SlideShare a Scribd company logo
1 of 36
Delay Analysis from a Technical & Legal Perspective
21 June 2023
2
Senior Director, Ankura Consulting
Global Construction Disputes, Delay Expert
Anel is a Senior Director in the Global Construction Practice at Ankura.
He specialises in programming and forensic delay analysis for clients
within the Asia Pacific Region, advising on complex disputes as a result
of delay or disruption on construction and engineering projects.
Anel Idriz Hong Kong
+852 61899424
anel.idriz@ankura.com
Degree:
• MSc Construction Law, Arbitration and Adjudication
• BSc Construction Project Management
• NEC Accredited Project Manager
Years of Experience:
• 15 Years
Professional Field:
• Member of Chartered Institute of Arbitrators, MCIArb
• Member of Chartered Institute of Building, MCIOB
• Member of Association of Project Managers, MAPM
• LLM Arbitration & Adjudication
• Practicing Associate of The Academy of Experts, AMAE
• Society of Construction Law HK – Chairman 2021
• Chartered Institute of Building Mentor
3
Independent recognition
• Ranked as a Global Elite Thought Leader by Who's Who Legal for
Construction 2023. Dennis Wong is "one of the best construction lawyers
in Hong Kong, thanks to his deep knowledge and experience in
construction disputes".
• Chambers and Partners 2022: “Dennis Wong has a great eye for detail and
delivers clear and precise legal solutions to difficult legal issues.”
Dennis Wong
Partner, Cocking & Co
• Commercial dispute resolution: mediation,
arbitration, litigation and adjudication
• Specializes in resolving complex contractual
and construction disputes
4
1. Introduction to Planning and Programming
2. The Role of a Programming and Delay Expert
3. Understanding Delay Analysis
4. Accepted Methods of Delay Analysis
5. Selecting a Method for the Analysis
6. What Records are important to be maintained for a
robust Analysis
7. Q&A Session
Cocking & Co / Ankura - Session Overview
5
INTRODUCTION TO
PLANNING & PROGRAMMING
6
Planning Vs Programming
Planning:
• Conceptualising HOW things are to be
done
• Use construction drawings and method
statements
• The where, why, whom, what, and
when will follow naturally
Programming:
• Scheduling when in time things are to
be done
“You can plan without
programming, but you
cannot programme
without planning”
Mr Alasdair Maclennan, Regional
Chairman, ICE Glasgow
7
Adequate planning leads to the correct completion of work
Inadequate planning leads to frustration towards the end
of the project & poor project performance
(Project over run & Increased Costs)
Project Start
Project
End
8
HKSAR GCC for Civil Engineering Works (1999 Edition)
Extension of Time for Completion (extracts)
50(1)(b) If in the opinion of the Engineer the cause of the delay is:
(i) inclement weather
(ii) the hoisting of tropical cyclone warning signal No. 8 or above, or a Black Rainstorm
Warning
(iii) an instruction issued by the Engineer under Clause 5
(iv) a variation ordered under Clause 60
(v) a substantial increase in the quantity of any item of work included in the Contract
(vi) the Contractor not being given possession of the Site
(vii)a disturbance to the progress of the Works for which the Employer or the Engineer
or a Specialist Contractor is responsible ….
then the Engineer shall within a reasonable time consider whether the Contractor is
fairly entitled to an extension of time for the completion of the Works or any Section
thereof.
9
Liquidated Damages for Delay
52. (1) If the Contractor fails to complete the Works…then the Employer shall
be entitled to recover from the Contractor liquidated damages, and may
but shall not be bound to deduct such damages either in whole or in part, in
accordance with the provisions of Clause 83. The payment of such damages
shall not relieve the Contractor from his obligations to complete the
Works or from any other of his obligations under the Contract.
…
(3) The period for which liquidated damages shall be calculated shall be the
number of days from the prescribed date for completion or any extension
thereof of the Works or the relevant Section until and including the certified
date of completion.
HKSAR GCC for Civil Engineering Works (1999 Edition)
10
ROLE OF PROGRAMMING &
DELAY EXPERT & CHALLENGES
11
o The delay expert must assist the tribunal in a non-bias manner to understand
