SlideShare a Scribd company logo
1 of 2
Download to read offline
First, we show that the graph is connected. Suppose G is not connected, so that G has at least two
components. Then we could partition V = V0 V1 into two non-empty pieces so there are no
edges between V0 and V1. (V0 and V1 might not be components themselves, because there
might be more than two components; instead V0 and V1 are unions of components.) Since n = |V
| = |V0| + |V1|, we must have either |V0| n/2 or |V1| n/2. Say V0 has size n/2 and pick any v
V0. Then deg(v) n/2, but every neighbor of v is contained in V0 and is not v, so deg(v) < n/2;
this is a contradiction. So G is connected. We prove there is a Hamilton circuit by induction. Let
pm be the statement “As long as m + 1 n, there is a path visiting m + 1 distinct vertices with no
repetitions”. p0 is trivial—just take a single vertex. Suppose pm is true, so we have a path v0 v1
· · · vm. We want to show that we can extend this to a circuit with one more element. If v0 is
adjacent to any vertex not already in the path, we could just add it before v0 and be done.
Similarly, if vm were adjacent to any vertex not already in the path, we could add it after vm and
be done. So we have to consider the hard case. In this case, we have an important additional fact:
all neighbors of v0 and all neighbors of vm are somewhere in the path. We want to turn our path
into a cycle. If v0 is adjacent to vm then we already have a circuit. Suppose not. We want to find
the following arrangement: v0 v1 vt1 vt vm because then we could break the link between vt1
and vt and have the circuit vt · · · vm vt1 · · · v1 v0 vt. We know that v0 has n/2 neighbors,
all of them are in this path, and none are vm. Let A be the vertices adjacent to v0, so |A| n/2.
to show above thm is flse if requirement of defree >=1/2 (n-1)
f n=2m+1n=2m+1 and m1m1, then the complete bipartite graph Km,m+1Km,m+1 has no
Hamilton cycle and the minimum degree is m=(n1)/2m=(n1)/2. [Any Hamilton cycle would
alternate between the two parts, implying they must be of equal size.]
In the even nn case, "at least (n1)/2(n1)/2" is equivalent to "at least n/2n/2", so Dirac's
Theorem implies there is a Hamilton cycle. Dropping down by half: If n=2m+2n=2m+2 and
m1m1, then Km,m+2Km,m+2 has no Hamilton cycle and the minimum degree is
m=(n2)/2m=(n2)/2.
Solution
First, we show that the graph is connected. Suppose G is not connected, so that G has at least two
components. Then we could partition V = V0 V1 into two non-empty pieces so there are no
edges between V0 and V1. (V0 and V1 might not be components themselves, because there
might be more than two components; instead V0 and V1 are unions of components.) Since n = |V
| = |V0| + |V1|, we must have either |V0| n/2 or |V1| n/2. Say V0 has size n/2 and pick any v
V0. Then deg(v) n/2, but every neighbor of v is contained in V0 and is not v, so deg(v) < n/2;
this is a contradiction. So G is connected. We prove there is a Hamilton circuit by induction. Let
pm be the statement “As long as m + 1 n, there is a path visiting m + 1 distinct vertices with no
repetitions”. p0 is trivial—just take a single vertex. Suppose pm is true, so we have a path v0 v1
· · · vm. We want to show that we can extend this to a circuit with one more element. If v0 is
adjacent to any vertex not already in the path, we could just add it before v0 and be done.
Similarly, if vm were adjacent to any vertex not already in the path, we could add it after vm and
be done. So we have to consider the hard case. In this case, we have an important additional fact:
all neighbors of v0 and all neighbors of vm are somewhere in the path. We want to turn our path
into a cycle. If v0 is adjacent to vm then we already have a circuit. Suppose not. We want to find
the following arrangement: v0 v1 vt1 vt vm because then we could break the link between vt1
and vt and have the circuit vt · · · vm vt1 · · · v1 v0 vt. We know that v0 has n/2 neighbors,
all of them are in this path, and none are vm. Let A be the vertices adjacent to v0, so |A| n/2.
to show above thm is flse if requirement of defree >=1/2 (n-1)
f n=2m+1n=2m+1 and m1m1, then the complete bipartite graph Km,m+1Km,m+1 has no
Hamilton cycle and the minimum degree is m=(n1)/2m=(n1)/2. [Any Hamilton cycle would
alternate between the two parts, implying they must be of equal size.]
In the even nn case, "at least (n1)/2(n1)/2" is equivalent to "at least n/2n/2", so Dirac's
Theorem implies there is a Hamilton cycle. Dropping down by half: If n=2m+2n=2m+2 and
m1m1, then Km,m+2Km,m+2 has no Hamilton cycle and the minimum degree is
m=(n2)/2m=(n2)/2.

