Why we need to switch over now
Richard.Patterson@mottmac.com
NEC4 vs NEC3
Mott MacDonald 7 December 2020
Richard Patterson
BA MBA CEng FICE
Mott MacDonald NEC
Advisory Services
32Years with
Mott MacDonald
25Years with
The NEC
1 Year with NEC as
NEC Consultant
30/11/2021 Mott MacDonald | NEC Programme 3
ⓘ Start presenting to display the poll results on this slide.
30/11/2021 (c) Mott MacDonald 2020 | NEC001 4
Mott
MacDonald’s
NEC Bitesize
2021
https://mottmac.sha
repoint.com/legal/in
dustryforms/nec/Pa
ges/necsessions.as
px
Date Session Code
22 January 2021 NEC Contracts - An Introduction - Why are they so different? NEC0001
09 February 2021 NEC - Introduction to the NEC Professional Services Contract (PSC) - pre-award NEC0020
01 March 2021 NEC - Introduction to the NEC Professional Services Contract (PSC) - contract
management
NEC0021
30 March 2021 NEC Engineering and Construction Contract (ECC) - Contract strategy (main &
secondary options)
NEC0003
29 April 2021 NEC Engineering and Construction Contract (ECC) - Preparing the tender
documents; tender evaluation
NEC0004
24 May 2021 NEC Engineering and Construction Short Contract (ECSC) NEC00??
22 June 2021 NEC ECC and temporary works NEC0028
14 July 2021 NEC Contracts - Programmes under ECC and PSC NEC0005
17 August 2021 NEC Contracts - The Risk Register/Early Warning Register and risk allocation and
management
NEC0006
13 September 2021 NEC Engineering and Construction Contract (ECC) - compensation events NEC0007
13 October 2021 NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and
responsibilities
NEC0008
08 November 2021 NEC Engineering and Construction Contract (ECC) - Defined Cost, the
Contractor's system and auditing
NEC0009
08 December 2021 NEC and BIM NEC0026
30/11/2021 (c) Mott MacDonald 2020 | NEC001 5
What industry do you work in?
ⓘ Start presenting to display the poll results on this slide.
30/11/2021 (c) Mott MacDonald 2020 | NEC001 6
Do you work for:
Client, Contractor, Subcontractor, Consultant
30/11/2021 (c) Mott MacDonald 2020 | NEC001 7
NEC experience:
Heard about it; used it; confident with it; give training on it
30/11/2021 (c) Mott MacDonald 2020 | NEC001 8
•16 June 2021 – NEC contacts – an introduction
•20 July 2021 - NEC contacts – programmes
•19 August 2021 - NEC contacts – early warning
•29 September 2021 - NEC contacts - compensation events
•27 October 2021 – NEC contacts - the Supervisor
•24 November 2021 – NEC contracts - NEC3 to NEC4- key
changes
•Mott MacDonald's NEC sessions for APM
•All 18:00 – 19:00
The following slides are developed from a version of those developed by
Richard Patterson of Mott MacDonald for NEC Contracts.
The original set was delivered as an NEC ECC4 webinar by Richard
Patterson and Rob Gerrard.
Recording available here:
https://youtu.be/hfjI5qDVJDE
The original ECC4 slides are also available on the NEC website.
Mott MacDonald 7 December 2020
See also Richard Patterson’s CLQ article:
‘NEC3 to NEC4 – evolution, not revolution; some
fixes and some good ideas!’
https://www.neccontract.com/About-
NEC/News-Media/NEC3-to-NEC4-evolution-
not-revolution-some-fix
NEC4 - key changes : (c) Mott McDonald
This presentation focuses on the main changes.
A second is available giving details of most of the other changes.
And full ‘track change’
comparison and
explanation detail here:
Mott MacDonald 7 December 2020
Flexibility
Clarity and simplicity
Stimulus to good management
NEC4 - key changes : (c) Mott McDonald
Clarity, Flexibility, Good Management
NEC’s core principles
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
o plain, readable English
o short sentences and bullet points
o excellent structure
o free from references to specific laws
o minor secondary options to suit specific local
law - eg Y(UK)2, Y(NZ)2
o so easy to translate, if required
You can read it
NEC Clarity
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Flexibility as you need it
NEC
• any aspects of any project, any service
• and supply
• ‘complex’ or ‘simple’
• any sector
• any procurement strategy
• any level of ‘Contractor’ design
• range of payment options
• clear and flexible risk allocation
What?
