SlideShare a Scribd company logo
1 of 37
Download to read offline
1

10th Annual Rocky Mountain Project Management Symposium
Denver Colorado, April 2008

FIVE EASY PIECES†:
THE ESSENTIALS OF
MANAGING
PROGRAMMATIC RISK

Managing the risk to cost, schedule, and technical performance is the basis of a
successful project management method.
† With apologies to Carole Eastman and Bob Rafelson for their 1970 film staring Jack Nicholson
The Five Easy Pieces of Risk Management
2

1.  Hope is not a strategy; Only
preparedness is
2.  No point estimate of cost or schedule can
be correct
3.  Cost, schedule and technical performance
must be integrated for risk assessment to
have credibility
4.  Risk management requires adherence to
a well defined process
5.  Communication is the number one success
factor
3

HOPE IS NOT A STRATEGY;
ONLY PREPAREDNESS IS
Have specific outcomes defined before hand, with risks identified
and mitigations in place should the risks become active.
Hope is Not a Strategy
4

A Strategy is the plan to successfully complete the project

If the project’s success factors, the processes that deliver them, the
alternatives when they fail, and the measurement of this success
are not defined in meaningful ways for both the customer and
managers of the project – Hope is the only strategy left.
Hope is Not a Strategy
5

The Plan for the project is the Strategy
for its successful completion
!  This Plan needs to define:
! 

!  How

the products and services will be
“matured” as the project progresses
!  What are the “units of measure” for this
increasing maturity
!  At what points in the project will this
maturity be assessed be assessed to confirm
progress is being made
Hope is Not a Strategy
6

! 

Hope means:
! “I

hope we can get
done by the
weekend with the
integration test”
! “I hope the control
bus will be fast
enough for the
command loop”
! “I hope we’ll have
enough
management
reserve to
complete the
project on budget”

! 

A Plan means:
! If

we don’t get the
integration test done by
Friday, we’ll release
without features A, B and
F
! If the control bus is not
fats enough, we’ll run two
in parallel until the new
version is complete
! At each 20% budget
level, we’ll confirm our
deliverables value
(BCWP) match is
investment value (BCWS)
Replace Hope with a Plan to Reduce
Technical and Programmatic Risk
7

Implement	
  Best	
  Prac/ces:	
  Program	
  Schedule/Cost	
  
Analysis	
  Reflects	
  On-­‐going	
  Program	
  Risk/
Uncertainty	
  Reali/es	
  

0	
  

+	
  
Risk	
  Must	
  Decrease	
  with	
  
Program	
  Maturity	
  along	
  
with	
  the	
  tolerance	
  for	
  risk	
  

–	
  

Allowed	
  	
  Risk	
  	
  Variance	
  

! 

Ini8al	
  Concept	
  

Milestone	
  A	
  

Milestone	
  B	
  

Milestone	
  C	
  

Time	
  
8

NO POINT ESTIMATE CAN
BE CORRECT
Point estimates of cost and schedule are not only incorrect, they
are misleading – stating confidence where there is none.
No Point Estimate of duration or cost
can be correct
9

When
estimating cost
and duration
for planning
purposes using
Point Estimates
results in the
least likely
result.
A result with a
50/50 chance
of being true

Single Point Estimates use sample data to calculate
a single value (a statistic) that serves as a "best
guess" for an unknown (fixed or random) population
parameter
!  Bayesian Inference is a statistical inference where
evidence or observations are used to infer the
probability that a hypothesis may be true
!  Identifying underlying statistical behavior of the cost
and schedule parameters of the project is the first
step in forecasting future behavior
!  Without this information and the model in which it is
used any statements about cost, schedule and
completion dates are a 50/50 guesses
! 
No Point Estimate of duration or cost
can be correct
10

! 

Schedule duration and cost values are random variables
! 
! 
! 

! 

Point Estimates cannot be correct because:
! 
! 
! 

! 

