SlideShare a Scribd company logo
1 of 16
Download to read offline
Dominion Cove Point LNG, LP
701 East Cary Street, Richmond, VA 23219
June 23, 2016
Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426
Re: Dominion Cove Point LNG, LP
Cove Point Liquefaction Project
Docket No. CP13-113-000
Monthly Status and Progress Report – May 2016
Dear Secretary Bose:
By Order dated September 29, 2014, the Federal Energy Regulatory Commission (FERC or
Commission) authorized Dominion Cove Point LNG, LP (DCP or Dominion) to construct and
operate certain facilities that comprise the Cove Point Liquefaction Project (Project). Dominion
Cove Point LNG, LP. 148 FERC ¶ 61,244 (the “Order”).
As required under Condition Nos. 9 and 76 of Appendix B to the Order, DCP hereby submits the
updated status report and progress on the construction of the proposed systems for the Project.
If you have any questions, please contact me at 804-771-4796.
Respectfully submitted,
/s/ Deborah T. Gholson
Deborah T. Gholson
Gas Transmission Certificates Program Manager
cc: Joanne Wachholder, FERC
Ghanshyam Patel, FERC
Thach Nguyen, FERC
Service List
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
Dominion Cove Point LNG, LP
Cove Point Liquefaction Project
Docket No. CP13-113-000
Monthly Status and Progress Report – May 2016
Table of contents.........................................................................................................................................2
1:Update on Federal authorizations ................................................................................................ 3
2:Construction Status – Executive Summary.................................................................................... 3
3:Construction Status Activity Summary.......................................................................................... 4
4:Schedule changes for stream crossings/other Environmentally-sensitive areas................................. 8
5:Listing of problem areas encountered and/or instances of noncompliance Observed by each
Environmental Inspector (EI) ......................................................................................................... 8
6:Copies of Correspondence Received Concerning Instances of Noncompliance from other
Federal, State, or Local Permitting Agencies and Dominion’s Response.............................................. 8
7:Contractor Non-Conformance/Deficiency Logs .............................................................................. 8
8:Landowner/Resident Complaint Tracking...................................................................................... 9
9:Construction photos ................................................................................................................. 10
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
1: Update on Federal Authorizations
Dominion has received all applicable authorizations under federal law for the Project.
2: Construction Status – Executive Summary
Construction status during the reporting period of May 2016:
For this review period, the following project completion status for the Maryland Facilities
has been accomplished:
• Engineering is 99.8% complete
• Engineered Equipment Procurement is 99% complete
• Construction is 38% complete
Offsite area B (OAB):
There was one barge equipment delivery during the month of May. The following pieces
of equipment were transported through OAB; high pressure knock out drum, north and
south cold flare knock out drums. Monitoring and maintenance of E&S controls continues
to ensure proper environmental protection.
Existing plant modifications:
At the terminal, work continued on modifications to the existing plant in the areas of the
jetty platforms and tie-in scope.
FERC authorized scope at the terminal:
At the terminal, work scope continued on foundations, grading, steel erection, equipment
placement, piping, tie-in’s, and electrical installation as described below.
FERC authorized scope at the Virginia Facilities:
Construction activities conducted during the May period included continued materials
delivery, site work, foundation work, piping work, equipment work, and building erection.
Work during the May reporting period coincided with an outage of the compressor station
and M&R station operations to facilitate construction and tie-in activities.
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
3: Construction Status Activity Summary
Maryland Construction status
Area Work Activities Work for next work period.
Offsite
Areas
• Maintenance of E&S controls.
• Barges that were received:
o 5/18/16 - Barge 31 delivery - HP Flare KO Drum, South Cold Flare KO Drum,
North Cold Flare KO Drum.
• Continue receiving barges and supporting heavy haul
equipment deliveries.
Terminal
Completed
Concrete Placement:
• Placement of concrete for the air Compressor Building foundation, dry air receiver,
and the south VFD transformer blast wall.
Equipment:
• Setting of north and south VFD transformers.
• Setting of the regeneration gas filter (A/B), separator, heater steam condensate
pot, and compressors (A/B).
• Setting of the demercurizer dust filter (A/B).
• Setting of the dehydrator gas filter (A/B).
• Setting of the North HP and LP flare KO drum.
• Setting of the North Cold flare KO drum.
• Setting of the amine circulation pump (A/B).
• Setting of the propane and ethane dehydrator/demercurizers.
• Setting of the hydrocarbon condensate dehydrators.
• Setting of the feed gas heater.
• Setting of the air compressor building internal equipment air compressors,
receivers, skids.
• Installation of the south CT building bridge crane.
• Installation of the main steam condensate pumps (3).
• Installing ammonia manifold, steel work, and internal insulation/liners on north
HRSG.
Electrical:
• Installation of cable tray under sub 18 and 21.
• Installation of batteries at sub-stations 20 and 21.
• Structural Steel:
• Erection of the North STG and auxiliary boiler platform steel.
• Steel erection for the deaerator and feed water pump structure.
• Structural steel installation for utility and common racks.
• Concrete placement for the spare transformer pads.
• Erection of the pre-fab electrical building in the STG
area.
• Erection of the air compressor building.
• Pull cable from sub-station 21 to thermal oxidizer.
• Installation of the following equipment:
• Setting of the north and south STG control oil
tank/ module and pumps.
• Setting of the quench water pumps (2).
• Setting of the north CT train ACHE unit.
• Setting the north & south GE VFD air cooled heat
exchangers.
• Setting of the main steam condensate filters and
pumps.
• Setting of the propane reclaimer and condenser.
20160623-5086FERCPDF(Unofficial)6/23/201611:11:57AM
Maryland Construction status
• Hollywood & Central Avenue pipe bridge structural steel.
• Installation of the south flare shielding wall panels minus leave outs.
• Mezzanine deck installation on the north CT/Compressor deck.
• Erection of the fuel gas flash gas building structural steel minus leave outs.
Continued
Equipment:
