2. SUMMARY
Citizen-initiated request for pedestrian
improvements on Townsend near Cambridge
Elementary
Potential improvements to complete sidewalk
network immediately around school’s property
Estimated project costs of $25,000 to $45,000
Proposed to split project over two fiscal years
3. BACKGROUND
In September 2023, resident presented City Council with
petition requesting pedestrian improvements along
Townsend, across street from Cambridge Elementary (CE)
Current condition on west side of Townsend
Only half the block has sidewalks between Cambridge Oval &
Harrison; sidewalks at middle of block only extend south
No sidewalks between Harrison & Ogden (next block north)
No sidewalks west on Ogden (key access to Cottage District)
4. BACKGROUND
Heavy traffic on Townsend, pick-up area for car
passengers at CE
Limited sidewalks for pedestrians traveling west of
school
City studied
Location of Right of Way (ROW) boundaries via new
survey
Current conditions of Townsend & nearby pedestrian
network
Potential improvements to enhance safety & accessibility
6. CURRENT CONDITION – SECTION A
Townsend – south toward
Crosswalk & Cambridge Oval
Townsend – north toward
Harrison
7. CURRENT CONDITION – SECTION B
Townsend – Ogden
south toward Harrison
Townsend – Harrison north
toward Ogden
8. CURRENT CONDITION – SECTION C
Ogden – east toward
Townsend
Ogden – Townsend west toward
Columbine
9. POTENTIAL IMPROVEMENTS
ROW large enough for
sidewalk & ADA
improvements
Propose 2 phases
Phase 1, Sections A & B
– sidewalks, ADA, curb
alignment, SB right-turn
only
Phase 2, Section C –
sidewalks & ADA
Phase 1, Sec. A & B
Townsend
Harrison
Ogden
Columbine
Phase 2, Sec. C
10. PROPOSAL COST ESTIMATE & TIMELINE
Estimated $45,000 cost for proposed pedestrian
improvements currently unbudgeted
Phase 1 proposal: Sections A & B in FY 2024
Estimated cost $25,000 from operating funds
2-3 months to complete
Phase 2 proposal: Section C in FY 2025
Estimated cost $20,000 from operating funds
1-2 months to complete