SlideShare a Scribd company logo
1 of 23
Download to read offline
ARUSHA TECHNICAL COLLEGE
KIKULETWA HYDROPOWER STATION AS A
TRAINING CENTER AND FOR POWER
GENERATION
LOCATION AND STATUS
 Along the Kikuletwa River
flowing from Mt. Meru.
 The vicinity of the
confluence of the Kware and
Mbuguni Rivers
 The plant is 19 km from
Boma Ng’ombe area (Hai
District)
 It was built by the German
Missionaries in the 1930’s
with 2 units
 Upgraded in the 1950’s with
additional 1 unit
 Stopped operation in 1989
Slide 2
Cont……
 Was owned by
TANESCO after
Independence
 Handed over to ATC in
April 2013
 Have three low head
Turbine Units
 It is a run off the river
hydro power plant
 It was having a firm
capacity of 1.16MW
Slide 3
Slide 4
LAND AREA (Three plots)
First Plot: Area 339 Acres
Slide 5
Second Plot: Area 8.53 Acres
Slide 6
Third Plot: Area 41,600 Sq. Ft (1 acre)
KIKULETWA PROJECT CONCEPT
 Electricity
Generation
 Feeding to the national grid
 Selling to the utility
company
 Supply electricity to the
local community (local grid)
 Hydropower training
and research center for:
 Artisans
 Technicians
 Plant operators
 Engineers
 Other hydropower experts and
professionals
Slide 7
PLANNED ACTIVITIES:
PHASE A: PLANNING & PREPARATIONS
A-1: ATC Hydropower Training
Center at Kikuletwa
A-2: Feasibility Studies and
Business Plan
Slide 8
1
Kikuletwa Plant O&M
History
2
Prepare Training Schemes and
Infrastructure Requirements
3
Training Scheme Situation Analysis,
Strategy & Curricula
4
International
Accreditation
5
ATC Turbine and Technology
Platform Market
6 ATC Capacity Building
7
Training Centre Facilities &
Infrastructure
8 Turbine Testing Station
9
Training Centre Marketing &
Inauguration
1 Stakeholder Outreach Meetings
2 Hydrological Programme
3
Concessions, Licenses, Permits,
Tariffs
4 Community Participation
5
Review & Update Feasibility Studies
(Kikuletwa 1)
6 Investigational Works
7 Environmental & Social Studies
8
Authority Approval of Env. & Tech.
Plans
9 Business Plan
10 Feasibility Study of Cascade
11 Programme Management Meetings
Slide 9
WORK PLAN PHASE A:
Slide 10
Cont……
PLANNED DEVELOPMENT
 HYDROPOWER
TRAINING CENTER
 Short courses
 Long courses
 Professional courses
 Specialized courses
  HYDROPOWER
RESEARCH CENTER
 ATC Turbine designs and
testing
 Turbine performance
characteristics
 Optimization of locally
manufactured turbine
Slide 11
End of Phase A
Feasibility Studies and
Business Plan Report
Feasible PHASE B
Not Feasible ???
Slide 12
PHASE B: IMPLEMENTATION
B-1: Kikuletwa I Reconstruction
Slide 13
1 HydrologicalProgramme
2 TransactionAdviceServices
3 Owner'sEngineerServices
4 CapacityBuilding-PlantO&Mstaff
WORK PLAN PHASE B:
Slide 14
KIKULETWA I
RE-CONSTRUCTION
 Using existing canals and reservoir
 Construct new penstock
 Construct new power house, adjacent
to the old plant
 Expected power output
2 x 1.7MW
 Using existing reservoir as water
storage
 Retain one existing turbine unit for
training purposes
KIKULETWA CASCADING
 Developing three cascading
stages (17 MW - JICA studies)
Slide 15
Summary of activities:
PHASE A & B
Slide 16
Area
No. Description 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2
A PHASE A - PLANNING & PREPARATION
A1 ATC Hydropower Training Centre at Kikuletwa
A2 Feasibility Studies & Business Plan
A3 Cooperation Partner Administration & Backstopping
Total - Phase A:
B PHASE B - IMPLEMENTATION
B1 Kikuletwa I Reconstruction
B2 Cooperation Partner Administration & Backstopping
B3 Kikuletwa Cascade Implementation (not included)
2018-192014-15 2015-16 2016-17 2017-18
PLANNED CAPACITY
Slide 17
Project
Catchment
Area
(Km2)
Firm Capacity
(kW)
(from
JICA
studies)
Planned
capacity
(kW)
Remarks
Kikuletwa I
Re-Construction
2,200 2 x 1,000 2 x 1,700 Phase A
activities
started
COMPARISON WITH NEARBY TANESCO
HYDROPOWER PLANTS
Slide 18
 Nyumba ya Mungu: 8 MW
 Hale: 21 MW
 Pangani: 68 MW
Slide 19
CONCLUSION
 The concept presents the idea of developing
Hydropower Training Center at Kikuletwa
that will save the following purposes:
 Electricity generation and feed/sold to the grid
 Training center for the hydropower education to the
artisans, technicians, engineers and plant operators
 Research and testing the locally manufactured hydro
turbines
Slide 20
Slide 21
Slide 22
THANK YOU
Slide 23