• Installing ammonia manifold, steel work, and internal insulation/liners on south
HRSG.
• Ground assembly and setting of the ACC fan housings, tube sheet placements,
modular fabrication of the "A" frames shrouds and motor bridges (1 remaining)
and structural support steel.
• Installation of instrumentation on north and south HRSGs.
• Installation of crystallizer vapor ductwork.
• Setting of the fire pump house enclosures.
Structural Steel:
• Exterior wall panel installation on the north and south CT buildings, and the water
treatment building.
• Erection of the auxiliary boiler building, steam turbine generator building, north &
south CT buildings, fuel/flash gas compressor building and the water treatment
building.
• Erection of the north and south STG platform steel.
• Mezzanine deck installation on the south CT/Compressor deck.
• Steel work at Maryland marina - fabricated and loaded at the site to load onto
barge.
• Erection of the following pipe racks in the following areas:
– Pretreatment pipe rack
– Main Liquefaction north/south, east/west pipe rack, fuel/flash gas pipe
rack and the lean gas pipe rack.
– Power Block utility pipe rack.
Piping – welding and installations:
• Installation and welding of piping systems in the following areas:
– Liquefaction:
• North/south and east/west pipe racks- Mixed refrigerant, propane,
natural gas, and utilities.
20160623-5086FERCPDF(Unofficial)6/23/201611:11:57AM
Maryland Construction status
– Pre-treatment:
• North/south rack- Natural gas, flare, and utilities
– Power Block:
• Gas turbine buildings and common rack- Propane, mixed
refrigerant, and utilities.
– OSBL:
• North jetty and north/south flare- Flare and nitrogen.
• Installation of the concrete trough in the north/south pre-treatment pipe rack.
• Installation/testing of underground FW, RW, FG, blow down piping, DMW piping
and plant air piping (all underground piping is approximately 99% complete).
Electrical:
• Pulling of electrical cable between substations and utility power and lighting.
• Installing electrical tray at sub-station 19, throughout liquefaction and power block
area.
• Installation of bus duct in sub-station 18 and 19.
Virginia Construction status
Area Work Activities Work Planned for Next Period
Pleasant
Valley
• Mobilization of crew, equipment, and materials.
• Site work including
1. E&S control maintenance,
2. construction of permanent stormwater management units, and
3. excess soil removal for offsite landfill disposal.
• Foundation work including concrete pilings and pads for new equipment,
sound wall and compressor building.
• Piping work including trenching, fabrication, coating, installation, and
backfilling at compressor station and M&R station.
• Outage completion:
1. M&R placed back in operation May 2.
2. Station placed back in operation May 9.
• Continued materials delivery.
• Continued site work including trenching, grading, soil
removal, and E&S control maintenance.
• Foundation work for new equipment, sound wall, and
compressor building.
• Piping and equipment work including installation of 36”
suction pipeline from M&R to compressor station.
20160623-5086FERCPDF(Unofficial)6/23/201611:11:57AM
4: Schedule Changes for Stream Crossings/Other Environmentally-Sensitive Areas:
No schedule changes for stream crossings or work in other environmentally-sensitive
areas were noted during this reporting period or are expected to occur in the next
reporting period for the Maryland and Virginia Facilities.
5: Listing of Problem Areas Encountered and/or Instances of Noncompliance
Observed by each Environmental Inspector (EI)
Maryland Environmental Non-Compliances or Problem Areas
Non-compliance or Problem Area Remedial actions taken Effectiveness of Corrective
Actions Implemented
1. There was no environmental non-
compliance or problem area for this
reporting period.
N/A N/A
Virginia Environmental Non-Compliances or Problem Areas
Non-compliance or Problem Area Remedial actions taken Effectiveness of Corrective
Actions Implemented
1. There was no environmental non-
compliance or problem area for this
reporting period.
N/A N/A
6: Copies of Correspondence Received Concerning Instances of Noncompliance from
other Federal, State, or Local Permitting Agencies and Dominion’s Response
No correspondence was received concerning instances of noncompliance from other
federal, state, or local permitting agencies for the Maryland and Virginia Facilities.
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
7: Maryland Contractor Non-Conformance/Deficiency and Logs
From previous reports, NCR 161 resolution has been determined to be okay to remain as
is and is now closed.
Contractor Non-Conformance/Deficiency Logs
Maryland Contractor Non-Conformance/Deficiency Logs
Non-conformance
(NCR)
Description Remedial actions taken
172. Welding:
Low Porosity
A weld on a water drain line for the air compressor
building had a RT performed and was rejected due to
excessive porosity. Before the weld was repaired, the
joint was encapsulated in concrete.
After engineering review, the line
will see “0.0” PSI at normal
operating conditions and will be
okay to remain as is.-closed
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
8: MARYLAND AND VIRGINIA LANDOWNER/RESIDENT COMPLAINT TRACKING
Caller Name Date
Facility/Location
Affected
Description of Problem/Concern
Explanation of How and When Problem
was Resolved/Will be Resolved/Why it
has not been Resolved
MARYLAND:
None.
VIRGINIA:
None.
20160623-5086FERCPDF(Unofficial)6/23/201611:11:57AM
9: Maryland Construction photos:
LNG Terminal: South flare vendor piping being installed. 03MAY2016
LNG Terminal: Lean amine pumps. 05MAY2016
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
LNG Terminal
LNG Terminal:
LNG Terminal: ACC tube sheet installation. 12MAY2016
LNG Terminal: Tie-In point 68 hot tap. 18MAY2016
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
LNG Terminal: Air cooled condenser s
LNG Terminal:
ir cooled condenser street 1 steam condensate collecting manifolds
24MAY2016
LNG Terminal: South HRSG silencers. 26MAY2016
steam condensate collecting manifolds being aligned.
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
LNG Terminal: Platform installation
LNG Terminal: Welding the expansion joints on the
Platform installation for the amine regenerator. 26MAY201
expansion joints on the steam distribution manifolds
2016
steam distribution manifolds. 31MAY2016
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
Virginia Construction photos:
Pleasant Valley: Piping and valve installation at M&R station. 2MAY2016
Pleasant Valley: Setting piers for soundwall east of new compressor building. 14MAY2016
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
Pleasant Valley: Foundation work for new compressor building and compressor units. 16MAY2016
Pleasant Valley: Survey stakes and material staging for upcoming 36” pipeline installation from M&R to
compressor Station. 24MAY2016
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
Document Content(s)
PUBLIC - DCP Monthly Report - May 2016.PDF............................1-15
20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM

More Related Content

What's hot

Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Fairfax County
 
Summerton Way Pond Retrofit
Summerton Way Pond RetrofitSummerton Way Pond Retrofit
Summerton Way Pond RetrofitFairfax County
 
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...Fairfax County
 
Paul Spring Branch Stream Restoration Project Community Meeting
Paul Spring Branch Stream Restoration Project Community MeetingPaul Spring Branch Stream Restoration Project Community Meeting
Paul Spring Branch Stream Restoration Project Community MeetingFairfax County
 
Overview & Application 2010 CBCvChapter 16, 16A, 17 &17A
Overview & Application 2010 CBCvChapter 16, 16A, 17 &17AOverview & Application 2010 CBCvChapter 16, 16A, 17 &17A
Overview & Application 2010 CBCvChapter 16, 16A, 17 &17AHemmatyar
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationFairfax County
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveFairfax County
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationFairfax County
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaMichaelUberti
 
Terra Grande Pond PSP and Riser Replacement
Terra Grande Pond PSP and Riser ReplacementTerra Grande Pond PSP and Riser Replacement
Terra Grande Pond PSP and Riser ReplacementFairfax County
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Fairfax County
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Jeffrey Pickett
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Fairfax County
 
short cv Jan 96 onward
short cv Jan 96 onwardshort cv Jan 96 onward
short cv Jan 96 onwardJohn Jones
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Fairfax County
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsFairfax County
 

What's hot (20)

Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
 
Summerton Way Pond Retrofit
Summerton Way Pond RetrofitSummerton Way Pond Retrofit
Summerton Way Pond Retrofit
 
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
 
Paul Spring Branch Stream Restoration Project Community Meeting
Paul Spring Branch Stream Restoration Project Community MeetingPaul Spring Branch Stream Restoration Project Community Meeting
Paul Spring Branch Stream Restoration Project Community Meeting
 
Overview & Application 2010 CBCvChapter 16, 16A, 17 &17A
Overview & Application 2010 CBCvChapter 16, 16A, 17 &17AOverview & Application 2010 CBCvChapter 16, 16A, 17 &17A
Overview & Application 2010 CBCvChapter 16, 16A, 17 &17A
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road Presentation
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
Terra Grande Pond PSP and Riser Replacement
Terra Grande Pond PSP and Riser ReplacementTerra Grande Pond PSP and Riser Replacement
Terra Grande Pond PSP and Riser Replacement
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration Project
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016
 