How?
• anywhere in the world Where?
Mott MacDonald 7 December 2020
ECC
Engineering and Construction Contract
TSC
Term Service Contract
ECSC
Engineering and Construction
Short Contract
TSSC
Term Service Short Contract
PSC
Prof’l
Services
Contract
SC & SSC
Supply Contract & Supply Short Contract
design construction operation
business
case
ECS
Engineering and Construction
Subcontract
ECSS
Engineering and Construction
Short Subcontract
Framework Contract
Adjudicator’s Contract
Supply
Low
High
Project
Complexity
PSSC
Prof’l
Services
Short
Contract
NEC4 - key changes : (c) Mott McDonald
Family of Contracts
NEC3
DBOC
Design Build and Operate Contract
PSSC
Prof’l
Services
Subcontract
design construction operation
business
case
Dispute Resolution Services Contract
NEC4 new members
30/11/2021 15
Low
High
Project
Complexity
Alliance Contract TSSC
Term Service
Subcontract
FMC
Facilities
Management
Contract
(Feb
2021)
FMSC
Facilities
Management
Short
Contract
(Feb
2021)
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Flexibility
The ECC4
A B C D E F
Z
1 - 9
W2
core clauses
payment option
dispute resolution option
secondary options
jurisdiction-specific options
additional conditions
C
W1 W3
W2
X1
X2
X3
X4
X5
X6
X7
X8
X9
X10
X11
X12
X13
X14
X15
X16
X17
X18
X20
X21
X22
X14
X14
X7
Y(UK)3
Y(UK)1 Y(UK)2
Y(UK)2
X10
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
– and good for collaboration
Stimulus to good management
Communications
Accepted
Programme
Compensation
events
Early warning
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Compensation events
(Almost) all in
one place
Assess time and
cost for all
Assess forecast
now – not ‘wait
and see’
Based on ‘real’
effect of event
Clear
timebound
process for
assessment
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
RT_C
Read the _ contract
10.1 The Parties, the Project Manager and the Supervisor shall act as stated in
this contract.
10.2 The Parties, the Project Manager and the Supervisor act in a spirit of
mutual trust and co-operation.
DWISIT_C
_TalTEO
Do what it says in the _
contract
_ talk (and listen) to
each other
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Key Changes
NEC 4
New and
changed
options
Language
Detail
1-9
1
2
3
5
6
4
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott MacDonald
New and
changed
ECC
options
W1 & W2 – Seniors Reps.
first
Has to be optional in W2
W3 – Dispute Avoidance Board
Not for UK…. but
ECC4 , not
PSC4
X9 Transfer of rights
X8 Undertakings to Client and
others ‘collateral warranties’
Key Changes
NEC 4
Mott MacDonald 7 December 2020
New
and
changed
ECC
options
Information
Model
Information Model
Requirements
Information
Execution Plan
X10 Information modelling
X22 Early
Contractor
Involvement
IP and license
to use
Retention
of docs
PII
Due skill
and care
X15 The Contractor’s design
X21 Whole life cost
Contractor can propose
changes to Client’s Scope to
reduce OPEX
Do a deal on Scope, Prices,
Completion Date
X11 Termination by the Client
X4 Ultimate holding company guarantee
Also apply to PSC4
Key Changes
NEC 4
Mott MacDonald 7 December 2020
Deleted
options
PSC Option
G Term contract
Key Changes
NEC 4
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Language
‘Risk Register’
(RIP) is now
‘Early Warning
Register’
ECC ‘Works
Information’ is now
‘Scope’
‘Employer’ is
now ‘Client’
‘Employer’s risk’
is ‘Client’s liability’
ECC4 , not
PSC4
Gender neutral
Key Changes
NEC 4
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Core clauses
Detail
1-9
1
2
3
5
6
4
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Core clauses
NEC4 Changes
1
1
PSC4: ‘Service Manager’ introduced
for all actions under the contract (except
pay, terminate, dispute and change the
Service Manager – left with Client)
(replicates ECC (Project Manager) and
TSC (Service Manager))
No real difference in principle from PSC3
with ‘Employer’s Agent’ option
Client may appoint own staff or an
external consultant to the role – issues?
