Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Deepwater rig & equipment selection
1. December 2008 Kingdom Drilling Services Ltd.
Deepwater Rig and
equipment selection
Peter Aird:
Schiedam
December 2008
2. Kingdom Drilling Services Ltd
Objective
Understand the issues
to Optimize* Material,
Tools, Equipment
systems, Environment,
Personnel & Costs to
construct, manage and
service
safe, effective and cost
efficient deepwater well
operations.
3. Kingdom Drilling Services Ltd
Rig Build Schedule
Rig Construction
Pre-engineering work
2-rig commitment (1Q2008 and 1Q2009 delivery);
Option for 3rd Rig executed (1Q2010 delivery)
Owner Furnished Equipment (OFE)
All OFE equipment/vendors selected prior to December 1, 2005
3rd Party equipment interfaces completed
4. Kingdom Drilling Services Ltd
Rig Build Process
Cleary define the work process & environments
Determine Design, Selection Specifications.
Evaluate rig requirements to meet Design,
Selection Specifications.
Select and construct rig type, to design,
specifications to deliver
sustainable, measureable added value to the work
processes involved.
Put vessel to work
Inspect.
Qualify.
Acceptance.
Assurance
5. Kingdom Drilling Services Ltd
Operational Area(s)
Primary Market: Brasil, Gulf of Mexico, West Africa and Far East/India
Or Designed for Harsh Environment Areas
6. Kingdom Drilling Services Ltd
Fit For Purpose?
Speed/Acceleration
Appearance
Social Status
Manufacturer
Maintenance
Power
Functionality
Reliability
Operating Cost
7. Kingdom Drilling Services Ltd
7
Operating requirements
Rig build selection process
Dual, single activity, offline ability needed?
Drilling operating environment
Geological aspects
Met ocean environment
Maximum water depths
Well design & well operations to be conducted
Drilling, development, completing, work-over,
intervention
Drilling tools and systems equipment required
Rules and regulations
Safety management systems
8. Kingdom Drilling Services Ltd
Rig build design drivers (2)
Exploration
Flexibility, Mobility, Speed
Load Capacity
Capability in Extreme Conditions
Development
Delivers Maximum Value $/bbl
Completion / Intervention Efficiency
Dual / Concurrent Operations
Facility Installation Capability
Template, manifold, flowline pull-in
ROV tools and equipment, moon pool
facilities
Decks pace!, cranes maximum lift
9. Kingdom Drilling Services Ltd
System design requirements?
1. Safer, faster, more reliable
than conventional tools &
equipment
2. Flexibility in operation
3. Redundancy vs. simplicity
4. Cost efficiency vs. safety and
environment
5. Control functions
6. Ease of inspection,
maintenance and repair.
10. Kingdom Drilling Services Ltd
Rig system issues
1. Operating requirements
2. Station keeping
required
3. Marine riser and
tensioner systems
4. BOP and auxiliary
requirements
5. Deck load and
materials capacities
11. Kingdom Drilling Services Ltd
Rig Efficiency / Focus Areas
Reduced environmental
loads
Drilling & marine equipment
to reduce dead load weights
Robust, reliable < flat spot
time
Simplicity, flexibility,
redundancy in design
Good I.M.R.