‘what happened when, and why’.
o From an analysis of the as-built and baseline schedules, the expert must help
the tribunal to understand the schedule of works and the tasks comprising the
as-built critical path.
The Role of a Programming and Delay Expert
The Challenge for Programming and Delay Expert
o Cut through the jargon and make sense of it all
o Simple reports that assist, rather than confuse
o Translate dark art mystique into common sense
o Produce powerful illustrative presentations
o Clear, credible, factual, uncomplicated andpersuasive
o Provide Clarity from Confusion
o Provide a qualified opinion.
12
UNDERSTANDING DELAY ANALYSIS
13
• Delay analysis techniques allow the analyst to:
• Distinguish critical delays from non-critical delays and calculate their
impact on the project duration.
• Identify concurrent delays that did or would have delayed the project
completion.
• Differentiate between concurrent and pacing delays.
• Identify the causal link i.e. causation
Understanding Delay Analysis
The Causal Link
14
Time “at Large”
• In practice, Courts reluctant to put time “at large”
• Courts lean in favour of operable EOT provisions
• Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2)
EWHC 447 (TCC) (6 March 2007)
15
Multiplex Constructions (UK) Ltd v Honeywell Control
Systems Ltd (No. 2) EWHC 4a47 (TCC) (6 March 2007)
• Construction of new national stadium at Wembley
• Multiplex sub-contracted design, supply and installation of electronic system
to Honeywell
• Multiplex issued to Honeywell three revised programmes
• Adjudicator awarded prolongation costs to Honeywell and held that time had
been put “at large”
16
Multiplex Constructions (UK) Ltd v Honeywell Control
Systems Ltd (No. 2) EWHC 4a47 (TCC) (6 March 2007)
• Under the Sub-Contract:
• Contractor may issue any reasonable direction (including ordering
variation)
• EOT will be granted if “relevant event” was likely to cause delay to
completion
• However, list of “relevant events” do not include variation, but referred to
“delay caused by any act of prevention or default by the contractor”
17
Three Propositions
“From this review of authority I derive three propositions.
(i) Actions by the employer which are perfectly legitimate under a
construction contract may still be characterised as prevention, if those
actions cause delay beyond the contractual completion date.
(ii) Acts of prevention by an employer do not set time at large, if the contract
provides for extension of time in respect of those events.
(iii) In so far as the extension of time clause is ambiguous, it should be
construed in favour of the contractor.”
18
Court’s decision
• Time had not been put at large
• If a direction which constitutes a variation leads to completion on a later
date, such a direction constitutes “an act of prevention”
• “If a variation instruction affects the date…by a small period, one may say
that this is a hindrance; it does not in any sense make the installation of the
electronic systems impossible. On the other hand, that matter does prevent
completion on the due date and it should be characterised as “prevention”
19
ACCEPTED METHODS OF DELAY ANALYSIS
20
Accepted Methods of Delay Analysis
Method of Analysis Analysis Type
Critical Path
Determined
Delay Impact
Determined
Requires
Impacted As- Planned
Analysis
Cause & Effect Prospectively Prospectively
• Logic linked baseline programme
• A selection of delay events to be modelled.
Time Impact Analysis Cause & Effect Contemporaneously Prospectively
• Logic linked baseline programme
• Update programmes or progress information with
which to update the baseline programme
• A selection of delay events to be modelled.
Time Slice Windows
Analysis
Effect & Cause Contemporaneously Retrospectively
• Logic linked baseline programme
• Update programmes or progress information with
which to update the baseline programme.
As-Planned versus As-
Built Windows Analysis
Effect & Cause Contemporaneously Retrospectively
• Baseline programme
• As-built data.
Retrospective Longest
Path Analysis
Effect & Cause Retrospectively Retrospectively
• Baseline Programme
• As-built programme.
Collapsed As- Built
Analysis
Cause & Effect Retrospectively Retrospectively
• Logic linked as-built programme
• A selection of delay events to be modelled.
