection from fixed nozzle systems
only.
Summary of Water Spray Fixed System
Inspection, Testing, and Maintenance
Summary of Water Spray Fixed System
Inspection, Testing, and Maintenance
Summary of Water Spray Fixed System
Inspection, Testing, and Maintenance
Inspection and Maintenance
Procedures
 Items in areas that are inaccessible for safety
considerations due to factors such as continuous process
operations and energized electrical equipment shall be
inspected during each scheduled shutdown but not more
than every 18 months.
 Nozzle strainers shall be removed, inspected, and
cleaned during the flushing procedure for the mainline
strainer.
 Mainline strainers shall be removed and inspected
every 5 years for damaged and corroded parts.
Automatic Detection Equipment
 Automatic detection equipment shall be inspected,
tested, and maintained in accordance with NFPA
72, National Fire Alarm and Signaling Code.
System Components
 System piping, fittings, hangers, and supports shall
be inspected and maintained to ensure continuity of
water delivery to the spray nozzles at full
waterflow and design pressure.
Piping and Fittings
 System piping and fittings shall be inspected for the
following:
 (1) Mechanical damage (e.g., broken piping or
cracked fittings)
 (2) External conditions (e.g., missing or damaged
paint or coatings, rust, and corrosion)
 (3) Misalignment or trapped sections
 (4) Low-point drains (automatic or manual)
 (5) Location of rubber-gasketed fittings
Hangers and Supports
 Hangers and supports shall be inspected for the
following and repaired or replaced as necessary:
 (1) Condition (e.g., missing or damaged paint or
coating, rust, and corrosion)
 (2) Secure attachment to structural supports and
piping
 (3) Damaged or missing hangers
Water Spray Nozzles
 Water spray nozzles shall be inspected and
maintained to ensure that they are in place, continue
to be aimed or pointed in the direction intended in
the system design, and are free from external
loading and corrosion.
Water Supply
 The dependability of the water supply shall be
ensured by regular inspection and maintenance,
whether furnished by a municipal source, on-site
storage tanks, a fire pump, or private underground
piping systems.
 Water supply piping shall be maintained free of
internal obstructions.
Strainers
 Mainline strainers (basket or screen) shall be flushed
until clear after each operation or flow test.
 Individual water spray nozzle strainers shall be
removed, cleaned, and inspected after each
operation or flow test.
 Damaged or corroded parts shall be replaced or
repaired
Drainage
 The area beneath and surrounding a water spray
fixed system shall be inspected visually on a
quarterly basis to ensure that drainage facilities,
such as trap sumps and drainage trenches, are not
blocked and retention embankments or dikes are in
good repair.
Test Preparation
 Precautions shall be taken to prevent damage to
property during the test.
 Operational tests shall be conducted to ensure that the
water spray fixed systems respond as designed, both
automatically and manually.
 Under test conditions, the heat detection systems, where
exposed to a heat test source, shall operate within 40
seconds.
 These response times shall be recorded
 The time lapse between operation of detection systems
and water delivery time to the protected area shall be
recorded.
Pressure Readings
 Pressure readings shall be recorded at the
hydraulically most remote nozzle to ensure the
water flow has not been impeded by partially
closed valves or by plugged strainers or piping.
Multiple Systems
 The maximum number of systems expected to
operate in case of fire shall be tested
simultaneously to check the adequacy of the water
supply.
 After the full flow test, the water spray system shall
be maintained and returned to service
Main Drain Tests
 Main drain tests shall be conducted at the main riser
to determine whether there has been any change in
the condition of the water supply piping and
controlling valves.
 Static and residual water pressures shall be
recorded respectively before, during, and after the
operation of the fully opened drain valve.
Ultra-High-Speed Water Spray System
(UHSWSS) Operational Tests.
 full operational test, including measurements of
response time, shall be conducted at intervals not
exceeding 1 year.
 Systems out of service shall be tested before being
placed back in service.
Summary of Component
Replacement Action Requirements
Sprinkler Systems
Summary of Sprinkler System
Inspection, Testing, and Maintenance
Inspection, Sprinklers
 Any sprinkler that shows signs of any of the following shall
be replaced:
 (1) Leakage
 (2) Corrosion
 (3) Physical damage
 (4) Loss of fluid in the glass bulb heat responsive element
 (5)*Loading
 (6) Painting unless painted by the sprinkler manufacturer
 Sprinklers installed in areas that are inaccessible for safety
considerations due to process operations shall be inspected
during each scheduled shutdown.
Pipe and Fittings
 Sprinkler pipe and fittings shall be inspected
annually from the floor level.
 Pipe and fittings shall be in good condition and free
of mechanical damage, leakage, and corrosion.
 Sprinkler pipe hangers and seismic braces shall be
inspected annually from the floor level
Gauges
 Gauges on wet pipe sprinkler systems shall be inspected monthly to
ensure that they are in good condition and that normal water supply
pressure is being maintained.
 Gauges on dry, preaction, and deluge systems shall be inspected
weekly to ensure that normal air and water pressures are being
maintained.
 Where air pressure supervision is connected to a constantly
attended location, gauges shall be inspected monthly.
 For dry pipe or preaction systems protecting freezers with two air
pressure gauges on the air line(s) between the compressor and the
dry pipe or preaction valve, the air pressure gauge near the
compressor shall be compared weekly to the pressure gauge above
the dry pipe or preaction valve.
Water flow Alarm and Supervisory
Devices
 Water flow alarm and supervisory alarm devices
shall be inspected quarterly to verify that they are
free of physical damage.
Hydraulic Design Information Sign
 The hydraulic design information sign for
hydraulically designed systems shall be inspected
quarterly to verify that it is attached securely to the
sprinkler riser and is legible.
Testing, sprinklers
 Where required by this section, sample sprinklers (not
less than four sprinklers )shall be submitted to a
recognized testing laboratory acceptable to the
authority having jurisdiction for field service testing.
 Where sprinklers have been in service for 50 years,
they shall be replaced or representative samples from
one or more sample areas shall be tested.
 Test procedures shall be repeated at 10-year intervals.
 Sprinklers manufactured prior to 1920 shall be
replaced.
Testing, sprinklers
 Sprinklers manufactured using fast-response
elements that have been in service for 20 years
shall be replaced, or representative samples shall
be tested and then retested at 10-year intervals.
 Representative samples of solder-type sprinklers
with a temperature classification of extra high
[325°F (163°C)] or greater that are exposed to
semi-continuous to continuous maximum allowable
ambient temperature conditions shall be tested at
5-year intervals.
Testing, sprinklers
 Dry sprinklers that have been in service for 10
years shall be replaced or representative samples
shall be tested and then retested at 10-year
intervals.
 Where sprinklers are subjected to harsh
environments, including corrosive atmospheres and
corrosive water supplies, on a 5-year basis, either
sprinklers shall be replaced or representative
sprinkler samples shall be tested.
Testing, gauges
 Gauges shall be replaced every 5 years or tested
every 5 years by comparison with a calibrated
gauge.
 Gauges not accurate to within 3 percent of the full
scale shall be recalibrated or replaced.
Water flow Alarm Devices
 Mechanical water-flow alarm devices including, but
not limited to, water motor gongs, shall be tested
quarterly.
 Vane-type and pressure switch–type water flow
alarm devices shall be tested semiannually.
 Testing water flow alarm devices on dry pipe,
