SlideShare a Scribd company logo
1 of 8
Download to read offline
Photos:
Top: view of the tunnel boring machine in the Southern Approach Trench.
Bottom left: No. 9 Sewer Diversion trench, looking back at laid pipe and backfill.
Bottom Right: No. 9 Sewer Diversion trench, looking forward.
Practical Work Report
Friday 14th March 2014
For: Jade Littleton (1549126)
Jade Littleton
Civil and Environmental Engineering
Employer: Fletcher Construction
Address: Level One, 816 Great South Road, Penrose
Dates of work: 12-11-2012 to 22-02-2013
Summary
Fletcher is a well-known name in the New Zealand construction industry founded in 1908 in
Dunedin. Since then the company has grown substantially in both size and strength. Fletcher
construction has joined with several other engineering companies as part of the Well-Connected
Alliance which has been formed to undertake the Waterview Connection Project which will connect
SH20 to SH16, the final step in completing Auckland’s motorway network.
During my time as part of the Well-Connected Alliance I worked on the No. 9 Sewer Diversion. Seven
lateral sewer lines crossing the Hendon Reserve had to be decommissioned to allow excavation of
the main tunnel trench. This involved the installation of a 1km pipeline running along the edge of the
excavation that would pick up each of these existing pipelines.
My work on this project included construction and earthwork supervision, environmental checks,
contract documentation and general site engineer tasks. The skills I gained from my work on this
project have set me up well to begin work as a site engineer.
Acknowledgements
I would like to thank the following person for their contributions to my development as an Engineer.
Mark Mullaney for giving me the opportunity to organise projects, and helping me at every step,
explaining all the works to me and organising days to see other works.
Table of Contents
1.0 Introduction ......................................................................................................................................1
2.0 The Waterview Connection Project..................................................................................................1
3.0 No. 9 Sewer Diversion.......................................................................................................................1
3.1 My extra mini projects............................................................................................................2
3.2 Observed Activities .................................................................................................................4
3.3 Other work..............................................................................................................................5
4.0 Conclusions .......................................................................................................................................5
Table of Figures
Figure 1: View of pipe ending prior to the sports field...........................................................................3
Figure 2: Sewer Diversion Outfall ...........................................................................................................3
Figure 3: Clegg Hammer..........................................................................................................................4
1 | P a g e
1.0 Introduction
Fletcher is a well-known name in the New Zealand construction industry. It began as a company
called Fletcher and Morris, founded by Albert Morris, and James and William John Fletcher in 1908
in Dunedin. Since then the company has grown substantially in both size and strength. The company
now runs under the name Fletcher Building which is split into five divisions which are further split
into subsidiary companies.
Fletcher Construction is one of two subsidiaries that make up the Construction Division, the other
being Fletcher Residential. Fletcher Construction then splits again into four sectors; Infrastructure,
Building and Interiors, Earthquake Recovery, and South Pacific. Under Infrastructure Fletcher has
three key brands and businesses; Brian Perry Civil, Piletech, and Pipeworks.
Fletcher construction has joined with the NZ Transport Agency, McConnell Dowell, Beca
Infrastructure, Tonkin & Taylor, Parsons Brinkerhoff, and Obayashi Corporation as part of the Well-
Connected Alliance which has been formed to undertake the Waterview Connection Project which
will connect SH20 to SH16, the final step in completing Auckland’s motorway network.
2.0 The Waterview Connection Project
The Waterview Connection Project is the last step in completing Auckland’s motorway network. It
will provide a route for West and South Auckland to compute having to travel through Spaghetti
Junction, a bottleneck in the system. After years of debates on where this section of motorway
would go and whether it would be a road or an over bridge it was decided that a tunnel would be
necessary to keep all the stakeholders content. This option involved having two construction sites,
one at the Southern end in Hendon Reserve and the other at the Northern end in the Waterview
reserve.
Due to the many volcanic cones in Auckland there are layers and pockets of basalt caused by lava
flows. Under this basalt there is, in most parts, clay. Tunnel boring machines (TBM) are unable to
bore through basalt, so an excavation had to be made to allow the TBM to tunnel under the basalt,