SCL Delay and Disruption Protocol 2nd Edition: February 2017
21
Critical Path
Prospective
Forward looking
Theoretical
What might have
been critical
May not reflect
reality
Contemporaneous
At the time
Considers the
evolving nature of
a project
Identifies change
to the critical path
Justifies decisions
made in context
of progress
Retrospective
Backwards view
Based on as built
information
Does not consider
changes in
criticality
Misses what was
important at the
time
Critical Path Determined
22
Analysis Type: ‘Cause and Effect’ or ‘Effect and Cause’
Programme
Update
Cause
Time Impact
Analysis
(Prospective)
Effect
(Theoretical)
Weaknesses in causal link Theoretical effect
Cause &
Effect
• Cause and Effect:
o Identify all causes of delay, see which of them identify additional entitlement
o If a cause is not identified at the outset, it will not be analysed
Planned and
As-Built Data (Factual)
Factual
Statements
Supporting
Documents
Evidence
Cause
Strong causal link grounded on facts
Effect &
Cause
Effect
• Effect and Cause:
o Identify the effect then research the cause
o Causes can be investigated in greater detail, if disputed
23
Prospective or
Retrospective
analysis - When and
Why?
Fluor v Shanghai
Zhenhua Heavy
Industry Co [2018]
EWHC 1 (TCC)
• Fluor was engaged to construct 140 wind turbine
generators for the wind farm.
• Fluor subcontracted the fabrication of steel
foundation structures for the turbines to Shanghai
Zhenhua Heavy Industry Co (SZHIC).
• The works carried out by SZHIC were defective.
• As a result, Flour had to carry out lengthy inspection
and rectification works, leading to substantial delay
to the project.
• Fluor sued SZHIC for breach of contract. At a liability
hearing the TCC held materials supplied by SZHIC
were not fit for purpose.
• In a subsequent hearing on damages, there was
extensive debate about the correct approach to
delay analysis. The assessment of damages was
further complicated by additional defects, which led
to further delays.
24
Prospective or Retrospective analysis- When and Why?
Fluor v Shanghai Zhenhua Heavy Industry Co [2018]
EWHC 1 (TCC)
• Sir Anthony-Edwards Stuart, having considered two expert delay reports,
rejected a straightforward prospective analysis of the loss.
• Paragraph 275 of the judgement highlighted the difference between
prospective and retrospective analysis;
“There has been an extensive debate about the correct approach to delay
analysis. Mr Morgan said, and I would accept, that a prospective analysis - in
other words considering the critical path at any particular point in time as viewed
by those on the ground at that time - does not necessarily produce the same
answer as an analysis carried out retrospectively. The former is the correct
approach when considering matters such as the award of an extension of time,
but that is not the exercise with which the court is concerned in this case. I agree
that some form of retrospective analysis is required"
25
Prospective or Retrospective analysis - When and
Why? Fluor v Shanghai Zhenhua Heavy Industry Co
[2018] EWHC 1 (TCC)
• The court recognizes that prospective and retrospective delay analysis
may produce different result.
• The Court did not form a view as to whether prospective or retrospective
delay analysis is the “better” approach.
• Different analysis serves different purposes at different times.
• SCL Delay and Disruption Protocol (2 edition):-
Core principle 11
Analysis time-distant from the delay event
Where an EOT application is assessed after completion of the
works, or significantly after the effect of an Employer Risk
Event, then the prospective analysis of delay referred to in the
guidance to Core Principle 4 may no longer be appropriate.
• In practice, the approach may be determined by the terms in contract.
26
Standard Form of Building Contract
Private Edition – Without Quantities (2006)
Clause 25.3 (1) “After receipt of the Contractor’s second notice the Architect
shall give an extension of time to the Contractor by fixing a later Completion
Date if he is satisfied that the completion of the Works or a Section is
being or is likely to be delayed beyond the Completion Date by the listed
event stated by the Contractor in his first and second notices to be the cause
of the delay.”
27
Clause 25.3 (8) “The Architect shall finally decide the overall extension of time,
