SlideShare a Scribd company logo
1 of 60
Download to read offline
SITE INVESTIGATION AND TYPES OF
FOUNDATION
Prepared by
Dr. V. VIGNESH
Assistant Professor
Sanjivani College of Engineering, Kopargaon
Content
• Types of Shallow Foundations
• Soil Investigation or Exploration
• Types of Borings
• Spacing of Boring
• Types of Soil Samples
• Types of sampler
• Geophysical Exploration
DEFINITION
 Foundation is the lower portion of the building, usually located below the
ground level, which transmits the load of the super-structure to the sub- soil.
 Types of foundations:-
 Shallow foundation
 Deep foundation
SHALLOW FOUNDATION
Shallow foundations are further classified into the following types:
 Spread footing
 Combined footing
 Strap footing
 Grillage foundations
 Raft foundations
SPREAD FOOTING
 The footing whose base is extended or spread to distribute the load of the
structure over a large area of sub-soil is called spread footing.
 Types:-
 Single footing:- Suitable for light loaded column.
 Stepped footing:- For Heavily loaded column if single footing is provided, the
footing may fail or crack in the cantilever portion hence to avoid this
It is used in load
stepped footing is provided.
bearing structures.
 Slopped footing
SPREAD FOOTING
COMBINED FOOTING
 Sometimes two columns are located very near to each other in a structure. If
separate footing under these columns are provided, they may interfere with
other. Therefore, providing a combined footing, is essential.
 Types:-
 Rectangular:- when columns carry equal load
 Trapezoidal:- when columns carry unequal load
STRAP FOOTING
 If the independent footing of two columns are connected by a beam, is called a
strap footing.
 It may be used where the distance between the columns is so great.
 Each column is provided with its independent footings & a beam is used to
connect the two footing.
GRILLAGE FOUNDATION
 It is a special type of isolated footing generally provided for these locations
where bearing capacity of soil is poor.
 The depth of such a foundation is limited to 1 to 1.5 m.
 The load of the column is distributed or spread to a very large area by means
of two or more layers of rolled steel joists, each layer being laid at right angle
to the layer bellow it.
 Both the tiers of the joists are then embedded in cement concrete to keep the
joists in position and to prevent their corrosion.
TYPES
 Depending upon the material used in construction, grillage foundations are
further classified into two types.
 Steel Grillage Foundation
 Timber Grillage Foundation
 Steel grillage foundations are useful for structures like columns, piers, stanchions
subjected to heavy concentrated loads and hence are employed for foundations
of the buildings such as theatres, factories, town, halls etc.
 Timber grillage foundations re usually provided for timber columns subjected to
heavy concentrated loads.
 Timber grillage foundation can also be safely used for light buildings where the
soil encountered is soft and is permanently water-logged.
RAFT OR MAT FOUNDATION
 The foundation consisting of a thick R.C.C slab covering the whole area of a
mat is known as raft foundation.
SUITABILITY
 This type of foundation is useful for public buildings, office buildings, school
buildings, residential quarters etc, where the ground conditions are very poor and
bearing power of the soil is so low that individual spread footing cannot be
provided.
Isolated Footing
Combined Footing
Raft or Mat Foundation
Factors affecting the selection of type of foundations
There are certain factors that should be considered during the selecting
the foundation.
1.Type of structure
2.Type of loading pattern
3.Location of the building (region of building)
4.Soil condition
5.Water table level
6.Types of material that will used in construction
7.Lifespan of structure
Choosing the right foundation type based on soil condition is a
critical step in the construction process and can significantly impact
the safety and longevity of the structure. It's essential to rely on the
expertise of geotechnical and structural engineers to make informed
decisions throughout this process.
STEPS IN CHOOSING TYPES OF FOUNDATION BASED ON
SOIL CONDITION:
Choosing the right type of foundation for a building based on the soil
condition is crucial for ensuring the structural integrity and stability of
the structure. Here are the steps to follow:
1. **Soil Investigation:**
- Start by conducting a thorough soil investigation. This typically
involves hiring a geotechnical engineer or soil expert to assess the
soil's composition, bearing capacity, and other relevant properties.
- Soil tests may include boring, sampling, and laboratory testing to
determine soil types, moisture content, compaction, and load-bearing
capacity.
2. **Soil Classification:**
- Based on the results of the soil investigation, classify the soil into
categories such as clay, silt, sand, gravel, or a combination thereof.
- Determine the soil's properties, such as its cohesion, angle of
internal friction, and bearing capacity.
3. **Load Analysis:**
- Calculate the loads that the foundation will need to
support, including the weight of the building, live loads, and
any additional loads such as equipment or snow loads.
- Consider both vertical and horizontal loads.
4. **Foundation Types:**
- Select potential foundation types that are suitable for
the soil condition. Common types include:
• Shallow Foundations: Suitable for soils with good bearing
capacity.
• Spread Footings: Used for evenly distributed loads.
• Mat Foundations: Suitable for soft soils or heavy loads.
• Deep Foundations: Used when the soil near the surface is
not suitable for bearing the loads.
• Piles: Driven into the ground to transfer loads to deeper,
more stable soil or bedrock.
• Caissons: Large-diameter, drilled shafts used in similar
situations as piles.
5. **Bearing Capacity Calculation:**
- Calculate the ultimate bearing capacity of the selected foundation
types to ensure they can support the expected loads.
- Ensure that the calculated bearing capacity exceeds the design
loads with an appropriate factor of safety.
6. **Consider Settlement:**
- Evaluate potential settlement issues based on the soil's
compressibility. Soils with high compressibility may require
special foundation designs or ground improvement
techniques.
7. **Consider Environmental Factors:**
- Consider any environmental factors that may affect the
foundation, such as groundwater levels, soil expansion or
shrinkage due to moisture changes, and seismic activity.
8. **Consultation with Structural Engineer:**
- Work closely with a structural engineer who can help you
make informed decisions based on the soil investigation, load
analysis, and other relevant data.
9. **Foundation Design and Detailing:**
- Once you've chosen the appropriate foundation type, work with
an engineer to design the foundation with the necessary dimensions,
reinforcement, and construction details.
10. **Construction and Inspection:**
- Ensure that the foundation is constructed according to the design
specifications.
- Regularly inspect the construction to ensure quality and
compliance with the design.
11. **Monitoring and Maintenance:**
- After construction, monitor the foundation's performance and
address any settlement or stability issues promptly.
- Implement a maintenance plan to ensure the foundation's long-
term integrity.
12. **Documentation:**
- Keep comprehensive records of the soil investigation, design
calculations, construction process, and any modifications made
during the construction phase.
SITE INVESTIGATION OR SITE
EXPLORATION
• Site Investigation is the process of collecting information, assessment of the data
and reporting potential hazards beneath a site which are unknown.
• Site investigation can be broadly classified into four stages:
• Reconnaissance
• Data and map study