More Related Content

More from anushasarees

Huntingtons disease and other hereditary diseas.pdf
                     Huntingtons disease and other hereditary diseas.pdf                     Huntingtons disease and other hereditary diseas.pdf
Huntingtons disease and other hereditary diseas.pdfanushasarees
 
ionic character BaF MgO FeO SO2 N2 .pdf
                     ionic character BaF  MgO  FeO  SO2  N2  .pdf                     ionic character BaF  MgO  FeO  SO2  N2  .pdf
ionic character BaF MgO FeO SO2 N2 .pdfanushasarees
 
Nitrogen can hold up to 4 bonds. In sodium amide.pdf
                     Nitrogen can hold up to 4 bonds.  In sodium amide.pdf                     Nitrogen can hold up to 4 bonds.  In sodium amide.pdf
Nitrogen can hold up to 4 bonds. In sodium amide.pdfanushasarees
 
C. hydrogen bonding. between N and H of differen.pdf
                     C. hydrogen bonding.  between N and H of differen.pdf                     C. hydrogen bonding.  between N and H of differen.pdf
C. hydrogen bonding. between N and H of differen.pdfanushasarees
 
  import java.util.;import acm.program.;public class FlightPla.pdf
  import java.util.;import acm.program.;public class FlightPla.pdf  import java.util.;import acm.program.;public class FlightPla.pdf
  import java.util.;import acm.program.;public class FlightPla.pdfanushasarees
 
We Know that    Amines are generally basic in naturebecause of th.pdf
We Know that    Amines are generally basic in naturebecause of th.pdfWe Know that    Amines are generally basic in naturebecause of th.pdf
We Know that    Amines are generally basic in naturebecause of th.pdfanushasarees
 
There are so many java Input Output classes that are available in it.pdf
There are so many java Input Output classes that are available in it.pdfThere are so many java Input Output classes that are available in it.pdf
There are so many java Input Output classes that are available in it.pdfanushasarees
 
Three are ways to protect unused switch ports Option B,D and E is.pdf
Three are ways to protect unused switch ports Option B,D and E is.pdfThree are ways to protect unused switch ports Option B,D and E is.pdf
Three are ways to protect unused switch ports Option B,D and E is.pdfanushasarees
 
The water turns green because the copper(II)sulfate is breaking apar.pdf
The water turns green because the copper(II)sulfate is breaking apar.pdfThe water turns green because the copper(II)sulfate is breaking apar.pdf
The water turns green because the copper(II)sulfate is breaking apar.pdfanushasarees
 
The mutation is known as inversion. In this a segment from one chrom.pdf
The mutation is known as inversion. In this a segment from one chrom.pdfThe mutation is known as inversion. In this a segment from one chrom.pdf
The mutation is known as inversion. In this a segment from one chrom.pdfanushasarees
 
The main organelles in protein sorting and targeting are Rough endop.pdf
The main organelles in protein sorting and targeting are Rough endop.pdfThe main organelles in protein sorting and targeting are Rough endop.pdf
The main organelles in protein sorting and targeting are Rough endop.pdfanushasarees
 
Successfully supporting managerial decision-making is critically dep.pdf
Successfully supporting managerial decision-making is critically dep.pdfSuccessfully supporting managerial decision-making is critically dep.pdf
Successfully supporting managerial decision-making is critically dep.pdfanushasarees
 
SolutionTo know that the team has identified all of the significa.pdf
SolutionTo know that the team has identified all of the significa.pdfSolutionTo know that the team has identified all of the significa.pdf
SolutionTo know that the team has identified all of the significa.pdfanushasarees
 
Solutiona) Maximum bus speed = bus driver delay + propagation del.pdf
Solutiona) Maximum bus speed = bus driver delay + propagation del.pdfSolutiona) Maximum bus speed = bus driver delay + propagation del.pdf
Solutiona) Maximum bus speed = bus driver delay + propagation del.pdfanushasarees
 
Solution Polymerase chain reaction is process in which several co.pdf
Solution Polymerase chain reaction is process in which several co.pdfSolution Polymerase chain reaction is process in which several co.pdf
Solution Polymerase chain reaction is process in which several co.pdfanushasarees
 