if any, that he considers the Contractor is entitled to under clause 25, whether
by reviewing any extension of time previously granted or otherwise, and
shall fix the Completion Date, which may be the same as but not earlier than
the Completion Date previously fixed, within 90 days after Substantial
Completion or such later date as may be agreed by the parties.”
Standard Form of Building Contract
Private Edition – Without Quantities (2006)
28
SELECTING A METHOD FOR THE ANALYSIS
29
‘DELAY is simply a MATTER of FACT’
‘the ANALYSIS of DELAY is merely COMMON SENSE’
• No one best way to analyse a project
• Formulate a balanced view of delay
• Objectively be ‘Fair and Reasonable’
• Important to form a balanced view
• Provide an objective opinion
• Read the Contract!
• Analysts enjoy the “rank the methods” game.
• There is no “best method” – there is only a best method for your specific
case, given the available facts and data.
Selecting a Method for the Analysis
30
• Often pursued by contractors if they lack documentation to prove which
losses are directly caused by a specific delay
• Do not have the necessary resources or time to carry out a detailed delay
analysis
• The Courts are increasing lenient towards Global Claims.
Global Claims
31
• Defendants in Walter Lilly had argued that a number of claims advanced by
Contractor consisted of “global” claims and were barred by authority
• Held: Nothing in principle “wrong” with global claims
Walter Lilly & Co Ltd v Mackay & Anor [2012] EWHC 1773 (TCC)
32
1. Contractor does not have to show that it is impossible to prove cause and
effect
2. In the absence of contractual restrictions on global loss claims, Contractor
simply has to prove its case on balance of probabilities
3. Nothing in principle “wrong” with global claims. However, there are added
evidential difficulties for Contractor, i.e. need to establish that loss which it
has incurred would not have been incurred in any event
4. The fact that one or a series of events (which are risk or fault of Contractor)
caused or contributed to total or global loss does not necessarily mean that
Contractor can recover nothing
5. A Court will NOT usually allow global claims if actual costs attributable to
individual loss causing events can be readily and practically determined
Walter Lilly & Co Ltd v Mackay & Anor [2012] EWHC 1773 (TCC)
33
WHAT RECORDS ARE IMPORTANT TO BE
MAINTAINED FOR A ROBUST ANALYSIS
34
Why Records Are Important
• The basis for a factual analysis
• Difficult to argue against the facts
• Convincing in dispute resolution proceedings
• Records stay with the project when the site team move on.
• Quality documentation is better than quantity
• Minimize inconsistencies and conflicting positions on blame for problems in project records
What records are needed
Primary Records
The original source of actual progress
• Daily progress reports
• Equipment logs; piling, concrete pours etc.
• Delivery notes, particularly major equipment
• Completion certificates
• Photographs, drones or other recording technology
Secondary Records
Summaries based on primary records
• Monthly Progress Reports
• Meeting Minutes
• Correspondence
• Claim submission documents
35
• Contract / Sub-contract documents (and contract backup documents)
• Programme Information (soft copies)
o Original Plans (Master Programme, Other early programmes as relevant)
o Updated Programmes (progressed, as-builts, etc.)
o Look ahead, monthly work plans, etc.
o Subcontractor Programmes or work plans, etc.
o T&C programmes
• Progress Information
o All Daily/Weekly/Monthly detailed Reports, Diaries, Photographs, all meeting minutes
etc
• Issued Change information
o Instructions, RFIs, TQs, STQs, etc
• Drawings:
o Including, for example, the tender design drawings, submitted drawings and approvals
for the subcontractors works.
• Inspection Records & Certificates
o All inspection records / emails and the Non-Compliant lists.
o Handover certificates including Temporary Occupation Certificate.
• Claim document
o Notices of Claims, Claim information, Responses, etc.
• Photographs
• Any other documents you consider relevant to the claims
For Delay Analysis, some of the most important documents are likely to be
needed for proof of fact and evidence include:
37
Q&A SESSION

