SlideShare a Scribd company logo
1 of 20
Download to read offline
Estimating Costing and Valuation
Diploma โ€“Vth Semester
Topic: Detail Estimate
(centre line and long wall short wall method)
Subject Code:3350604
Prepared by:
Y A .Challawala
Civil Engineering Department
Government Polytechnic Dahod
Exercise-2
Estimate the quantities of following items of a two roomed building given in Fig.
a. Earthwork in excavation in foundation trench
b. Lime concrete in foundation
c. First class brick work in 1:6 cement mortar in foundation and plinth
d. 2.5 cm thick DPC (1:2:4) with water proofing compound
e. 1st class brick work in cement mortar superstructure
Using (a) Centre line method (b) Long wall short wall method
D1=1.2 x 2.1 m
W1=1.2 x 1.2m
W1
W1D1
D1
(a) Centre line Method
Using the above image, we can first find the total length of Centre line.
Centre to Centre length of wall A = 6.3+ (1/2ร—0.30) + (1/2 x 0.30) = 6.60 m
Centre to Centre length of wall B = 4+ (1/2 x 0.30) + (1/2ร—0.30) = 4.30 m
Total length of Centre line = 6.6 +6.6 +4.3+ 4.3+4.3=26.1m
Net Centre Line = Total centre line โ€“ 1/2 ( no of junction x width of junction)
After finding out the total length of centre line, now find the quantity of the various
items which are used in construction.
W1
W1
D1
D1
a. Earthwork in excavation in foundation trench
Net Centre Line = Total centre line โ€“ 1/2 ( no of junction x width of junction)
= 26.1-1 /2 (2 x 0.9 ) =25.2
Total quantity of earth work = L x B x H m3
= 25.2 m x 0.9 x 0.9
Total quantity =20.412 m3
b. Lime concrete in foundation:
Net Centre Line = 26.1-1 /2 (2 x 0.9 ) =25.2m
Total quantity of earth work = L x B x H m3
= 25.2 x 0.9 x 0.3
Total quantity =6.804 m3
c. First class brick work in 1:6 cement mortar in foundation and plinth
Net Centre Line = Total centre line โ€“ 1/2 ( no of junction x width of junction)
Net Centre Line (60 cm Layer) =26.1-1 /2 (2 x 0.6 ) =25.5m
Net Centre Line (50 cm Layer) =26.1-1 /2 (2 x 0.5 ) =25.6m
Net Centre Line (40 cm Layer) =26.1-1 /2 (2 x 0.4 ) =25.7m