More Related Content

What's hot

INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
ADITYA ARYAN
 
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONCOST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
Rajeev Kumar
 

What's hot (20)

Ntpc information
Ntpc informationNtpc information
Ntpc information
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
 
Thermal power plant ppt
Thermal power plant pptThermal power plant ppt
Thermal power plant ppt
 
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONCOST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
 
HYDRO POWER PLANT
HYDRO POWER PLANT HYDRO POWER PLANT
HYDRO POWER PLANT
 
Power scenario in india ppt
Power scenario in india pptPower scenario in india ppt
Power scenario in india ppt
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
 
Hydro Electric Power Plant
Hydro  Electric  Power  PlantHydro  Electric  Power  Plant
Hydro Electric Power Plant
 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
 
Power plants in pakistan
Power plants in pakistanPower plants in pakistan
Power plants in pakistan
 
NPCIL RAWATBHATA PPT
NPCIL RAWATBHATA PPTNPCIL RAWATBHATA PPT
NPCIL RAWATBHATA PPT
 
Solar energy two case studies
Solar energy   two case studiesSolar energy   two case studies
Solar energy two case studies
 
Picohydro systems
Picohydro systemsPicohydro systems
Picohydro systems
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
 
Summer Training Report on thermal power plant
Summer Training Report on thermal power plantSummer Training Report on thermal power plant
Summer Training Report on thermal power plant
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
Hydropowerplant 160313180104
Hydropowerplant 160313180104Hydropowerplant 160313180104
Hydropowerplant 160313180104
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Small hydroelectric power
Small hydroelectric powerSmall hydroelectric power
Small hydroelectric power
 

Similar to Kikuletwa Hydropower Station - TANZANIA

ABB EPC_General Presentation_March 15
ABB EPC_General Presentation_March 15ABB EPC_General Presentation_March 15
ABB EPC_General Presentation_March 15
Antonio Biasiolo
 

Similar to Kikuletwa Hydropower Station - TANZANIA (20)

Start (ceb) new
Start (ceb) newStart (ceb) new
Start (ceb) new
 
Performance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantPerformance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power Plant
 
Sagar mehta summer training thermal power station full report
Sagar mehta summer training thermal power station full reportSagar mehta summer training thermal power station full report
Sagar mehta summer training thermal power station full report
 
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
 
Training reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishorTraining reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishor
 
Training report
Training reportTraining report
Training report
 
Training report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalTraining report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electrical
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...
 