More Related Content

What's hot

Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...Gaurav Verma
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptxssuserb337ce1
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
construction contracts case study
construction contracts case studyconstruction contracts case study
construction contracts case studyMahSobeh
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotKhaled M. Al Kolfat MS.Eng,MoP,P3O,PMOC,PMP,M.ASCE
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 

What's hot (20)

Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Claims
ClaimsClaims
Claims
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
construction contracts case study
construction contracts case studyconstruction contracts case study
construction contracts case study
 
Contract Management
Contract ManagementContract Management
Contract Management
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 

Similar to Delay Analysis from a Technical and Legal Perspective presentation slides.pdf

Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guidelineZuzi Evangelista
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
10 lecture project scheduling 2
10 lecture project scheduling 210 lecture project scheduling 2
10 lecture project scheduling 2Ahmad Basim Hamza
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesGensol Engineering Limited
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
An improved, productive, skilled, innovative and efficient sector копия
An improved, productive, skilled, innovative and efficient sector   копияAn improved, productive, skilled, innovative and efficient sector   копия
An improved, productive, skilled, innovative and efficient sector копияLAZOVOY
 

Similar to Delay Analysis from a Technical and Legal Perspective presentation slides.pdf (20)

Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guideline
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
I0313048051
I0313048051I0313048051
I0313048051
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
10 lecture project scheduling 2
10 lecture project scheduling 210 lecture project scheduling 2
10 lecture project scheduling 2
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
Schedule Integrity - The Key to Successful Project Management
Schedule Integrity - The Key to Successful Project ManagementSchedule Integrity - The Key to Successful Project Management
Schedule Integrity - The Key to Successful Project Management
 
3 pma salehuddin - resource and project management
3   pma salehuddin - resource and project management3   pma salehuddin - resource and project management
3 pma salehuddin - resource and project management
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 
TURNKEY PROJECT.pptx
TURNKEY PROJECT.pptxTURNKEY PROJECT.pptx
TURNKEY PROJECT.pptx
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
An improved, productive, skilled, innovative and efficient sector копия
An improved, productive, skilled, innovative and efficient sector   копияAn improved, productive, skilled, innovative and efficient sector   копия
An improved, productive, skilled, innovative and efficient sector копия
 

More from Association for Project Management

Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakAssociation for Project Management
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Association for Project Management
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Association for Project Management
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Association for Project Management
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...Association for Project Management
 

More from Association for Project Management (20)

Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peak
 
Demystifying digital accessibility webinar
Demystifying digital accessibility webinarDemystifying digital accessibility webinar
Demystifying digital accessibility webinar
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...
 
Burnout_ Prevention Intervention Recovery.pdf
Burnout_ Prevention Intervention  Recovery.pdfBurnout_ Prevention Intervention  Recovery.pdf
Burnout_ Prevention Intervention Recovery.pdf
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...
 
Risk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threatRisk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threat
 
Time-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA LeadersTime-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA Leaders
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
 
Including mental health support in project delivery
Including mental health support in project deliveryIncluding mental health support in project delivery
Including mental health support in project delivery
 

Recently uploaded

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 

Recently uploaded (20)