Environmental Challenges in Oil and Gas Production by Gary E. Slagel
Environmental Challenges in Oil and Gas Production by Gary E. Slagel Environmental Challenges in Oil and Gas Production by Gary E. Slagel
Environmental Challenges in Oil and Gas Production by Gary E. Slagel
 
short cv Jan 96 onward
short cv Jan 96 onwardshort cv Jan 96 onward
short cv Jan 96 onward
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
 
CV - AGK LinkedIn
CV - AGK LinkedInCV - AGK LinkedIn
CV - AGK LinkedIn
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk Improvements
 

Viewers also liked

Marca Personal: Cómo Sobresalir en un Mercado Ultra Competitivo
Marca Personal: Cómo Sobresalir en un Mercado Ultra CompetitivoMarca Personal: Cómo Sobresalir en un Mercado Ultra Competitivo
Marca Personal: Cómo Sobresalir en un Mercado Ultra CompetitivoEmmanuel Gutierrez
 
Zita's Mit optional essay
Zita's Mit optional essayZita's Mit optional essay
Zita's Mit optional essaybetterman9394
 
Acto de escribir
Acto de escribirActo de escribir
Acto de escribirJorge León
 
Valoración en aduana
Valoración en aduanaValoración en aduana
Valoración en aduanaEveJ26
 
Snowden traitor or spy
Snowden traitor or spySnowden traitor or spy
Snowden traitor or spyMohsin Abbasi
 
Moderco Crystal Glass Walls - 44 STC
Moderco Crystal Glass Walls - 44 STCModerco Crystal Glass Walls - 44 STC
Moderco Crystal Glass Walls - 44 STCCharles Joslin
 
Change Management_Change Before You Have To
Change Management_Change Before You Have ToChange Management_Change Before You Have To
Change Management_Change Before You Have ToJenn Haskell MBA
 
soal UKK semester 2 kelas XI
soal UKK semester 2 kelas XIsoal UKK semester 2 kelas XI
soal UKK semester 2 kelas XIandi33333
 
SugarCRM Presents the New Rules of Social CRM
SugarCRM Presents the New Rules of Social CRMSugarCRM Presents the New Rules of Social CRM
SugarCRM Presents the New Rules of Social CRMClint Oram
 
Internet pour découvrir l'art
Internet pour découvrir l'artInternet pour découvrir l'art
Internet pour découvrir l'artmahemard
 
Conférence Spa&Beauté Kispa
 Conférence Spa&Beauté Kispa  Conférence Spa&Beauté Kispa
Conférence Spa&Beauté Kispa TRAN Denis
 
Glosario ilustrado sobre conceptos relacionados con el DUA
Glosario ilustrado sobre conceptos relacionados con el DUAGlosario ilustrado sobre conceptos relacionados con el DUA
Glosario ilustrado sobre conceptos relacionados con el DUACarmen Salas
 
Real World Business Intelligence and Data Warehousing
Real World Business Intelligence and Data WarehousingReal World Business Intelligence and Data Warehousing
Real World Business Intelligence and Data Warehousingukc4
 

Viewers also liked (19)

Presentation1 Norway Kitchen
Presentation1  Norway KitchenPresentation1  Norway Kitchen
Presentation1 Norway Kitchen
 
Marca Personal: Cómo Sobresalir en un Mercado Ultra Competitivo
Marca Personal: Cómo Sobresalir en un Mercado Ultra CompetitivoMarca Personal: Cómo Sobresalir en un Mercado Ultra Competitivo
Marca Personal: Cómo Sobresalir en un Mercado Ultra Competitivo
 
John locke
John lockeJohn locke
John locke
 
Zita's Mit optional essay
Zita's Mit optional essayZita's Mit optional essay
Zita's Mit optional essay
 
Acto de escribir
Acto de escribirActo de escribir
Acto de escribir
 
Valoración en aduana
Valoración en aduanaValoración en aduana
Valoración en aduana
 
Snowden traitor or spy
Snowden traitor or spySnowden traitor or spy
Snowden traitor or spy
 
Fearless presenter
Fearless presenterFearless presenter
Fearless presenter
 
Moderco Crystal Glass Walls - 44 STC
Moderco Crystal Glass Walls - 44 STCModerco Crystal Glass Walls - 44 STC
Moderco Crystal Glass Walls - 44 STC
 
Change Management_Change Before You Have To
Change Management_Change Before You Have ToChange Management_Change Before You Have To
Change Management_Change Before You Have To
 
soal UKK semester 2 kelas XI
soal UKK semester 2 kelas XIsoal UKK semester 2 kelas XI
soal UKK semester 2 kelas XI
 
SugarCRM Presents the New Rules of Social CRM
SugarCRM Presents the New Rules of Social CRMSugarCRM Presents the New Rules of Social CRM
SugarCRM Presents the New Rules of Social CRM
 
Storyboard
StoryboardStoryboard
Storyboard
 
Internet pour découvrir l'art
Internet pour découvrir l'artInternet pour découvrir l'art
Internet pour découvrir l'art
 