Doubling [NO] would quadruple the rate .pdf
                     Doubling [NO] would quadruple the rate           .pdf                     Doubling [NO] would quadruple the rate           .pdf
Doubling [NO] would quadruple the rate .pdfanushasarees
 
Correct answer F)4.0 .pdf
                     Correct answer F)4.0                            .pdf                     Correct answer F)4.0                            .pdf
Correct answer F)4.0 .pdfanushasarees
 
D.) The system is neither at steady state or equi.pdf
                     D.) The system is neither at steady state or equi.pdf                     D.) The system is neither at steady state or equi.pdf
D.) The system is neither at steady state or equi.pdfanushasarees
 
public class Team {Attributes private String teamId; private.pdf
public class Team {Attributes private String teamId; private.pdfpublic class Team {Attributes private String teamId; private.pdf
public class Team {Attributes private String teamId; private.pdfanushasarees
 
Pr(E) shows the probability of only event E happening.Pr(F) shows .pdf
Pr(E) shows the probability of only event E happening.Pr(F) shows .pdfPr(E) shows the probability of only event E happening.Pr(F) shows .pdf
Pr(E) shows the probability of only event E happening.Pr(F) shows .pdfanushasarees
 

More from anushasarees (20)

Huntingtons disease and other hereditary diseas.pdf
                     Huntingtons disease and other hereditary diseas.pdf                     Huntingtons disease and other hereditary diseas.pdf
Huntingtons disease and other hereditary diseas.pdf
 
ionic character BaF MgO FeO SO2 N2 .pdf
                     ionic character BaF  MgO  FeO  SO2  N2  .pdf                     ionic character BaF  MgO  FeO  SO2  N2  .pdf
ionic character BaF MgO FeO SO2 N2 .pdf
 
Nitrogen can hold up to 4 bonds. In sodium amide.pdf
                     Nitrogen can hold up to 4 bonds.  In sodium amide.pdf                     Nitrogen can hold up to 4 bonds.  In sodium amide.pdf
Nitrogen can hold up to 4 bonds. In sodium amide.pdf
 
C. hydrogen bonding. between N and H of differen.pdf
                     C. hydrogen bonding.  between N and H of differen.pdf                     C. hydrogen bonding.  between N and H of differen.pdf
C. hydrogen bonding. between N and H of differen.pdf
 
  import java.util.;import acm.program.;public class FlightPla.pdf
  import java.util.;import acm.program.;public class FlightPla.pdf  import java.util.;import acm.program.;public class FlightPla.pdf
  import java.util.;import acm.program.;public class FlightPla.pdf
 
We Know that    Amines are generally basic in naturebecause of th.pdf
We Know that    Amines are generally basic in naturebecause of th.pdfWe Know that    Amines are generally basic in naturebecause of th.pdf
We Know that    Amines are generally basic in naturebecause of th.pdf
 
There are so many java Input Output classes that are available in it.pdf
There are so many java Input Output classes that are available in it.pdfThere are so many java Input Output classes that are available in it.pdf
There are so many java Input Output classes that are available in it.pdf
 
Three are ways to protect unused switch ports Option B,D and E is.pdf
Three are ways to protect unused switch ports Option B,D and E is.pdfThree are ways to protect unused switch ports Option B,D and E is.pdf
Three are ways to protect unused switch ports Option B,D and E is.pdf
 
The water turns green because the copper(II)sulfate is breaking apar.pdf
The water turns green because the copper(II)sulfate is breaking apar.pdfThe water turns green because the copper(II)sulfate is breaking apar.pdf
The water turns green because the copper(II)sulfate is breaking apar.pdf
 
The mutation is known as inversion. In this a segment from one chrom.pdf
The mutation is known as inversion. In this a segment from one chrom.pdfThe mutation is known as inversion. In this a segment from one chrom.pdf
The mutation is known as inversion. In this a segment from one chrom.pdf
 
The main organelles in protein sorting and targeting are Rough endop.pdf
The main organelles in protein sorting and targeting are Rough endop.pdfThe main organelles in protein sorting and targeting are Rough endop.pdf
The main organelles in protein sorting and targeting are Rough endop.pdf
 
Successfully supporting managerial decision-making is critically dep.pdf
Successfully supporting managerial decision-making is critically dep.pdfSuccessfully supporting managerial decision-making is critically dep.pdf
Successfully supporting managerial decision-making is critically dep.pdf
 
SolutionTo know that the team has identified all of the significa.pdf
SolutionTo know that the team has identified all of the significa.pdfSolutionTo know that the team has identified all of the significa.pdf
SolutionTo know that the team has identified all of the significa.pdf
 
Solutiona) Maximum bus speed = bus driver delay + propagation del.pdf
Solutiona) Maximum bus speed = bus driver delay + propagation del.pdfSolutiona) Maximum bus speed = bus driver delay + propagation del.pdf
Solutiona) Maximum bus speed = bus driver delay + propagation del.pdf
 
Solution Polymerase chain reaction is process in which several co.pdf
Solution Polymerase chain reaction is process in which several co.pdfSolution Polymerase chain reaction is process in which several co.pdf
Solution Polymerase chain reaction is process in which several co.pdf
 
Doubling [NO] would quadruple the rate .pdf
                     Doubling [NO] would quadruple the rate           .pdf                     Doubling [NO] would quadruple the rate           .pdf
Doubling [NO] would quadruple the rate .pdf
 
Correct answer F)4.0 .pdf
                     Correct answer F)4.0                            .pdf                     Correct answer F)4.0                            .pdf
Correct answer F)4.0 .pdf
 
D.) The system is neither at steady state or equi.pdf
                     D.) The system is neither at steady state or equi.pdf                     D.) The system is neither at steady state or equi.pdf
D.) The system is neither at steady state or equi.pdf
 
public class Team {Attributes private String teamId; private.pdf
public class Team {Attributes private String teamId; private.pdfpublic class Team {Attributes private String teamId; private.pdf
public class Team {Attributes private String teamId; private.pdf
 
Pr(E) shows the probability of only event E happening.Pr(F) shows .pdf
Pr(E) shows the probability of only event E happening.Pr(F) shows .pdfPr(E) shows the probability of only event E happening.Pr(F) shows .pdf
Pr(E) shows the probability of only event E happening.Pr(F) shows .pdf
 

Recently uploaded

Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjMohammed Sikander
 
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhĐề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhleson0603
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽中 央社
 
OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsSandeep D Chaudhary
 
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxAnalyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxLimon Prince
 
8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital ManagementMBA Assignment Experts
 
SPLICE Working Group: Reusable Code Examples
SPLICE Working Group:Reusable Code ExamplesSPLICE Working Group:Reusable Code Examples
SPLICE Working Group: Reusable Code ExamplesPeter Brusilovsky
 
ANTI PARKISON DRUGS.pptx
ANTI         PARKISON          DRUGS.pptxANTI         PARKISON          DRUGS.pptx
ANTI PARKISON DRUGS.pptxPoojaSen20
 
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文中 央社
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...EADTU
 
MOOD STABLIZERS DRUGS.pptx
MOOD     STABLIZERS           DRUGS.pptxMOOD     STABLIZERS           DRUGS.pptx
MOOD STABLIZERS DRUGS.pptxPoojaSen20
 
Major project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesMajor project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesAmanpreetKaur157993
 
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of TransportBasic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of TransportDenish Jangid
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxAdelaideRefugio
 
Trauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesTrauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesPooky Knightsmith
 
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...Nguyen Thanh Tu Collection
 
Improved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppImproved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppCeline George
 
Climbers and Creepers used in landscaping
Climbers and Creepers used in landscapingClimbers and Creepers used in landscaping
Climbers and Creepers used in landscapingDr. M. Kumaresan Hort.
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...Nguyen Thanh Tu Collection
 

Recently uploaded (20)

Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhĐề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
 
OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & Systems
 
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxAnalyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
 
8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management
 
SPLICE Working Group: Reusable Code Examples
SPLICE Working Group:Reusable Code ExamplesSPLICE Working Group:Reusable Code Examples
SPLICE Working Group: Reusable Code Examples
 
ANTI PARKISON DRUGS.pptx
ANTI         PARKISON          DRUGS.pptxANTI         PARKISON          DRUGS.pptx
ANTI PARKISON DRUGS.pptx
 
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
MOOD STABLIZERS DRUGS.pptx
MOOD     STABLIZERS           DRUGS.pptxMOOD     STABLIZERS           DRUGS.pptx
MOOD STABLIZERS DRUGS.pptx
 
Major project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesMajor project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategies
 
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of TransportBasic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
Trauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesTrauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical Principles
 
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
 
Improved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppImproved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio App
 
Climbers and Creepers used in landscaping
Climbers and Creepers used in landscapingClimbers and Creepers used in landscaping
Climbers and Creepers used in landscaping
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 

First, we show that the graph is connected. Suppose G is not connect.pdf

  • 1. First, we show that the graph is connected. Suppose G is not connected, so that G has at least two components. Then we could partition V = V0 V1 into two non-empty pieces so there are no edges between V0 and V1. (V0 and V1 might not be components themselves, because there might be more than two components; instead V0 and V1 are unions of components.) Since n = |V | = |V0| + |V1|, we must have either |V0| n/2 or |V1| n/2. Say V0 has size n/2 and pick any v V0. Then deg(v) n/2, but every neighbor of v is contained in V0 and is not v, so deg(v) < n/2; this is a contradiction. So G is connected. We prove there is a Hamilton circuit by induction. Let pm be the statement “As long as m + 1 n, there is a path visiting m + 1 distinct vertices with no repetitions”. p0 is trivial—just take a single vertex. Suppose pm is true, so we have a path v0 v1 · · · vm. We want to show that we can extend this to a circuit with one more element. If v0 is adjacent to any vertex not already in the path, we could just add it before v0 and be done. Similarly, if vm were adjacent to any vertex not already in the path, we could add it after vm and be done. So we have to consider the hard case. In this case, we have an important additional fact: all neighbors of v0 and all neighbors of vm are somewhere in the path. We want to turn our path into a cycle. If v0 is adjacent to vm then we already have a circuit. Suppose not. We want to find the following arrangement: v0 v1 vt1 vt vm because then we could break the link between vt1 and vt and have the circuit vt · · · vm vt1 · · · v1 v0 vt. We know that v0 has n/2 neighbors, all of them are in this path, and none are vm. Let A be the vertices adjacent to v0, so |A| n/2. to show above thm is flse if requirement of defree >=1/2 (n-1) f n=2m+1n=2m+1 and m1m1, then the complete bipartite graph Km,m+1Km,m+1 has no Hamilton cycle and the minimum degree is m=(n1)/2m=(n1)/2. [Any Hamilton cycle would alternate between the two parts, implying they must be of equal size.] In the even nn case, "at least (n1)/2(n1)/2" is equivalent to "at least n/2n/2", so Dirac's Theorem implies there is a Hamilton cycle. Dropping down by half: If n=2m+2n=2m+2 and m1m1, then Km,m+2Km,m+2 has no Hamilton cycle and the minimum degree is m=(n2)/2m=(n2)/2. Solution First, we show that the graph is connected. Suppose G is not connected, so that G has at least two components. Then we could partition V = V0 V1 into two non-empty pieces so there are no edges between V0 and V1. (V0 and V1 might not be components themselves, because there might be more than two components; instead V0 and V1 are unions of components.) Since n = |V | = |V0| + |V1|, we must have either |V0| n/2 or |V1| n/2. Say V0 has size n/2 and pick any v V0. Then deg(v) n/2, but every neighbor of v is contained in V0 and is not v, so deg(v) < n/2;
  • 2. this is a contradiction. So G is connected. We prove there is a Hamilton circuit by induction. Let pm be the statement “As long as m + 1 n, there is a path visiting m + 1 distinct vertices with no repetitions”. p0 is trivial—just take a single vertex. Suppose pm is true, so we have a path v0 v1 · · · vm. We want to show that we can extend this to a circuit with one more element. If v0 is adjacent to any vertex not already in the path, we could just add it before v0 and be done. Similarly, if vm were adjacent to any vertex not already in the path, we could add it after vm and be done. So we have to consider the hard case. In this case, we have an important additional fact: all neighbors of v0 and all neighbors of vm are somewhere in the path. We want to turn our path into a cycle. If v0 is adjacent to vm then we already have a circuit. Suppose not. We want to find the following arrangement: v0 v1 vt1 vt vm because then we could break the link between vt1 and vt and have the circuit vt · · · vm vt1 · · · v1 v0 vt. We know that v0 has n/2 neighbors, all of them are in this path, and none are vm. Let A be the vertices adjacent to v0, so |A| n/2. to show above thm is flse if requirement of defree >=1/2 (n-1) f n=2m+1n=2m+1 and m1m1, then the complete bipartite graph Km,m+1Km,m+1 has no Hamilton cycle and the minimum degree is m=(n1)/2m=(n1)/2. [Any Hamilton cycle would alternate between the two parts, implying they must be of equal size.] In the even nn case, "at least (n1)/2(n1)/2" is equivalent to "at least n/2n/2", so Dirac's Theorem implies there is a Hamilton cycle. Dropping down by half: If n=2m+2n=2m+2 and m1m1, then Km,m+2Km,m+2 has no Hamilton cycle and the minimum degree is m=(n2)/2m=(n2)/2.