FORTH:
Electrifying Trucking
April 12, 2022
Ian Beil, PhD, PE
Principal Engineer, Grid Edge Solutions
Portland General Electric
How to charge your fleet
Slow, overnight charging is the most cost-effective way to charge an EV:
• A lower charge rate means less expensive equipment and infrastructure.
• Customers benefit from lower demand and off-peak electricity pricing.
• By using charge management software, customers can optimize charging and further reduce costs.
Trucks are bigger than cars
Have to get creative with parking…
Electric Island
2019
2020
Site Design
Plan view of facility layout
12.47kV / 480V 1000 MVA
Transformers (x2)
DCFC Rectifiers
Pre-cast concrete trench
and cableway
EVSE dispensers
Tons of conduit!
(for long-term electrical capacity)
Ongoing Federal and State
Transit Corridor Electrification Initiatives
https://westcoastcleantransit.com/
• A number of groups are working to
install DC Fast Charging across major
highways in the US
• Federal funding is expected to be
available from the states by Q3 2022
• Many utilities also have programs that
can assist with up front infrastructure
costs
Questions?

FORTH: Electrifying Trucking by Ian Beil

  • 1.
    FORTH: Electrifying Trucking April 12,2022 Ian Beil, PhD, PE Principal Engineer, Grid Edge Solutions Portland General Electric
  • 2.
    How to chargeyour fleet Slow, overnight charging is the most cost-effective way to charge an EV: • A lower charge rate means less expensive equipment and infrastructure. • Customers benefit from lower demand and off-peak electricity pricing. • By using charge management software, customers can optimize charging and further reduce costs.
  • 3.
    Trucks are biggerthan cars Have to get creative with parking…
  • 4.
  • 5.
  • 6.
    Plan view offacility layout 12.47kV / 480V 1000 MVA Transformers (x2) DCFC Rectifiers Pre-cast concrete trench and cableway EVSE dispensers
  • 7.
    Tons of conduit! (forlong-term electrical capacity)
  • 8.
    Ongoing Federal andState Transit Corridor Electrification Initiatives https://westcoastcleantransit.com/ • A number of groups are working to install DC Fast Charging across major highways in the US • Federal funding is expected to be available from the states by Q3 2022 • Many utilities also have programs that can assist with up front infrastructure costs
  • 9.