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 

Delay Analysis from a Technical and Legal Perspective presentation slides.pdf

  • 1. Delay Analysis from a Technical & Legal Perspective 21 June 2023
  • 2. 2 Senior Director, Ankura Consulting Global Construction Disputes, Delay Expert Anel is a Senior Director in the Global Construction Practice at Ankura. He specialises in programming and forensic delay analysis for clients within the Asia Pacific Region, advising on complex disputes as a result of delay or disruption on construction and engineering projects. Anel Idriz Hong Kong +852 61899424 anel.idriz@ankura.com Degree: • MSc Construction Law, Arbitration and Adjudication • BSc Construction Project Management • NEC Accredited Project Manager Years of Experience: • 15 Years Professional Field: • Member of Chartered Institute of Arbitrators, MCIArb • Member of Chartered Institute of Building, MCIOB • Member of Association of Project Managers, MAPM • LLM Arbitration & Adjudication • Practicing Associate of The Academy of Experts, AMAE • Society of Construction Law HK – Chairman 2021 • Chartered Institute of Building Mentor
  • 3. 3 Independent recognition • Ranked as a Global Elite Thought Leader by Who's Who Legal for Construction 2023. Dennis Wong is "one of the best construction lawyers in Hong Kong, thanks to his deep knowledge and experience in construction disputes". • Chambers and Partners 2022: “Dennis Wong has a great eye for detail and delivers clear and precise legal solutions to difficult legal issues.” Dennis Wong Partner, Cocking & Co • Commercial dispute resolution: mediation, arbitration, litigation and adjudication • Specializes in resolving complex contractual and construction disputes
  • 4. 4 1. Introduction to Planning and Programming 2. The Role of a Programming and Delay Expert 3. Understanding Delay Analysis 4. Accepted Methods of Delay Analysis 5. Selecting a Method for the Analysis 6. What Records are important to be maintained for a robust Analysis 7. Q&A Session Cocking & Co / Ankura - Session Overview
  • 6. 6 Planning Vs Programming Planning: • Conceptualising HOW things are to be done • Use construction drawings and method statements • The where, why, whom, what, and when will follow naturally Programming: • Scheduling when in time things are to be done “You can plan without programming, but you cannot programme without planning” Mr Alasdair Maclennan, Regional Chairman, ICE Glasgow
  • 7. 7 Adequate planning leads to the correct completion of work Inadequate planning leads to frustration towards the end of the project & poor project performance (Project over run & Increased Costs) Project Start Project End
  • 8. 8 HKSAR GCC for Civil Engineering Works (1999 Edition) Extension of Time for Completion (extracts) 50(1)(b) If in the opinion of the Engineer the cause of the delay is: (i) inclement weather (ii) the hoisting of tropical cyclone warning signal No. 8 or above, or a Black Rainstorm Warning (iii) an instruction issued by the Engineer under Clause 5 (iv) a variation ordered under Clause 60 (v) a substantial increase in the quantity of any item of work included in the Contract (vi) the Contractor not being given possession of the Site (vii)a disturbance to the progress of the Works for which the Employer or the Engineer or a Specialist Contractor is responsible …. then the Engineer shall within a reasonable time consider whether the Contractor is fairly entitled to an extension of time for the completion of the Works or any Section thereof.
  • 9. 9 Liquidated Damages for Delay 52. (1) If the Contractor fails to complete the Works…then the Employer shall be entitled to recover from the Contractor liquidated damages, and may but shall not be bound to deduct such damages either in whole or in part, in accordance with the provisions of Clause 83. The payment of such damages shall not relieve the Contractor from his obligations to complete the Works or from any other of his obligations under the Contract. … (3) The period for which liquidated damages shall be calculated shall be the number of days from the prescribed date for completion or any extension thereof of the Works or the relevant Section until and including the certified date of completion. HKSAR GCC for Civil Engineering Works (1999 Edition)
  • 10. 10 ROLE OF PROGRAMMING & DELAY EXPERT & CHALLENGES
  • 11. 11 o The delay expert must assist the tribunal in a non-bias manner to understand ‘what happened when, and why’. o From an analysis of the as-built and baseline schedules, the expert must help the tribunal to understand the schedule of works and the tasks comprising the as-built critical path. The Role of a Programming and Delay Expert The Challenge for Programming and Delay Expert o Cut through the jargon and make sense of it all o Simple reports that assist, rather than confuse o Translate dark art mystique into common sense o Produce powerful illustrative presentations o Clear, credible, factual, uncomplicated andpersuasive o Provide Clarity from Confusion o Provide a qualified opinion.
  • 13. 13 • Delay analysis techniques allow the analyst to: • Distinguish critical delays from non-critical delays and calculate their impact on the project duration. • Identify concurrent delays that did or would have delayed the project completion. • Differentiate between concurrent and pacing delays. • Identify the causal link i.e. causation Understanding Delay Analysis The Causal Link
  • 14. 14 Time “at Large” • In practice, Courts reluctant to put time “at large” • Courts lean in favour of operable EOT provisions • Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) EWHC 447 (TCC) (6 March 2007)