Existing technical capabilities fall short of expectations
Requirements cannot be stated in a well defined list
“Normal” variance exists in all phases, especially the integration phase
Estimates of activity durations are not correct
The project duration is the sum of incorrect activity durations
Costs associated with duration may not be linear

The Actual project duration and cost will fall within some range
surrounding the “Point Estimate”
! 
! 

The best that can be expected is to understand the range of this
uncertainty
With this understanding, the project can not provision for the changes
that will occur
The Term “Best Estimate” has no
standard meaning
11

! 

The “Best Estimate” means:
!  The

“Most Likely” (Mode)?
!  The 50th percentile (Median)?
!  The expected value (Mean)?
! 

The roll up the “Best Estimates” is almost never one
of these three values
Each duration and cost has a
probability distribution
12

! 

How can it be known that:
!  The

“Best Estimate” is not the only possible estimate.
Other estimates may be worse, than the best
!  The “Most Likely” assumes that other possible duration
are possible
!  The Mean, Mode, Median are statistical terms that
characterize probability distributions – not point values
! 

The Actual duration or cost is a Random Variable,
drawn from a probability distribution
Statistics of a Triangle Distribution
13

50% of all possible values are under
this area of the curve. This is the
definition of the median

Minimum
1000 hrs
Mode = 2000 hrs

Maximum
7830 hrs
Mean = 3879 hrs
Median = 3415 hrs
A Check List for Accurate Estimates
14

! 

! 

! 

! 

Business results are
known an quantified
Project priorities are
clearly stated
A standard estimating
method is used for all
project elements
A proper Work
Breakdown Structure
has been developed

! 

! 

! 

! 

Estimates of durations
and costs have been
developed from
statistical distributions
Planned and actual
costs are being
collected
Lessons learned are
used to correct past
estimates
Management accepts
the detailed estimates
or redefines the
project
Probabilistic versus Deterministic
Estimating
15

Deterministic

Probabilistic

Simple calculation of critical path

Requires assessment of variances

Single valued durations estimates

Defined probability distribution
function (Triangle) with parametric
ranges

Cannot quantify risk

Risk defined in terms of confidence of
completing on or before a date

Criticality of an activity is either true
or not true

Criticality of an activity is probabilistic
and correlated to the network paths

Suited of “simple” project
management approaches

Suited for realistic project
management by “managing under
uncertainty” and “variability”
Points to Remember about Estimating
cost and schedule
16

! 
! 

Good planning and control depends on
good estimates
Good estimates are approximations that
depend on:
!  Experienced

cost and schedule estimators
!  Realistic assumptions
!  Recognizing unknowns with adequate reserves
!  Recognizing the past is prologue
! 

It is betetr to be aopprxitamey rhgit,

than

to be precisely wrong – Warren Buffet
17

INTEGRATE COST,
SCHEDULE AND TECHNICAL
PERFORMANCE
Connecting Schedule, Cost, and Technical Performance is the basis of establishing
a Performance Measurement Baseline (PMB) needed to successfully manage the
project
Connecting the independent variables
of project risk
18

The first impulse is to use the traditional Cost,
Schedule, and Quality
!  But a better approach is to connect
! 

!  Cost
!  Schedule
!  Technical

Performance
Without Integrating $, t, and TPM
you’re driving in the rearview mirror
19

Technical	
  
Performance	
  (TPM)	
  
Addressing customer satisfaction means incorporating products
requirements and planned quality into the Performance
Measurement Baseline to assure the true performance of the
project is made visible.
Measures of Technical Performance
20

Measure of Effectiveness
!  Measure of Performance
!  Key Performance Measures
!  Technical Performance Measures
! 

Type

Item

Threshold

Indicator

MOE

Service life

At least 18
years

Service life
expected

MOP

System capacity

At least 18
major
connections

Connections
support

TPM

Volume allocated to
storage

At least 17.5L

Tank capacity
There are other project variables
21

! 