Mott MacDonald 7 December 2020
General
• Prompt for Scope to specify ‘communication
system’
• PM prepares first Early Warning Register
• ‘early warning meetings’ at ‘no longer interval’
than in Contract Data
• Contractor’s proposals to change Client’s
Scope
• Options C and D – Prices not reduced – as ECC3
• Options A and B – if accepted Employer gets the
‘value engineering percentage’ of saving (63.12)
1
1
PSC now also allows
‘Consultant’s Scope’ but no
similar value engineering
percentage
Core clauses
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Time
• No response to a submitted
programme in two weeks?
• Contractor may prompt
• Another week of silence?
• Programme treated as accepted
3
3
ECC4 and PSC4
Core clauses
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Rebranded ‘Quality management’
• As PSC
• Quality
o quality management system as
requirements in Scope
o quality policy statement
• For acceptance of PM
o quality plan
• For acceptance of PM
• Changes for acceptance of PM
• PM may instruct C to correct
failures to comply
• Odd that it’s the PM, not Supervisor?
4
4
Core clauses
NEC4 Changes
Mott MacDonald 7 December 2020
Payment
• Contractor application for payment ‘in
form stated in Scope’ required to get
paid
• Fee – no separate ‘subcontracted fee
percentage’
• Defined Cost
• no exclusion of cost of preparing
compensation events (Options A
and B)
• ….but will still have to show
increase in planned Defined Cost
to increase the Prices.
5
5
Also applies to PSC4: Good
Money
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Final assessment (53)
• By PM four weeks after Defects
Certificate
• Contractor may prepare if PM has
not done so
• ‘conclusive evidence’ of final amount
due – unless…….taken through
dispute resolution process
5
5
Also applies to PSC4: Good
Money
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Final assessment…. more
• WI or W2
• referred to the Senior Representatives
within 4 weeks
• On and up to Adjudicator if Senior
Representatives have not agreed within 3
weeks
• On and up to tribunal within 4 weeks of
Adjudicator’s decision
• W3
• On and up to Dispute Avoidance Board
• On and up to tribunal within 4 weeks of
DAB’s recommendation
W
5
Money
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
‘Priced’ options A and B
• ‘Short Schedule of Cost Components’
• sets Defined Cost for compensation
events only
• People based on people rates
• Charge based on ‘percentage for people
overheads’ deleted
• Payments to Subcontractors now allowed
• Design and manufacture – no overhead %
applied to rates
5
5
Changes to role as QS support to
PM
Money
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
‘Cost based’ options C,D,E
• Schedule of Cost Components
• sets Defined Cost for compensation
events and routine payments
• Just the one ‘Schedule of Cost Components’
– no ‘Shorter SCC’ as ECC3
• Charge based on ‘percentage for Working
Areas overhead’ deleted
• Payments to Subcontractors (now in SCC)
• Design and manufacture – no overhead %
applied to rates
5
5
Changes to role as QS support to
PM
Money
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
‘Cost based’ options C,D,E
Finalisation of Defined Cost
• Contractor notifies when ‘a part’ of
Defined Cost is finalised
• PM responds within 13 weeks
• Contractor responds to comments
within 4 weeks
• PM accepts or corrects within 4
weeks
• If PM misses a response time,
Contractor’s assessment treated as
correct.
5
5
Same in PSC4 : Good
Money
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
PSC C and E – THE BIG ONE
• Radical – Consultants treated like Contractors
have been for 20 years
• No longer paid rates
• Instead ‘Defined Cost’ (in ‘Schedule of Cost
Components’) + Fee
• Detailed list of ‘cost to employ’ amounts
5
5
Consultants need to review how that relates
to their way of recording costs and so any
fee percentage required (will include profit)
Money
NEC4 Changes
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Money – Defined Cost in PSC4 Options C and E
amount due
(50.3)
Price for Services Provided to Date (PSPD)
expenses (if any) in Contract Data
plus …… less bits and pieces , less bits and
pieces
is the cost of the components in the Schedule of Cost
Components less Disallowed Cost.
is the total Defined Cost which the Service Manager forecasts
will have been paid by the Consultant before the next
assessment date plus the Fee.