preaction, or deluge systems shall be accomplished
by using the bypass connection.
Maintenance, sprinklers
 Replacement sprinklers shall have the proper
characteristics for the application intended, which
include the following:
 (1) Style
 (2) Orifice size and K-factor
 (3) Temperature rating
 (4) Coating, if any
 (5) Deflector type (e.g., upright, pendent, sidewall)
 (6) Design requirements
Maintenance, sprinklers
 A supply of spare sprinklers (never fewer than six)
shall be maintained on the premises so that any
sprinklers that have operated or been damaged in
any way can be promptly replaced.
 The sprinklers shall be kept in a cabinet located
where the temperature in which they are subjected
will at no time exceed 100°F (38°C).
Antifreeze Solutions to Be Used If Non-potable
Water Is Connected to Sprinklers
Antifreeze Solutions to Be Used If Potable
Water Is Connected to Sprinklers
Summary of Component
Replacement Action Requirements
Standpipe and Hose Systems
Minimum Requirements
 inspection, testing, and maintenance of all classes of
standpipe and hose systems shall follow Table
6.1.1.2
 Obstruction Investigations
 Notification to Supervisory Service
Inspection.
 Components of standpipe and hose systems shall be
visually inspected annually or as specified in Table
6.1.1.2.
Summary of Standpipe and Hose Systems
Inspection, Testing, and Maintenance
Standpipe and Hose Systems
Standpipe and Hose Systems
Gauges
 1 Gauges on automatic standpipe systems shall
be inspected monthly to ensure that they are in
good condition and that normal water supply
pressure is being maintained.
 Gauges on dry, preaction, and deluge valves shall
be inspected weekly to ensure that normal air and
water pressure are being maintained.
 Where air pressure supervision is connected to a
constantly attended location, gauges shall be
inspected monthly.
Hydraulic Design Information Sign.
 When provided, the hydraulic design information
sign for standpipe systems shall be inspected
annually to verify that it is attached securely and is
legible.
Testing
 A flow test shall be conducted every 5 years at the
hydraulically most remote hose connections of each
zone of an automatic standpipe system to verify the
water supply still provides the design pressure at
the required flow.
 All systems shall be flow tested and pressure tested
at the requirements for the design criteria in effect
at the time of the installation.
Hydrostatic Tests.
 Hydrostatic tests of not less than 200 psi (13.8 bar)
pressure for 2 hours, or at 50 psi (3.4 bar) in excess
of the maximum pressure, where maximum pressure
is in excess of 150 psi (10.3 bar), shall be
conducted every 5 years on manual standpipe
systems and semi-automatic dry standpipe systems,
including piping in the fire department connection.
Gauges.
 Gauges shall be replaced every 5 years or tested
every 5 years by comparison with a calibrated
gauge.
 Gauges not accurate to within 3 percent of the full
scale shall be recalibrated or replaced.
Maintenance
 Maintenance and repairs shall be in accordance
with 6.1.3 and Table 6.1.2.
 Equipment that does not pass the inspection or
testing requirements shall be repaired and tested
again or replaced.
Summary of Component
Replacement Action Requirements
Foam-Water Sprinkler Systems
Summary of Foam-Water Sprinkler System
Inspection, Testing, and Maintenance
Summary of Foam-Water Sprinkler System
Inspection, Testing, and Maintenance
Summary of Foam-Water Sprinkler System
Inspection, Testing, and Maintenance
Summary of Component
Replacement Action Requirements
Summary of Component
Replacement Action Requirements
Water Mist Systems
Maintenance of Water Mist Systems
Maintenance of Water Mist Systems
Maintenance of Water Mist Systems
Maintenance of Water Mist Systems
Maintenance of Water Mist Systems
High Pressure Cylinders
 High pressure cylinders used in water mist systems
shall not be recharged without a hydrostatic test
(and remarking) if more than 5 years have elapsed
from the date of the last test.
 Cylinders that have been in continuous service
without discharging shall be permitted to be
retained in service for a maximum of 12 years,
after which they shall be discharged and retested
before being returned to service.
Maintenance
 Mechanical waterflow devices, including but not
limited to water motor gongs, shall be tested
quarterly.
 Vane-type and pressure switch–type waterflow
devices shall be tested semiannually.
 Preventive maintenance includes, but is not limited
to, lubricating control valve stems, adjusting packing
glands on valves and pumps, bleeding moisture and
condensation from air compressors and air lines,
and cleaning strainers.
Maintenance Frequencies
Item Activity Frequency
Water tank
system
Strainers and
filters
Drain and refill
Flushing
Clean or replace
as required
Annually
Annually
After system
operation
Maintenance
 Spare components shall be accessible and shall be
stored in a manner to prevent damage or
contamination.
 After each system operation, a representative
sample of operated water mist nozzles in the
activated zone shall be inspected. [750:13.3.10]
 After each system operation due to fire, the system
filters and strainers shall be cleaned or replaced.
Training.
 All persons who might be expected to inspect, test,
maintain, or operate water mist systems shall be
trained thoroughly in the functions they are
expected to perform.
 Refresher training shall be provided as
recommended by the manufacturer or by the
authority having jurisdiction.
Fire Pump Systems
Alternative Fire Pump Inspection,
Testing, and Maintenance Procedures
Auxiliary Equipment
 The pump assembly auxiliary equipment shall include the following:
(1) Pump accessories as follows:
(a) Pump shaft coupling
(b) Automatic air release valve
(c) Pressure gauges
(d) Circulation relief valve (not used in conjunction with diesel engine drive with
heat exchanger)
(2) Pump test device(s)
(3) Pump relief valve and piping (where maximum pump discharge pressure
exceeds the rating of the system components or the driver is of variable
speed)
(4) Alarm sensors and indicators
(5) Right-angle gear sets (for engine-driven vertical shaft turbine pumps)
(6) Pressure maintenance (jockey) pump and accessories
Auxiliary Equipment
Summary of Fire Pump Inspection,
Testing, and Maintenance
Inspection
 The purpose of inspection shall be to verify that the
pump assembly appears to be in operating
condition and is free from physical damage.
 The pertinent visual observations specified in the
following checklists shall be performed weekly
(page 127)
Testing
 Diesel engine–driven fire pumps shall be operated
weekly.
 Electric motor–driven fire pumps shall be operated
monthly.
Testing, No-Flow Condition
 A test of fire pump assemblies shall be conducted without
flowing water.
 The test shall be conducted by starting the pump
automatically.
 The electric pump shall run a minimum of 10 minutes.
 The diesel pump shall run a minimum of 30 minutes.
 A valve installed to open as a safety feature shall be
permitted to discharge water.
 An automatic timer shall be permitted to be substituted for
the starting procedure.
 Qualified operating personnel shall be in attendance
whenever the pump is in operation.
The pertinent visual observations or
adjustments checklist
 Page 128
Annual Flow Testing
 An annual test of each pump assembly shall be
conducted by qualified personnel under minimum,
rated, and peak flows of the fire pump by
controlling the quantity of water discharged through
approved test devices.
 If available suction supplies do not allow flowing of
150 percent of the rated pump
Use of Pump Discharge via Bypass Flowmeter
to Pump Suction (Closed-Loop Metering).
 Pump suction and discharge pressures and the flow
meter measurements shall determine the total pump
output.
 The pertinent visual observations, measurements,
and adjustments specified in the following checklists
shall be conducted annually while the pump is
running and flowing water under the specified
output condition: Page 129
Summary of Component
Replacement Testing Requirements
Summary of Component
Replacement Testing Requirements
Summary of Component
Replacement Testing Requirements
Summary of Component
Replacement Testing Requirements