Not just the traditional “iron triangle,” but other
aspects of the project comes in three’s

Risk

CMMI

Cost burden assigned to activities

Process framework guides improvement

Customer Satisfaction

Six Sigma

Income enhancement improved

Problem solving methods

Quality

Lean

Customer retention maintained

Execution principles reduce waste
Putting it all together means dealing
with three levels of risk reduction
22

Technical	
  
Performance	
  
Quality	
  
23

PROGRAMMATIC RISK
PROCESSES MUST BE WELL
DEFINED AND PROVEN TO
WORK AND FOLLOWED
WITH RIGOR
Use a defined risk management processes that is proven to provide value to
the project and provide a consistent method of managing risk
Without	
  a	
  model	
  for	
  risk	
  management,	
  you’re	
  driving	
  in	
  the	
  
dark	
  with	
  the	
  headlights	
  turn	
  off	
  
24

Risk	
  Management	
  means	
  using	
  a	
  proven	
  risk	
  management	
  
process,	
  adap/ng	
  this	
  to	
  the	
  project	
  environment,	
  and	
  using	
  this	
  
process	
  for	
  everyday	
  decision	
  making.	
  
25

RISK COMMUNICATION
It does no good to manage risks if the results are not
communicated to the participants
Risk Communication is not …
26

Telling people what we want them to know, in order to
get them to behave “rationally”, that is, the way we
think they should behave.
Risk Communication is …
27

An interactive process of the exchange of information
and opinion among individuals, groups, and
institutions; often involving multiple messages about
the nature of risk or expressing concerns, opinions, or
reactions to risk messages or to legal or institutional
arrangements for risk management.
Components of Risk Communication
28

! 

Understand the Perceptions of
Risk
– 

– 

– 

Key barrier is the term “risk”: how
it is measured, described, and
ultimately received
People do not believe that risks
are of the same type, size or
importance
Perception of risk for the technical
and lay audiences are often
dissimilar

! 

Acknowledge Uncertainty
– 
– 
– 
– 

If information is not known or not
available, admit it
“I don’t know” can actually build
credibility
Provide as much information as
possible
Demands for 100% certainty are
more likely based on underlying
values and process, not the
science. Try to identify the real
concerns behind the demand
Communicate Risk Graphically
29
30

WRAP UP
RISK MANAGEMENT IS HOW
ADULTS MANAGE PROJECTS
“In theory there is no difference between theory and practice.
In practice there is.”
– Yogi Berra
Summary
31

Risk management is project management
!  Risk mitigation must be made visible in the schedule
with resources, budget and risk buy down plan
!  Measure project progress with increasing maturity
of the deliverables. Measure risk progress with
reducing risk.
! 
The train wreck starts when we don’t
pay attention to the details
32

!  Inattention to budgetary

responsibilities

!  Lack of predictive variance analysis
!  Untimely and unrealistic Latest

!  Work authorization not always

followed

!  Progress not monitored in a regular

!  Budget and data reconciliation

issues exist
!  Lack of an integrated

management system
!  Baseline fluctuations and

frequent replanning

Revised Estimates (LRE)
and consistent manner

!  Lack of vertical and horizontal

traceability cost and schedule data
for corrective action
!  Lack of internal surveillance and

controls

!  Current period and retroactive!  Managerial actions not

changes
!  Improper use of management

reserve
!  EV techniques do not reflect

actual performance

demonstrated using Earned Value
Putting Risk Management to Work
33
Start With a Risk Assessment Technique
34

Risk Assessment Techniques
Process risk assessment

Used to assess (identify and analyze) program technical risks resulting from the contractor's
processes

Program Documentation
Evaluation Risk Identification

Provides a methodology for the comparison of key program documents and plans to ensure
that they are consistent and traceable to one another.

Threat and Requirements Risk
Assessment

Describes an approach to assess risk associated with requirements and threats and to
identify those requirements and threat elements that are risk drivers.

Product (WBS) Risk Assessment

Identifies those risks associated with a given system concept and design.

Cost Risk Assessment

Provides a program-level cost estimate at completion (EAC) that is a function of performance
and schedule risks.