through the soft clay. At the Southern approach this meant needing to excavate 34m down. The
length of road needed to slope down to the tunnel face was about 700m so the extent of the
Southern Approach work site dominated Hendon Reserve. At the Northern Approach there was no
basalt so the depth of the excavation was only determined by design.
This project is one of the largest civil construction projects to be undertaken in New Zealand with a
price tag of $1.6 billion and the use of the 10th
largest TBM in the world. To undertake such a large
scale project the works were split into many mini projects that could take place apart from one
another, at the same or different times, and right alongside each other.
3.0 No. 9 Sewer Diversion
During my time as part of the Well-Connected Alliance I only worked on a very small part of the
project, none the less this part was but one of many significant pieces in the grand scheme of things.
The mini project that I worked on was a Watercare Services Ltd pipeline; the No. 9 Sewer Diversion.
In order to allow the main Southern Approach Trench excavation, seven lateral sewer lines that
2 | P a g e
crossed the Hendon Reserve had to be decommissioned. This involved the installation of a 1km
pipeline running along the edge of the excavation that would pick up each of these existing
pipelines. In order to allow the excavations to make a start while this mini project was underway, the
new line was to be live. To do this the pipeline began at the lowest point and was connected to a
sewer trunk near the tunnel face. As each of the laterals were connected to the new line they were
decommissioned allowing for the excavation beneath them. This work began near the future tunnel
face and continued south.
This pipeline was placed up to 5m at the deepest point and for most of the length of the pipeline
very solid basalt had to be excavated. The excavation of this basalt began to hold up in the sewer
diversion. A hold up on this mini project would hold up the entire project so an ingenious plan was
necessary. It was decided that the live sewage from the next lateral pipe would be diverted using an
overland flow pipe. This allowed the next lateral pipe to be decommissioned and the project as a
whole continued on as if nothing had happened.
3.1 My extra mini projects
With many other mini projects going on in conjunction with the No 9 Sewer Diversion it
came as no surprise that certain items had been placed above the intended excavation
path for the new sewer line. As moving or rectifying these things was an unforeseen
part of the project they became great extra mini projects for me to undertake.
The Weather station
As part of the Waterview Connection Project air quality and dust levels needed to be
recorded, as well general weather records. When the weather station was set up it
was in a nice quiet corner of a car park. But this spot was right on top of where the
sewer would be placed.
To move this station I had to complete the necessary contract documentation; a
work break down structure (WBS), a method statement and a Job Safety and
Environmental Analysis (JSEA). I had to liaise with the technician that installed the
station, letting them know it needed to be moved, figuring out the process for this
and finding a suitable place to put it. Once all of this had been done I was able to
organise the men and plant needed to move it.
Site access
The Sewer Diversion pipeline needed to cross the only light vehicle access into site.
This caused a lot of logistic issues. At the time there was ample parking on site, but
only one entrance for everyday workers and very little offsite parking. Many
solutions were thought up such as fast tracking an alternative entrance through a
side street and into a sports field that would soon become site parking. Although I
fully investigated this option, creating a WBS, method statement and JSEA, it was
not possible due to the late hand over of new sports fields elsewhere on the project
delaying the takeover of this particular field.
3 | P a g e
The final solution was to allow workers to enter the site through site access points
(SAP) before 7am and leave after 6pm to park in the site parking. This meant that if
you parked on site you could not leave during work hours. This option worked ok as
a good deal of workers worked during these hours but many still parked in the
residential streets around site which caused some issues with residents in the area.
Sports fields
The sports field mentioned above (in the site
access section) also caused a need for re-
planning. The pipeline soon needed to cross
through one corner of the field. At this point
the new pipe was nearing an end with only one
last lateral left to pick up. This one lateral was
not on the critical path for the project as a
whole but to complete the line before winter it
was not an option to wait for the handover of
the sports field.
The solution was to skip the section of pipe
that would cross the sports field, leaving a gap
in the pipeline which would be connected once
the field was handed over. This would mean
that this section of pipe would not be live but
this would not affect other site works as it
would have previously.
Sewer Outfall Installation
At the lower end of the pipe an overflow outfall into Oakley Creek was being
installed. The outfall pipe itself had been planned and was being installed when the