GLASS
GLASS GLASS
GLASS
 
Conférence Spa&Beauté Kispa
 Conférence Spa&Beauté Kispa  Conférence Spa&Beauté Kispa
Conférence Spa&Beauté Kispa
 
Animales salvajes
Animales salvajesAnimales salvajes
Animales salvajes
 
Glosario ilustrado sobre conceptos relacionados con el DUA
Glosario ilustrado sobre conceptos relacionados con el DUAGlosario ilustrado sobre conceptos relacionados con el DUA
Glosario ilustrado sobre conceptos relacionados con el DUA
 
Real World Business Intelligence and Data Warehousing
Real World Business Intelligence and Data WarehousingReal World Business Intelligence and Data Warehousing
Real World Business Intelligence and Data Warehousing
 

Similar to Dominion Cove Point LNG Facility May 2016 Status Report

Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Jeffrey Pickett
 
SUA presentation of the Power Generation Station Project
SUA presentation of the Power Generation Station ProjectSUA presentation of the Power Generation Station Project
SUA presentation of the Power Generation Station ProjectCity of Stillwater
 
Fairfax County Tertiary Filtration System Rehabilitation July 2020
Fairfax County Tertiary Filtration System Rehabilitation July 2020Fairfax County Tertiary Filtration System Rehabilitation July 2020
Fairfax County Tertiary Filtration System Rehabilitation July 2020Fairfax County
 
Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Dennis Kehoe
 
IJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptxIJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptxAGNELVVARKEY
 
Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities Fairfax County
 
Patrick_C._McDuffie CV and EXP 2016
Patrick_C._McDuffie CV and EXP 2016Patrick_C._McDuffie CV and EXP 2016
Patrick_C._McDuffie CV and EXP 2016Patrick McDuffie
 
In situ Ship repair maintenance Presentation.pptx
In situ Ship repair maintenance Presentation.pptxIn situ Ship repair maintenance Presentation.pptx
In situ Ship repair maintenance Presentation.pptxHieu Dang
 
Jvs resume' word chronological format r5tasks
Jvs  resume' word chronological format r5tasksJvs  resume' word chronological format r5tasks
Jvs resume' word chronological format r5tasksJohn V. Sandbothe
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectFairfax County
 
What Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning jobWhat Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning jobjoseph william
 
ResumeofKennethThompson09242015(LOCAL)
ResumeofKennethThompson09242015(LOCAL)ResumeofKennethThompson09242015(LOCAL)
ResumeofKennethThompson09242015(LOCAL)Kenneth Thompson
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationFairfax County
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description detailsAonghus Murray
 
JC RESUME 08-08-15
JC RESUME 08-08-15JC RESUME 08-08-15
JC RESUME 08-08-15john coombe
 

Similar to Dominion Cove Point LNG Facility May 2016 Status Report (20)

Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.
 
SUA presentation of the Power Generation Station Project
SUA presentation of the Power Generation Station ProjectSUA presentation of the Power Generation Station Project
SUA presentation of the Power Generation Station Project
 
Fairfax County Tertiary Filtration System Rehabilitation July 2020
Fairfax County Tertiary Filtration System Rehabilitation July 2020Fairfax County Tertiary Filtration System Rehabilitation July 2020
Fairfax County Tertiary Filtration System Rehabilitation July 2020
 
Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015
 
IJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptxIJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptx
 
Pipininspect
PipininspectPipininspect
Pipininspect
 
Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities
 
Patrick_C._McDuffie CV and EXP 2016
Patrick_C._McDuffie CV and EXP 2016Patrick_C._McDuffie CV and EXP 2016
Patrick_C._McDuffie CV and EXP 2016
 
Jack Oler 1
Jack Oler 1Jack Oler 1
Jack Oler 1
 
Richard Martinez #1 PDF
Richard Martinez #1 PDFRichard Martinez #1 PDF
Richard Martinez #1 PDF
 
In situ Ship repair maintenance Presentation.pptx
In situ Ship repair maintenance Presentation.pptxIn situ Ship repair maintenance Presentation.pptx
In situ Ship repair maintenance Presentation.pptx
 
Jvs resume' word chronological format r5tasks
Jvs  resume' word chronological format r5tasksJvs  resume' word chronological format r5tasks
Jvs resume' word chronological format r5tasks
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation Project
 
JG Mech Eng CV
JG Mech Eng CVJG Mech Eng CV
JG Mech Eng CV
 
What Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning jobWhat Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning job
 
ResumeofKennethThompson09242015(LOCAL)
ResumeofKennethThompson09242015(LOCAL)ResumeofKennethThompson09242015(LOCAL)
ResumeofKennethThompson09242015(LOCAL)
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
 
Resume C Brewer
Resume C BrewerResume C Brewer
Resume C Brewer
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
JC RESUME 08-08-15
JC RESUME 08-08-15JC RESUME 08-08-15
JC RESUME 08-08-15
 

More from Marcellus Drilling News

Five facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strongFive facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strongMarcellus Drilling News
 