• Detailed investigation and
• Laboratory testing.
Purpose of Site Investigation
 1. To select the type of foundation and depth of foundation.
 2. To determine the bearing capacity of the soil.
 3. To locate the ground water table.
 4. To select suitable construction techniques.
 5. To estimate the probable maximum and differential settlement.
 6. To investigate the safety of existing strutures and to suggest the remedial
measures.
 7. To ascertain the suitability of base of soil as a construction material.
Methods of Exploration
 1. Open Excavation
 a) Pits and Trenches (Long shallow pits)
 b) Drifts and Shafts
Horrizontal tunnels Large vertical holes
2. Borings
a) Auger boring
b) Wash boring
c) Rotary drilling
d) Percussion drilling
e) Core boring
Auger boring
Wash Boring
Rotary drilling
Percussion Drilling
Percussion drilling is a drilling method which involves lifting and dropping heavy
tools to break rock, and uses steel casing tubes to stop the borehole from
collapsing. Percussion drilling is carried out by breaking up the formation by
repeated blows of a heavy bit or a chisel inside a casing pipe.
• Core drilling is the process of drilling below the earth's surface to obtain a
core of soil or rock sample in order to determine its properties.
• The core boring operation is the insertion of this cutting circle into the
material that is being drilled with a power drill or other means of pushing
this cutting bit into the material.
Core boring
SPACING OF BORING
1. For a compact building site covering an area of about 0.4 hectare (i.e. 4000
m2), one bore hole in each corner and one in the centre (i.e. 5 boreholes in all)
should be adequate.
2. For smaller areas and less important buildings even one bore hole in the
centre should be sufficient.
3. For very large areas covering industrial and residential colonies, the
geological nature of the terrain will help in deciding the number of bore holes.
Dynamic or static cone penetration tests may be performed at every 100
metre by dividing the area in a grid pattern and numbers of boreholes are
decided by examining the variation in the penetration curves.
4. For Highways-Along the centerline-150 to 300m spacing
5. In case of Gravity dam – 40 to 80 m.
TYPES OF SOIL SAMPLE
Basically, in civil engineering, there are two main types of soil sample that is
collected for the study of the properties of soils:
• Disturbed Soil Samples
• Undisturbed Soil Samples
Disturbed Soil Samples
During the sampling process of the soil sample If the natural structure of the soil
gets disturbed, then this type of soil sample is called a Disturbed Soil Sample.
The Disturbed Soil Samples can be used for the determination of the grain size,
plasticity characteristics, and specific gravity of the soil.
The collection of disturbed soil samples is done by different methods such as
Auger Boring, Wash Boring, Rotary Drilling, and Percussion Drilling, even if the
disturbed soil sample is collected by hand excavating of soil with picks and
shovels.
 Undisturbed soil sample:
 During the sampling process of the soil sample, if the natural structure of
the soil and water content does not disturb, that means the soil retained its
natural structure and water content, then these types of soil samples are called
undisturbed soil samples.
 The undisturbed soil samples are used for the determination of engineering
properties of soils such as shear strength, permeability, and compressibility.
SOIL SAMPLER
 Types of sampler
1. Split spoon sampler
2. Thin-walled tube sampler
3. Stationary piston sampler
Design Factors Affecting Sample Disturbance
The disturbance of soil depends mainly depends upon the following
design features:
1.Area Ratio
2.Inside Clearance
3.Outside Clearance
Area Ratio(Ar):
• It is ratio of the volume of the soil displaced by the sampler to
the ratio of the sample volume.
• The larger the value, the larger is the degree of disturbance.
• For obtaining a good quality undisturbed soil sample, the area
ratio should be 10% or less.
 Inside Clearance (Ci):
• It is to reduce the friction between the soil sample and
the sampler, when the soil enters the tube by allowing
for elastic expansion of the sample.
• For an undisturbed sample the inside clearance should
be between 1 to 3%.
 Outside Clearance (Co):
• This will help in reducing the friction while the
sampler is driven and when it is being withdrawn after
the collection of sample.
• For an undisturbed soil sample the outside clearance
should be lies between 0 and 2%. Co should be less
than Ci.
Examples:
1. A sampler has the following dimensions, internal dia of sampler
tube is 70mm and outer dia is 72mm , the internal dia of cutting
edge is 69 mm and the outer dia is 73mm. Compute its inside
clearance, outside clearance and area ratio. Also comment on the
sample collected from the sampler.
2. The cutting edge of the sampling tube has outer dia of 75mm
and wall thickness of 1.7mm. Find out the area ratio.
3. Compute the area ratio of thin walled tube sampler having an
external dia of 6cm and a wall thickness of 2.25 mm. Do you
recommend the sampler for undisturbed soil sample and why?
4. One sampler has the area ratio of 8% while another has 16%
which of these samplers do you prefer to extract undisturbed
soil sample and why?
BORE LOG REPORT
• Information on subsurface conditions obtained from the boring
operation is typically presented in the form of a boring record
commonly known as ‘boring log’.
• It is also known as sub-soil investigation report which should
contain the data obtained from boreholes, site recommendations
about the suitable type of foundation, soil pressure and expected
settlements.
• It is essential to give a complete and accurate record of data
collected. All relevant data for the bore bole is recorded in a
boring log.
• A boring log gives the description or classification of various
strata encountered at different depths.
 A soil exploration report generally consists of the following:
1. Introduction, which gives the scope of the investigation.
2. Description of the proposed structure, the location and the geological
conditions at the site.
3. Details of the field exploration programme, indicating the number of
borings, their location and depths.
4. Details of the method of exploration.
5. General description of the sub-soil conditions as obtained from in-
sites tests, such as standard penetration Test, cone test.
6. Details of the laboratory test conducted on the soil samples obtained
and the results obtained.
7. Date and weather condition during investigation.
8. Depth of ground water table and the change in water levels.
9. Discussion of the results.
10. 10.Recommendation about the allowable bearing pressure, the type
of foundation or structure.
11. 11.Conclusion:The main findings of the bore hole investigations
should be clearly stated.
GEOPHYSICAL EXPLORATION
• Geophysical exploration may be used with advantage to locate
boundaries between different elements of the subsoil as these
procedures are based on the fact that the gravitational, magnetic,
electrical, radioactive or elastic properties of the different elements of
the subsoil may be different.
 Different methods of geophysical explorations
1. Electrical resistivity method
• Electrical Profiling method
• Electrical Sounding method
2. Seismic Method
Electrical Resistivity Method
 Electrical resistivity method is based on the difference in the
electrical conductivity or the electrical resistivity of different
soils. Resistivity is defined as resistance in ohms between the
opposite phases of a unit cube of a material.
ρ is resistivity in ohm-cm,
R is resistance in ohms,
A is the cross sectional area (cm2),
L is length of the conductor (cm).
 The electrical resistivity methods are of the following two types:
1. Electrical Profiling Method.
2. Electrical Sounding method.
 Electrical Profiling Method.