Quantified Schedule Risk
Assessment

Provides a means to determine program-level schedule risk as a function of the technical
performance and cost risk associated with the various activities that comprise the program.

Expert Interviews

Provides a means for collecting relevant risk-related data from subject-matter experts and
personnel who are intimately involved with the various aspects of the program

Analog Comparison/Lessons
Learned Studies

Uses lessons learned and historical information about the risk associated with programs that
are similar to the new system to identify the risk associated with a new program.

Risk Prioritization and Risk
Aggregation

Provides a means to prioritize the risks present in a program and to roll-up lower level risks
into a meaningful value at the critical risk area and process level.
Manage Risk
35

Risk Process

Activities performed during the process

Controlling

Lowering the chance that an event will occur by using multiple contractors, conducting
multiple tests, reusing proven software versus developing new software, parallel
design and development of key sub-systems and components, and incremental
upgrades

Avoiding

Changing the source (element or constraint) that is subjecting the program to risk by
reducing the scope of performance objectives, using more expensive materials or
processes with proven track records, extending the schedule to increase the
probability of success.

Assuming

Planning for the potential consequences by accepting the risk, putting a monitoring
process in place, and taking action now that will support contingency actions if the
risk materializes into an actual problem.

Transferring

Transfer cost or schedule risk to another organization, and assigning responsibility to
the organization that is best suited to minimize the probability of a negative
consequence.
Top 9 Reasons Projects Fail
36

Reason
28%

Poor Communication

18%

Insufficient resource planning

13.2%

Unrealistic schedules

9.8%

Poor project Requirements
Lack of stakeholder buy in
Undefined project success factors or closure criteria
Unrealistic budgets
Insufficient or no risk planning
Lack of control or change process

6.7%
5.2%
4.8%
4.4%
4.3%
37

More Related Content

What's hot

Probabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementProbabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementGlen Alleman
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment templateGlen Alleman
 
Agile project management and normative
Agile project management and normativeAgile project management and normative
Agile project management and normativeGlen Alleman
 
Applying risk radar (v2)
Applying risk radar (v2)Applying risk radar (v2)
Applying risk radar (v2)Glen Alleman
 
Risk Management Processes (v2)
Risk Management Processes (v2)Risk Management Processes (v2)
Risk Management Processes (v2)Glen Alleman
 
Options based decisions processes
Options based decisions processesOptions based decisions processes
Options based decisions processesGlen Alleman
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMRGlen Alleman
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned valueGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Iwsm2014 defining technical risk in software development (vard antinyan)
Iwsm2014   defining technical risk in software development (vard antinyan)Iwsm2014   defining technical risk in software development (vard antinyan)
Iwsm2014 defining technical risk in software development (vard antinyan)Nesma
 
Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Glen Alleman
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Glen Alleman
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & templateAllie Gentry
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOKGeoDiga
 

What's hot (20)

Probabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementProbabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
 
Agile project management and normative
Agile project management and normativeAgile project management and normative
Agile project management and normative
 
Applying risk radar (v2)
Applying risk radar (v2)Applying risk radar (v2)
Applying risk radar (v2)
 
Handling risk
Handling riskHandling risk
Handling risk
 
Risk Management Processes (v2)
Risk Management Processes (v2)Risk Management Processes (v2)
Risk Management Processes (v2)
 
Options based decisions processes
Options based decisions processesOptions based decisions processes
Options based decisions processes
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMR
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Iwsm2014 defining technical risk in software development (vard antinyan)
Iwsm2014   defining technical risk in software development (vard antinyan)Iwsm2014   defining technical risk in software development (vard antinyan)
Iwsm2014 defining technical risk in software development (vard antinyan)
 
Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)
 
Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & template
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOK
 
Project risk management
Project risk managementProject risk management
Project risk management
 

Viewers also liked

32 Earned Value Management guidelines
32 Earned Value Management guidelines32 Earned Value Management guidelines
32 Earned Value Management guidelinesGlen Alleman
 