Brick work for (60 cm Layer)= 25.5 x 0.6 x 0.3 = 4.59m3
Brick work for (50 cm Layer)= 25.6 x 0.5 x 0.3 = 3.84m3
Brick work for (40 cm Layer)= 25.7 x 0.4 x 0.57 = 5.911 m3
Total Quantity = 14.341 m3
d. 2.5 cm thick DPC (1:2:4) with water proofing compound
Net Centre Line (40 cm Layer) =26.1-1 /2 (2 x 0.4 ) =25.7m
Total quantity of D.P.C work= L x B m2
= 25.7 x 0.4
Total quantity =10.28 m3
e. 1st class brick work in cement mortar superstructure
Net Centre Line (30 cm Layer) =26.1-1 /2 (2 x 0.3 ) =25.8m
Total quantity of 1st class brick work work = L x B x H m3
= 25.8 x 0.3 x 3.5
Total quantity =27.09m3
Sr.
No. Description
No
.
Leng
th
M.
Brea
dth
M.
Height
M.
Qty. Total Unit
1
Earthwork in
excavation
1 25.2 0.9 0.9 21.141 20.412
Cu.
m
2
Lime Concrete in
Foundation
1 25.2 0.9 0.3 7.047 6.804
Cu.
m.
3
Brickwork in
foundation and Plinth
(a) 60 cm layer 1 25.5 0.6 0.3 4.59
(b) 50 cm layer 1 25.6 0.5 0.3 3.84
(c) 40 cm layer 1 25.7 0.4 0.57 5.911
14.341
Cu.
m
Measurement Sheet
Sr.
No.
Description No.
Lengt
h M.
Bread
th M.
Height
M.
Qty. Total Unit
3 D.P.C 1 25.7 0.4 -- 10.44 10.28 Sq.m
4
1st class brick work in
cement mortar
superstructure
1 25.8 0.3 3.5 27.405 27.09
Cu.
m.
Deduction for Doors and
Windows
D1 2 1.2 0.3 2.1 1.512
W1 2 1.2 0.3 1.2 0.864
-2.376 Cu.m
Deduction for Lintels above
doors and windows with 15
cm bearing at each end (20
cm thick)
D1 2 1.5 0.3 0.2 0.18
W1 2 1.5 0.3 0.2 0.18
-0.36 Cu.m
Net Quantity of 1st class brick work in cement
mortar superstructure
24.354 Cu.m
(b) Long wall short wall method
Using the above image, we can first find the length of long wall and short wall.
Centre to Centre length of long wall = 5+ (1/2ร—0.30) + (1/2 x 0.30) = 6.60 m
Centre to Centre length of short wall = 4+ (1/2 x 0.30) + (1/2ร—0.30) = 4.30 m
After finding out the length of the long wall and short wall, now find the quantity of
the various items which are used in construction.
Room-1
3 x 4 m
Room-2
3 x 4 m
D1
D1
W1
W1
a. Earthwork in excavation in foundation trench
Length of long wall = c/c length + width of earthwork
= 6.6+ 0.9= 7.5m
Length of short wall = c/c length -width of earthwork
= 4.3 - 0.9= 3.4m
Total quantity of earth work = L x B x H m3
Long wall = 2 x 7.5 x 0.9 x 0.9 =12.15m3
Short wall = 3 x 3.4 x 0.9 x 0.9 =8.262m3
Total =12.15 + 8.262=20.412 m3
Sr.
No.
Description No.
Length
M.
Breadth
M.
Height
M.
Qty. Total
1
Earthwork in
excavation
Long Wall 2 7.5 0.9 0.9 12.15
Short Wall 3 3.4 0.9 0.9 8.262
20.412
b. Lime concrete in foundation:
Length of long wall = c/c length + width of concrete in foundation
= 6.6 + 0.9= 7.5m
Length of short wall = c/c length - width of concrete in foundation
= 4.3 - 0.9= 3.4m
Total quantity of earth work = L x B x H m3
Long wall = 2 x 7.5 x 0.9 x 0.3 = 4.05m3
Short wall = 3 x 3.4 x 0.9 x 0.3 = 2.754m3
Total =4.05 + 2.754=6.804m3
Sr.
No.
Description No.
Length
M.
Breadth
M.
Height
M.
Qty. Total
2
Lime
Concrete in
Foundation
Long Wall 2 7.5 0.9 0.3 4.05
Short Wall 3 3.4 0.9 0.3 2.754
6.804
c. First class brick work in 1:6 cement mortar in foundation and plinth
Length of long wall (60 cm Layer)= c/c length + width of First class brick work
= 6.6+ 0.6= 7.2m
Length of short wall (60 cm Layer) = c/c length - width of First class brick work
= 4.3 - 0.6= 3.7m
Length of long wall (50 cm Layer)= c/c length + width of First class brick work
= 6.6+ 0.5= 7.1m
Length of short wall (50 cm Layer) = c/c length - width of First class brick work
= 4.3 - 0.5= 3.8m
Length of long wall (40 cm Layer)= c/c length + width of First class brick work