More Related Content

What's hot

National fire service day 14 th april
National fire service day   14 th aprilNational fire service day   14 th april
National fire service day 14 th april
Nalin Chaudhary
 
Safeworkpmits
SafeworkpmitsSafeworkpmits
Safeworkpmits
istrain
 

What's hot (20)

Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...
Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...
Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...
 
Risk Assessment (Master).pdf
Risk Assessment (Master).pdfRisk Assessment (Master).pdf
Risk Assessment (Master).pdf
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
Confined Spaces Training Powerpoint by OSHA
Confined Spaces Training Powerpoint by OSHAConfined Spaces Training Powerpoint by OSHA
Confined Spaces Training Powerpoint by OSHA
 
Hand safety
Hand safetyHand safety
Hand safety
 
Gas cylinder safety
Gas cylinder safetyGas cylinder safety
Gas cylinder safety
 
BREATHING APPARATUS
BREATHING APPARATUSBREATHING APPARATUS
BREATHING APPARATUS
 
Storage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh RajputStorage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh Rajput
 
National fire service day 14 th april
National fire service day   14 th aprilNational fire service day   14 th april
National fire service day 14 th april
 
NFPA
NFPANFPA
NFPA
 
Basic Fire Safety
Basic Fire Safety Basic Fire Safety
Basic Fire Safety
 
Hazard Communication- LinkedIn
Hazard Communication- LinkedInHazard Communication- LinkedIn
Hazard Communication- LinkedIn
 
Firewatch
FirewatchFirewatch
Firewatch
 
Compressed gas safety
Compressed gas safetyCompressed gas safety
Compressed gas safety
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
Emergency Action Plans Training by NMED
Emergency Action Plans Training by NMEDEmergency Action Plans Training by NMED
Emergency Action Plans Training by NMED
 
Safeworkpmits
SafeworkpmitsSafeworkpmits
Safeworkpmits
 
NEBOSH HSE PSM Element 1 v1.pdf
NEBOSH HSE PSM Element 1 v1.pdfNEBOSH HSE PSM Element 1 v1.pdf
NEBOSH HSE PSM Element 1 v1.pdf
 
Loto presentation
Loto presentationLoto presentation
Loto presentation
 
Novec 1230
Novec 1230Novec 1230
Novec 1230
 

Similar to Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput

Explosion protection theory and practice
Explosion protection   theory and practiceExplosion protection   theory and practice
Explosion protection theory and practice
David Pires
 
Fire & safety
Fire & safetyFire & safety
Fire & safety
Reliance
 

Similar to Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput (20)

Atx haza loca
Atx haza locaAtx haza loca
Atx haza loca
 
Combustible dust
Combustible dust Combustible dust
Combustible dust
 
Explosion protection theory and practice
Explosion protection   theory and practiceExplosion protection   theory and practice
Explosion protection theory and practice
 
Combustible Dust Hazards
Combustible Dust HazardsCombustible Dust Hazards
Combustible Dust Hazards
 
David Woolgar DSEAR and gas safety
David Woolgar  DSEAR and gas safetyDavid Woolgar  DSEAR and gas safety
David Woolgar DSEAR and gas safety
 
Fire & safety
Fire & safetyFire & safety
Fire & safety
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
 
Air based hazard
Air based hazardAir based hazard
Air based hazard
 
Hazardous Locations 101 by Pepperl+Fuchs
Hazardous Locations 101 by Pepperl+FuchsHazardous Locations 101 by Pepperl+Fuchs
Hazardous Locations 101 by Pepperl+Fuchs
 
Hazards Symposium Xxii 2011
Hazards Symposium Xxii 2011Hazards Symposium Xxii 2011
Hazards Symposium Xxii 2011
 
Flame arrestor
Flame arrestorFlame arrestor
Flame arrestor
 
CHAPTER 17- EXPOSICIÓN INGLES.pptx
CHAPTER 17- EXPOSICIÓN INGLES.pptxCHAPTER 17- EXPOSICIÓN INGLES.pptx
CHAPTER 17- EXPOSICIÓN INGLES.pptx
 
Technor - Explosion Proof, Hazardous Area Control Panels
Technor - Explosion Proof, Hazardous Area Control PanelsTechnor - Explosion Proof, Hazardous Area Control Panels
Technor - Explosion Proof, Hazardous Area Control Panels
 
57910334-5-MEP-Fire-Protection-rev.ppt
57910334-5-MEP-Fire-Protection-rev.ppt57910334-5-MEP-Fire-Protection-rev.ppt
57910334-5-MEP-Fire-Protection-rev.ppt
 
Analysis of Damaged Floor Coverings Emissions in Indoor Air Quality with Cant...
Analysis of Damaged Floor Coverings Emissions in Indoor Air Quality with Cant...Analysis of Damaged Floor Coverings Emissions in Indoor Air Quality with Cant...
Analysis of Damaged Floor Coverings Emissions in Indoor Air Quality with Cant...
 
Thomas & Betts - Hazardous Area Electrical Equipment & Cable Accessories
Thomas & Betts - Hazardous Area Electrical Equipment & Cable AccessoriesThomas & Betts - Hazardous Area Electrical Equipment & Cable Accessories
Thomas & Betts - Hazardous Area Electrical Equipment & Cable Accessories
 
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...
 
Clean Agent Fire Extinguishing Systems_Emaco.ppsx
Clean Agent Fire Extinguishing Systems_Emaco.ppsxClean Agent Fire Extinguishing Systems_Emaco.ppsx
Clean Agent Fire Extinguishing Systems_Emaco.ppsx
 
Understanding Industrial Flame Arrestors
Understanding Industrial Flame ArrestorsUnderstanding Industrial Flame Arrestors
Understanding Industrial Flame Arrestors
 
Lecture 4 Industrial Hazards Engineering.pptx
Lecture 4 Industrial Hazards Engineering.pptxLecture 4 Industrial Hazards Engineering.pptx
Lecture 4 Industrial Hazards Engineering.pptx
 

More from Gaurav Singh Rajput

More from Gaurav Singh Rajput (20)

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 
Forklift Safety | Gaurav Singh Rajput
Forklift Safety | Gaurav Singh RajputForklift Safety | Gaurav Singh Rajput
Forklift Safety | Gaurav Singh Rajput
 

Recently uploaded

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 

Recently uploaded (20)

NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 

Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput

  • 1. INSPECTION OF FIRE FIGHTING EQUIPMENT, TOOLS, DEVICES, VEHICLES & APPARATUS (NFPA REGULATIONS)
  • 2. Introduction to Fire Hazards and Fire Risk Assessment  Occidental's Piper Alpha platform was destroyed by explosion and fire in 1988. 167 workers were killed in the blaze.  A support vessel collided with Mumbai High North in 2005, rupturing a riser and causing a major fire that destroyed the platform.  BP, Texas 2005  The April 2010 BP “Deepwater Horizon” blow-out disaster
  • 3. Principles of fire and explosion
  • 10. Fire growth rates Examples Fire growth rate Category Open plan office – with limited combustible materials, stored or used Slow 1 Warehouse – which is likely to have stacked cardboard boxes, wooden pallets Medium 2 Production unit/warehouse – baled thermoplastic chips for packaging, stacked plasticproducts, baled clothing awaiting delivery Fast 3 Production unit/warehouse – flammable liquids, expanded cellular plastics and foam Manufacturing, processing, repairing, cleaning or otherwise treating any hazardous goods or materials Ultra- fast 4
  • 11. Factors affecting the growth rate  Construction and layout of the building  Ventilation into, throughout and out of the building  Use of the building (including the types of activity being undertaken)  Fire loading within the building.
  • 12. Types of fire accidents
  • 13. Explosion  An abrupt oxidation, or decomposition reaction, that produces an increase in temperature, or pressure, or in both temperature and pressure simultaneously.
  • 14. Explosive atmosphere  flammable substances in the form of gases, vapors, mists or dusts mixed with air under atmospheric conditions, which, after ignition has occurred, combustion spreads to the entire unburned mixture.
  • 15. Deflagration  Combustion wave propagating from an explosion at subsonic velocity relative to the unburnt gas immediately ahead of the flame (flame front).
  • 16. Detonation  A combustion wave propagating from an explosion at supersonic velocity relative to the unburnt gas immediately ahead of the flame (flame front).
  • 17. BLEVE – boiling liquid expanding vapor explosion  An explosion due to the flashing of liquids when a vessel with a high vapor pressure substance fails.
  • 18. CGE – confined gas explosion  Explosion within tanks, process equipment, sewage systems, underground installations, closed rooms, etc.
  • 19. UVCE – Unconfined Vapor Cloud Explosion  A vapor/gas explosion (deflagration or detonation) in an unconfined, unobstructed cloud.
  • 20. The mechanism of explosion  A dust explosion occurs when a combustible material is dispersed within the air forming a flammable cloud, this allows the flame to propagate through it.  A gas explosion follows a very similar principle when gas and oxygen are premixed within explosive limits
  • 21. Explosive limits and the flammable/explosion range
  • 22. Deflagration, detonation and explosive atmospheres  When a cloud is ignited the flame can propagate in two different modes through it. These modes are:  ➤ Deflagration  ➤ Detonation.
  • 23. Lower explosion limit (LEL  The minimum concentration of vapour in air below which the propagation of flame will not occur in the presence of an ignition source. Also referred to as the lower flammable limit or the lower explosive limit.
  • 24. Upper explosion limit (UEL)  The maximum concentration of vapor in air above which the propagation of flame will not occur in the presence of an ignition source. Also referred to as the upper flammable limit or the upper explosive limit.
  • 25. Explosive conditions  The types of materials that often cause dust explosions include:  ➤ Coal and peat  ➤ Metals such as iron, zinc, aluminium  ➤ Natural organic materials such as grain, linen,sugar, etc.  ➤ Processed materials such as plastics, organic pigments (paint), pesticides, etc.
  • 26. Creating an explosive atmosphere  The presence of a flammable substance  The degree of dispersion of the flammable substance (this will vary dependent upon its state – dusts, gases, vapours and mists)  ➤The concentration of the flammable substance in air within the explosive range
  • 28. Ignition sources  Hot surfaces  ➤ Naked fl ames and other hot gases  ➤ Mechanically generated sparks  ➤ Electrical equipment  ➤ Static electricity  ➤ Lightning  ➤ Radio frequency (RF) – electromagnetic waves  ➤ Ionising radiation.
  • 30. Principles of explosion management  Control  Design and construction – equipment, protective systems and system components  Dilution by ventilation  Mitigation (Explosion venting)
  • 31. Plant layout and classification of zones
  • 32. Plant layout and classification of zones
  • 33. Fire hazard identification  Combustion of Gases  Explosive Risk  Flammable Gas Risk  Toxic Gas Risk
  • 34. Fire Explosion Mitigation  Passive fire protection (barriers and special coatings)  Containment and spill control - Isolation valves - Blowdown/ Depressurization - fire divisions - limiting and controlling spills and releases  Water deluge and pray systems  Water monitor system
  • 35. Fire Explosion Mitigation  Foam system  Dry chemicals  Water mist system  Gas dispersion with water spray  Portable firefighting equipment - Extinguishers - Hand hold nozzles - Monitors/ Cameras - breathing apparatus Firefighting (FIFI) tugs
  • 36. Alarm Levels  Workers are often under risk of gas exposure in situations where atmospheres cannot be controlled, such as in confined space entry applications where alarming at TWA values would be inappropriate.
  • 37. Gas Detection Systems  Catalytic gas detection  Infra red gas detection  Smoke detection  Incipient fire detection  Flame detection
  • 38. Gas Detection Systems  Fixed gas detectors can be positioned in strategic zones, for example in confined spaces or ‘hot work’ areas  Most gas detectors should be calibrated every six months to ensure optimum operation. However, a new range of IR (infrared) detectors allow users to extend maintenance checks to once every 12 months
  • 39. Future Trends  It is likely that both portable and fixed hydrocarbon gas detectors will use IR sensors rather than the traditional catalytic bead (pellistor) sensors currently used in most detectors.  Sensor technologies such as PID (photo-ionisation) are being used more commonly as requirements for monitoring levels of VOCs (volatile organic compounds) in industry increase.
  • 40. Future Trends  Optical sensing developments and solid-electrolyte sensors will provide solutions in toxic gas and oxygen sensing applications where traditional electrochemical cells have operating limitations  Fixed detection systems will also continue to utilize a variety of technologies (such as point-type detectors, open-path detectors, acoustic sensors and even gas cameras) for the most comprehensive coverage. Wireless connectivity will replace cables in some applications.
  • 41. The five steps of Fire and Explosion Hazard Management FEHM  Step 1: Reviewing fire and explosion scenarios that can occur  Step 2: Reviewing different policies to reduce fire and explosion risk  Step 3: Decide which policy is the most appropriate  Step 4: Implement and maintain policy  Step 5: Update policy according to change in facilities or operating environment
  • 42. Fire Risk Assessment Process  Look for the hazards  Decide who might be harmed and how  Evaluate the risks and decide whether the existing precautions are adequate or whether more should be done  Record your findings  Review your assessment and revise if necessary.
  • 45. Gaseous Extinguishing Agent Systems  A gas extinguishing system is a fire extinguishing system that extinguishes fire with the help of a gaseous extinguishing agent either through oxygen displacement (reduction of oxygen content) or physical effects (heat extraction).  In contrast to a sprinkler system, a gas extinguishing system is designed to extinguish and not only suppress fire.
  • 46. AREAS OF USE  IT systems and computer rooms  Archive rooms, document safes  Emergency call centres, flight navigation and control towers, mobile phone transmitter stations.  Art galleries, libraries, film projector rooms, museums  Medical sector: imaging systems, operating rooms, mobile stations  Industrial facilities such as laboratories, control rooms, offshore drilling platforms, robotic equipment  Emergency power generators, battery compartments, low- voltage compartments, cable compartments, etc.  Flight simulators, ships, military vehicles
  • 47. EXTINGUISHING AGENT Oxygen-displacing extinguishing gases - inert gases and carbon dioxide (CO2)  Carbon dioxide (CO2)  Argon - IG-01  Nitrogen - IG-100  Argonite® - IG-55  Inergen® - IG-541 Chemically-acting extinguishing gases  Novec 1230 ® (Keton)  FM 200 (HFC227ea)  HFC-125  FE-13
  • 49. Introduction  Dry chemical is an excellent extinguishing agent due to its rapid flame suppressing capability on hydrocarbon, three-dimensional and natural gas pressure fires.
  • 50. Applications for DC Units and Systems  Compressor Stations  Oil and Gas Well Servicing  Drilling Operations  Off-Shore Platforms  Fuel Loading Racks  Storage Tank Vents  Electrical Transformers  Chemical and Petro-Chemical Plants  Storage Facilities  Airports and Heliports  Manufacturing Facilities
  • 51. DETERMINING REQUIREMENTS  The first steps in determining the requirements for a Dry Chemical System is to identify the hazard, size of hazard and any conditions requiring special consideration such as wind exposure or objects blocking discharge of agent to the hazard.
  • 52. COMMON TYPES OF FIRE HAZARDS  Spill Fires  Liquid in Depth  Three Dimensional Fires  Pressure Fires  Class “A” Fires