Glen alleman agile 04 ev+agile=success
Glen alleman agile 04 ev+agile=successGlen alleman agile 04 ev+agile=success
Glen alleman agile 04 ev+agile=successGlen Alleman
 
Earned Value numbers
Earned Value numbersEarned Value numbers
Earned Value numbersGlen Alleman
 
Probability and statistics
Probability and statisticsProbability and statistics
Probability and statisticsGlen Alleman
 
Balanced Scorecard Based Enterprise IT Organization
Balanced Scorecard Based Enterprise IT OrganizationBalanced Scorecard Based Enterprise IT Organization
Balanced Scorecard Based Enterprise IT OrganizationGlen Alleman
 
Simple plan for agile
Simple plan for agileSimple plan for agile
Simple plan for agileGlen Alleman
 
Incose vee and the imp
Incose vee and the impIncose vee and the imp
Incose vee and the impGlen Alleman
 

Viewers also liked (11)

Closed loop
Closed loopClosed loop
Closed loop
 
Open closed loop
Open closed loopOpen closed loop
Open closed loop
 
32 Earned Value Management guidelines
32 Earned Value Management guidelines32 Earned Value Management guidelines
32 Earned Value Management guidelines
 
Glen alleman agile 04 ev+agile=success
Glen alleman agile 04 ev+agile=successGlen alleman agile 04 ev+agile=success
Glen alleman agile 04 ev+agile=success
 
Earned Value numbers
Earned Value numbersEarned Value numbers
Earned Value numbers
 
Probability and statistics
Probability and statisticsProbability and statistics
Probability and statistics
 
Balanced Scorecard Based Enterprise IT Organization
Balanced Scorecard Based Enterprise IT OrganizationBalanced Scorecard Based Enterprise IT Organization
Balanced Scorecard Based Enterprise IT Organization
 
Simple plan for agile
Simple plan for agileSimple plan for agile
Simple plan for agile
 
Incose vee and the imp
Incose vee and the impIncose vee and the imp
Incose vee and the imp
 
BoE methods
BoE methodsBoE methods
BoE methods
 
Positive deviance
Positive deviancePositive deviance
Positive deviance
 

Similar to Notes on IT programmatic risk in 5 not so easy pieces

Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk toleranceGlen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Mihai Buta
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleGlen Alleman
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure CycleGlen Alleman
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityAcumen
 
Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalSEKHAR KOMMURI
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project managementGlen Alleman
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleKate Pynn
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Association for Project Management
 
Nine best practices of project management
Nine best practices of project managementNine best practices of project management
Nine best practices of project managementGlen Alleman
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceLewisFowlerLLC
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 

Similar to Notes on IT programmatic risk in 5 not so easy pieces (20)

Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk tolerance
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-Final
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
 
Nine best practices of project management
Nine best practices of project managementNine best practices of project management
Nine best practices of project management
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
Estimating
EstimatingEstimating
Estimating
 

More from Glen Alleman

A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 

More from Glen Alleman (20)

A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 

Recently uploaded

Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowranineha57744
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165meghakumariji156
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...pujan9679
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptxRoofing Contractor
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannaBusinessPlans
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Availablepr788182
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 

Recently uploaded (20)

Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 

Notes on IT programmatic risk in 5 not so easy pieces

  • 1. 1 10th Annual Rocky Mountain Project Management Symposium Denver Colorado, April 2008 FIVE EASY PIECES†: THE ESSENTIALS OF MANAGING PROGRAMMATIC RISK Managing the risk to cost, schedule, and technical performance is the basis of a successful project management method. † With apologies to Carole Eastman and Bob Rafelson for their 1970 film staring Jack Nicholson
  • 2. The Five Easy Pieces of Risk Management 2 1.  Hope is not a strategy; Only preparedness is 2.  No point estimate of cost or schedule can be correct 3.  Cost, schedule and technical performance must be integrated for risk assessment to have credibility 4.  Risk management requires adherence to a well defined process 5.  Communication is the number one success factor
  • 3. 3 HOPE IS NOT A STRATEGY; ONLY PREPAREDNESS IS Have specific outcomes defined before hand, with risks identified and mitigations in place should the risks become active.
  • 4. Hope is Not a Strategy 4 A Strategy is the plan to successfully complete the project If the project’s success factors, the processes that deliver them, the alternatives when they fail, and the measurement of this success are not defined in meaningful ways for both the customer and managers of the project – Hope is the only strategy left.
  • 5. Hope is Not a Strategy 5 The Plan for the project is the Strategy for its successful completion !  This Plan needs to define: !  !  How the products and services will be “matured” as the project progresses !  What are the “units of measure” for this increasing maturity !  At what points in the project will this maturity be assessed be assessed to confirm progress is being made
  • 6. Hope is Not a Strategy 6 !  Hope means: ! “I hope we can get done by the weekend with the integration test” ! “I hope the control bus will be fast enough for the command loop” ! “I hope we’ll have enough management reserve to complete the project on budget” !  A Plan means: ! If we don’t get the integration test done by Friday, we’ll release without features A, B and F ! If the control bus is not fats enough, we’ll run two in parallel until the new version is complete ! At each 20% budget level, we’ll confirm our deliverables value (BCWP) match is investment value (BCWS)
  • 7. Replace Hope with a Plan to Reduce Technical and Programmatic Risk 7 Implement  Best  Prac/ces:  Program  Schedule/Cost   Analysis  Reflects  On-­‐going  Program  Risk/ Uncertainty  Reali/es   0   +   Risk  Must  Decrease  with   Program  Maturity  along   with  the  tolerance  for  risk   –   Allowed    Risk    Variance   !  Ini8al  Concept   Milestone  A   Milestone  B   Milestone  C   Time  
  • 8. 8 NO POINT ESTIMATE CAN BE CORRECT Point estimates of cost and schedule are not only incorrect, they are misleading – stating confidence where there is none.
  • 9. No Point Estimate of duration or cost can be correct 9 When estimating cost and duration for planning purposes using Point Estimates results in the least likely result. A result with a 50/50 chance of being true Single Point Estimates use sample data to calculate a single value (a statistic) that serves as a "best guess" for an unknown (fixed or random) population parameter !  Bayesian Inference is a statistical inference where evidence or observations are used to infer the probability that a hypothesis may be true !  Identifying underlying statistical behavior of the cost and schedule parameters of the project is the first step in forecasting future behavior !  Without this information and the model in which it is used any statements about cost, schedule and completion dates are a 50/50 guesses ! 
  • 10. No Point Estimate of duration or cost can be correct 10 !  Schedule duration and cost values are random variables !  !  !  !  Point Estimates cannot be correct because: !  !  !  !  Existing technical capabilities fall short of expectations Requirements cannot be stated in a well defined list “Normal” variance exists in all phases, especially the integration phase Estimates of activity durations are not correct The project duration is the sum of incorrect activity durations Costs associated with duration may not be linear The Actual project duration and cost will fall within some range surrounding the “Point Estimate” !  !  The best that can be expected is to understand the range of this uncertainty With this understanding, the project can not provision for the changes that will occur
  • 11. The Term “Best Estimate” has no standard meaning 11 !  The “Best Estimate” means: !  The “Most Likely” (Mode)? !  The 50th percentile (Median)? !  The expected value (Mean)? !  The roll up the “Best Estimates” is almost never one of these three values
  • 12. Each duration and cost has a probability distribution 12 !  How can it be known that: !  The “Best Estimate” is not the only possible estimate. Other estimates may be worse, than the best !  The “Most Likely” assumes that other possible duration are possible !  The Mean, Mode, Median are statistical terms that characterize probability distributions – not point values !  The Actual duration or cost is a Random Variable, drawn from a probability distribution
  • 13. Statistics of a Triangle Distribution 13 50% of all possible values are under this area of the curve. This is the definition of the median Minimum 1000 hrs Mode = 2000 hrs Maximum 7830 hrs Mean = 3879 hrs Median = 3415 hrs
  • 14. A Check List for Accurate Estimates 14 !  !  !  !  Business results are known an quantified Project priorities are clearly stated A standard estimating method is used for all project elements A proper Work Breakdown Structure has been developed !  !  !  !  Estimates of durations and costs have been developed from statistical distributions Planned and actual costs are being collected Lessons learned are used to correct past estimates Management accepts the detailed estimates or redefines the project
  • 15. Probabilistic versus Deterministic Estimating 15 Deterministic Probabilistic Simple calculation of critical path Requires assessment of variances Single valued durations estimates Defined probability distribution function (Triangle) with parametric ranges Cannot quantify risk Risk defined in terms of confidence of completing on or before a date Criticality of an activity is either true or not true Criticality of an activity is probabilistic and correlated to the network paths Suited of “simple” project management approaches Suited for realistic project management by “managing under uncertainty” and “variability”
  • 16. Points to Remember about Estimating cost and schedule 16 !  !  Good planning and control depends on good estimates Good estimates are approximations that depend on: !  Experienced cost and schedule estimators !  Realistic assumptions !  Recognizing unknowns with adequate reserves !  Recognizing the past is prologue !  It is betetr to be aopprxitamey rhgit, than to be precisely wrong – Warren Buffet
  • 17. 17 INTEGRATE COST, SCHEDULE AND TECHNICAL PERFORMANCE Connecting Schedule, Cost, and Technical Performance is the basis of establishing a Performance Measurement Baseline (PMB) needed to successfully manage the project
  • 18. Connecting the independent variables of project risk 18 The first impulse is to use the traditional Cost, Schedule, and Quality !  But a better approach is to connect !  !  Cost !  Schedule !  Technical Performance
  • 19. Without Integrating $, t, and TPM you’re driving in the rearview mirror 19 Technical   Performance  (TPM)   Addressing customer satisfaction means incorporating products requirements and planned quality into the Performance Measurement Baseline to assure the true performance of the project is made visible.
  • 20. Measures of Technical Performance 20 Measure of Effectiveness !  Measure of Performance !  Key Performance Measures !  Technical Performance Measures !  Type Item Threshold Indicator MOE Service life At least 18 years Service life expected MOP System capacity At least 18 major connections Connections support TPM Volume allocated to storage At least 17.5L Tank capacity
  • 21. There are other project variables 21 !  Not just the traditional “iron triangle,” but other aspects of the project comes in three’s Risk CMMI Cost burden assigned to activities Process framework guides improvement Customer Satisfaction Six Sigma Income enhancement improved Problem solving methods Quality Lean Customer retention maintained Execution principles reduce waste
  • 22. Putting it all together means dealing with three levels of risk reduction 22 Technical   Performance   Quality  
  • 23. 23 PROGRAMMATIC RISK PROCESSES MUST BE WELL DEFINED AND PROVEN TO WORK AND FOLLOWED WITH RIGOR Use a defined risk management processes that is proven to provide value to the project and provide a consistent method of managing risk
  • 24. Without  a  model  for  risk  management,  you’re  driving  in  the   dark  with  the  headlights  turn  off   24 Risk  Management  means  using  a  proven  risk  management   process,  adap/ng  this  to  the  project  environment,  and  using  this   process  for  everyday  decision  making.  
  • 25. 25 RISK COMMUNICATION It does no good to manage risks if the results are not communicated to the participants
  • 26. Risk Communication is not … 26 Telling people what we want them to know, in order to get them to behave “rationally”, that is, the way we think they should behave.
  • 27. Risk Communication is … 27 An interactive process of the exchange of information and opinion among individuals, groups, and institutions; often involving multiple messages about the nature of risk or expressing concerns, opinions, or reactions to risk messages or to legal or institutional arrangements for risk management.