= 6.6+ 0.4= 7.0m
Length of short wall (40 cm Layer) = c/c length - width of First class brick work
= 4.3 - 0.4= 3.9m
Sr.
No.
Description No.
Length
M.
Breadth
M.
Height M. Qty. Total Unit
3
Brickwork in foundation and
plinth
Long Wall
1st footing 60 cm 2 7.2 0.6 0.3 2.592
2nd footing 50 cm 2 7.1 0.5 0.3 2.13
2nd footing 40 cm 2 7 0.4 0.575 3.22
Short Wall
1st footing 60 cm 3 3.7 0.6 0.3 1.998
2nd footing 50 cm 3 3.8 0.5 0.3 1.71
2nd footing 40 cm 3 3.9 0.4 0.575 2.691
14.341 Cu.m.
d. 2.5 cm thick DPC (1:2:4) with water proofing compound
Length of long wall = c/c length + width of DPC
= 6.6+ 0.4=7.0 m
Length of short wall = c/c length + width of DPC
= 4.3 โ€“ 0.4= 3.9m
Total quantity of earth work = L x B m2
Long wall = 2 x7.0 x 0.4 =5.6m2
Short wall = 3 x 3.9 x 0.4 =4.68m2
Total =5.6 +4.68=10.28 m2
Sr.
No.
Description
No
.
Leng
th M.
Brea
dth
M.
Height
M.
Qty. Total Unit
4
2.5 cm thick DPC
(1:2:4) with water
proofing compound
Long Wall 2 7.0 0.4 - 5.6
Short Wall 3 3.9 0.4 - 4.68
10.28 Sq.m
e. 1st class brick work in cement mortar superstructure
Length of long wall = c/c length + width of 1st class brick work
= 6.6+ 0.3= 6.9m
Length of short wall = c/c length - width of 1st class brick work
= 4.3 โ€“ 0.3= 4.0m
Total quantity of earth work = L x B x H m3
Long wall = 2 x6.9 x 0.3 x3.5=14.59m3
Short wall = 3 x 4.0 x 0.3 x 3.5=12.6m3
Total =14.59+12.6=27.09 m3
Sr.
No.
Description No.
Lengt
h M.
Bread
th M.
Height
M.
Qty. Total Unit
5
1st class brick work in
cement mortar
superstructure
Long Wall
2 6.9 0.3 3.5 14.59
Short Wall 3 4.0 0.3 3.5 12.6 .
27.09 Cu.m
Sr.
No. Description
No
.
Len
gth
M.
Bre
adth
M.
Height
M.
Qty. Total Unit
1
Earthwork in
excavation
Long Wall 2
7.5 0.9 0.9 12.15
Short Wall 3
3.4 0.9 0.9 8.262
20.412 Cu.m
2
Lime Concrete in
Foundation
Long Wall 2 7.5 0.9 0.3 4.05
Short Wall 3
3.4 0.9 0.3 2.754
6.804 Cu.m.
(b) Long wall short wall method
Sr.
No. Description
No
.
Leng
th
M.
Brea
dth
M.
Heigh
t M.
Qty. Total Unit
3
Brickwork in
foundation and plinth
Long Wall
1st footing 60 cm 2 7.2 0.6 0.3 2.592
2nd footing 50 cm 2 7.1 0.5 0.3 2.13
2nd footing 40 cm 2 7 0.4 0.575 3.22
Short Wall
1st footing 60 cm 3 3.7 0.6 0.3 1.998
2nd footing 50 cm 3 3.8 0.5 0.3 1.71
2nd footing 40 cm 3 3.9 0.4 0.575 2.691
14.341
Cu.
m.
Sr.
No.
Description
No
.
Leng
th M.
Brea
dth
M.
Height
M.
Qty. Total Unit
4
2.5 cm thick DPC
(1:2:4) with water
proofing compound
Long Wall 2 7 0.4 - 5.6
Short Wall 3 3.9 0.4 - 4.68
10.28
Sq.m
5
1st class brick work in
cement mortar
superstructure
Long Wall 2 6.9 0.3 3.5 14.49
Short Wall 3 4.0 0.3 3.5 12.6 .
27.09 Cu.m
Deduction for Doors and
Windows
D1 2 1.2 0.3 2.1 1.512
W1 2 1.2 0.3 1.2 0.864
-2.376 Cu.m
Deduction for Lintels
above doors and windows
with 15 cm bearing at
each end (20 cm thick)
D1 2 1.5 0.3 0.2 0.18
W1 2 1.5 0.3 0.2 0.18
-0.36 Cu.m
Net Quantity of 1st class brick work in
cement mortar superstructure
24.354 Cu.m
Thank you
Any Question???
Exercise-3:
Estimate the quantities of following items of a two roomed building given in Fig.
a. Earthwork in excavation in foundation trench
b. Lime concrete in foundation
c. First class brick work in 1:6 cement mortar in foundation and plinth
d. 2.5 cm thick DPC (1:2:4) with water proofing compound
e. 1st class brick work in cement mortar superstructure
The dimensions of doors, windows and selves are
Door D = 1.20 m ร— 2.10 m.
Windows W = 1.00 m ร— 1.50 m
Shelves S = 1.00 m ร— 1.50 m
4.20
0.6
0.2
0.2
0.2
0.2
0.2
0.3
30
40
50
60
70
80
L.c.c
1.10
P.L
G.L
1.1 m