• The method is also known as the resistivity mapping method.
Four electrodes are used at a constant spacing ‘a’. To conduct the
test, four electrodes, which are usually in the form of metal
spikes, are driven into the ground.
• The two outer electrodes are known as current electrodes.
• The two inner electrodes are called potential electrodes.
• The mean resistivity of the strata is determined by applying a
D.C. current to the outer electrodes and by measuring the voltage
drop between the inner electrodes. A current of 50 to 100
milliamp is usually supplied.
• The mean resistivity (ρ) is given by the formula, ρ = 2πaV/I
Where I= Current supplied, a=Spacing of electrodes, V=Voltage
drop
2. Electrical Sounding method
• In this method, the electrode system, consisting of four
electrodes, is expanded about a fixed location, say P. The spacing
in the first setting is a1, which is increased to a2 in the second
setting and to a3 in the third setting.
• The spacing is thus gradually increased to a distance equal to the
depth of exploration.
• As the depth of the current penetration is equal to the electrode
spacing, the changes in the mean resistivity is correlated to the
changes in strata at that location.
Limitations of Electrical resistivity method:
(1) The methods are capable of detecting only the strata having different
electrical resistivity.
(2) The results are considerably influenced by surface irregularities,
wetness of the strata and electrolyte concentration of the ground
water.
(3) As the resistivity of different strata at the interface changes gradually
and not abruptly as assumed, the interpretation becomes difficult.
(4) The services of an expert in the field are needed.
Seismic Method:
• The seismic methods are based on the principle that the elastic
shock waves have different velocities in different materials. At the
interface of two different materials, the waves get partly reflected
and partly refracted. Seismic methods of subsurface explorations
generally utilise the refracted waves.
• The shock wave is created by a hammer blow or by a small
explosive charge at a point P.
• The shock wave travels through the top layer of the soil (or rock)
with a velocity V₁, depending upon the type of material in layer-I.
• The observation of the first arrival of the waves is recorded by
geophones located at various points, such as A, B, C.
• The geophones convert the ground vibration into electrical
impulses and transmit them to a recording apparatus
Limitation of the seismic methods
(1) The methods cannot be used if a hard layer with a greater
seismic velocity overlies a softer layer with a smaller seismic
velocity.
(2) The methods cannot be used for the areas covered by concrete,
asphalt pavements or any other artificial hard crust, having a
high seismic velocity.
(3) If the area contains some underground features, such as buried
conduits, irregularly dipping strata, and irregular water table,
the interpretation of the results becomes very difficult.
(4) If the surface layer is frozen, the method cannot be
successfully used, as it corresponds to a case of harder layer
overlying a softer layer.
(5) The methods require sophisticated and costly equipment.
(6) For proper interpretations of the seismic survey results, the
services of an expert are required.
^types baved on
1/613
4 Wash
To
AvnER
luson
Core
wedl
when he
ofBoINh:
Ahe
loatt t
Collocd tho
Cordel th
qwpment
BoRNG:
inmaion
nd
Sol Samples .
A-1n)
mothod
Aeph ttoyatin,s
ork
laparten
tetd ten.
sed
than bmtheonoyinys
HAND
b
Const
(ertial
AvefRS
bia
at the
9
he
Tthote
3
nFHANIAL AvfR
hard sthahe
chere
AovANW:
r
1:The
34
hok
Sme Yime
DisADVANTALE S:
3.2}
Sols
larpred
the
and
Jreray
Sol strata
man
becmes
Cannl
obsimeitr ohith
driyen
20
be
shan k
wbresdy
Can
suew.The
ad van(ed y
we
5
advantiS
thrut
Soll
4pto
hole uo a
in th down wad
Power, 13
sbsngatinvedlgaion
anoth y
an be
whck Can
we when the are
used
Small
guite apdy and
hoe.
opeyatad ihanta
diveton
12 m.
w.houd
and
epnomialy
Sampu a
hilunyany ae
and
ho in
kyly dstwda
bouldrs olhy
t In
ten seri
W
tnd
Khon
water
nl
wash
water
AoVANTANGES
qupnnd
into
T hole
hode :s
Rumped
jethy
CABLE
the hole
halow drll
doon
adhvan (ed
autn
the
tus thranyh 7-shaped pipt
oten
Soil.
advanced
iS
<che meHod is ho Slau
T-PIPE
the
Br7
Tod
drlled
CAS'NG
th
and
hrtuyh
hal
a
,TUR
alienatively r
DisAoVAN7AAE Th Wah sanply lolerkd in
pt
hd in
and
ard ats
Small opning he
h
Choping pt at lony
hruorly
and
atton
(plleeked in a
Joil.
the
and he
dushubed
Ro1AR DeING
Tthe
Rod whi
As
made
borehole
Depth
"the
ha
Consists
doumwod
diling
Can
thiy method.
ExpLORATUON:
a
*Grhensy
advanted by
to the boton o) ho hole,.
mehod is
shapt
Too
So
anl
prse.
struuturp
progile.
at owey
methansm
Roodng
depth uto ohit thy
cajad in Clay sand and oces.
duperds
atating
sress
loads, Can prudnu ryan
On
end.
oadd
inAYemet de to uper
selMemen? anol shesr rees
houdl
Foy
t
o
re
Aol
e
l
,Coveriy
thu
Inal
pi
t
in
l
e
nt
Smal
and
even
Eor
e
ho
or
a
he
Vonaton
t
h
e
shrata
honzona
drehon
dam
t
h
e
mh
S
nunbtr
")
Jt
o
rey
h
val
a
e
i
3
o
l
y
h
a
mulhitvrey
hul
d
i
n
g
the
t
v
en
by
etalsh
The
mi
nimun
kong
into
t
b
e
d
oc
e
shoud
b
to
tnetion
pl
e
i
NWidih
entre
3
t
i
m
1s
i
m
es
t
h
w
width.(1.ss)
adleast
gcant
deph
Wed
to
Seat
t
h
e
Sonpl
Consol
i
d
at
o
n
chateristo.
we
d
to
datermine
charshenth
ande
intu
val
e
2
Contert
is
o
Shatun
distrtton
hoistuwbtd
One
presemy
and
arborat
bntnt
an
Gan
L
wed
ntr
ntent
abo
hare
chanjd
Joi
l
ldrwtur
ma
y
Jemahy
citnheol,
wht
colcka.
bislbed
Sompleu(,A
Grdore
a
m
y
TEs
of
Cale
rroy
ridued
o
Iso
to
bytrton
aoticr
th
palin
.
C
arrmed
a
u
t
t
h
e
bore
holes
loto
t
h
e
mforat
oatonu
an
nhe
dst
urbenu
tor
deyu
thh
he
design
ures
govemg
Area
roio
cleaiante
nsiàe
atsieu
clearanu.
3ndion.
4
Non-
reain
wall.
(O71N6
FoE
du
w
Sorpl
ag
tho
so)
voumo
Tato
the
dskrbae
volum
the
sampu
the
Lampler
t
4he
ratio
En
candstubed
so/,
aeo
qualty
thar
retro
fes,
les
Shadd
do
kenp
thi
D.-
D,
D:
Ar
Area
radio
Oukr
1
in
ratio
Recovened
Pentraktn
lng
Jamplo
comprwe
9vod
e
overy
indiat
sorl
Sanplo
Swel
Soil
ha
cknss
Sbl
sampu
and
eleonanu
blw
he
cion
reduco
th
to
4
elastre
Hhe
tube,
lay
all
Sampler
,hen
Soil.
the
eapanston
in
%
di
:
inteal
diamcter
o
Sempey
tube.
ndstusbedl
deovan
Ovts
tde
y.
Do-do
keng
the
ncibn
wkile
the
voduing
ithaon
artey
the
Colldon
hi
bong
is
shen
an
dyiven
Samplu
.
Otsde
cheovanl
n,
iemal
dimenon,
Sampr
A
To
m
tube
69
Cutd
clnant,
tompute
)
Ares
ratro
di
lo
doe
D;
cleavan
1o-
69
69
d
loo
Do-do
S:ds
Out
Area
rotfo
A,
0;
69
69
Siree
Samply
the
gop
Ttheepre
t
u
o
dy
soisSlo
lo
im
th
clank
clearanu
ô.
s
o
yatio
value
4The
shapened
Sampler
ha
th
camee
14
is
usecl
ndtnd
Thin
wwal
l
e
d
t
u
oe
Sampler:
sandard
penedraon
test:
di
a
isSo
al
o
wr
d
Sampler.
The
insd
cnl
cdck
cstwbed
Somple
t
h
e
Sol
4he
most
cbtana4
steej
tube
Splt
Spoon
Sarer:
Shalorony
piston
Somle
waled
ube
Campl
Sumpl
o
r
Types
nap.d
Shall de
Dston
mwion
Stetionany eton ampen.
stotunany
insiclo
The
piston
plau.
SpLIT SpooN SAMpER
cONts
dowend to duned dph
pilon
Thread torod
by Contce
prak apd guazng o)
wncliuked
PisTON SAplFR