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)Marcellus Drilling News
 
Access Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 UpdateAccess Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 UpdateMarcellus Drilling News
 
Rover Pipeline Letter to FERC Requesting Final Certificate
Rover Pipeline Letter to FERC Requesting Final CertificateRover Pipeline Letter to FERC Requesting Final Certificate
Rover Pipeline Letter to FERC Requesting Final CertificateMarcellus Drilling News
 
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA CountriesDOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA CountriesMarcellus Drilling News
 
LSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. ManufacturingLSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. ManufacturingMarcellus Drilling News
 
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...Marcellus Drilling News
 
Report: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental ExternalitiesReport: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental ExternalitiesMarcellus Drilling News
 
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015Marcellus Drilling News
 
U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015Marcellus Drilling News
 
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids PlantsVelocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids PlantsMarcellus Drilling News
 
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...Marcellus Drilling News
 
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...Marcellus Drilling News
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsMarcellus Drilling News
 
US EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy OutlookUS EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy OutlookMarcellus Drilling News
 
Northeast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical GuideNortheast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical GuideMarcellus Drilling News
 
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee AuditPA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee AuditMarcellus Drilling News
 
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...Marcellus Drilling News
 
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final ReportClyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final ReportMarcellus Drilling News
 
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion ProjectFERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion ProjectMarcellus Drilling News
 

More from Marcellus Drilling News (20)

Five facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strongFive facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strong
 
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
 
Access Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 UpdateAccess Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 Update
 
Rover Pipeline Letter to FERC Requesting Final Certificate
Rover Pipeline Letter to FERC Requesting Final CertificateRover Pipeline Letter to FERC Requesting Final Certificate
Rover Pipeline Letter to FERC Requesting Final Certificate
 
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA CountriesDOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
 
LSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. ManufacturingLSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. Manufacturing
 
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
 
Report: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental ExternalitiesReport: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental Externalities
 
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
 
U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015
 
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids PlantsVelocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
 
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
 
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas Operations
 
US EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy OutlookUS EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy Outlook
 
Northeast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical GuideNortheast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical Guide
 
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee AuditPA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
 
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
 
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final ReportClyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
 
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion ProjectFERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
 

Recently uploaded

Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsnaxymaxyy
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...Ismail Fahmi
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012ankitnayak356677
 
Chandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfChandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfauroraaudrey4826
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfauroraaudrey4826
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Axel Bruns
 
Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Ismail Fahmi
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victoryanjanibaddipudi1
 
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election CampaignN Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaignanjanibaddipudi1
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerOmarCabrera39
 
Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationReyMonsales
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoSABC News
 

Recently uploaded (16)

Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the rounds
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012
 
Chandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfChandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdf
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdf
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
 
Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
 
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election CampaignN Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert Oppenheimer
 
Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and information
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election Manifesto
 