Defined Cost
(11.2(17))
PSPD
(11.2(21))
Money
NEC4 Changes
Mott MacDonald 7 December 2020
Fee
52.1
Defined Cost
– as in the…
… Schedule of Cost
Components
Red =
Tendered
1 People:
close to ‘real’ cost to employ
2 payments to Subcontractors
3
charge for ‘support people and office
overheads = overhead percentage *
people costs
4 insurance – NOT incl premiums
= fee percentage * Defined Cost
Disallowed
Cost
expenses
completely
separate
Defined Cost
PSC4 Options C and E
Mott MacDonald 7 December 2020
Defined Cost
PSC4 Options C and E
NEC4 PSC: understanding the new
payment regime
Our article on NEC website:
https://www.neccontract.com/About-
NEC/News-and-Media/NEC4-PSC-
understanding-the-new-payment-regime
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Core clauses
NEC4
Compensation events
• Additional compensation events in
Contract Data part one
• Proposed instructions given its own
clause (65)
• New compensation event if quotation for
proposed instruction not accepted
• ‘dividing date’ between ‘actual’ and
‘forecast’ Defined Cost (63.1)
• delays assessed using Accepted
Programme ‘current at the dividing
date’…updated for progress (63.5)
6
6
Same in PSC4 : Good
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Evolution, not revolution
New contracts, new options
Some ‘fixes’
Some (good) new ideas
Lots of ‘tidying’ improvements
Summary
SB1
Slide 41
SB1 this summary needs to drive a call to action and needs to make stronger case for NEC4.
Saurabh Bhandari, 08/12/2020
Mott MacDonald 7 December 2020
NEC4 - key changes : (c) Mott McDonald
Moving from 3 to 4 is a
no-brainer.
NEC3 contracts no
longer ‘maintained’
Opportunity to improve:
• Z clauses
• Training
• Templates
• Communication forms
https://www.neccontract.com/About-NEC/News-and-
Media/Three-years-on-it-is-time-clients-switched-to-
NEC
Questions?
NEC4 - key changes : (c) Mott McDonald
Thank you
30/11/2021 Mott MacDonald | NEC Programme 45
ⓘ Start presenting to display the poll results on this slide.
30/11/2021 Mott MacDonald | NEC Programme 46
ⓘ Start presenting to display the poll results on this slide.

NEC3 to NE4 webinar

  • 1.
    Why we needto switch over now Richard.Patterson@mottmac.com NEC4 vs NEC3
  • 2.
    Mott MacDonald 7December 2020 Richard Patterson BA MBA CEng FICE Mott MacDonald NEC Advisory Services 32Years with Mott MacDonald 25Years with The NEC 1 Year with NEC as NEC Consultant
  • 3.
    30/11/2021 Mott MacDonald| NEC Programme 3 ⓘ Start presenting to display the poll results on this slide.
  • 4.
    30/11/2021 (c) MottMacDonald 2020 | NEC001 4 Mott MacDonald’s NEC Bitesize 2021 https://mottmac.sha repoint.com/legal/in dustryforms/nec/Pa ges/necsessions.as px Date Session Code 22 January 2021 NEC Contracts - An Introduction - Why are they so different? NEC0001 09 February 2021 NEC - Introduction to the NEC Professional Services Contract (PSC) - pre-award NEC0020 01 March 2021 NEC - Introduction to the NEC Professional Services Contract (PSC) - contract management NEC0021 30 March 2021 NEC Engineering and Construction Contract (ECC) - Contract strategy (main & secondary options) NEC0003 29 April 2021 NEC Engineering and Construction Contract (ECC) - Preparing the tender documents; tender evaluation NEC0004 24 May 2021 NEC Engineering and Construction Short Contract (ECSC) NEC00?? 22 June 2021 NEC ECC and temporary works NEC0028 14 July 2021 NEC Contracts - Programmes under ECC and PSC NEC0005 17 August 2021 NEC Contracts - The Risk Register/Early Warning Register and risk allocation and management NEC0006 13 September 2021 NEC Engineering and Construction Contract (ECC) - compensation events NEC0007 13 October 2021 NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and responsibilities NEC0008 08 November 2021 NEC Engineering and Construction Contract (ECC) - Defined Cost, the Contractor's system and auditing NEC0009 08 December 2021 NEC and BIM NEC0026
  • 5.