  • 28. Components of Risk Communication 28 !  Understand the Perceptions of Risk –  –  –  Key barrier is the term “risk”: how it is measured, described, and ultimately received People do not believe that risks are of the same type, size or importance Perception of risk for the technical and lay audiences are often dissimilar !  Acknowledge Uncertainty –  –  –  –  If information is not known or not available, admit it “I don’t know” can actually build credibility Provide as much information as possible Demands for 100% certainty are more likely based on underlying values and process, not the science. Try to identify the real concerns behind the demand
  • 30. 30 WRAP UP RISK MANAGEMENT IS HOW ADULTS MANAGE PROJECTS “In theory there is no difference between theory and practice. In practice there is.” – Yogi Berra
  • 31. Summary 31 Risk management is project management !  Risk mitigation must be made visible in the schedule with resources, budget and risk buy down plan !  Measure project progress with increasing maturity of the deliverables. Measure risk progress with reducing risk. ! 
  • 32. The train wreck starts when we don’t pay attention to the details 32 !  Inattention to budgetary responsibilities !  Lack of predictive variance analysis !  Untimely and unrealistic Latest !  Work authorization not always followed !  Progress not monitored in a regular !  Budget and data reconciliation issues exist !  Lack of an integrated management system !  Baseline fluctuations and frequent replanning Revised Estimates (LRE) and consistent manner !  Lack of vertical and horizontal traceability cost and schedule data for corrective action !  Lack of internal surveillance and controls !  Current period and retroactive!  Managerial actions not changes !  Improper use of management reserve !  EV techniques do not reflect actual performance demonstrated using Earned Value
  • 34. Start With a Risk Assessment Technique 34 Risk Assessment Techniques Process risk assessment Used to assess (identify and analyze) program technical risks resulting from the contractor's processes Program Documentation Evaluation Risk Identification Provides a methodology for the comparison of key program documents and plans to ensure that they are consistent and traceable to one another. Threat and Requirements Risk Assessment Describes an approach to assess risk associated with requirements and threats and to identify those requirements and threat elements that are risk drivers. Product (WBS) Risk Assessment Identifies those risks associated with a given system concept and design. Cost Risk Assessment Provides a program-level cost estimate at completion (EAC) that is a function of performance and schedule risks. Quantified Schedule Risk Assessment Provides a means to determine program-level schedule risk as a function of the technical performance and cost risk associated with the various activities that comprise the program. Expert Interviews Provides a means for collecting relevant risk-related data from subject-matter experts and personnel who are intimately involved with the various aspects of the program Analog Comparison/Lessons Learned Studies Uses lessons learned and historical information about the risk associated with programs that are similar to the new system to identify the risk associated with a new program. Risk Prioritization and Risk Aggregation Provides a means to prioritize the risks present in a program and to roll-up lower level risks into a meaningful value at the critical risk area and process level.
  • 35. Manage Risk 35 Risk Process Activities performed during the process Controlling Lowering the chance that an event will occur by using multiple contractors, conducting multiple tests, reusing proven software versus developing new software, parallel design and development of key sub-systems and components, and incremental upgrades Avoiding Changing the source (element or constraint) that is subjecting the program to risk by reducing the scope of performance objectives, using more expensive materials or processes with proven track records, extending the schedule to increase the probability of success. Assuming Planning for the potential consequences by accepting the risk, putting a monitoring process in place, and taking action now that will support contingency actions if the risk materializes into an actual problem. Transferring Transfer cost or schedule risk to another organization, and assigning responsibility to the organization that is best suited to minimize the probability of a negative consequence.
  • 36. Top 9 Reasons Projects Fail 36 Reason 28% Poor Communication 18% Insufficient resource planning 13.2% Unrealistic schedules 9.8% Poor project Requirements Lack of stakeholder buy in Undefined project success factors or closure criteria Unrealistic budgets Insufficient or no risk planning Lack of control or change process 6.7% 5.2% 4.8% 4.4% 4.3%
  • 37. 37