Dominion Cove Point LNG Facility May 2016 Status Report

  • 1. Dominion Cove Point LNG, LP 701 East Cary Street, Richmond, VA 23219 June 23, 2016 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Dominion Cove Point LNG, LP Cove Point Liquefaction Project Docket No. CP13-113-000 Monthly Status and Progress Report – May 2016 Dear Secretary Bose: By Order dated September 29, 2014, the Federal Energy Regulatory Commission (FERC or Commission) authorized Dominion Cove Point LNG, LP (DCP or Dominion) to construct and operate certain facilities that comprise the Cove Point Liquefaction Project (Project). Dominion Cove Point LNG, LP. 148 FERC ¶ 61,244 (the “Order”). As required under Condition Nos. 9 and 76 of Appendix B to the Order, DCP hereby submits the updated status report and progress on the construction of the proposed systems for the Project. If you have any questions, please contact me at 804-771-4796. Respectfully submitted, /s/ Deborah T. Gholson Deborah T. Gholson Gas Transmission Certificates Program Manager cc: Joanne Wachholder, FERC Ghanshyam Patel, FERC Thach Nguyen, FERC Service List 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 2. Dominion Cove Point LNG, LP Cove Point Liquefaction Project Docket No. CP13-113-000 Monthly Status and Progress Report – May 2016 Table of contents.........................................................................................................................................2 1:Update on Federal authorizations ................................................................................................ 3 2:Construction Status – Executive Summary.................................................................................... 3 3:Construction Status Activity Summary.......................................................................................... 4 4:Schedule changes for stream crossings/other Environmentally-sensitive areas................................. 8 5:Listing of problem areas encountered and/or instances of noncompliance Observed by each Environmental Inspector (EI) ......................................................................................................... 8 6:Copies of Correspondence Received Concerning Instances of Noncompliance from other Federal, State, or Local Permitting Agencies and Dominion’s Response.............................................. 8 7:Contractor Non-Conformance/Deficiency Logs .............................................................................. 8 8:Landowner/Resident Complaint Tracking...................................................................................... 9 9:Construction photos ................................................................................................................. 10 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 3. 1: Update on Federal Authorizations Dominion has received all applicable authorizations under federal law for the Project. 2: Construction Status – Executive Summary Construction status during the reporting period of May 2016: For this review period, the following project completion status for the Maryland Facilities has been accomplished: • Engineering is 99.8% complete • Engineered Equipment Procurement is 99% complete • Construction is 38% complete Offsite area B (OAB): There was one barge equipment delivery during the month of May. The following pieces of equipment were transported through OAB; high pressure knock out drum, north and south cold flare knock out drums. Monitoring and maintenance of E&S controls continues to ensure proper environmental protection. Existing plant modifications: At the terminal, work continued on modifications to the existing plant in the areas of the jetty platforms and tie-in scope. FERC authorized scope at the terminal: At the terminal, work scope continued on foundations, grading, steel erection, equipment placement, piping, tie-in’s, and electrical installation as described below. FERC authorized scope at the Virginia Facilities: Construction activities conducted during the May period included continued materials delivery, site work, foundation work, piping work, equipment work, and building erection. Work during the May reporting period coincided with an outage of the compressor station and M&R station operations to facilitate construction and tie-in activities. 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 4. 3: Construction Status Activity Summary Maryland Construction status Area Work Activities Work for next work period. Offsite Areas • Maintenance of E&S controls. • Barges that were received: o 5/18/16 - Barge 31 delivery - HP Flare KO Drum, South Cold Flare KO Drum, North Cold Flare KO Drum. • Continue receiving barges and supporting heavy haul equipment deliveries. Terminal Completed Concrete Placement: • Placement of concrete for the air Compressor Building foundation, dry air receiver, and the south VFD transformer blast wall. Equipment: • Setting of north and south VFD transformers. • Setting of the regeneration gas filter (A/B), separator, heater steam condensate pot, and compressors (A/B). • Setting of the demercurizer dust filter (A/B). • Setting of the dehydrator gas filter (A/B). • Setting of the North HP and LP flare KO drum. • Setting of the North Cold flare KO drum. • Setting of the amine circulation pump (A/B). • Setting of the propane and ethane dehydrator/demercurizers. • Setting of the hydrocarbon condensate dehydrators. • Setting of the feed gas heater. • Setting of the air compressor building internal equipment air compressors, receivers, skids. • Installation of the south CT building bridge crane. • Installation of the main steam condensate pumps (3). • Installing ammonia manifold, steel work, and internal insulation/liners on north HRSG. Electrical: • Installation of cable tray under sub 18 and 21. • Installation of batteries at sub-stations 20 and 21. • Structural Steel: • Erection of the North STG and auxiliary boiler platform steel. • Steel erection for the deaerator and feed water pump structure. • Structural steel installation for utility and common racks. • Concrete placement for the spare transformer pads. • Erection of the pre-fab electrical building in the STG area. • Erection of the air compressor building. • Pull cable from sub-station 21 to thermal oxidizer. • Installation of the following equipment: • Setting of the north and south STG control oil tank/ module and pumps. • Setting of the quench water pumps (2). • Setting of the north CT train ACHE unit. • Setting the north & south GE VFD air cooled heat exchangers. • Setting of the main steam condensate filters and pumps. • Setting of the propane reclaimer and condenser. 20160623-5086FERCPDF(Unofficial)6/23/201611:11:57AM