More Related Content

What's hot

Concrete technology
Concrete technologyConcrete technology
Concrete technologyKartikeya Pandey
ย 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structuresAishwarya Deopujari
ย 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildingsSimarpreet Singh
ย 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall kamariya keyur
ย 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
ย 
5 major-causes-for-damage
5 major-causes-for-damage5 major-causes-for-damage
5 major-causes-for-damageVijaya Lakshmi
ย 
Composite masonry
Composite masonryComposite masonry
Composite masonryRimpi Baro
ย 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
ย 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure constructionmohdasrimohdhasim
ย 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of buildingKrishnagnr
ย 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of ratesSimarpreet Singh
ย 
Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC) Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC) Simran Aggarwal
ย 
Pre-stressed Concrete
Pre-stressed ConcretePre-stressed Concrete
Pre-stressed ConcreteKatrina Mabini
ย 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
ย 

What's hot (20)

Concrete technology
Concrete technologyConcrete technology
Concrete technology
ย 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
ย 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
ย 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
ย 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
ย 
5 major-causes-for-damage
5 major-causes-for-damage5 major-causes-for-damage
5 major-causes-for-damage
ย 
Composite masonry
Composite masonryComposite masonry
Composite masonry
ย 
Stone as a building material.
Stone as a building material.Stone as a building material.
Stone as a building material.
ย 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
ย 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
ย 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
ย 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
ย 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
ย 
Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC) Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC)
ย 
Building materials
Building materialsBuilding materials
Building materials
ย 
Long wall and short wall method 4
Long wall and short wall method 4Long wall and short wall method 4
Long wall and short wall method 4
ย 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
ย 
Pre-stressed Concrete
Pre-stressed ConcretePre-stressed Concrete
Pre-stressed Concrete
ย 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
ย 
Steel structures
Steel structuresSteel structures
Steel structures
ย 