More Related Content

What's hot

Bridge foundation
Bridge  foundation Bridge  foundation
Bridge foundation Ghulam Yasin
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...Bhaddin Al-Naqshabandi
 
UNIT-1 PSC.pptx
UNIT-1 PSC.pptxUNIT-1 PSC.pptx
UNIT-1 PSC.pptxjairam131
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE VISHNU VIJAYAN
 
Failure of chauras bridge
Failure of chauras bridgeFailure of chauras bridge
Failure of chauras bridgeGaurav Parashar
 
Factors to consider in foundation design
Factors to consider in foundation designFactors to consider in foundation design
Factors to consider in foundation designMushtaq Zaib
 
Construction failure of structure due to geological drawbacks pisa tower
Construction failure of structure due to geological drawbacks   pisa towerConstruction failure of structure due to geological drawbacks   pisa tower
Construction failure of structure due to geological drawbacks pisa towerpavan kumar arigela
 
Types of isolated footing and design
Types of isolated footing and design Types of isolated footing and design
Types of isolated footing and design Sukhvinder Singh
 
Pile cap design structural guide
Pile cap design   structural guidePile cap design   structural guide
Pile cap design structural guideAlberto Rosado
 
Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundationstooty s
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptxAnanthakumar75
 
Module3 rajesh sir
Module3 rajesh sirModule3 rajesh sir
Module3 rajesh sirSHAMJITH KM
 

What's hot (20)

Bridge foundation
Bridge  foundation Bridge  foundation
Bridge foundation
 
components of building ppt
components of building pptcomponents of building ppt
components of building ppt
 
Pile Foundation
Pile FoundationPile Foundation
Pile Foundation
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...
 
