2. Summary Of Contract
Name of Project : Alternative Water Supply to KLIA,
Design and Build Water Treatment Plant and
Associated Works at Sg.Labu,Selangor
Contract No. : PAAB/B002-D&B/W/B/K/01/10
Employer : Pengurusan Aset Air Berhad (PAAB)
Supervising Consultant : SMHB Sdn. Bhd
Design & Build Contractor : Salcon Engineering Berhad
Design & Build Consultant : GHD Perunding Sdn. Bhd
2
3. Summary Of Contract
Commencement Date : 16 June 2010
Completion Date : 15 December 2011
Contract Period : 12 Mth - Stage 1 (52.5 MLD)
: 12 + 6 Mth - Stage 2 (105 MLD)
Defect Liability Period : 24 Months
Contract Value : RM 84,213,297.00
3
4. Brief Description of Project Scope
To design, procure, construct, install, commissioning, operate,
maintain, handover and training as follows:
• A new raw water gravity main of about 400 m length from off-
river storage to the water treatment plant
• A new water treatment plant located at Sg.Labu, Selangor
which will be designed for nominal output of 105MLD
• The treated water pumping main of about 3.5 km length from
the water treatment plant to the services reservoir at KLIA
4