Yet meet all operational
requirements
15. Kingdom Drilling Services Ltd
15
Water Depth Cost Comparison
Semi submersible costs
Key Systems &
components
Water depth
1,000 ft 10,000 ft
1.Station keeping
- Anchors/winches/chains
- Dynamic positioning/thrusters
- Fuel consumption
$40 million
-
10-20 t/d
-
$85 million
10-60 t/d
2. Marine riser system $5 million $20 million
3. Tensioning System $8 million $15 million
4. Blow out prevention & control
systems
$12 million $25 million
5. Cost of hull (Size and VDL) $150-250
million
$250-350
million
6. Day rate cost $180-350
K/day
$400-600 K/day
18. Kingdom Drilling Services Ltd
Rig data form: SBOP example
Well data time form Downtime
Days on
location
Remarks
Well
On
location
date
Well
area
Water
depth
(>1000m
)
Start of
well
Moorin
g (hrs)
Run
SBOP
(hrs)
TD
TVD
(mtrs)
Spud
to TD
(days)
Pull
SBOP
(hrs)
End of
well
Moorin
g (hrs)
WO
W
(hrs)
Rig
Eqpt
(hrs)
Sub
surfac
e (hrs)
well 1
24/03/200
0Balikpapan 1807 m 39 hrs 1 hrs 4640 m 15 days 1 hrs 38 hrs 0 hrs 3 hrs 0 hrs 23 days2 AHV's
well 2
12/04/200
0Balikpapan 1844 m 25 hrs 1 hrs 4932 m 15 days 1 hrs 23 hrs 0 hrs 0 hrs 0 hrs 23 days2 AHV's
well 3
23/05/200
0Balikpapan 2048 m 34 hrs 1 hrs 4891 m 13 days 1 hrs 28 hrs 0 hrs 0 hrs 0 hrs 18 days2 AHV's
well 4
07/06/200
1Brunei 723 m 55 hrs 1 hrs 2168 m 7 days 1 hrs 35 hrs 30 hrs 4 hrs 0 hrs 17 days
23hrs waiting on
loading boat 1 AHV
well 5
24/06/200
1Brunei 1023 m 41 hrs 1 hrs 2832 m 15 days 1 hrs 28 hrs 0 hrs 0 hrs 0 hrs 21 days1 AHV
well 6
11/07/200
1Brunei 836 m 36 hrs 1 hrs 2338 m 5 days 1 hrs 33 hrs 0 hrs 1 hrs 0 hrs 14 days1 AHV
well 7
03/01/200
2Balikpapan 1368 m 30 hrs 1 hrs 3034 m 5 days 1 hrs 23 hrs 0 hrs 1 hrs 0 hrs 11 days
Cantenary system
2AHV's
well 8
14/01/200
2Balikpapan 1711 m 28 hrs 1 hrs 4357 m 15 days 1 hrs 37 hrs 0 hrs 1 hrs 0 hrs 18 daysTaut leg system 1AHV
well 9
01/02/200
2Balikpapan 1553 m 40 hrs 1 hrs 3984 m 15 days 1 hrs 20 hrs 0 hrs 3 hrs 0 hrs 27 days
Taut leg system 1AHV,
DST
well 10
28/02/200
2Balikpapan 1605 m 22 hrs 1 hrs 3877 m 9 days 1 hrs 20 hrs 0 hrs 2 hrs 0 hrs 14 daysTaut leg system 2AHV
Any other relevant rig-related operational aspects:
1452 m 35 hrs 1 hrs 3705 m 11 days 1 hrs 29 hrs 3 hrs 1 hrs 0 hrs 19 days
18
19. Kingdom Drilling Services Ltd
Rig data form: 5th gen drillship
Well data time form Downtime
Days on
location
Remarks
Well
On
location
date
Well area
Water
depth
(>1000m)
DP Ops
Start of
well (hrs)
Run
SBOP
(hrs)
TD TVD
(mtrs)
Spud to
TD
(days)
Pull
SBOP
(hrs)
DP ops
end of
well (hrs)
WOW
(hrs)
Rig
Eqpt
(hrs)
Sub
surface
(hrs)
1 Dec-00Brazil 2483 m 74.0 hrs 4555 m 35 days 43.0 hrs 76.0 hrs 7.0 hrs 44 days
2 Jan-01Brazil 2391 m 51.0 hrs 4641 m 21 days 44.0 hrs 4.0 hrs 23.5 hrs 30 days
3 Feb-01Brazil 1639 m 32.0 hrs 3724 m 23 days 30.0 hrs 30.0 hrs 0.0 hrs 39 days
4 Apr-01GOM 1339 m 46.0 hrs 3303 m 14 days 34.0 hrs 3.0 hrs 18.5 hrs 28 days
5 May-01GOM 1170 m 42.0 hrs 3580 m 37 days 27.0 hrs 40.0 hrs 0.0 hrs 49 days
6 Jul-01GOM 1486 m 36.0 hrs 2398 m 7 days 27.0 hrs 1.0 hrs 0.0 hrs 15 days
7 Jul-01GOM 1281 m 28.0 hrs 3658 m 17 days 25.0 hrs 22.5 hrs 11.0 hrs 0.0 hrs 62 days