UNIT-1 PSC.pptx
UNIT-1 PSC.pptxUNIT-1 PSC.pptx
UNIT-1 PSC.pptx
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE
 
Failure of chauras bridge
Failure of chauras bridgeFailure of chauras bridge
Failure of chauras bridge
 
Guntry girder
Guntry girderGuntry girder
Guntry girder
 
Factors to consider in foundation design
Factors to consider in foundation designFactors to consider in foundation design
Factors to consider in foundation design
 
Design of steel structural elements
Design of steel structural elementsDesign of steel structural elements
Design of steel structural elements
 
DESIGN OF RCC CULVERT
DESIGN OF  RCC CULVERTDESIGN OF  RCC CULVERT
DESIGN OF RCC CULVERT
 
BCT MODULE 2 - Caisson
BCT MODULE 2 - CaissonBCT MODULE 2 - Caisson
BCT MODULE 2 - Caisson
 
Construction failure of structure due to geological drawbacks pisa tower
Construction failure of structure due to geological drawbacks   pisa towerConstruction failure of structure due to geological drawbacks   pisa tower
Construction failure of structure due to geological drawbacks pisa tower
 
Mat Foundation
Mat FoundationMat Foundation
Mat Foundation
 
Types of isolated footing and design
Types of isolated footing and design Types of isolated footing and design
Types of isolated footing and design
 
Pile cap design structural guide
Pile cap design   structural guidePile cap design   structural guide
Pile cap design structural guide
 
Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundation
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptx
 
Module3 rajesh sir
Module3 rajesh sirModule3 rajesh sir
Module3 rajesh sir
 

Similar to Types of Foundation and Site Investigation.pdf

building foundation kagemu SELEMANI
building foundation kagemu SELEMANIbuilding foundation kagemu SELEMANI
building foundation kagemu SELEMANISosthenes Laizer
 
Foundation_(Anshumi Tanna BCT-II).pptx
Foundation_(Anshumi Tanna BCT-II).pptxFoundation_(Anshumi Tanna BCT-II).pptx
Foundation_(Anshumi Tanna BCT-II).pptxAnshumiTanna
 
GT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptxGT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptxAPURWAYAWALE
 
substructures ppt.ppt
substructures ppt.pptsubstructures ppt.ppt
substructures ppt.pptYanyanYamson1
 
Exploring the Benefits of Deep Foundations
Exploring the Benefits of Deep FoundationsExploring the Benefits of Deep Foundations
Exploring the Benefits of Deep FoundationsPilingExperts1
 
Introduction to Types of Foundation
Introduction to Types of FoundationIntroduction to Types of Foundation
Introduction to Types of FoundationPhurba Tamang
 
Deep foundation full information
Deep foundation full informationDeep foundation full information
Deep foundation full informationAli Rizgar
 
7 building construction part 3 foundation - edit
7 building construction part 3   foundation - edit7 building construction part 3   foundation - edit
7 building construction part 3 foundation - editmuhammadumairallahdi
 
Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Jyoti Khatiwada
 
Foundation and types
Foundation and typesFoundation and types
Foundation and typesJamalAshraf29
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology ReportShao Xun Sean Thun
 
Ct assignment (2)
Ct assignment (2)Ct assignment (2)
Ct assignment (2)Shane Ah
 
Types of foundation...Sana Po May Matutunan tayo !
Types of foundation...Sana Po May Matutunan tayo !Types of foundation...Sana Po May Matutunan tayo !
Types of foundation...Sana Po May Matutunan tayo !Ricko Guerrero
 
Foundation 2
Foundation 2Foundation 2
Foundation 2cfdcfd2
 
Building technology.pptx
Building technology.pptxBuilding technology.pptx
Building technology.pptxNeha569445
 
Types of deep foundation
Types of deep foundationTypes of deep foundation
Types of deep foundationMaliha Mehr
 

Similar to Types of Foundation and Site Investigation.pdf (20)

building foundation kagemu SELEMANI
building foundation kagemu SELEMANIbuilding foundation kagemu SELEMANI
building foundation kagemu SELEMANI
 
Foundation_(Anshumi Tanna BCT-II).pptx
Foundation_(Anshumi Tanna BCT-II).pptxFoundation_(Anshumi Tanna BCT-II).pptx
Foundation_(Anshumi Tanna BCT-II).pptx
 
GT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptxGT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptx
 
Foundation
FoundationFoundation
Foundation
 
substructures ppt.ppt
substructures ppt.pptsubstructures ppt.ppt
substructures ppt.ppt
 
Exploring the Benefits of Deep Foundations
Exploring the Benefits of Deep FoundationsExploring the Benefits of Deep Foundations
Exploring the Benefits of Deep Foundations
 
Introduction to Types of Foundation
Introduction to Types of FoundationIntroduction to Types of Foundation
Introduction to Types of Foundation
 
Foundation
FoundationFoundation
Foundation
 
Deep foundation full information
Deep foundation full informationDeep foundation full information
Deep foundation full information
 
7 building construction part 3 foundation - edit
7 building construction part 3   foundation - edit7 building construction part 3   foundation - edit
7 building construction part 3 foundation - edit
 
Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)
 
Foundation and types
Foundation and typesFoundation and types
Foundation and types
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology Report
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Ct assignment (2)
Ct assignment (2)Ct assignment (2)
Ct assignment (2)
 
Types of foundation...Sana Po May Matutunan tayo !
Types of foundation...Sana Po May Matutunan tayo !Types of foundation...Sana Po May Matutunan tayo !
Types of foundation...Sana Po May Matutunan tayo !
 