idea developed, by a few of the workers
installing it, that the outfall was in a section of
the reserve that was frequented by
pedestrians so instead of constructing a plain
concrete outfall we should construct a nice
stone wall beneath it to tie the work into the
design of the rest of the creek work going on
further upstream.
For this I contacted three stonemasons for
quotes, all of which were far too expensive. It
was decided that the men working on the
outfall would try their hand at masonry. This
worked out very well, with the final product
being of the same quality as an experienced
Figure 1: View of pipe ending prior to the
sports field
Figure 2: Sewer Diversion Outfall
4 | P a g e
stone masons work.
In the planning of this work extra care was taken with the environmental protection
of the creek. Oakley Creek is the only open air creek in Auckland and has a large
amount of wild life and fish living in it. Due to the use of mortar on the stream bank
we had to be sure to prevent any contamination of the creek. To do this we made a
barrier in the stream bed around the outfall using concrete barriers such as those
used on roads, placed a waterproof liner over the barrier, and between the barrier
and the bank. We then placed sandbags to hold the liner in place to seal off our area
from the creek. We then kept a pump at the ready to pump away any water inside
our contained work zone.
3.2Observed Activities
While onsite I was able to observe many of the other mini projects. But in particular I
spent a full day observing and assisting two separate projects.
Richardson Road Over Pass
Firstly I spent a day on Richardson Road Over Pass Bridge while the concrete deck
was being laid. I was tasked with checking the concrete truck’s dockets to be sure
the correct concrete was being delivered. There were 14 truckloads of concrete,
with loads ranging between four and six cubic meters. I assisted a technician from
Firth to carry at sump tests and add any necessary additives to the mix.
A Day in the Sewer Trench
When I started on the Sewer Diversion I spent a day in the trench to better my
understanding of the process of laying and backfilling over the pipe. I observed and
assisted in the whole process. Firstly a 200mm layer of drainage was laid and
compacted with a plate compactor, followed by a few pipe segments, the gap 20 laid
either side of the pipes and compacted in
200mm lifts. Once these layers were more
than half way up the pipe the winches
holding the pipes together could be
released. The gap 20 was then continued
until it was one meter above the pipe. Then
the gap 20 was compacted use a smooth
roller. Throughout this process a clegg
hammer was used to check the compaction.
Nuclear densometer tests were carried out
weekly to check the validity of the clegg
hammer results. A segment of the shoring
system was then picked up by an excavator
and moved forward so that the process
could continue. Figure 3: Clegg Hammer
5 | P a g e
3.3Other work
Prior to working on the No 9 Sewer Diversion Project I spent two weeks working for the
Communications team in the Waterview community. During this time I spent a lot of
time out and about in the community handing out brochures and newsletters about the
works, asking passers-bys whether they had any questions, explaining the works, and
going door to door around the neighbourhood asking residents for praise and
complaints. I found this to be one of the most important experiences while on this
project. The Waterview suburb had recently had two of its main entrances cut off by
the works leaving only one road in and out of their community. Prior to shutting the
community off residents were disgruntled by the coming inconvenience but after the
fact most residents were rather pleased at how little traffic there now was. They felt
that the streets were safer for their children and quieter. Most residents were eager to
find out what was happening on the project and to the streets around them so were
pleased to have us out there to inform them.
The Well-Connected Alliance then held a free BBQ for the residents where they gave
them a glimpse of works and informed people of works to come and how it will affect
them. The residents went away from this event very happy, comments were made
about how it was the first time many of them had talked to their neighbours and that
the event had brought the community together.
Residents were also very appreciative of the temporary playground and volleyball court
supplied in the reserve for the duration of the works and were looking forward to the
finished playground at the end of works which will include a BMX track and a skate
park.
4.0 Conclusions
I am grateful for the opportunity I was given to work on such an amazing project. Not only did I learn
a lot about the project I was on but I also learnt about all the other works going on around it and was
able to observe a good deal of it.
I learnt a lot about the importance of communication. Be it between an engineer and a workman,
between engineers on different projects and communication with stakeholders, especially residents.
I learnt about the organisation required for a project such as the contract documentation, ordering
of materials, and organising the plant and men to undertake the work. I believe the skills I gained on
this project have set me up well to begin work as a site engineer.