  • 5. Maryland Construction status • Hollywood & Central Avenue pipe bridge structural steel. • Installation of the south flare shielding wall panels minus leave outs. • Mezzanine deck installation on the north CT/Compressor deck. • Erection of the fuel gas flash gas building structural steel minus leave outs. Continued Equipment: • Installing ammonia manifold, steel work, and internal insulation/liners on south HRSG. • Ground assembly and setting of the ACC fan housings, tube sheet placements, modular fabrication of the "A" frames shrouds and motor bridges (1 remaining) and structural support steel. • Installation of instrumentation on north and south HRSGs. • Installation of crystallizer vapor ductwork. • Setting of the fire pump house enclosures. Structural Steel: • Exterior wall panel installation on the north and south CT buildings, and the water treatment building. • Erection of the auxiliary boiler building, steam turbine generator building, north & south CT buildings, fuel/flash gas compressor building and the water treatment building. • Erection of the north and south STG platform steel. • Mezzanine deck installation on the south CT/Compressor deck. • Steel work at Maryland marina - fabricated and loaded at the site to load onto barge. • Erection of the following pipe racks in the following areas: – Pretreatment pipe rack – Main Liquefaction north/south, east/west pipe rack, fuel/flash gas pipe rack and the lean gas pipe rack. – Power Block utility pipe rack. Piping – welding and installations: • Installation and welding of piping systems in the following areas: – Liquefaction: • North/south and east/west pipe racks- Mixed refrigerant, propane, natural gas, and utilities. 20160623-5086FERCPDF(Unofficial)6/23/201611:11:57AM
  • 6. Maryland Construction status – Pre-treatment: • North/south rack- Natural gas, flare, and utilities – Power Block: • Gas turbine buildings and common rack- Propane, mixed refrigerant, and utilities. – OSBL: • North jetty and north/south flare- Flare and nitrogen. • Installation of the concrete trough in the north/south pre-treatment pipe rack. • Installation/testing of underground FW, RW, FG, blow down piping, DMW piping and plant air piping (all underground piping is approximately 99% complete). Electrical: • Pulling of electrical cable between substations and utility power and lighting. • Installing electrical tray at sub-station 19, throughout liquefaction and power block area. • Installation of bus duct in sub-station 18 and 19. Virginia Construction status Area Work Activities Work Planned for Next Period Pleasant Valley • Mobilization of crew, equipment, and materials. • Site work including 1. E&S control maintenance, 2. construction of permanent stormwater management units, and 3. excess soil removal for offsite landfill disposal. • Foundation work including concrete pilings and pads for new equipment, sound wall and compressor building. • Piping work including trenching, fabrication, coating, installation, and backfilling at compressor station and M&R station. • Outage completion: 1. M&R placed back in operation May 2. 2. Station placed back in operation May 9. • Continued materials delivery. • Continued site work including trenching, grading, soil removal, and E&S control maintenance. • Foundation work for new equipment, sound wall, and compressor building. • Piping and equipment work including installation of 36” suction pipeline from M&R to compressor station. 20160623-5086FERCPDF(Unofficial)6/23/201611:11:57AM
  • 7. 4: Schedule Changes for Stream Crossings/Other Environmentally-Sensitive Areas: No schedule changes for stream crossings or work in other environmentally-sensitive areas were noted during this reporting period or are expected to occur in the next reporting period for the Maryland and Virginia Facilities. 5: Listing of Problem Areas Encountered and/or Instances of Noncompliance Observed by each Environmental Inspector (EI) Maryland Environmental Non-Compliances or Problem Areas Non-compliance or Problem Area Remedial actions taken Effectiveness of Corrective Actions Implemented 1. There was no environmental non- compliance or problem area for this reporting period. N/A N/A Virginia Environmental Non-Compliances or Problem Areas Non-compliance or Problem Area Remedial actions taken Effectiveness of Corrective Actions Implemented 1. There was no environmental non- compliance or problem area for this reporting period. N/A N/A 6: Copies of Correspondence Received Concerning Instances of Noncompliance from other Federal, State, or Local Permitting Agencies and Dominion’s Response No correspondence was received concerning instances of noncompliance from other federal, state, or local permitting agencies for the Maryland and Virginia Facilities. 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 8. 7: Maryland Contractor Non-Conformance/Deficiency and Logs From previous reports, NCR 161 resolution has been determined to be okay to remain as is and is now closed. Contractor Non-Conformance/Deficiency Logs Maryland Contractor Non-Conformance/Deficiency Logs Non-conformance (NCR) Description Remedial actions taken 172. Welding: Low Porosity A weld on a water drain line for the air compressor building had a RT performed and was rejected due to excessive porosity. Before the weld was repaired, the joint was encapsulated in concrete. After engineering review, the line will see “0.0” PSI at normal operating conditions and will be okay to remain as is.-closed 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 9. 8: MARYLAND AND VIRGINIA LANDOWNER/RESIDENT COMPLAINT TRACKING Caller Name Date Facility/Location Affected Description of Problem/Concern Explanation of How and When Problem was Resolved/Will be Resolved/Why it has not been Resolved MARYLAND: None. VIRGINIA: None. 20160623-5086FERCPDF(Unofficial)6/23/201611:11:57AM
  • 10. 9: Maryland Construction photos: LNG Terminal: South flare vendor piping being installed. 03MAY2016 LNG Terminal: Lean amine pumps. 05MAY2016 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 11. LNG Terminal LNG Terminal: LNG Terminal: ACC tube sheet installation. 12MAY2016 LNG Terminal: Tie-In point 68 hot tap. 18MAY2016 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 12. LNG Terminal: Air cooled condenser s LNG Terminal: ir cooled condenser street 1 steam condensate collecting manifolds 24MAY2016 LNG Terminal: South HRSG silencers. 26MAY2016 steam condensate collecting manifolds being aligned. 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 13. LNG Terminal: Platform installation LNG Terminal: Welding the expansion joints on the Platform installation for the amine regenerator. 26MAY201 expansion joints on the steam distribution manifolds 2016 steam distribution manifolds. 31MAY2016 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 14. Virginia Construction photos: Pleasant Valley: Piping and valve installation at M&R station. 2MAY2016 Pleasant Valley: Setting piers for soundwall east of new compressor building. 14MAY2016 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 15. Pleasant Valley: Foundation work for new compressor building and compressor units. 16MAY2016 Pleasant Valley: Survey stakes and material staging for upcoming 36” pipeline installation from M&R to compressor Station. 24MAY2016 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM
  • 16. Document Content(s) PUBLIC - DCP Monthly Report - May 2016.PDF............................1-15 20160623-5086 FERC PDF (Unofficial) 6/23/2016 11:11:57 AM