Foundation 2
Foundation 2Foundation 2
Foundation 2
 
Building technology.pptx
Building technology.pptxBuilding technology.pptx
Building technology.pptx
 
Types of deep foundation
Types of deep foundationTypes of deep foundation
Types of deep foundation
 

Recently uploaded

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 

Recently uploaded (20)

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 

Types of Foundation and Site Investigation.pdf

  • 1. SITE INVESTIGATION AND TYPES OF FOUNDATION Prepared by Dr. V. VIGNESH Assistant Professor Sanjivani College of Engineering, Kopargaon
  • 2. Content • Types of Shallow Foundations • Soil Investigation or Exploration • Types of Borings • Spacing of Boring • Types of Soil Samples • Types of sampler • Geophysical Exploration
  • 3. DEFINITION  Foundation is the lower portion of the building, usually located below the ground level, which transmits the load of the super-structure to the sub- soil.  Types of foundations:-  Shallow foundation  Deep foundation SHALLOW FOUNDATION Shallow foundations are further classified into the following types:  Spread footing  Combined footing  Strap footing  Grillage foundations  Raft foundations
  • 4. SPREAD FOOTING  The footing whose base is extended or spread to distribute the load of the structure over a large area of sub-soil is called spread footing.  Types:-  Single footing:- Suitable for light loaded column.  Stepped footing:- For Heavily loaded column if single footing is provided, the footing may fail or crack in the cantilever portion hence to avoid this It is used in load stepped footing is provided. bearing structures.  Slopped footing
  • 6. COMBINED FOOTING  Sometimes two columns are located very near to each other in a structure. If separate footing under these columns are provided, they may interfere with other. Therefore, providing a combined footing, is essential.  Types:-  Rectangular:- when columns carry equal load  Trapezoidal:- when columns carry unequal load
  • 7. STRAP FOOTING  If the independent footing of two columns are connected by a beam, is called a strap footing.  It may be used where the distance between the columns is so great.  Each column is provided with its independent footings & a beam is used to connect the two footing.
  • 8. GRILLAGE FOUNDATION  It is a special type of isolated footing generally provided for these locations where bearing capacity of soil is poor.  The depth of such a foundation is limited to 1 to 1.5 m.  The load of the column is distributed or spread to a very large area by means of two or more layers of rolled steel joists, each layer being laid at right angle to the layer bellow it.  Both the tiers of the joists are then embedded in cement concrete to keep the joists in position and to prevent their corrosion.
  • 9. TYPES  Depending upon the material used in construction, grillage foundations are further classified into two types.  Steel Grillage Foundation  Timber Grillage Foundation  Steel grillage foundations are useful for structures like columns, piers, stanchions subjected to heavy concentrated loads and hence are employed for foundations of the buildings such as theatres, factories, town, halls etc.  Timber grillage foundations re usually provided for timber columns subjected to heavy concentrated loads.  Timber grillage foundation can also be safely used for light buildings where the soil encountered is soft and is permanently water-logged.
  • 10. RAFT OR MAT FOUNDATION  The foundation consisting of a thick R.C.C slab covering the whole area of a mat is known as raft foundation.
  • 11. SUITABILITY  This type of foundation is useful for public buildings, office buildings, school buildings, residential quarters etc, where the ground conditions are very poor and bearing power of the soil is so low that individual spread footing cannot be provided.
  • 13. Factors affecting the selection of type of foundations There are certain factors that should be considered during the selecting the foundation. 1.Type of structure 2.Type of loading pattern 3.Location of the building (region of building) 4.Soil condition 5.Water table level 6.Types of material that will used in construction 7.Lifespan of structure
  • 14. Choosing the right foundation type based on soil condition is a critical step in the construction process and can significantly impact the safety and longevity of the structure. It's essential to rely on the expertise of geotechnical and structural engineers to make informed decisions throughout this process.
  • 15. STEPS IN CHOOSING TYPES OF FOUNDATION BASED ON SOIL CONDITION: Choosing the right type of foundation for a building based on the soil condition is crucial for ensuring the structural integrity and stability of the structure. Here are the steps to follow: 1. **Soil Investigation:** - Start by conducting a thorough soil investigation. This typically involves hiring a geotechnical engineer or soil expert to assess the soil's composition, bearing capacity, and other relevant properties. - Soil tests may include boring, sampling, and laboratory testing to determine soil types, moisture content, compaction, and load-bearing capacity. 2. **Soil Classification:** - Based on the results of the soil investigation, classify the soil into categories such as clay, silt, sand, gravel, or a combination thereof. - Determine the soil's properties, such as its cohesion, angle of internal friction, and bearing capacity.
  • 16. 3. **Load Analysis:** - Calculate the loads that the foundation will need to support, including the weight of the building, live loads, and any additional loads such as equipment or snow loads. - Consider both vertical and horizontal loads. 4. **Foundation Types:** - Select potential foundation types that are suitable for the soil condition. Common types include: • Shallow Foundations: Suitable for soils with good bearing capacity. • Spread Footings: Used for evenly distributed loads. • Mat Foundations: Suitable for soft soils or heavy loads. • Deep Foundations: Used when the soil near the surface is not suitable for bearing the loads. • Piles: Driven into the ground to transfer loads to deeper, more stable soil or bedrock. • Caissons: Large-diameter, drilled shafts used in similar situations as piles.
  • 17. 5. **Bearing Capacity Calculation:** - Calculate the ultimate bearing capacity of the selected foundation types to ensure they can support the expected loads. - Ensure that the calculated bearing capacity exceeds the design loads with an appropriate factor of safety. 6. **Consider Settlement:** - Evaluate potential settlement issues based on the soil's compressibility. Soils with high compressibility may require special foundation designs or ground improvement techniques. 7. **Consider Environmental Factors:** - Consider any environmental factors that may affect the foundation, such as groundwater levels, soil expansion or shrinkage due to moisture changes, and seismic activity. 8. **Consultation with Structural Engineer:** - Work closely with a structural engineer who can help you make informed decisions based on the soil investigation, load analysis, and other relevant data.