    30/11/2021 (c) MottMacDonald 2020 | NEC001 5 What industry do you work in? ⓘ Start presenting to display the poll results on this slide.
  • 6.
    30/11/2021 (c) MottMacDonald 2020 | NEC001 6 Do you work for: Client, Contractor, Subcontractor, Consultant
  • 7.
    30/11/2021 (c) MottMacDonald 2020 | NEC001 7 NEC experience: Heard about it; used it; confident with it; give training on it
  • 8.
    30/11/2021 (c) MottMacDonald 2020 | NEC001 8 •16 June 2021 – NEC contacts – an introduction •20 July 2021 - NEC contacts – programmes •19 August 2021 - NEC contacts – early warning •29 September 2021 - NEC contacts - compensation events •27 October 2021 – NEC contacts - the Supervisor •24 November 2021 – NEC contracts - NEC3 to NEC4- key changes •Mott MacDonald's NEC sessions for APM •All 18:00 – 19:00
  • 9.
    The following slidesare developed from a version of those developed by Richard Patterson of Mott MacDonald for NEC Contracts. The original set was delivered as an NEC ECC4 webinar by Richard Patterson and Rob Gerrard. Recording available here: https://youtu.be/hfjI5qDVJDE The original ECC4 slides are also available on the NEC website.
  • 10.
    Mott MacDonald 7December 2020 See also Richard Patterson’s CLQ article: ‘NEC3 to NEC4 – evolution, not revolution; some fixes and some good ideas!’ https://www.neccontract.com/About- NEC/News-Media/NEC3-to-NEC4-evolution- not-revolution-some-fix NEC4 - key changes : (c) Mott McDonald This presentation focuses on the main changes. A second is available giving details of most of the other changes. And full ‘track change’ comparison and explanation detail here:
  • 11.
    Mott MacDonald 7December 2020 Flexibility Clarity and simplicity Stimulus to good management NEC4 - key changes : (c) Mott McDonald Clarity, Flexibility, Good Management NEC’s core principles
  • 12.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald o plain, readable English o short sentences and bullet points o excellent structure o free from references to specific laws o minor secondary options to suit specific local law - eg Y(UK)2, Y(NZ)2 o so easy to translate, if required You can read it NEC Clarity
  • 13.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Flexibility as you need it NEC • any aspects of any project, any service • and supply • ‘complex’ or ‘simple’ • any sector • any procurement strategy • any level of ‘Contractor’ design • range of payment options • clear and flexible risk allocation What? How? • anywhere in the world Where?
  • 14.
    Mott MacDonald 7December 2020 ECC Engineering and Construction Contract TSC Term Service Contract ECSC Engineering and Construction Short Contract TSSC Term Service Short Contract PSC Prof’l Services Contract SC & SSC Supply Contract & Supply Short Contract design construction operation business case ECS Engineering and Construction Subcontract ECSS Engineering and Construction Short Subcontract Framework Contract Adjudicator’s Contract Supply Low High Project Complexity PSSC Prof’l Services Short Contract NEC4 - key changes : (c) Mott McDonald Family of Contracts NEC3
  • 15.
    DBOC Design Build andOperate Contract PSSC Prof’l Services Subcontract design construction operation business case Dispute Resolution Services Contract NEC4 new members 30/11/2021 15 Low High Project Complexity Alliance Contract TSSC Term Service Subcontract FMC Facilities Management Contract (Feb 2021) FMSC Facilities Management Short Contract (Feb 2021)
  • 16.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Flexibility The ECC4 A B C D E F Z 1 - 9 W2 core clauses payment option dispute resolution option secondary options jurisdiction-specific options additional conditions C W1 W3 W2 X1 X2 X3 X4 X5 X6 X7 X8 X9 X10 X11 X12 X13 X14 X15 X16 X17 X18 X20 X21 X22 X14 X14 X7 Y(UK)3 Y(UK)1 Y(UK)2 Y(UK)2 X10
  • 17.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald – and good for collaboration Stimulus to good management Communications Accepted Programme Compensation events Early warning
  • 18.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Compensation events (Almost) all in one place Assess time and cost for all Assess forecast now – not ‘wait and see’ Based on ‘real’ effect of event Clear timebound process for assessment
  • 19.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald RT_C Read the _ contract 10.1 The Parties, the Project Manager and the Supervisor shall act as stated in this contract. 10.2 The Parties, the Project Manager and the Supervisor act in a spirit of mutual trust and co-operation. DWISIT_C _TalTEO Do what it says in the _ contract _ talk (and listen) to each other
  • 20.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Key Changes NEC 4 New and changed options Language Detail 1-9 1 2 3 5 6 4
  • 21.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott MacDonald New and changed ECC options W1 & W2 – Seniors Reps. first Has to be optional in W2 W3 – Dispute Avoidance Board Not for UK…. but ECC4 , not PSC4 X9 Transfer of rights X8 Undertakings to Client and others ‘collateral warranties’ Key Changes NEC 4
  • 22.