training reportON Thermal power plantt (nashik tps)pdf
 training reportON Thermal power plantt (nashik tps)pdf training reportON Thermal power plantt (nashik tps)pdf
training reportON Thermal power plantt (nashik tps)pdf
 
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd Unchahar
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd UnchaharAbhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd Unchahar
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd Unchahar
 
Rps plant
Rps plantRps plant
Rps plant
 
ABB EPC_General Presentation_March 15
ABB EPC_General Presentation_March 15ABB EPC_General Presentation_March 15
ABB EPC_General Presentation_March 15
 
Lyes boudiaf
Lyes boudiafLyes boudiaf
Lyes boudiaf
 
kota super thermal power plant report
kota super thermal power plant reportkota super thermal power plant report
kota super thermal power plant report
 
Sihwa tidal power
Sihwa tidal powerSihwa tidal power
Sihwa tidal power
 
Industrial visit Report
 Industrial visit Report Industrial visit Report
Industrial visit Report
 
Industrial training report on NHPC TLD-III
Industrial training report on NHPC TLD-IIIIndustrial training report on NHPC TLD-III
Industrial training report on NHPC TLD-III
 
Project report on MTPS
Project report on MTPSProject report on MTPS
Project report on MTPS
 
TBEA ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTDTBEA ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTD
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
 

Recently uploaded

一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
A
 
一比一原版(Griffith毕业证书)格里菲斯大学毕业证成绩单学位证书
一比一原版(Griffith毕业证书)格里菲斯大学毕业证成绩单学位证书一比一原版(Griffith毕业证书)格里菲斯大学毕业证成绩单学位证书
一比一原版(Griffith毕业证书)格里菲斯大学毕业证成绩单学位证书
c3384a92eb32
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
Kira Dess
 

Recently uploaded (20)

Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...
 
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded Systems
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) ppt
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdf
 
一比一原版(Griffith毕业证书)格里菲斯大学毕业证成绩单学位证书
一比一原版(Griffith毕业证书)格里菲斯大学毕业证成绩单学位证书一比一原版(Griffith毕业证书)格里菲斯大学毕业证成绩单学位证书
一比一原版(Griffith毕业证书)格里菲斯大学毕业证成绩单学位证书
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
 
Databricks Generative AI Fundamentals .pdf
Databricks Generative AI Fundamentals  .pdfDatabricks Generative AI Fundamentals  .pdf
Databricks Generative AI Fundamentals .pdf
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
Call for Papers - Journal of Electrical Systems (JES), E-ISSN: 1112-5209, ind...
Call for Papers - Journal of Electrical Systems (JES), E-ISSN: 1112-5209, ind...Call for Papers - Journal of Electrical Systems (JES), E-ISSN: 1112-5209, ind...
Call for Papers - Journal of Electrical Systems (JES), E-ISSN: 1112-5209, ind...
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
 