  • 18. 9. **Foundation Design and Detailing:** - Once you've chosen the appropriate foundation type, work with an engineer to design the foundation with the necessary dimensions, reinforcement, and construction details. 10. **Construction and Inspection:** - Ensure that the foundation is constructed according to the design specifications. - Regularly inspect the construction to ensure quality and compliance with the design. 11. **Monitoring and Maintenance:** - After construction, monitor the foundation's performance and address any settlement or stability issues promptly. - Implement a maintenance plan to ensure the foundation's long- term integrity. 12. **Documentation:** - Keep comprehensive records of the soil investigation, design calculations, construction process, and any modifications made during the construction phase.
  • 19. SITE INVESTIGATION OR SITE EXPLORATION • Site Investigation is the process of collecting information, assessment of the data and reporting potential hazards beneath a site which are unknown. • Site investigation can be broadly classified into four stages: • Reconnaissance • Data and map study • Detailed investigation and • Laboratory testing.
  • 20. Purpose of Site Investigation  1. To select the type of foundation and depth of foundation.  2. To determine the bearing capacity of the soil.  3. To locate the ground water table.  4. To select suitable construction techniques.  5. To estimate the probable maximum and differential settlement.  6. To investigate the safety of existing strutures and to suggest the remedial measures.  7. To ascertain the suitability of base of soil as a construction material.
  • 21. Methods of Exploration  1. Open Excavation  a) Pits and Trenches (Long shallow pits)  b) Drifts and Shafts Horrizontal tunnels Large vertical holes 2. Borings a) Auger boring b) Wash boring c) Rotary drilling d) Percussion drilling e) Core boring
  • 25. Percussion Drilling Percussion drilling is a drilling method which involves lifting and dropping heavy tools to break rock, and uses steel casing tubes to stop the borehole from collapsing. Percussion drilling is carried out by breaking up the formation by repeated blows of a heavy bit or a chisel inside a casing pipe.
  • 26.
  • 27. • Core drilling is the process of drilling below the earth's surface to obtain a core of soil or rock sample in order to determine its properties. • The core boring operation is the insertion of this cutting circle into the material that is being drilled with a power drill or other means of pushing this cutting bit into the material. Core boring
  • 29. 1. For a compact building site covering an area of about 0.4 hectare (i.e. 4000 m2), one bore hole in each corner and one in the centre (i.e. 5 boreholes in all) should be adequate. 2. For smaller areas and less important buildings even one bore hole in the centre should be sufficient. 3. For very large areas covering industrial and residential colonies, the geological nature of the terrain will help in deciding the number of bore holes. Dynamic or static cone penetration tests may be performed at every 100 metre by dividing the area in a grid pattern and numbers of boreholes are decided by examining the variation in the penetration curves. 4. For Highways-Along the centerline-150 to 300m spacing 5. In case of Gravity dam – 40 to 80 m.
  • 30. TYPES OF SOIL SAMPLE Basically, in civil engineering, there are two main types of soil sample that is collected for the study of the properties of soils: • Disturbed Soil Samples • Undisturbed Soil Samples Disturbed Soil Samples During the sampling process of the soil sample If the natural structure of the soil gets disturbed, then this type of soil sample is called a Disturbed Soil Sample. The Disturbed Soil Samples can be used for the determination of the grain size, plasticity characteristics, and specific gravity of the soil. The collection of disturbed soil samples is done by different methods such as Auger Boring, Wash Boring, Rotary Drilling, and Percussion Drilling, even if the disturbed soil sample is collected by hand excavating of soil with picks and shovels.
  • 31.  Undisturbed soil sample:  During the sampling process of the soil sample, if the natural structure of the soil and water content does not disturb, that means the soil retained its natural structure and water content, then these types of soil samples are called undisturbed soil samples.  The undisturbed soil samples are used for the determination of engineering properties of soils such as shear strength, permeability, and compressibility.
  • 32. SOIL SAMPLER  Types of sampler 1. Split spoon sampler 2. Thin-walled tube sampler 3. Stationary piston sampler
  • 33. Design Factors Affecting Sample Disturbance The disturbance of soil depends mainly depends upon the following design features: 1.Area Ratio 2.Inside Clearance 3.Outside Clearance Area Ratio(Ar): • It is ratio of the volume of the soil displaced by the sampler to the ratio of the sample volume. • The larger the value, the larger is the degree of disturbance. • For obtaining a good quality undisturbed soil sample, the area ratio should be 10% or less.
  • 34.  Inside Clearance (Ci): • It is to reduce the friction between the soil sample and the sampler, when the soil enters the tube by allowing for elastic expansion of the sample. • For an undisturbed sample the inside clearance should be between 1 to 3%.  Outside Clearance (Co): • This will help in reducing the friction while the sampler is driven and when it is being withdrawn after the collection of sample. • For an undisturbed soil sample the outside clearance should be lies between 0 and 2%. Co should be less than Ci.
  • 35.
  • 36. Examples: 1. A sampler has the following dimensions, internal dia of sampler tube is 70mm and outer dia is 72mm , the internal dia of cutting edge is 69 mm and the outer dia is 73mm. Compute its inside clearance, outside clearance and area ratio. Also comment on the sample collected from the sampler. 2. The cutting edge of the sampling tube has outer dia of 75mm and wall thickness of 1.7mm. Find out the area ratio. 3. Compute the area ratio of thin walled tube sampler having an external dia of 6cm and a wall thickness of 2.25 mm. Do you recommend the sampler for undisturbed soil sample and why? 4. One sampler has the area ratio of 8% while another has 16% which of these samplers do you prefer to extract undisturbed soil sample and why?
  • 37. BORE LOG REPORT • Information on subsurface conditions obtained from the boring operation is typically presented in the form of a boring record commonly known as ‘boring log’. • It is also known as sub-soil investigation report which should contain the data obtained from boreholes, site recommendations about the suitable type of foundation, soil pressure and expected settlements. • It is essential to give a complete and accurate record of data collected. All relevant data for the bore bole is recorded in a boring log. • A boring log gives the description or classification of various strata encountered at different depths.
  • 38.  A soil exploration report generally consists of the following: 1. Introduction, which gives the scope of the investigation. 2. Description of the proposed structure, the location and the geological conditions at the site. 3. Details of the field exploration programme, indicating the number of borings, their location and depths. 4. Details of the method of exploration. 5. General description of the sub-soil conditions as obtained from in- sites tests, such as standard penetration Test, cone test. 6. Details of the laboratory test conducted on the soil samples obtained and the results obtained. 7. Date and weather condition during investigation. 8. Depth of ground water table and the change in water levels. 9. Discussion of the results. 10. 10.Recommendation about the allowable bearing pressure, the type of foundation or structure. 11. 11.Conclusion:The main findings of the bore hole investigations should be clearly stated.
  • 39.
  • 40. GEOPHYSICAL EXPLORATION • Geophysical exploration may be used with advantage to locate boundaries between different elements of the subsoil as these procedures are based on the fact that the gravitational, magnetic, electrical, radioactive or elastic properties of the different elements of the subsoil may be different.  Different methods of geophysical explorations 1. Electrical resistivity method • Electrical Profiling method • Electrical Sounding method 2. Seismic Method
  • 41. Electrical Resistivity Method  Electrical resistivity method is based on the difference in the electrical conductivity or the electrical resistivity of different soils. Resistivity is defined as resistance in ohms between the opposite phases of a unit cube of a material. ρ is resistivity in ohm-cm, R is resistance in ohms, A is the cross sectional area (cm2), L is length of the conductor (cm).
  • 42.  The electrical resistivity methods are of the following two types: 1. Electrical Profiling Method. 2. Electrical Sounding method.  Electrical Profiling Method. 
  • 43. • The method is also known as the resistivity mapping method. Four electrodes are used at a constant spacing ‘a’. To conduct the test, four electrodes, which are usually in the form of metal spikes, are driven into the ground. • The two outer electrodes are known as current electrodes. • The two inner electrodes are called potential electrodes. • The mean resistivity of the strata is determined by applying a D.C. current to the outer electrodes and by measuring the voltage drop between the inner electrodes. A current of 50 to 100 milliamp is usually supplied. • The mean resistivity (ρ) is given by the formula, ρ = 2πaV/I Where I= Current supplied, a=Spacing of electrodes, V=Voltage drop
  • 45. • In this method, the electrode system, consisting of four electrodes, is expanded about a fixed location, say P. The spacing in the first setting is a1, which is increased to a2 in the second setting and to a3 in the third setting. • The spacing is thus gradually increased to a distance equal to the depth of exploration. • As the depth of the current penetration is equal to the electrode spacing, the changes in the mean resistivity is correlated to the changes in strata at that location.
  • 46. Limitations of Electrical resistivity method: (1) The methods are capable of detecting only the strata having different electrical resistivity. (2) The results are considerably influenced by surface irregularities, wetness of the strata and electrolyte concentration of the ground water. (3) As the resistivity of different strata at the interface changes gradually and not abruptly as assumed, the interpretation becomes difficult. (4) The services of an expert in the field are needed.
  • 48. • The seismic methods are based on the principle that the elastic shock waves have different velocities in different materials. At the interface of two different materials, the waves get partly reflected and partly refracted. Seismic methods of subsurface explorations generally utilise the refracted waves. • The shock wave is created by a hammer blow or by a small explosive charge at a point P. • The shock wave travels through the top layer of the soil (or rock) with a velocity V₁, depending upon the type of material in layer-I. • The observation of the first arrival of the waves is recorded by geophones located at various points, such as A, B, C. • The geophones convert the ground vibration into electrical impulses and transmit them to a recording apparatus
  • 49. Limitation of the seismic methods (1) The methods cannot be used if a hard layer with a greater seismic velocity overlies a softer layer with a smaller seismic velocity. (2) The methods cannot be used for the areas covered by concrete, asphalt pavements or any other artificial hard crust, having a high seismic velocity. (3) If the area contains some underground features, such as buried conduits, irregularly dipping strata, and irregular water table, the interpretation of the results becomes very difficult. (4) If the surface layer is frozen, the method cannot be successfully used, as it corresponds to a case of harder layer overlying a softer layer. (5) The methods require sophisticated and costly equipment. (6) For proper interpretations of the seismic survey results, the services of an expert are required.
  • 50. ^types baved on 1/613 4 Wash To AvnER luson Core wedl when he ofBoINh: Ahe loatt t Collocd tho Cordel th qwpment BoRNG: inmaion nd Sol Samples . A-1n) mothod Aeph ttoyatin,s ork laparten tetd ten. sed than bmtheonoyinys
  • 51. HAND b Const (ertial AvefRS bia at the 9 he Tthote 3 nFHANIAL AvfR hard sthahe chere AovANW: r 1:The 34 hok Sme Yime DisADVANTALE S: 3.2} Sols larpred the and Jreray Sol strata man becmes Cannl obsimeitr ohith driyen 20 be shan k wbresdy Can suew.The ad van(ed y we 5 advantiS thrut Soll 4pto hole uo a in th down wad Power, 13 sbsngatinvedlgaion anoth y an be whck Can we when the are used Small guite apdy and hoe. opeyatad ihanta diveton 12 m. w.houd and epnomialy Sampu a hilunyany ae and ho in kyly dstwda bouldrs olhy
  • 52. t In ten seri W tnd Khon water nl wash water AoVANTANGES qupnnd into T hole hode :s Rumped jethy CABLE the hole halow drll doon adhvan (ed autn the tus thranyh 7-shaped pipt oten Soil. advanced iS <che meHod is ho Slau T-PIPE the Br7 Tod drlled CAS'NG th and hrtuyh hal a ,TUR alienatively r DisAoVAN7AAE Th Wah sanply lolerkd in pt hd in and ard ats Small opning he h Choping pt at lony hruorly and atton (plleeked in a Joil. the and he dushubed
  • 53. Ro1AR DeING Tthe Rod whi As made borehole Depth "the ha Consists doumwod diling Can thiy method. ExpLORATUON: a *Grhensy advanted by to the boton o) ho hole,. mehod is shapt Too So anl prse. struuturp progile. at owey methansm Roodng depth uto ohit thy cajad in Clay sand and oces. duperds atating sress loads, Can prudnu ryan On end. oadd inAYemet de to uper selMemen? anol shesr rees
  • 60. nap.d Shall de Dston mwion Stetionany eton ampen. stotunany insiclo The piston plau. SpLIT SpooN SAMpER cONts dowend to duned dph pilon Thread torod by Contce prak apd guazng o) wncliuked PisTON SAplFR