    Mott MacDonald 7December 2020 New and changed ECC options Information Model Information Model Requirements Information Execution Plan X10 Information modelling X22 Early Contractor Involvement IP and license to use Retention of docs PII Due skill and care X15 The Contractor’s design X21 Whole life cost Contractor can propose changes to Client’s Scope to reduce OPEX Do a deal on Scope, Prices, Completion Date X11 Termination by the Client X4 Ultimate holding company guarantee Also apply to PSC4 Key Changes NEC 4
  • 23.
    Mott MacDonald 7December 2020 Deleted options PSC Option G Term contract Key Changes NEC 4
  • 24.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Language ‘Risk Register’ (RIP) is now ‘Early Warning Register’ ECC ‘Works Information’ is now ‘Scope’ ‘Employer’ is now ‘Client’ ‘Employer’s risk’ is ‘Client’s liability’ ECC4 , not PSC4 Gender neutral Key Changes NEC 4
  • 25.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Core clauses Detail 1-9 1 2 3 5 6 4
  • 26.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Core clauses NEC4 Changes 1 1 PSC4: ‘Service Manager’ introduced for all actions under the contract (except pay, terminate, dispute and change the Service Manager – left with Client) (replicates ECC (Project Manager) and TSC (Service Manager)) No real difference in principle from PSC3 with ‘Employer’s Agent’ option Client may appoint own staff or an external consultant to the role – issues?
  • 27.
    Mott MacDonald 7December 2020 General • Prompt for Scope to specify ‘communication system’ • PM prepares first Early Warning Register • ‘early warning meetings’ at ‘no longer interval’ than in Contract Data • Contractor’s proposals to change Client’s Scope • Options C and D – Prices not reduced – as ECC3 • Options A and B – if accepted Employer gets the ‘value engineering percentage’ of saving (63.12) 1 1 PSC now also allows ‘Consultant’s Scope’ but no similar value engineering percentage Core clauses NEC4 Changes
  • 28.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Time • No response to a submitted programme in two weeks? • Contractor may prompt • Another week of silence? • Programme treated as accepted 3 3 ECC4 and PSC4 Core clauses NEC4 Changes
  • 29.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Rebranded ‘Quality management’ • As PSC • Quality o quality management system as requirements in Scope o quality policy statement • For acceptance of PM o quality plan • For acceptance of PM • Changes for acceptance of PM • PM may instruct C to correct failures to comply • Odd that it’s the PM, not Supervisor? 4 4 Core clauses NEC4 Changes
  • 30.