8 Sep-01GOM 1551 m 41.0 hrs 4184 m 35 days 26.0 hrs 17.0 hrs 0.0 hrs 43 days
1668 m 43.8 hrs 3755 m 24 days 32.0 hrs 22.5 hrs 22.8 hrs 6.1 hrs 39 days
19
20. Kingdom Drilling Services Ltd
Comparative evaluation
SE Asia
Benign environment
Complex difficult wells
Little infrastructure
Support facilities
limited
Few rigs to select from
Pre-lay and AHSV
needed to support ops
GOM 5th Gen Drillship
Mob –demob costs
Much higher day-rate
High equipment
downtime
Longer on wells
DP
Less support
requirements
More difficult to crew
up for?
22. December 2008 Kingdom Drilling Services Ltd.
System and key
operational
considerations
23. Kingdom Drilling Services Ltd
Key work areas (1)
Drill-floor
BHA and ad-hoc component handling
SIMOPS
Moon-pool
Conductors, guide, flow bases
Subsea equipment, trees, manifolds etc
SIMOPS
24. Kingdom Drilling Services Ltd
Rig Floor & Moonpool
Flexibility for pipe
handling, casing,
and riser at rig floor
Moonpool flexibility
for BOP/riser,
SXTree systems,
concurrent
operations
25. Kingdom Drilling Services Ltd
Drill Floor – Starboard Side
Main rotary and
drawworks
Rotary B in
background
Pipe/casing racking
(aft)
Vertical Riser
storage (Fwd)
26. Kingdom Drilling Services Ltd
Main Particulars - Moonpool
NLine Riser tensioner
Skiddable system to reach
underneath A or B
Wet store riser hang-off option (stbd
side)
BOP Handling (stbd)
BOP & LMRP
SXTree handling (port)
Staging area for trees
Can handle accessory items (EDP,
LRP, tubing spool)
Underhull Guide
Guide for each rotary
29. Kingdom Drilling Services Ltd
Key work areas (2)
Mud pits and fluids management
BHA and ad-hoc component handling
BOP’s and marine risers
BOP’s and marine riser operations inter-faces
etc.
Cementing
3rd party equipment
30. Kingdom Drilling Services Ltd
Mud pits & fluid management
LP circulating system
Fluid storage
Riser-less drilling, drilling,
completion
Dual mud system
capability?
HP circulating system
Solids control
Shakers, centrifuge
Well control
Degasser, poor boy,
diverters systems
32. Kingdom Drilling Services Ltd
Main Particulars – LP Mud
Pit Design
Split system; can treat two different
drilling fluid systems simultaneously
750 m3 (4500 bbls) each
bulk system can supply at least two
mud surge tanks at the same time.
Solids control
Gravity feed
Split shaker banks to provide reduced
time to change fluids
Cuttings Handling
Provision for cuttings drier, blower,
cuttings boxes
Mud Additive/Mixing system
Completion Fluids
Configured for reduced time to change
to completion fluid
33. Kingdom Drilling Services Ltd
BOP/Riser/Well Control
BOP:
Hydril 15 ksi 6 ram 2x 10 ksi annulars;
BOP Controls:
Hydril Multiplex
Emergency BOP Controls: Acoustic,
ROV panel
Riser:
75’ joint length; Kvaerner Clip Connection
Service Lines: 4” ID 15 ksi C/K lines; mud
boost line; 2x hydraulic line
Annular type diverter
Well Control:
CK manifold & MGS
Annular below TJ for handling gas in riser
(Option for future managed pressure
drilling option)
34. Kingdom Drilling Services Ltd
Diverter and surface capabilities
Choke and standpipe manifolds
IBOP devices.
Subsea BOP. (service, track history.)
Surface BOP
No and placement of rams.
Choke and kill lines
Instrumentation and control
Competencies.
BOP systems
35. Kingdom Drilling Services Ltd
Blow Out Prevention Equipment
• Diverter and surface capabilities
• Choke and standpipe manifolds
• IBOP devices.
• Subsea BOP.
• Service, track history.
• No and placement of rams.
• Choke and kill lines
• Instrumentation and control
• Competencies.
37. Kingdom Drilling Services Ltd
Deepwater Sub Sea BOP
15,000psi 18 ¾” Multiplex BOP stack
6 rams
Three 4 ½” – 7” VBR
Two blind/shear
One casing shear ram
10K annular’s
Combination annular lower flex joint
Temperature and pressure probes and gas
bleed v/v installed under annular.
38. Kingdom Drilling Services Ltd
Subsea BOP Stack issues
External pressure loading
may exceed capability of
BOP equipment due to
Total loss returns in wellbore
& riser
Gas in riser unloading
Removal and venting of
trapped gas
During completions
During production testing
IADC supplement 3.1.4.13
39. Kingdom Drilling Services Ltd
S.S. BOP controls considerations
Closing times, working pressures
ROV intervention
Accumulator / closing fluid requirements
Automatic sequencing
Redundancy vs. simplicity
Instrumentation & controls
Back up systems
40. Kingdom Drilling Services Ltd
Control system selection
Water Depth
0 – 2,000 ft
2,000 – 4,000 ft
Above 4,000 ft
Control System
Conventional Hydraulic
System Operated from
Surface
Deepwater Hydraulic Pod
Deepwater
Electro – Hydraulic Pod
41. Kingdom Drilling Services Ltd
SSBOP MUX control system
Central control unit
Data logging system
Driller & Toolpushers
control panels
Diverter control
Electro-hydraulic back
up system
42. Kingdom Drilling Services Ltd
Why SBOP?
Cost
Optimize drilling operation
Extends envelope of
existing rigs
Reduce non productive
time
Simpler well control
43. Kingdom Drilling Services Ltd
Relative Capabilities of Conventional Subsea BOP's vs Surface BOP's
Day Rate
Operating Water Depth
Dynamically Positioned Capability
Moored Capability
Metocean Conditions
Maximum Closed in PressureTubing Diameter
Hydrogen Sulphide
omplete as a Producer
Production Testing
Riser Fatigue Life
Subsea Capabilities
Surface BOP Now
High
Low
10,000ft
6,800ft
Yes
Not Yet
Canada
SE Asia
15,000psi
Yes
With Caution
45. Kingdom Drilling Services Ltd
45
Cementing Pumps and Mixers
Higher capacity pump
and improved mixer
Cement-mud pump
combination
46. Kingdom Drilling Services Ltd
3rd Party Items
Optimize equipment layouts for
all field development activities
3rd Party Equipment (Drlg &
Completion)
Alliance for most services
Workshop/reviews with focal points
Optimize interfaces; Identify
improvement areas (HSE, efficiency)
Well Test equipment: Power Well
Services
ROV interface - Oceaneering
Subsea Trees, Accessories and
Subsea Facility Installation
Equipment dimensions; Layouts;
Sequences
3D Animation of rig/Deployment
sequences
47. Kingdom Drilling Services Ltd
Key work areas (3)
Tensioning and
compensating systems
Station keeping and marine
systems
Deck loadings, materials
and logistics management
To be covered in following
presentation