  • 15. 15 Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) EWHC 4a47 (TCC) (6 March 2007) • Construction of new national stadium at Wembley • Multiplex sub-contracted design, supply and installation of electronic system to Honeywell • Multiplex issued to Honeywell three revised programmes • Adjudicator awarded prolongation costs to Honeywell and held that time had been put “at large”
  • 16. 16 Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) EWHC 4a47 (TCC) (6 March 2007) • Under the Sub-Contract: • Contractor may issue any reasonable direction (including ordering variation) • EOT will be granted if “relevant event” was likely to cause delay to completion • However, list of “relevant events” do not include variation, but referred to “delay caused by any act of prevention or default by the contractor”
  • 17. 17 Three Propositions “From this review of authority I derive three propositions. (i) Actions by the employer which are perfectly legitimate under a construction contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date. (ii) Acts of prevention by an employer do not set time at large, if the contract provides for extension of time in respect of those events. (iii) In so far as the extension of time clause is ambiguous, it should be construed in favour of the contractor.”
  • 18. 18 Court’s decision • Time had not been put at large • If a direction which constitutes a variation leads to completion on a later date, such a direction constitutes “an act of prevention” • “If a variation instruction affects the date…by a small period, one may say that this is a hindrance; it does not in any sense make the installation of the electronic systems impossible. On the other hand, that matter does prevent completion on the due date and it should be characterised as “prevention”
  • 19. 19 ACCEPTED METHODS OF DELAY ANALYSIS
  • 20. 20 Accepted Methods of Delay Analysis Method of Analysis Analysis Type Critical Path Determined Delay Impact Determined Requires Impacted As- Planned Analysis Cause & Effect Prospectively Prospectively • Logic linked baseline programme • A selection of delay events to be modelled. Time Impact Analysis Cause & Effect Contemporaneously Prospectively • Logic linked baseline programme • Update programmes or progress information with which to update the baseline programme • A selection of delay events to be modelled. Time Slice Windows Analysis Effect & Cause Contemporaneously Retrospectively • Logic linked baseline programme • Update programmes or progress information with which to update the baseline programme. As-Planned versus As- Built Windows Analysis Effect & Cause Contemporaneously Retrospectively • Baseline programme • As-built data. Retrospective Longest Path Analysis Effect & Cause Retrospectively Retrospectively • Baseline Programme • As-built programme. Collapsed As- Built Analysis Cause & Effect Retrospectively Retrospectively • Logic linked as-built programme • A selection of delay events to be modelled. SCL Delay and Disruption Protocol 2nd Edition: February 2017
  • 21. 21 Critical Path Prospective Forward looking Theoretical What might have been critical May not reflect reality Contemporaneous At the time Considers the evolving nature of a project Identifies change to the critical path Justifies decisions made in context of progress Retrospective Backwards view Based on as built information Does not consider changes in criticality Misses what was important at the time Critical Path Determined
  • 22. 22 Analysis Type: ‘Cause and Effect’ or ‘Effect and Cause’ Programme Update Cause Time Impact Analysis (Prospective) Effect (Theoretical) Weaknesses in causal link Theoretical effect Cause & Effect • Cause and Effect: o Identify all causes of delay, see which of them identify additional entitlement o If a cause is not identified at the outset, it will not be analysed Planned and As-Built Data (Factual) Factual Statements Supporting Documents Evidence Cause Strong causal link grounded on facts Effect & Cause Effect • Effect and Cause: o Identify the effect then research the cause o Causes can be investigated in greater detail, if disputed
  • 23. 23 Prospective or Retrospective analysis - When and Why? Fluor v Shanghai Zhenhua Heavy Industry Co [2018] EWHC 1 (TCC) • Fluor was engaged to construct 140 wind turbine generators for the wind farm. • Fluor subcontracted the fabrication of steel foundation structures for the turbines to Shanghai Zhenhua Heavy Industry Co (SZHIC). • The works carried out by SZHIC were defective. • As a result, Flour had to carry out lengthy inspection and rectification works, leading to substantial delay to the project. • Fluor sued SZHIC for breach of contract. At a liability hearing the TCC held materials supplied by SZHIC were not fit for purpose. • In a subsequent hearing on damages, there was extensive debate about the correct approach to delay analysis. The assessment of damages was further complicated by additional defects, which led to further delays.
  • 24. 24 Prospective or Retrospective analysis- When and Why? Fluor v Shanghai Zhenhua Heavy Industry Co [2018] EWHC 1 (TCC) • Sir Anthony-Edwards Stuart, having considered two expert delay reports, rejected a straightforward prospective analysis of the loss. • Paragraph 275 of the judgement highlighted the difference between prospective and retrospective analysis; “There has been an extensive debate about the correct approach to delay analysis. Mr Morgan said, and I would accept, that a prospective analysis - in other words considering the critical path at any particular point in time as viewed by those on the ground at that time - does not necessarily produce the same answer as an analysis carried out retrospectively. The former is the correct approach when considering matters such as the award of an extension of time, but that is not the exercise with which the court is concerned in this case. I agree that some form of retrospective analysis is required"