More Related Content

What's hot

ACT December 2015 - OM (2)
ACT December 2015 - OM (2)ACT December 2015 - OM (2)
ACT December 2015 - OM (2)Mark Shanholtzer
 
Final seia report english opened for public comments new
Final seia  report english opened for public comments newFinal seia  report english opened for public comments new
Final seia report english opened for public comments newlbrlbo
 
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsPADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsSajal Eahsan
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Soumalya Bag
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA WinnersLars Forslöf
 
Honolulu Authority for Rapid Transportation (HART) - THE RAIL - Unsafe at Any...
Honolulu Authority for Rapid Transportation (HART) - THE RAIL - Unsafe at Any...Honolulu Authority for Rapid Transportation (HART) - THE RAIL - Unsafe at Any...
Honolulu Authority for Rapid Transportation (HART) - THE RAIL - Unsafe at Any...Clifton M. Hasegawa & Associates, LLC
 
20160704 Carline_Andrew
20160704 Carline_Andrew20160704 Carline_Andrew
20160704 Carline_AndrewAndrew Carline
 
Presentation civil
Presentation civilPresentation civil
Presentation civilRoshan Mani
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Oswar Mungkasa
 

What's hot (12)

ACT December 2015 - OM (2)
ACT December 2015 - OM (2)ACT December 2015 - OM (2)
ACT December 2015 - OM (2)
 
Final seia report english opened for public comments new
Final seia  report english opened for public comments newFinal seia  report english opened for public comments new
Final seia report english opened for public comments new
 
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsPADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
 
report draft
report draftreport draft
report draft
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
 
Honolulu Authority for Rapid Transportation (HART) - THE RAIL - Unsafe at Any...
Honolulu Authority for Rapid Transportation (HART) - THE RAIL - Unsafe at Any...Honolulu Authority for Rapid Transportation (HART) - THE RAIL - Unsafe at Any...
Honolulu Authority for Rapid Transportation (HART) - THE RAIL - Unsafe at Any...
 
TCExpression Sep'11
TCExpression Sep'11TCExpression Sep'11
TCExpression Sep'11
 
Tnl design
Tnl designTnl design
Tnl design
 
20160704 Carline_Andrew
20160704 Carline_Andrew20160704 Carline_Andrew
20160704 Carline_Andrew
 
Presentation civil
Presentation civilPresentation civil
Presentation civil
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
 

Viewers also liked

Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report finalShubham Parab
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. trainingRam1239
 
Field trip report writeup
Field trip report writeupField trip report writeup
Field trip report writeupAmake
 
Introduction to plumbing part 1
Introduction to plumbing part 1Introduction to plumbing part 1
Introduction to plumbing part 1vigyanashram
 
Sanitary fitting
Sanitary fittingSanitary fitting
Sanitary fittingAB MAKASANA
 
S3 SANITARY PIPE WORK ASSIGNMENT
S3 SANITARY PIPE WORK ASSIGNMENTS3 SANITARY PIPE WORK ASSIGNMENT
S3 SANITARY PIPE WORK ASSIGNMENTno suhaila
 
Topik 1 sanitary appliances
Topik 1 sanitary appliancesTopik 1 sanitary appliances
Topik 1 sanitary appliancesInazarina Ady
 
Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbingLiguidliguid
 

Viewers also liked (9)

Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. training
 
Field trip report writeup
Field trip report writeupField trip report writeup
Field trip report writeup
 
Basic Plumbing System
Basic Plumbing System Basic Plumbing System
Basic Plumbing System
 
Introduction to plumbing part 1
Introduction to plumbing part 1Introduction to plumbing part 1
Introduction to plumbing part 1
 
Sanitary fitting
Sanitary fittingSanitary fitting
Sanitary fitting
 
S3 SANITARY PIPE WORK ASSIGNMENT
S3 SANITARY PIPE WORK ASSIGNMENTS3 SANITARY PIPE WORK ASSIGNMENT
S3 SANITARY PIPE WORK ASSIGNMENT
 
Topik 1 sanitary appliances
Topik 1 sanitary appliancesTopik 1 sanitary appliances
Topik 1 sanitary appliances
 
Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbing
 

Similar to Practical Work Report - Fletcher

216631544 Ntuli S.I EXP I.docx
216631544 Ntuli S.I EXP I.docx216631544 Ntuli S.I EXP I.docx
216631544 Ntuli S.I EXP I.docxSbusisoNtuli1
 
SIX LANNING OF DAVANAGERE-HAVERI SECTION OF NH48
SIX LANNING OF DAVANAGERE-HAVERI SECTION OF NH48SIX LANNING OF DAVANAGERE-HAVERI SECTION OF NH48
SIX LANNING OF DAVANAGERE-HAVERI SECTION OF NH48AkifPerwez
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologydinesh sharma
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaStephen McKnight
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
 
Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Ryan Johnson
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Angelo Indelicato
 
Waterman Drainage Project
Waterman Drainage ProjectWaterman Drainage Project
Waterman Drainage ProjectAndrew Motycka
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Building Construction and Technology
Building Construction and TechnologyBuilding Construction and Technology
Building Construction and TechnologySultan M Muzahir
 

Similar to Practical Work Report - Fletcher (20)

Drainage Salvation-JRiopelle
Drainage Salvation-JRiopelleDrainage Salvation-JRiopelle
Drainage Salvation-JRiopelle
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
 
216631544 Ntuli S.I EXP I.docx
216631544 Ntuli S.I EXP I.docx216631544 Ntuli S.I EXP I.docx
216631544 Ntuli S.I EXP I.docx
 
Shib
ShibShib
Shib
 
Think Outside The Box
Think Outside The BoxThink Outside The Box
Think Outside The Box
 
SIX LANNING OF DAVANAGERE-HAVERI SECTION OF NH48
SIX LANNING OF DAVANAGERE-HAVERI SECTION OF NH48SIX LANNING OF DAVANAGERE-HAVERI SECTION OF NH48
SIX LANNING OF DAVANAGERE-HAVERI SECTION OF NH48
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Bridge report
Bridge reportBridge report
Bridge report
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
Oresund
OresundOresund
Oresund
 
Waterman Drainage Project
Waterman Drainage ProjectWaterman Drainage Project
Waterman Drainage Project
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Building Construction and Technology
Building Construction and TechnologyBuilding Construction and Technology
Building Construction and Technology
 

Practical Work Report - Fletcher

  • 1. Photos: Top: view of the tunnel boring machine in the Southern Approach Trench. Bottom left: No. 9 Sewer Diversion trench, looking back at laid pipe and backfill. Bottom Right: No. 9 Sewer Diversion trench, looking forward. Practical Work Report Friday 14th March 2014 For: Jade Littleton (1549126) Jade Littleton Civil and Environmental Engineering Employer: Fletcher Construction Address: Level One, 816 Great South Road, Penrose Dates of work: 12-11-2012 to 22-02-2013
  • 2. Summary Fletcher is a well-known name in the New Zealand construction industry founded in 1908 in Dunedin. Since then the company has grown substantially in both size and strength. Fletcher construction has joined with several other engineering companies as part of the Well-Connected Alliance which has been formed to undertake the Waterview Connection Project which will connect SH20 to SH16, the final step in completing Auckland’s motorway network. During my time as part of the Well-Connected Alliance I worked on the No. 9 Sewer Diversion. Seven lateral sewer lines crossing the Hendon Reserve had to be decommissioned to allow excavation of the main tunnel trench. This involved the installation of a 1km pipeline running along the edge of the excavation that would pick up each of these existing pipelines. My work on this project included construction and earthwork supervision, environmental checks, contract documentation and general site engineer tasks. The skills I gained from my work on this project have set me up well to begin work as a site engineer. Acknowledgements I would like to thank the following person for their contributions to my development as an Engineer. Mark Mullaney for giving me the opportunity to organise projects, and helping me at every step, explaining all the works to me and organising days to see other works.
  • 3. Table of Contents 1.0 Introduction ......................................................................................................................................1 2.0 The Waterview Connection Project..................................................................................................1 3.0 No. 9 Sewer Diversion.......................................................................................................................1 3.1 My extra mini projects............................................................................................................2 3.2 Observed Activities .................................................................................................................4 3.3 Other work..............................................................................................................................5 4.0 Conclusions .......................................................................................................................................5 Table of Figures Figure 1: View of pipe ending prior to the sports field...........................................................................3 Figure 2: Sewer Diversion Outfall ...........................................................................................................3 Figure 3: Clegg Hammer..........................................................................................................................4
  • 4. 1 | P a g e 1.0 Introduction Fletcher is a well-known name in the New Zealand construction industry. It began as a company called Fletcher and Morris, founded by Albert Morris, and James and William John Fletcher in 1908 in Dunedin. Since then the company has grown substantially in both size and strength. The company now runs under the name Fletcher Building which is split into five divisions which are further split into subsidiary companies. Fletcher Construction is one of two subsidiaries that make up the Construction Division, the other being Fletcher Residential. Fletcher Construction then splits again into four sectors; Infrastructure, Building and Interiors, Earthquake Recovery, and South Pacific. Under Infrastructure Fletcher has three key brands and businesses; Brian Perry Civil, Piletech, and Pipeworks. Fletcher construction has joined with the NZ Transport Agency, McConnell Dowell, Beca Infrastructure, Tonkin & Taylor, Parsons Brinkerhoff, and Obayashi Corporation as part of the Well- Connected Alliance which has been formed to undertake the Waterview Connection Project which will connect SH20 to SH16, the final step in completing Auckland’s motorway network. 2.0 The Waterview Connection Project The Waterview Connection Project is the last step in completing Auckland’s motorway network. It will provide a route for West and South Auckland to compute having to travel through Spaghetti Junction, a bottleneck in the system. After years of debates on where this section of motorway would go and whether it would be a road or an over bridge it was decided that a tunnel would be necessary to keep all the stakeholders content. This option involved having two construction sites, one at the Southern end in Hendon Reserve and the other at the Northern end in the Waterview reserve. Due to the many volcanic cones in Auckland there are layers and pockets of basalt caused by lava flows. Under this basalt there is, in most parts, clay. Tunnel boring machines (TBM) are unable to bore through basalt, so an excavation had to be made to allow the TBM to tunnel under the basalt, through the soft clay. At the Southern approach this meant needing to excavate 34m down. The length of road needed to slope down to the tunnel face was about 700m so the extent of the Southern Approach work site dominated Hendon Reserve. At the Northern Approach there was no basalt so the depth of the excavation was only determined by design. This project is one of the largest civil construction projects to be undertaken in New Zealand with a price tag of $1.6 billion and the use of the 10th largest TBM in the world. To undertake such a large scale project the works were split into many mini projects that could take place apart from one another, at the same or different times, and right alongside each other. 3.0 No. 9 Sewer Diversion During my time as part of the Well-Connected Alliance I only worked on a very small part of the project, none the less this part was but one of many significant pieces in the grand scheme of things. The mini project that I worked on was a Watercare Services Ltd pipeline; the No. 9 Sewer Diversion. In order to allow the main Southern Approach Trench excavation, seven lateral sewer lines that
  • 5. 2 | P a g e crossed the Hendon Reserve had to be decommissioned. This involved the installation of a 1km pipeline running along the edge of the excavation that would pick up each of these existing pipelines. In order to allow the excavations to make a start while this mini project was underway, the new line was to be live. To do this the pipeline began at the lowest point and was connected to a sewer trunk near the tunnel face. As each of the laterals were connected to the new line they were decommissioned allowing for the excavation beneath them. This work began near the future tunnel face and continued south. This pipeline was placed up to 5m at the deepest point and for most of the length of the pipeline very solid basalt had to be excavated. The excavation of this basalt began to hold up in the sewer diversion. A hold up on this mini project would hold up the entire project so an ingenious plan was necessary. It was decided that the live sewage from the next lateral pipe would be diverted using an overland flow pipe. This allowed the next lateral pipe to be decommissioned and the project as a whole continued on as if nothing had happened. 3.1 My extra mini projects With many other mini projects going on in conjunction with the No 9 Sewer Diversion it came as no surprise that certain items had been placed above the intended excavation path for the new sewer line. As moving or rectifying these things was an unforeseen part of the project they became great extra mini projects for me to undertake. The Weather station As part of the Waterview Connection Project air quality and dust levels needed to be recorded, as well general weather records. When the weather station was set up it was in a nice quiet corner of a car park. But this spot was right on top of where the sewer would be placed. To move this station I had to complete the necessary contract documentation; a work break down structure (WBS), a method statement and a Job Safety and Environmental Analysis (JSEA). I had to liaise with the technician that installed the station, letting them know it needed to be moved, figuring out the process for this and finding a suitable place to put it. Once all of this had been done I was able to organise the men and plant needed to move it. Site access The Sewer Diversion pipeline needed to cross the only light vehicle access into site. This caused a lot of logistic issues. At the time there was ample parking on site, but only one entrance for everyday workers and very little offsite parking. Many solutions were thought up such as fast tracking an alternative entrance through a side street and into a sports field that would soon become site parking. Although I fully investigated this option, creating a WBS, method statement and JSEA, it was not possible due to the late hand over of new sports fields elsewhere on the project delaying the takeover of this particular field.
  • 6. 3 | P a g e The final solution was to allow workers to enter the site through site access points (SAP) before 7am and leave after 6pm to park in the site parking. This meant that if you parked on site you could not leave during work hours. This option worked ok as a good deal of workers worked during these hours but many still parked in the residential streets around site which caused some issues with residents in the area. Sports fields The sports field mentioned above (in the site access section) also caused a need for re- planning. The pipeline soon needed to cross through one corner of the field. At this point the new pipe was nearing an end with only one last lateral left to pick up. This one lateral was not on the critical path for the project as a whole but to complete the line before winter it was not an option to wait for the handover of the sports field. The solution was to skip the section of pipe that would cross the sports field, leaving a gap in the pipeline which would be connected once the field was handed over. This would mean that this section of pipe would not be live but this would not affect other site works as it would have previously. Sewer Outfall Installation At the lower end of the pipe an overflow outfall into Oakley Creek was being installed. The outfall pipe itself had been planned and was being installed when the idea developed, by a few of the workers installing it, that the outfall was in a section of the reserve that was frequented by pedestrians so instead of constructing a plain concrete outfall we should construct a nice stone wall beneath it to tie the work into the design of the rest of the creek work going on further upstream. For this I contacted three stonemasons for quotes, all of which were far too expensive. It was decided that the men working on the outfall would try their hand at masonry. This worked out very well, with the final product being of the same quality as an experienced Figure 1: View of pipe ending prior to the sports field Figure 2: Sewer Diversion Outfall