Similar to E.C.V detail estimate By centre line and Long wall short wall method

1. UNIT -I ESTIMATION OF BUILDINGS.pdf
1. UNIT -I ESTIMATION OF BUILDINGS.pdf1. UNIT -I ESTIMATION OF BUILDINGS.pdf
1. UNIT -I ESTIMATION OF BUILDINGS.pdfAnuPriya323
ย 
Long wall and short wall method 2
Long wall and short wall method 2Long wall and short wall method 2
Long wall and short wall method 2Saiyyed Akbar
ย 
270 .pdf
270 .pdf270 .pdf
270 .pdfOptional3
ย 
EC Unit 002 new (1).pdf
EC  Unit 002 new (1).pdfEC  Unit 002 new (1).pdf
EC Unit 002 new (1).pdfmohsin mohammad
ย 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfAvin Kharel
ย 
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Nafisa Nazneen Choudhury
ย 
estimation of structure
estimation of structureestimation of structure
estimation of structurekamariya keyur
ย 
Structural Analysis of SIRI House
Structural Analysis of SIRI HouseStructural Analysis of SIRI House
Structural Analysis of SIRI HouseCarmen Chan
ย 
Building Structure Project 2 Group report
Building Structure Project 2 Group reportBuilding Structure Project 2 Group report
Building Structure Project 2 Group reportsuzzanekan
ย 
Mmup questionnaire 7
Mmup questionnaire 7Mmup questionnaire 7
Mmup questionnaire 7Omar Selim
ย 
Beam and Column Analysis | Group Component
Beam and Column Analysis | Group ComponentBeam and Column Analysis | Group Component
Beam and Column Analysis | Group ComponentJoyce Wee
ย 
civil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasancivil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasanEngr Mirza S Hasan
ย 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a BuildingARAVINDBORRA1
ย 
Building Structures Report (Group and Individual)
Building Structures Report (Group and Individual)Building Structures Report (Group and Individual)
Building Structures Report (Group and Individual)Patch Yuen
ย 
45010341 planning-estimate
45010341 planning-estimate45010341 planning-estimate
45010341 planning-estimateimaduddin91
ย 
C21 21.1
C21 21.1C21 21.1
C21 21.1BGEsp1
ย 

Similar to E.C.V detail estimate By centre line and Long wall short wall method (20)

1. UNIT -I ESTIMATION OF BUILDINGS.pdf
1. UNIT -I ESTIMATION OF BUILDINGS.pdf1. UNIT -I ESTIMATION OF BUILDINGS.pdf
1. UNIT -I ESTIMATION OF BUILDINGS.pdf
ย 
Long wall and short wall method 5
Long wall and short wall method 5Long wall and short wall method 5
Long wall and short wall method 5
ย 
Long wall and short wall method 3
Long wall and short wall method 3Long wall and short wall method 3
Long wall and short wall method 3
ย 
Long wall and short wall method 2
Long wall and short wall method 2Long wall and short wall method 2
Long wall and short wall method 2
ย 
270 .pdf
270 .pdf270 .pdf
270 .pdf
ย 
EC Unit 002 new (1).pdf
EC  Unit 002 new (1).pdfEC  Unit 002 new (1).pdf
EC Unit 002 new (1).pdf
ย 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
ย 
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
ย 
estimation of structure
estimation of structureestimation of structure
estimation of structure
ย 
Center line method 1
Center line method 1Center line method 1
Center line method 1
ย 
tpp3k
tpp3ktpp3k
tpp3k
ย 
Structural Analysis of SIRI House
Structural Analysis of SIRI HouseStructural Analysis of SIRI House
Structural Analysis of SIRI House
ย 
Building Structure Project 2 Group report
Building Structure Project 2 Group reportBuilding Structure Project 2 Group report
Building Structure Project 2 Group report
ย 
Mmup questionnaire 7
Mmup questionnaire 7Mmup questionnaire 7
Mmup questionnaire 7
ย 
Beam and Column Analysis | Group Component
Beam and Column Analysis | Group ComponentBeam and Column Analysis | Group Component
Beam and Column Analysis | Group Component
ย 
civil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasancivil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasan
ย 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
ย 
Building Structures Report (Group and Individual)
Building Structures Report (Group and Individual)Building Structures Report (Group and Individual)
Building Structures Report (Group and Individual)
ย 
45010341 planning-estimate
45010341 planning-estimate45010341 planning-estimate
45010341 planning-estimate
ย 
C21 21.1
C21 21.1C21 21.1
C21 21.1
ย 

Recently uploaded

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
ย 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
ย 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
ย 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
ย 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
ย 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
ย 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
ย 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
ย 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
ย 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
ย 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
ย 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
ย 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
ย 
Model Call Girl in Narela Delhi reach out to us at ๐Ÿ”8264348440๐Ÿ”
Model Call Girl in Narela Delhi reach out to us at ๐Ÿ”8264348440๐Ÿ”Model Call Girl in Narela Delhi reach out to us at ๐Ÿ”8264348440๐Ÿ”
Model Call Girl in Narela Delhi reach out to us at ๐Ÿ”8264348440๐Ÿ”soniya singh
ย 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxnull - The Open Security Community
ย 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
ย 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
ย 