  • 53. TYPE OF EQUIPMENT AND APPLICATION  The type of system required (handline application, total flooding, manual, semi automatic or full automatic) is normally a judgment call based on the following:  Is the facility manned full time?  Are experienced fire-fighting personnel available at all times?  Visibility of hazard in the event of fire.  Power source available for automatic system?  Hazard to personnel that might be in area during?  Discharge of equipment?  Obstacles which would prevent extinguishment using handlines.
  • 54. When Hand line Protection is Used  The unit must have the capacity to maintain flow through the hand lines for a minimum of 30 seconds.  A fixed system providing total flooding must maintain flow for a minimum time of 30 seconds
  • 55. Types of dry chemical powder  PK Potassium Bicarbonate Based is a premium powder suitable for use in high-risk areas  BC Dry Chemical Powder Mixture of sodium bicarbonate, silicates and stearates.
  • 56. Data for dry chemical unit method of figuring dry chemical agent requirements for specific hazards Unit Size Capacity (lbs.) BC Capacity (lbs.) PK/ABC Max Flow Rate (lbs./sec.) BC Max Flow Rate (lbs./sec.) PK/ABC DISCHARGE OPENING Inch. CDC200 230 200 7.5 6.5 1-1/2 CDC500 600 500 20 16 2 CDC1000 1200 1050 40 35 2-1/2 CDC1500 1550 1400 50 45 2-1/2 CDC2000 2100 1850 70 60 3 CDC2500 2600 2300 85 75 3 CDC3000 3000 2750 100 90 3 CDC3500 3500 3100 115 100 3 CDC4000 4000 3750 140 125 4 CDC4500 4500 4050 150 135 4 CDC5000 5000 4500 170 150 4
  • 57. Dry Chemical Units System Performance On Hydrocarbon Fires NFPA 17 Requires minimum of discharge time
  • 58. The types of hazards  Flammable or combustible liquids  Flammable or combustible gases  Combustible solids including plastics, which melt when involved in fire  Electrical hazards such as oil-filled transformers or circuit breakers  Textile operations subject to flash surface fires  Ordinary combustibles such as wood, paper, or cloth  Restaurant and commercial hoods, ducts, and associated cooking appliance hazards such as deep-fat fryers
  • 59. 5.1.2 Limitations DC extinguishing systems shall not be considered satisfactory protection for the following:  Chemicals containing their own oxygen supply, such as cellulose nitrate  Combustible metals such as sodium, potassium, magnesium, titanium, and zirconium  Deep-seated or burrowing fires in ordinary combustibles where the dry chemical cannot reach the point of combustion  Delicate electrical equipment  The minimum temperature limitation shall be at most 32°F (0°C).  The maximum temperature limitation shall be at least 120°F (48.9°C)
  • 60. Multiple Systems Protecting a Common Hazard.  two or more systems are used to protect a common hazard, they shall be arranged for simultaneous operation.  Operation of a single actuator shall cause all systems to operate.
  • 61. Systems Protecting Two or More Hazards.  Where two or more hazards could be simultaneously involved in fire by reason of their proximity, the hazards shall be protected by either of the following:  (1) Individual systems installed to operate simultaneously  (2) A single system designed to protect all hazards that could be simultaneously involved
  • 62. Dry Chemical Requirements and Distribution.  The following factors shall be considered in determining the amount of dry chemical required:  (1) Minimum quantity of dry chemical  (2) Minimum flow rate of dry chemical  (3) Nozzle placement limitations, including spacing, distribution, and obstructions  (4) High ventilation rates, if applicable  (5) Prevailing wind conditions, if applicable
  • 63. 5.5 Special Considerations  Ensuring shutoff of power and fuel valves upon operation of the extinguishing systems.  Conveyors moving flammable or combustible materials or commodities, shall be automatically shut off upon operation of the extinguishing systems.  All shutoff systems shall be fail-safe.  All shutoff systems shall require manual resetting prior to restoration of the operating conditions existing before operation of the extinguishing systems.  All shutoff devices shall function with the system operation
  • 64. 5.6* Personnel Safety  (1) Personnel training  (2) Warning signs  (3) Predischarge alarms  (4) Discharge alarms  (5) Respiratory protection
  • 65. 5.6.2 Electrical Clearances  The following references shall be considered as the minimum electrical clearance requirements for the installation of dry chemical systems:  (1) ANSI C-2, National Electrical Safety Code  (2) NFPA 70, National Electrical Code  (3) 29 CFR 1910 S
  • 66. 5.7* Operation and Control of Systems
  • 67. 5.7.1 Methods of Actuation  Systems shall be provided with both automatic and manual independent means of operation  All operating devices shall be designed, located, installed, or protected so that they are not subject to mechanical, environmental, or other conditions that could render them inoperative  the manual actuation device shall be installed no more than 48 in. and no less than 42 in. above the floor.
  • 68. 5.7.3* Notification  An audible or visual indicator shall be provided to show that the system has operated, that personnel response might be needed, and that the system is in need of recharge.
  • 69. Connection to the Alarm System  The extinguishing system shall be connected to the fire alarm system, if provided, in accordance with the requirements of NFPA 72
  • 70. Piping & Nozzles  For engineered systems, pipe sizes and nozzles shall be selected, on the basis of calculations, to deliver the required dry chemical flow rate at each nozzle.  For pre-engineered systems, pipe sizes and nozzles shall be selected in accordance with the manufacturer’s listed installation and maintenance manual  All discharge nozzles shall be designed and subsequently located, installed, and protected so that they are not subject to mechanical, environmental, or other conditions that could render them inoperative.
  • 71. Hand Hose Line Systems  Dry chemical hand hose line systems shall be provided with turrets, skid-mounted hose reels, remote hose reels, or combinations thereof.  If multiple cylinders are used to pressurize the dry chemical agent containers, each cylinder shall be provided with a pressure gauge and a manual means of operation.
  • 72. System Operational Tests  System operational tests shall be performed in accordance with the manufacturer’s design, installation, and maintenance manual and shall include functional tests of the automatic detection system, the manual release devices, and shutdown devices, where provided.  The installing contractor shall complete and sign an acceptance test report acceptable to the authority having jurisdiction.
  • 73. Inspection, Maintenance, and Recharging  Storage shall be in a constantly dry area, and the dry chemical shall be contained in metal drums .  A service technician who performs maintenance on an extinguishing system shall be certified after passing a written test.  A service technician shall service the dry chemical fire-extinguishing system at intervals no more than 6 months apart
  • 74. Recharge Agents  Dry chemical provided for the system shall be listed for the system.  Expellant gas for stored pressure cylinders shall be standard industrial-grade nitrogen with a dew point of −60°F (−51°C) or lower (CGA nitrogen specification G10.1).  Where carbon dioxide or nitrogen is used as the expellant gas, it shall be of good commercial grade and free of water and other contaminants that might cause container corrosion.
  • 75. Owner’s Inspection  On a monthly basis, inspection shall be conducted in accordance with the manufacturer’s design, installation, and maintenance manual or the owner’s manual.  As a minimum, inspection shall include verification of the following:  (1) The extinguishing system is in its proper location. (2) The manual actuators are unobstructed.  (3) The tamper indicators and seals are intact.  (4) The maintenance tag or certificate is in place.  (5) The system shows no physical damage or condition that might prevent operation.
  • 76. Owner’s Inspection  (6) The pressure gauge(s), if provided, is inspected physically or electrically to ensure it is in the operable range.  (7) The nozzle blowoff caps, where provided, are intact and undamaged.  (8) Neither the protected equipment nor the hazard has been replaced, modified, or relocated.  Personnel making inspections shall keep records for those extinguishing systems that were found to require corrective actions.  The records shall be retained until the next semiannual maintenance.
  • 77. Maintenance  At least semiannually and after any system activation, maintenance shall be conducted in accordance with the manufacturer’s design, installation, and maintenance manual.  As a minimum, such maintenance shall include thefollowing:  (1) A check to see that the hazard has not changed  (2) An examination of all detectors, expellant gas container( s), agent container(s), releasing devices, piping, hose assemblies, nozzles, signals, and all auxiliary equipment  (3)*Verification that the agent distribution piping is not obstructed  (4) Examination of the dry chemical (If there is evidence of caking, the dry chemical shall be discarded and the system shall be recharged in accordance with the manufacturer’s instructions.)
  • 78. Maintenance  Dry chemical in stored pressure systems shall not require semiannual examination but shall be examined at least every 6 years.  Dry chemical containers that pass the applicable 6-year requirement of 11.3.1.2 shall have the maintenance information recorded on a durable weatherproof label that is a minimum size of 2 in. × 31⁄2 in. (51 mm × 89 mm)  The label shall include the following information:  (1) Month and year the maintenance was performed, indicated by a perforation such as done by a hand punch  (2) Name or initials of the person performing the maintenance and the name of the agency performing the maintenance
  • 79. Maintenance  Each system container that has undergone maintenance that includes internal examination or has been recharged shall have a verification-of-service collar located around the neck of the container.  The collar shall include the following information:  (1) Month and year the service was performed, indicated by a perforation such as done by a hand  punch  (2) Name of the agency performing the maintenance or recharge
  • 80. Maintenance  Where maintenance of any dry chemical containers or any system components reveals conditions such as, but not limited to, corrosion or pitting in excess of the manufacturer’s limits; structural damage; fire damage; or repairs by soldering, welding, or brazing, the affected container shall be replaced or hydrostatically  Until such repairs are accomplished, the system(s) shall be tagged as noncompliant, and after repair parties shall be informed.
  • 81. Maintenance  Pressure regulators shall be operationally checked at least annually.  Defective regulator(s) shall not be adjusted but shall be replaced  The maintenance report, including any recommendations, shall be filed with the owner or with the owner’s representative.  The owner or owner’s representative shall retain all maintenance reports for a period of 1 year after the next maintenance of that type required by this standard.
  • 82. Maintenance  Fixed temperature-sensing elements of the fusible metal alloy type shall be replaced at least semiannually from the date of installation.  Heat detectors other than metal alloy–type fusible links shall be permitted to remain continuously in service, provided they are inspected, cleaned, and tested,
  • 83. Recharging  All extinguishing systems shall be recharged after use or as indicated by an inspection or a maintenance check in accordance with the manufacturer’s design, installation, and maintenance manual.  The following parts of dry chemical extinguishing systems shall be subjected to a hydrostatic pressure test at intervals not exceeding 12 years:  (1) Dry chemical containers  (2) Auxiliary pressure containers  (3) Hose assemblies
  • 84. Recharging  No leakage, rupture, or movement of hose couplings shall be permitted.  The pressure in a hydrostatic test of a cylinder shall be maintained for a minimum of 30 seconds but for no less time than is required for complete expansion of the cylinder and to complete the visual examination of the cylinder.
  • 86. General Requirements  The building owner shall ensure that all areas of the building containing water-filled piping shall be maintained at a minimum temperature of 40°F (4.4°C) and not exposed to freezing conditions.  Inspection, testing, and maintenance shall be performed by personnel who have developed competence through training and experience.  Accessibility..  Notification of System Shutdown.  Changes in Occupancy, Use, Process, or Materials.
  • 87. Re-evaluation  (1) Occupancy changes such as converting office or production space into warehousing  (2) Process or material changes such as metal stamping to molded plastics  (3) Building revisions such as relocated walls, added mezzanines, and ceilings added below sprinklers  (4) Removal of heating systems in spaces with piping subject to freezing
  • 88. Addressing Changes in Hazard  In case of any change, the owner or his representative shall promptly take steps to evaluate the adequacy of the installed system in order to protect the building or hazard in question.  Corrections shall be approved
  • 89. Valve Location.  The location of shutoff valves shall be identified.
  • 90. Information Sign.  The sign shall indicate at least the following information:  (1) Location of the area served by the system  (2) Location of auxiliary drains and low-point drains for dry pipe and preaction systems  (3) The presence and location of antifreeze or other auxiliary systems  (4) The presence and location(s) of heat tape
  • 91. Records  Records shall indicate the procedure performed (e.g., inspection, test, or maintenance), the organization that performed the work, the results, and the date.  Records shall be maintained by the property owner.
  • 92. Testing  All components and systems shall be tested to verify that they function as intended.  Test results shall be compared with those of the original acceptance test (if available) and with the most recent test results.
  • 94. System Components and System Types  All components shall be listed for their intended use.
  • 95. Water Supplies  Quality & Quantity  Pressure.(the minimum pressure for which the system has been designed)  Temperature (water at temperatures between 4°C (40°F) and 37.8°C (100°F).  Design. The water system shall be designed and installed in accordance with NFPA 24.  Storage Water supply or premixed solution shall be protected against freezing
  • 96. Water and Foam Concentrate Pumps.  When water or foam concentrate pumps are required for automatic foam system operation, they shall be designed and installed in accordance with NFPA 20.  Controllers in accordance with NFPA 20 shall not be required for manual systems.
  • 97. Foam Concentrates  Foam concentrate shall be listed and be one of the following types:  1. Protein  2. Fluoroprotein  3. Aqueous film-forming foam (AFFF)  4. Film-forming fluoroprotein (FFFP)  5. Alcohol-resistant  6. High-expansion  7. Medium-expansion  8. Others listed for this purpose
  • 98. Concentrate Storage.  shall be stored in a location not exposed to the hazard they protect and in a noncombustible structure.  Bulk liquid storage tanks shall be fabricated from or be lined with materials compatible with the concentrate.  The storage tank shall be designed to minimize evaporation of foam concentrate.
  • 99. Foam Proportioning  The method of foam proportioning shall conform to one of the following:  1. Self-educting nozzle  2. In-line eductor  3. Pressure proportioners (with or without bladder)  4. Around-the-pump proportioners  5. Direct injection variable output foam pump system  6. Coupled-water motor pump  7. Balanced pressure pump-type proportioners
  • 100. Foam Concentrate Pumps.  The design and materials of construction for foam concentrate pumps shall be in accordance with NFPA 20.
  • 101. Piping.  Pipe Materials. Pipe within the hazard area shall be of steel or other alloy rated for the pressure and temperature involved.  Shall conform to one of the following standards:  1. ASTM (American Society for Testing Matwerial) A 135  2. ASTM A 53  3. ASTM A 795  Galvanized pipe shall be used for noncorrosive atmospheres.
  • 102. Fittings.  All pipe fittings shall be in accordance with one of the  following:  (1) ANSI B16.1  (2) ANSI B16.3  (3) ANSI B16.4  (4) ANSI B16.5  (5) ANSI B16.9  (6) ANSI B16.11  (7) ANSI B16.25  (8) ASTM A 234
  • 103. Valves.  All valves shall be of the indicator type, such as OS&Y or post indicator.  Inside the hazard or diked area, automatic control valves and shutoff valves shall be of steel or other alloy capable of withstanding exposure to fire temperatures.  All valves required for automatic foam systems shall be supervised in their normal operating position by one of the following methods:  (1) Electrical, in accordance with NFPA 72  (2) Locked  (3) Sealed
  • 104. System Types  The following four types of systems shall be  permitted:  (1) Fixed  (2) Semifixed  (3) Mobile  (4) Portable
  • 105. Operation and Control of Systems  Systems shall be permitted to be actuated automatically or manually.  All systems shall have provisions for manual actuation.
  • 106. Low-Expansion System Design  Types of Hazards. (protect outdoor storage tanks, interior flammable liquid hazards, loading racks, diked areas, and nondiked spill areas)
  • 107. Outdoor Fixed Roof (Cone) Tanks.  The following methods for protecting exterior fixed- roof tanks shall be included within this section:  (1) Foam monitors and handlines  (2) Surface application with fixed foam discharge outlets  (3) Subsurface application  (4) Semisubsurface injection methods
  • 108. Foam Handline and Monitor Protection for Fixed-Roof Storage Tanks Containing Hydrocarbons
  • 109. Number of Fixed Foam Discharge Outlets for Fixed-Roof Tanks Containing Hydrocarbons or Flammable and Combustible Liquids Requiring Alcohol-Resistant Foams
  • 110. Minimum Discharge Times and Application Rate for Type I and Type II Fixed Foam Discharge Outlets on Fixed-Roof (Cone) Storage Tanks Containing Hydrocarbons
  • 111. Application Rate and Discharge Times for Fixed-Roof (Cone) Tanks Containing Flammable and Combustible Liquids Requiring Alcohol-Resistant Foams
  • 112. Minimum Number of Subsurface Foam Discharge Outlets for Fixed-Roof
  • 113. Minimum Discharge Times and Application Rates for Subsurface Application on Fixed- Roof Storage Tanks
  • 115. Hazards Protected  (1) Ordinary combustibles  (2) Flammable and combustible liquids  (3) Combinations of (1) and (2)  (4) Liquefied natural gas (high-expansion foam only)
  • 116. Medium- and high-expansion foam systems  Medium- and high-expansion foam systems shall not be used on fires in the following hazards:  (1) Chemicals, such as cellulose nitrate, that release sufficient oxygen or other oxidizing agents to sustain combustion  (2) Energized unenclosed electrical equipment  (3) Water-reactive metals such as sodium, potassium, and NaK (sodium-potassium alloys)  (4) Hazardous water-reactive materials, such as triethyl aluminum and phosphorus pentoxide  (5) Liquefied flammable gas  (6) Hazards listed in (1)–(5) where competent evaluation, including tests, indicates acceptability
  • 117. Types of Systems  (1) Total flooding systems  (2) Local application systems  (3) Portable foam-generating devices
  • 119. Operation and Control of Systems  Detection of Fires  Supervision  Alarms (operation – failure )  Operating Devices (power - foam generators, valves, proportioners, eductors, discharge controls, and shutdown equipment)  window closers, vent openers, and electrical equipment shutdown devices shall be considered integral parts of the system and shall function simultaneously with the system operation.  All manual operating devices shall be identified with signs as to the hazards they protect.