  • 7. 4 | P a g e stone masons work. In the planning of this work extra care was taken with the environmental protection of the creek. Oakley Creek is the only open air creek in Auckland and has a large amount of wild life and fish living in it. Due to the use of mortar on the stream bank we had to be sure to prevent any contamination of the creek. To do this we made a barrier in the stream bed around the outfall using concrete barriers such as those used on roads, placed a waterproof liner over the barrier, and between the barrier and the bank. We then placed sandbags to hold the liner in place to seal off our area from the creek. We then kept a pump at the ready to pump away any water inside our contained work zone. 3.2Observed Activities While onsite I was able to observe many of the other mini projects. But in particular I spent a full day observing and assisting two separate projects. Richardson Road Over Pass Firstly I spent a day on Richardson Road Over Pass Bridge while the concrete deck was being laid. I was tasked with checking the concrete truck’s dockets to be sure the correct concrete was being delivered. There were 14 truckloads of concrete, with loads ranging between four and six cubic meters. I assisted a technician from Firth to carry at sump tests and add any necessary additives to the mix. A Day in the Sewer Trench When I started on the Sewer Diversion I spent a day in the trench to better my understanding of the process of laying and backfilling over the pipe. I observed and assisted in the whole process. Firstly a 200mm layer of drainage was laid and compacted with a plate compactor, followed by a few pipe segments, the gap 20 laid either side of the pipes and compacted in 200mm lifts. Once these layers were more than half way up the pipe the winches holding the pipes together could be released. The gap 20 was then continued until it was one meter above the pipe. Then the gap 20 was compacted use a smooth roller. Throughout this process a clegg hammer was used to check the compaction. Nuclear densometer tests were carried out weekly to check the validity of the clegg hammer results. A segment of the shoring system was then picked up by an excavator and moved forward so that the process could continue. Figure 3: Clegg Hammer
  • 8. 5 | P a g e 3.3Other work Prior to working on the No 9 Sewer Diversion Project I spent two weeks working for the Communications team in the Waterview community. During this time I spent a lot of time out and about in the community handing out brochures and newsletters about the works, asking passers-bys whether they had any questions, explaining the works, and going door to door around the neighbourhood asking residents for praise and complaints. I found this to be one of the most important experiences while on this project. The Waterview suburb had recently had two of its main entrances cut off by the works leaving only one road in and out of their community. Prior to shutting the community off residents were disgruntled by the coming inconvenience but after the fact most residents were rather pleased at how little traffic there now was. They felt that the streets were safer for their children and quieter. Most residents were eager to find out what was happening on the project and to the streets around them so were pleased to have us out there to inform them. The Well-Connected Alliance then held a free BBQ for the residents where they gave them a glimpse of works and informed people of works to come and how it will affect them. The residents went away from this event very happy, comments were made about how it was the first time many of them had talked to their neighbours and that the event had brought the community together. Residents were also very appreciative of the temporary playground and volleyball court supplied in the reserve for the duration of the works and were looking forward to the finished playground at the end of works which will include a BMX track and a skate park. 4.0 Conclusions I am grateful for the opportunity I was given to work on such an amazing project. Not only did I learn a lot about the project I was on but I also learnt about all the other works going on around it and was able to observe a good deal of it. I learnt a lot about the importance of communication. Be it between an engineer and a workman, between engineers on different projects and communication with stakeholders, especially residents. I learnt about the organisation required for a project such as the contract documentation, ordering of materials, and organising the plant and men to undertake the work. I believe the skills I gained on this project have set me up well to begin work as a site engineer.