    Mott MacDonald 7December 2020 Payment • Contractor application for payment ‘in form stated in Scope’ required to get paid • Fee – no separate ‘subcontracted fee percentage’ • Defined Cost • no exclusion of cost of preparing compensation events (Options A and B) • ….but will still have to show increase in planned Defined Cost to increase the Prices. 5 5 Also applies to PSC4: Good Money NEC4 Changes
  • 31.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Final assessment (53) • By PM four weeks after Defects Certificate • Contractor may prepare if PM has not done so • ‘conclusive evidence’ of final amount due – unless…….taken through dispute resolution process 5 5 Also applies to PSC4: Good Money NEC4 Changes
  • 32.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Final assessment…. more • WI or W2 • referred to the Senior Representatives within 4 weeks • On and up to Adjudicator if Senior Representatives have not agreed within 3 weeks • On and up to tribunal within 4 weeks of Adjudicator’s decision • W3 • On and up to Dispute Avoidance Board • On and up to tribunal within 4 weeks of DAB’s recommendation W 5 Money NEC4 Changes
  • 33.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald ‘Priced’ options A and B • ‘Short Schedule of Cost Components’ • sets Defined Cost for compensation events only • People based on people rates • Charge based on ‘percentage for people overheads’ deleted • Payments to Subcontractors now allowed • Design and manufacture – no overhead % applied to rates 5 5 Changes to role as QS support to PM Money NEC4 Changes
  • 34.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald ‘Cost based’ options C,D,E • Schedule of Cost Components • sets Defined Cost for compensation events and routine payments • Just the one ‘Schedule of Cost Components’ – no ‘Shorter SCC’ as ECC3 • Charge based on ‘percentage for Working Areas overhead’ deleted • Payments to Subcontractors (now in SCC) • Design and manufacture – no overhead % applied to rates 5 5 Changes to role as QS support to PM Money NEC4 Changes
  • 35.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald ‘Cost based’ options C,D,E Finalisation of Defined Cost • Contractor notifies when ‘a part’ of Defined Cost is finalised • PM responds within 13 weeks • Contractor responds to comments within 4 weeks • PM accepts or corrects within 4 weeks • If PM misses a response time, Contractor’s assessment treated as correct. 5 5 Same in PSC4 : Good Money NEC4 Changes
  • 36.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald PSC C and E – THE BIG ONE • Radical – Consultants treated like Contractors have been for 20 years • No longer paid rates • Instead ‘Defined Cost’ (in ‘Schedule of Cost Components’) + Fee • Detailed list of ‘cost to employ’ amounts 5 5 Consultants need to review how that relates to their way of recording costs and so any fee percentage required (will include profit) Money NEC4 Changes
  • 37.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Money – Defined Cost in PSC4 Options C and E amount due (50.3) Price for Services Provided to Date (PSPD) expenses (if any) in Contract Data plus …… less bits and pieces , less bits and pieces is the cost of the components in the Schedule of Cost Components less Disallowed Cost. is the total Defined Cost which the Service Manager forecasts will have been paid by the Consultant before the next assessment date plus the Fee. Defined Cost (11.2(17)) PSPD (11.2(21)) Money NEC4 Changes
  • 38.
    Mott MacDonald 7December 2020 Fee 52.1 Defined Cost – as in the… … Schedule of Cost Components Red = Tendered 1 People: close to ‘real’ cost to employ 2 payments to Subcontractors 3 charge for ‘support people and office overheads = overhead percentage * people costs 4 insurance – NOT incl premiums = fee percentage * Defined Cost Disallowed Cost expenses completely separate Defined Cost PSC4 Options C and E
  • 39.
    Mott MacDonald 7December 2020 Defined Cost PSC4 Options C and E NEC4 PSC: understanding the new payment regime Our article on NEC website: https://www.neccontract.com/About- NEC/News-and-Media/NEC4-PSC- understanding-the-new-payment-regime
  • 40.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Core clauses NEC4 Compensation events • Additional compensation events in Contract Data part one • Proposed instructions given its own clause (65) • New compensation event if quotation for proposed instruction not accepted • ‘dividing date’ between ‘actual’ and ‘forecast’ Defined Cost (63.1) • delays assessed using Accepted Programme ‘current at the dividing date’…updated for progress (63.5) 6 6 Same in PSC4 : Good
  • 41.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Evolution, not revolution New contracts, new options Some ‘fixes’ Some (good) new ideas Lots of ‘tidying’ improvements Summary SB1
  • 42.
    Slide 41 SB1 thissummary needs to drive a call to action and needs to make stronger case for NEC4. Saurabh Bhandari, 08/12/2020
  • 43.
    Mott MacDonald 7December 2020 NEC4 - key changes : (c) Mott McDonald Moving from 3 to 4 is a no-brainer. NEC3 contracts no longer ‘maintained’ Opportunity to improve: • Z clauses • Training • Templates • Communication forms https://www.neccontract.com/About-NEC/News-and- Media/Three-years-on-it-is-time-clients-switched-to- NEC
  • 44.
    Questions? NEC4 - keychanges : (c) Mott McDonald
  • 45.
  • 46.
    30/11/2021 Mott MacDonald| NEC Programme 45 ⓘ Start presenting to display the poll results on this slide.
  • 47.
    30/11/2021 Mott MacDonald| NEC Programme 46 ⓘ Start presenting to display the poll results on this slide.