  • 120. Foam-Generating Apparatus Location  Foam generating apparatus shall be located and arranged so that inspection, testing, recharging, and other maintenance is facilitated and interruption of protection is held to a minimum.
  • 121. Ducts.  Ducts shall be protected from undue mechanical, chemical, or other damage.
  • 122. Total Flooding Systems General Information  A total flooding system shall consist of fixed foam- generating apparatus complete with a piped supply of foam concentrate and water, arranged to discharge into an enclosed space or enclosure around the hazard
  • 123. Inspection and Visual Examination  Foam systems shall be examined visually to determine that they have been properly installed.  Foam systems shall be inspected for such items as conformity with installation plans; continuity of piping; removal of temporary blinds; accessibility of valves, controls, and gauges; and proper installation of vapor seals, where applicable.
  • 124. Flushing after Installation  The water supply mains shall be flushed thoroughly at the maximum practicable rate of flow before connection is made to system piping.
  • 125. Pressure Tests  All piping shall be subjected to a 2-hour hydrostatic pressure gauge test at 1379 kPa (200 psi) or 345 kPa (50 psi) in excess of the maximum pressure anticipated, whichever is greater, in accordance with NFPA 13.
  • 126. Operating Tests  Tests for total flooding systems shall establish that all automatic closing devices for doors, windows, and conveyor openings, and automatic equipment interlocks, as well as automatic opening of heat and smoke vents or ventilators, will function upon system operation.
  • 127. Discharge Tests  The following data shall be required:  (1) Static water pressure  (2) Residual water pressure at the control valve and at a remote reference point in the system  (3) Actual discharge rate  (4) Consumption rate of foam-producing material  (5) Concentration of the foam solution  (6) Foam quality (expansion and one-quarter drain time) or foam discharge shall be conducted, or the foam discharge shall be visually inspected to ensure that it is satisfactory for the purpose intended.
  • 128. Periodic Inspection  At least annually, all foam systems shall be thoroughly inspected and checked for correct operation.  inspection report, with recommendations, shall be filed with the owner.
  • 129. Water Spray Fixed Systems NFPA 25  This chapter shall provide the minimum requirements for the routine inspection, testing, and maintenance of water spray protection from fixed nozzle systems only.
  • 130. Summary of Water Spray Fixed System Inspection, Testing, and Maintenance
  • 131. Summary of Water Spray Fixed System Inspection, Testing, and Maintenance
  • 132. Summary of Water Spray Fixed System Inspection, Testing, and Maintenance
  • 133. Inspection and Maintenance Procedures  Items in areas that are inaccessible for safety considerations due to factors such as continuous process operations and energized electrical equipment shall be inspected during each scheduled shutdown but not more than every 18 months.  Nozzle strainers shall be removed, inspected, and cleaned during the flushing procedure for the mainline strainer.  Mainline strainers shall be removed and inspected every 5 years for damaged and corroded parts.
  • 134. Automatic Detection Equipment  Automatic detection equipment shall be inspected, tested, and maintained in accordance with NFPA 72, National Fire Alarm and Signaling Code.
  • 135. System Components  System piping, fittings, hangers, and supports shall be inspected and maintained to ensure continuity of water delivery to the spray nozzles at full waterflow and design pressure.
  • 136. Piping and Fittings  System piping and fittings shall be inspected for the following:  (1) Mechanical damage (e.g., broken piping or cracked fittings)  (2) External conditions (e.g., missing or damaged paint or coatings, rust, and corrosion)  (3) Misalignment or trapped sections  (4) Low-point drains (automatic or manual)  (5) Location of rubber-gasketed fittings
  • 137. Hangers and Supports  Hangers and supports shall be inspected for the following and repaired or replaced as necessary:  (1) Condition (e.g., missing or damaged paint or coating, rust, and corrosion)  (2) Secure attachment to structural supports and piping  (3) Damaged or missing hangers
  • 138. Water Spray Nozzles  Water spray nozzles shall be inspected and maintained to ensure that they are in place, continue to be aimed or pointed in the direction intended in the system design, and are free from external loading and corrosion.
  • 139. Water Supply  The dependability of the water supply shall be ensured by regular inspection and maintenance, whether furnished by a municipal source, on-site storage tanks, a fire pump, or private underground piping systems.  Water supply piping shall be maintained free of internal obstructions.
  • 140. Strainers  Mainline strainers (basket or screen) shall be flushed until clear after each operation or flow test.  Individual water spray nozzle strainers shall be removed, cleaned, and inspected after each operation or flow test.  Damaged or corroded parts shall be replaced or repaired
  • 141. Drainage  The area beneath and surrounding a water spray fixed system shall be inspected visually on a quarterly basis to ensure that drainage facilities, such as trap sumps and drainage trenches, are not blocked and retention embankments or dikes are in good repair.
  • 142. Test Preparation  Precautions shall be taken to prevent damage to property during the test.  Operational tests shall be conducted to ensure that the water spray fixed systems respond as designed, both automatically and manually.  Under test conditions, the heat detection systems, where exposed to a heat test source, shall operate within 40 seconds.  These response times shall be recorded  The time lapse between operation of detection systems and water delivery time to the protected area shall be recorded.
  • 143. Pressure Readings  Pressure readings shall be recorded at the hydraulically most remote nozzle to ensure the water flow has not been impeded by partially closed valves or by plugged strainers or piping.
  • 144. Multiple Systems  The maximum number of systems expected to operate in case of fire shall be tested simultaneously to check the adequacy of the water supply.  After the full flow test, the water spray system shall be maintained and returned to service
  • 145. Main Drain Tests  Main drain tests shall be conducted at the main riser to determine whether there has been any change in the condition of the water supply piping and controlling valves.  Static and residual water pressures shall be recorded respectively before, during, and after the operation of the fully opened drain valve.
  • 146. Ultra-High-Speed Water Spray System (UHSWSS) Operational Tests.  full operational test, including measurements of response time, shall be conducted at intervals not exceeding 1 year.  Systems out of service shall be tested before being placed back in service.
  • 147. Summary of Component Replacement Action Requirements
  • 149. Summary of Sprinkler System Inspection, Testing, and Maintenance
  • 150. Inspection, Sprinklers  Any sprinkler that shows signs of any of the following shall be replaced:  (1) Leakage  (2) Corrosion  (3) Physical damage  (4) Loss of fluid in the glass bulb heat responsive element  (5)*Loading  (6) Painting unless painted by the sprinkler manufacturer  Sprinklers installed in areas that are inaccessible for safety considerations due to process operations shall be inspected during each scheduled shutdown.
  • 151. Pipe and Fittings  Sprinkler pipe and fittings shall be inspected annually from the floor level.  Pipe and fittings shall be in good condition and free of mechanical damage, leakage, and corrosion.  Sprinkler pipe hangers and seismic braces shall be inspected annually from the floor level
  • 152. Gauges  Gauges on wet pipe sprinkler systems shall be inspected monthly to ensure that they are in good condition and that normal water supply pressure is being maintained.  Gauges on dry, preaction, and deluge systems shall be inspected weekly to ensure that normal air and water pressures are being maintained.  Where air pressure supervision is connected to a constantly attended location, gauges shall be inspected monthly.  For dry pipe or preaction systems protecting freezers with two air pressure gauges on the air line(s) between the compressor and the dry pipe or preaction valve, the air pressure gauge near the compressor shall be compared weekly to the pressure gauge above the dry pipe or preaction valve.
  • 153. Water flow Alarm and Supervisory Devices  Water flow alarm and supervisory alarm devices shall be inspected quarterly to verify that they are free of physical damage.
  • 154. Hydraulic Design Information Sign  The hydraulic design information sign for hydraulically designed systems shall be inspected quarterly to verify that it is attached securely to the sprinkler riser and is legible.
  • 155. Testing, sprinklers  Where required by this section, sample sprinklers (not less than four sprinklers )shall be submitted to a recognized testing laboratory acceptable to the authority having jurisdiction for field service testing.  Where sprinklers have been in service for 50 years, they shall be replaced or representative samples from one or more sample areas shall be tested.  Test procedures shall be repeated at 10-year intervals.  Sprinklers manufactured prior to 1920 shall be replaced.