  • 25. 25 Prospective or Retrospective analysis - When and Why? Fluor v Shanghai Zhenhua Heavy Industry Co [2018] EWHC 1 (TCC) • The court recognizes that prospective and retrospective delay analysis may produce different result. • The Court did not form a view as to whether prospective or retrospective delay analysis is the “better” approach. • Different analysis serves different purposes at different times. • SCL Delay and Disruption Protocol (2 edition):- Core principle 11 Analysis time-distant from the delay event Where an EOT application is assessed after completion of the works, or significantly after the effect of an Employer Risk Event, then the prospective analysis of delay referred to in the guidance to Core Principle 4 may no longer be appropriate. • In practice, the approach may be determined by the terms in contract.
  • 26. 26 Standard Form of Building Contract Private Edition – Without Quantities (2006) Clause 25.3 (1) “After receipt of the Contractor’s second notice the Architect shall give an extension of time to the Contractor by fixing a later Completion Date if he is satisfied that the completion of the Works or a Section is being or is likely to be delayed beyond the Completion Date by the listed event stated by the Contractor in his first and second notices to be the cause of the delay.”
  • 27. 27 Clause 25.3 (8) “The Architect shall finally decide the overall extension of time, if any, that he considers the Contractor is entitled to under clause 25, whether by reviewing any extension of time previously granted or otherwise, and shall fix the Completion Date, which may be the same as but not earlier than the Completion Date previously fixed, within 90 days after Substantial Completion or such later date as may be agreed by the parties.” Standard Form of Building Contract Private Edition – Without Quantities (2006)
  • 28. 28 SELECTING A METHOD FOR THE ANALYSIS
  • 29. 29 ‘DELAY is simply a MATTER of FACT’ ‘the ANALYSIS of DELAY is merely COMMON SENSE’ • No one best way to analyse a project • Formulate a balanced view of delay • Objectively be ‘Fair and Reasonable’ • Important to form a balanced view • Provide an objective opinion • Read the Contract! • Analysts enjoy the “rank the methods” game. • There is no “best method” – there is only a best method for your specific case, given the available facts and data. Selecting a Method for the Analysis
  • 30. 30 • Often pursued by contractors if they lack documentation to prove which losses are directly caused by a specific delay • Do not have the necessary resources or time to carry out a detailed delay analysis • The Courts are increasing lenient towards Global Claims. Global Claims
  • 31. 31 • Defendants in Walter Lilly had argued that a number of claims advanced by Contractor consisted of “global” claims and were barred by authority • Held: Nothing in principle “wrong” with global claims Walter Lilly & Co Ltd v Mackay & Anor [2012] EWHC 1773 (TCC)
  • 32. 32 1. Contractor does not have to show that it is impossible to prove cause and effect 2. In the absence of contractual restrictions on global loss claims, Contractor simply has to prove its case on balance of probabilities 3. Nothing in principle “wrong” with global claims. However, there are added evidential difficulties for Contractor, i.e. need to establish that loss which it has incurred would not have been incurred in any event 4. The fact that one or a series of events (which are risk or fault of Contractor) caused or contributed to total or global loss does not necessarily mean that Contractor can recover nothing 5. A Court will NOT usually allow global claims if actual costs attributable to individual loss causing events can be readily and practically determined Walter Lilly & Co Ltd v Mackay & Anor [2012] EWHC 1773 (TCC)
  • 33. 33 WHAT RECORDS ARE IMPORTANT TO BE MAINTAINED FOR A ROBUST ANALYSIS
  • 34. 34 Why Records Are Important • The basis for a factual analysis • Difficult to argue against the facts • Convincing in dispute resolution proceedings • Records stay with the project when the site team move on. • Quality documentation is better than quantity • Minimize inconsistencies and conflicting positions on blame for problems in project records What records are needed Primary Records The original source of actual progress • Daily progress reports • Equipment logs; piling, concrete pours etc. • Delivery notes, particularly major equipment • Completion certificates • Photographs, drones or other recording technology Secondary Records Summaries based on primary records • Monthly Progress Reports • Meeting Minutes • Correspondence • Claim submission documents
  • 35. 35 • Contract / Sub-contract documents (and contract backup documents) • Programme Information (soft copies) o Original Plans (Master Programme, Other early programmes as relevant) o Updated Programmes (progressed, as-builts, etc.) o Look ahead, monthly work plans, etc. o Subcontractor Programmes or work plans, etc. o T&C programmes • Progress Information o All Daily/Weekly/Monthly detailed Reports, Diaries, Photographs, all meeting minutes etc • Issued Change information o Instructions, RFIs, TQs, STQs, etc • Drawings: o Including, for example, the tender design drawings, submitted drawings and approvals for the subcontractors works. • Inspection Records & Certificates o All inspection records / emails and the Non-Compliant lists. o Handover certificates including Temporary Occupation Certificate. • Claim document o Notices of Claims, Claim information, Responses, etc. • Photographs • Any other documents you consider relevant to the claims For Delay Analysis, some of the most important documents are likely to be needed for proof of fact and evidence include: