Kikuletwa hydropower project has been operating since the 1930’s and the project was taken by the TANESCO in the 1970’s for power production in the Northern Tanzania. The power project has been running since then without proper maintenance and need major repair and this lead to the closure of the project in the late 1980’s. Since the major repair work can be done locally, Arusha Technical College (ATC), specifically in the departments of civil, mechanical and electrical, are in a position to do the repair works.
The areas that need repair have been categories into civil and electromechanical. All these works can be done by Arusha Technical College (ATC) staff and the other collaborating institutions in phases within a reasonable period of time two years. In this section discussions on the rehabilitations desired are highlighted.
2. LOCATION AND STATUS
Along the Kikuletwa River
flowing from Mt. Meru.
The vicinity of the
confluence of the Kware and
Mbuguni Rivers
The plant is 19 km from
Boma Ng’ombe area (Hai
District)
It was built by the German
Missionaries in the 1930’s
with 2 units
Upgraded in the 1950’s with
additional 1 unit
Stopped operation in 1989
Slide 2
3. Cont……
Was owned by
TANESCO after
Independence
Handed over to ATC in
April 2013
Have three low head
Turbine Units
It is a run off the river
hydro power plant
It was having a firm
capacity of 1.16MW
Slide 3
7. KIKULETWA PROJECT CONCEPT
Electricity
Generation
Feeding to the national grid
Selling to the utility
company
Supply electricity to the
local community (local grid)
Hydropower training
and research center for:
Artisans
Technicians
Plant operators
Engineers
Other hydropower experts and
professionals
Slide 7
8. PLANNED ACTIVITIES:
PHASE A: PLANNING & PREPARATIONS
A-1: ATC Hydropower Training
Center at Kikuletwa
A-2: Feasibility Studies and
Business Plan
Slide 8
1
Kikuletwa Plant O&M
History
2
Prepare Training Schemes and
Infrastructure Requirements
3
Training Scheme Situation Analysis,
Strategy & Curricula
4
International
Accreditation
5
ATC Turbine and Technology
Platform Market
6 ATC Capacity Building
7
Training Centre Facilities &
Infrastructure
8 Turbine Testing Station
9
Training Centre Marketing &
Inauguration
1 Stakeholder Outreach Meetings
2 Hydrological Programme
3
Concessions, Licenses, Permits,
Tariffs
4 Community Participation
5
Review & Update Feasibility Studies
(Kikuletwa 1)
6 Investigational Works
7 Environmental & Social Studies
8
Authority Approval of Env. & Tech.
Plans
9 Business Plan
10 Feasibility Study of Cascade
11 Programme Management Meetings
11. PLANNED DEVELOPMENT
HYDROPOWER
TRAINING CENTER
Short courses
Long courses
Professional courses
Specialized courses
HYDROPOWER
RESEARCH CENTER
ATC Turbine designs and
testing
Turbine performance
characteristics
Optimization of locally
manufactured turbine
Slide 11
12. End of Phase A
Feasibility Studies and
Business Plan Report
Feasible PHASE B
Not Feasible ???
Slide 12
15. KIKULETWA I
RE-CONSTRUCTION
Using existing canals and reservoir
Construct new penstock
Construct new power house, adjacent
to the old plant
Expected power output
2 x 1.7MW
Using existing reservoir as water
storage
Retain one existing turbine unit for
training purposes
KIKULETWA CASCADING
Developing three cascading
stages (17 MW - JICA studies)
Slide 15
16. Summary of activities:
PHASE A & B
Slide 16
Area
No. Description 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2
A PHASE A - PLANNING & PREPARATION
A1 ATC Hydropower Training Centre at Kikuletwa
A2 Feasibility Studies & Business Plan
A3 Cooperation Partner Administration & Backstopping
Total - Phase A:
B PHASE B - IMPLEMENTATION
B1 Kikuletwa I Reconstruction
B2 Cooperation Partner Administration & Backstopping
B3 Kikuletwa Cascade Implementation (not included)
2018-192014-15 2015-16 2016-17 2017-18
18. COMPARISON WITH NEARBY TANESCO
HYDROPOWER PLANTS
Slide 18
Nyumba ya Mungu: 8 MW
Hale: 21 MW
Pangani: 68 MW
19. Slide 19
CONCLUSION
The concept presents the idea of developing
Hydropower Training Center at Kikuletwa
that will save the following purposes:
Electricity generation and feed/sold to the grid
Training center for the hydropower education to the
artisans, technicians, engineers and plant operators
Research and testing the locally manufactured hydro
turbines