  • 156. Testing, sprinklers  Sprinklers manufactured using fast-response elements that have been in service for 20 years shall be replaced, or representative samples shall be tested and then retested at 10-year intervals.  Representative samples of solder-type sprinklers with a temperature classification of extra high [325°F (163°C)] or greater that are exposed to semi-continuous to continuous maximum allowable ambient temperature conditions shall be tested at 5-year intervals.
  • 157. Testing, sprinklers  Dry sprinklers that have been in service for 10 years shall be replaced or representative samples shall be tested and then retested at 10-year intervals.  Where sprinklers are subjected to harsh environments, including corrosive atmospheres and corrosive water supplies, on a 5-year basis, either sprinklers shall be replaced or representative sprinkler samples shall be tested.
  • 158. Testing, gauges  Gauges shall be replaced every 5 years or tested every 5 years by comparison with a calibrated gauge.  Gauges not accurate to within 3 percent of the full scale shall be recalibrated or replaced.
  • 159. Water flow Alarm Devices  Mechanical water-flow alarm devices including, but not limited to, water motor gongs, shall be tested quarterly.  Vane-type and pressure switch–type water flow alarm devices shall be tested semiannually.  Testing water flow alarm devices on dry pipe, preaction, or deluge systems shall be accomplished by using the bypass connection.
  • 160. Maintenance, sprinklers  Replacement sprinklers shall have the proper characteristics for the application intended, which include the following:  (1) Style  (2) Orifice size and K-factor  (3) Temperature rating  (4) Coating, if any  (5) Deflector type (e.g., upright, pendent, sidewall)  (6) Design requirements
  • 161. Maintenance, sprinklers  A supply of spare sprinklers (never fewer than six) shall be maintained on the premises so that any sprinklers that have operated or been damaged in any way can be promptly replaced.  The sprinklers shall be kept in a cabinet located where the temperature in which they are subjected will at no time exceed 100°F (38°C).
  • 162. Antifreeze Solutions to Be Used If Non-potable Water Is Connected to Sprinklers
  • 163. Antifreeze Solutions to Be Used If Potable Water Is Connected to Sprinklers
  • 164. Summary of Component Replacement Action Requirements
  • 165. Standpipe and Hose Systems
  • 166. Minimum Requirements  inspection, testing, and maintenance of all classes of standpipe and hose systems shall follow Table 6.1.1.2  Obstruction Investigations  Notification to Supervisory Service
  • 167. Inspection.  Components of standpipe and hose systems shall be visually inspected annually or as specified in Table 6.1.1.2.
  • 168. Summary of Standpipe and Hose Systems Inspection, Testing, and Maintenance
  • 169. Standpipe and Hose Systems
  • 170. Standpipe and Hose Systems
  • 171. Gauges  1 Gauges on automatic standpipe systems shall be inspected monthly to ensure that they are in good condition and that normal water supply pressure is being maintained.  Gauges on dry, preaction, and deluge valves shall be inspected weekly to ensure that normal air and water pressure are being maintained.  Where air pressure supervision is connected to a constantly attended location, gauges shall be inspected monthly.
  • 172. Hydraulic Design Information Sign.  When provided, the hydraulic design information sign for standpipe systems shall be inspected annually to verify that it is attached securely and is legible.
  • 173. Testing  A flow test shall be conducted every 5 years at the hydraulically most remote hose connections of each zone of an automatic standpipe system to verify the water supply still provides the design pressure at the required flow.  All systems shall be flow tested and pressure tested at the requirements for the design criteria in effect at the time of the installation.
  • 174. Hydrostatic Tests.  Hydrostatic tests of not less than 200 psi (13.8 bar) pressure for 2 hours, or at 50 psi (3.4 bar) in excess of the maximum pressure, where maximum pressure is in excess of 150 psi (10.3 bar), shall be conducted every 5 years on manual standpipe systems and semi-automatic dry standpipe systems, including piping in the fire department connection.
  • 175. Gauges.  Gauges shall be replaced every 5 years or tested every 5 years by comparison with a calibrated gauge.  Gauges not accurate to within 3 percent of the full scale shall be recalibrated or replaced.
  • 176. Maintenance  Maintenance and repairs shall be in accordance with 6.1.3 and Table 6.1.2.  Equipment that does not pass the inspection or testing requirements shall be repaired and tested again or replaced.
  • 177. Summary of Component Replacement Action Requirements
  • 179. Summary of Foam-Water Sprinkler System Inspection, Testing, and Maintenance
  • 180. Summary of Foam-Water Sprinkler System Inspection, Testing, and Maintenance
  • 181. Summary of Foam-Water Sprinkler System Inspection, Testing, and Maintenance
  • 182. Summary of Component Replacement Action Requirements
  • 183. Summary of Component Replacement Action Requirements
  • 185. Maintenance of Water Mist Systems
  • 186. Maintenance of Water Mist Systems
  • 187. Maintenance of Water Mist Systems
  • 188. Maintenance of Water Mist Systems
  • 189. Maintenance of Water Mist Systems
  • 190. High Pressure Cylinders  High pressure cylinders used in water mist systems shall not be recharged without a hydrostatic test (and remarking) if more than 5 years have elapsed from the date of the last test.  Cylinders that have been in continuous service without discharging shall be permitted to be retained in service for a maximum of 12 years, after which they shall be discharged and retested before being returned to service.
  • 191. Maintenance  Mechanical waterflow devices, including but not limited to water motor gongs, shall be tested quarterly.  Vane-type and pressure switch–type waterflow devices shall be tested semiannually.  Preventive maintenance includes, but is not limited to, lubricating control valve stems, adjusting packing glands on valves and pumps, bleeding moisture and condensation from air compressors and air lines, and cleaning strainers.
  • 192. Maintenance Frequencies Item Activity Frequency Water tank system Strainers and filters Drain and refill Flushing Clean or replace as required Annually Annually After system operation
  • 193. Maintenance  Spare components shall be accessible and shall be stored in a manner to prevent damage or contamination.  After each system operation, a representative sample of operated water mist nozzles in the activated zone shall be inspected. [750:13.3.10]  After each system operation due to fire, the system filters and strainers shall be cleaned or replaced.
  • 194. Training.  All persons who might be expected to inspect, test, maintain, or operate water mist systems shall be trained thoroughly in the functions they are expected to perform.  Refresher training shall be provided as recommended by the manufacturer or by the authority having jurisdiction.
  • 196. Alternative Fire Pump Inspection, Testing, and Maintenance Procedures
  • 197. Auxiliary Equipment  The pump assembly auxiliary equipment shall include the following: (1) Pump accessories as follows: (a) Pump shaft coupling (b) Automatic air release valve (c) Pressure gauges (d) Circulation relief valve (not used in conjunction with diesel engine drive with heat exchanger) (2) Pump test device(s) (3) Pump relief valve and piping (where maximum pump discharge pressure exceeds the rating of the system components or the driver is of variable speed) (4) Alarm sensors and indicators (5) Right-angle gear sets (for engine-driven vertical shaft turbine pumps) (6) Pressure maintenance (jockey) pump and accessories
  • 199. Summary of Fire Pump Inspection, Testing, and Maintenance
  • 200. Inspection  The purpose of inspection shall be to verify that the pump assembly appears to be in operating condition and is free from physical damage.  The pertinent visual observations specified in the following checklists shall be performed weekly (page 127)
  • 201. Testing  Diesel engine–driven fire pumps shall be operated weekly.  Electric motor–driven fire pumps shall be operated monthly.
  • 202. Testing, No-Flow Condition  A test of fire pump assemblies shall be conducted without flowing water.  The test shall be conducted by starting the pump automatically.  The electric pump shall run a minimum of 10 minutes.  The diesel pump shall run a minimum of 30 minutes.  A valve installed to open as a safety feature shall be permitted to discharge water.  An automatic timer shall be permitted to be substituted for the starting procedure.  Qualified operating personnel shall be in attendance whenever the pump is in operation.
  • 203. The pertinent visual observations or adjustments checklist  Page 128
  • 204. Annual Flow Testing  An annual test of each pump assembly shall be conducted by qualified personnel under minimum, rated, and peak flows of the fire pump by controlling the quantity of water discharged through approved test devices.  If available suction supplies do not allow flowing of 150 percent of the rated pump
  • 205. Use of Pump Discharge via Bypass Flowmeter to Pump Suction (Closed-Loop Metering).  Pump suction and discharge pressures and the flow meter measurements shall determine the total pump output.
  • 206.  The pertinent visual observations, measurements, and adjustments specified in the following checklists shall be conducted annually while the pump is running and flowing water under the specified output condition: Page 129
  • 207. Summary of Component Replacement Testing Requirements
  • 208. Summary of Component Replacement Testing Requirements
  • 209. Summary of Component Replacement Testing Requirements
  • 210. Summary of Component Replacement Testing Requirements