While performing maintenance at the Wellington II Pump Station, a problem was discovered with the existing 4-inch force main that was causing issues with proper flow. An emergency project was initiated to identify and repair the issue. This included installing a temporary bypass pumping system, relocating a gas line, and installing two new 2-inch parallel force mains to replace the existing line. The emergency project was substantially completed in November 2020.