Kikuletwa Hydropower Station - TANZANIA

  • 1. ARUSHA TECHNICAL COLLEGE KIKULETWA HYDROPOWER STATION AS A TRAINING CENTER AND FOR POWER GENERATION
  • 2. LOCATION AND STATUS  Along the Kikuletwa River flowing from Mt. Meru.  The vicinity of the confluence of the Kware and Mbuguni Rivers  The plant is 19 km from Boma Ng’ombe area (Hai District)  It was built by the German Missionaries in the 1930’s with 2 units  Upgraded in the 1950’s with additional 1 unit  Stopped operation in 1989 Slide 2
  • 3. Cont……  Was owned by TANESCO after Independence  Handed over to ATC in April 2013  Have three low head Turbine Units  It is a run off the river hydro power plant  It was having a firm capacity of 1.16MW Slide 3
  • 4. Slide 4 LAND AREA (Three plots) First Plot: Area 339 Acres
  • 5. Slide 5 Second Plot: Area 8.53 Acres
  • 6. Slide 6 Third Plot: Area 41,600 Sq. Ft (1 acre)
  • 7. KIKULETWA PROJECT CONCEPT  Electricity Generation  Feeding to the national grid  Selling to the utility company  Supply electricity to the local community (local grid)  Hydropower training and research center for:  Artisans  Technicians  Plant operators  Engineers  Other hydropower experts and professionals Slide 7
  • 8. PLANNED ACTIVITIES: PHASE A: PLANNING & PREPARATIONS A-1: ATC Hydropower Training Center at Kikuletwa A-2: Feasibility Studies and Business Plan Slide 8 1 Kikuletwa Plant O&M History 2 Prepare Training Schemes and Infrastructure Requirements 3 Training Scheme Situation Analysis, Strategy & Curricula 4 International Accreditation 5 ATC Turbine and Technology Platform Market 6 ATC Capacity Building 7 Training Centre Facilities & Infrastructure 8 Turbine Testing Station 9 Training Centre Marketing & Inauguration 1 Stakeholder Outreach Meetings 2 Hydrological Programme 3 Concessions, Licenses, Permits, Tariffs 4 Community Participation 5 Review & Update Feasibility Studies (Kikuletwa 1) 6 Investigational Works 7 Environmental & Social Studies 8 Authority Approval of Env. & Tech. Plans 9 Business Plan 10 Feasibility Study of Cascade 11 Programme Management Meetings
  • 9. Slide 9 WORK PLAN PHASE A:
  • 11. PLANNED DEVELOPMENT  HYDROPOWER TRAINING CENTER  Short courses  Long courses  Professional courses  Specialized courses   HYDROPOWER RESEARCH CENTER  ATC Turbine designs and testing  Turbine performance characteristics  Optimization of locally manufactured turbine Slide 11
  • 12. End of Phase A Feasibility Studies and Business Plan Report Feasible PHASE B Not Feasible ??? Slide 12
  • 13. PHASE B: IMPLEMENTATION B-1: Kikuletwa I Reconstruction Slide 13 1 HydrologicalProgramme 2 TransactionAdviceServices 3 Owner'sEngineerServices 4 CapacityBuilding-PlantO&Mstaff
  • 14. WORK PLAN PHASE B: Slide 14
  • 15. KIKULETWA I RE-CONSTRUCTION  Using existing canals and reservoir  Construct new penstock  Construct new power house, adjacent to the old plant  Expected power output 2 x 1.7MW  Using existing reservoir as water storage  Retain one existing turbine unit for training purposes KIKULETWA CASCADING  Developing three cascading stages (17 MW - JICA studies) Slide 15
  • 16. Summary of activities: PHASE A & B Slide 16 Area No. Description 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 A PHASE A - PLANNING & PREPARATION A1 ATC Hydropower Training Centre at Kikuletwa A2 Feasibility Studies & Business Plan A3 Cooperation Partner Administration & Backstopping Total - Phase A: B PHASE B - IMPLEMENTATION B1 Kikuletwa I Reconstruction B2 Cooperation Partner Administration & Backstopping B3 Kikuletwa Cascade Implementation (not included) 2018-192014-15 2015-16 2016-17 2017-18
  • 17. PLANNED CAPACITY Slide 17 Project Catchment Area (Km2) Firm Capacity (kW) (from JICA studies) Planned capacity (kW) Remarks Kikuletwa I Re-Construction 2,200 2 x 1,000 2 x 1,700 Phase A activities started
  • 18. COMPARISON WITH NEARBY TANESCO HYDROPOWER PLANTS Slide 18  Nyumba ya Mungu: 8 MW  Hale: 21 MW  Pangani: 68 MW
  • 19. Slide 19 CONCLUSION  The concept presents the idea of developing Hydropower Training Center at Kikuletwa that will save the following purposes:  Electricity generation and feed/sold to the grid  Training center for the hydropower education to the artisans, technicians, engineers and plant operators  Research and testing the locally manufactured hydro turbines