Recently uploaded (20)

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
ย 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
ย 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
ย 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
ย 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
ย 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
ย 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
ย 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
ย 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
ย 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
ย 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
ย 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
ย 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
ย 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
ย 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
ย 
Model Call Girl in Narela Delhi reach out to us at ๐Ÿ”8264348440๐Ÿ”
Model Call Girl in Narela Delhi reach out to us at ๐Ÿ”8264348440๐Ÿ”Model Call Girl in Narela Delhi reach out to us at ๐Ÿ”8264348440๐Ÿ”
Model Call Girl in Narela Delhi reach out to us at ๐Ÿ”8264348440๐Ÿ”
ย 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
ย 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
ย 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
ย 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
ย 

E.C.V detail estimate By centre line and Long wall short wall method

  • 1. Estimating Costing and Valuation Diploma โ€“Vth Semester Topic: Detail Estimate (centre line and long wall short wall method) Subject Code:3350604 Prepared by: Y A .Challawala Civil Engineering Department Government Polytechnic Dahod
  • 2. Exercise-2 Estimate the quantities of following items of a two roomed building given in Fig. a. Earthwork in excavation in foundation trench b. Lime concrete in foundation c. First class brick work in 1:6 cement mortar in foundation and plinth d. 2.5 cm thick DPC (1:2:4) with water proofing compound e. 1st class brick work in cement mortar superstructure Using (a) Centre line method (b) Long wall short wall method D1=1.2 x 2.1 m W1=1.2 x 1.2m W1 W1D1 D1
  • 3. (a) Centre line Method Using the above image, we can first find the total length of Centre line. Centre to Centre length of wall A = 6.3+ (1/2ร—0.30) + (1/2 x 0.30) = 6.60 m Centre to Centre length of wall B = 4+ (1/2 x 0.30) + (1/2ร—0.30) = 4.30 m Total length of Centre line = 6.6 +6.6 +4.3+ 4.3+4.3=26.1m Net Centre Line = Total centre line โ€“ 1/2 ( no of junction x width of junction) After finding out the total length of centre line, now find the quantity of the various items which are used in construction. W1 W1 D1 D1
  • 4. a. Earthwork in excavation in foundation trench Net Centre Line = Total centre line โ€“ 1/2 ( no of junction x width of junction) = 26.1-1 /2 (2 x 0.9 ) =25.2 Total quantity of earth work = L x B x H m3 = 25.2 m x 0.9 x 0.9 Total quantity =20.412 m3 b. Lime concrete in foundation: Net Centre Line = 26.1-1 /2 (2 x 0.9 ) =25.2m Total quantity of earth work = L x B x H m3 = 25.2 x 0.9 x 0.3 Total quantity =6.804 m3
  • 5. c. First class brick work in 1:6 cement mortar in foundation and plinth Net Centre Line = Total centre line โ€“ 1/2 ( no of junction x width of junction) Net Centre Line (60 cm Layer) =26.1-1 /2 (2 x 0.6 ) =25.5m Net Centre Line (50 cm Layer) =26.1-1 /2 (2 x 0.5 ) =25.6m Net Centre Line (40 cm Layer) =26.1-1 /2 (2 x 0.4 ) =25.7m Brick work for (60 cm Layer)= 25.5 x 0.6 x 0.3 = 4.59m3 Brick work for (50 cm Layer)= 25.6 x 0.5 x 0.3 = 3.84m3 Brick work for (40 cm Layer)= 25.7 x 0.4 x 0.57 = 5.911 m3 Total Quantity = 14.341 m3
  • 6. d. 2.5 cm thick DPC (1:2:4) with water proofing compound Net Centre Line (40 cm Layer) =26.1-1 /2 (2 x 0.4 ) =25.7m Total quantity of D.P.C work= L x B m2 = 25.7 x 0.4 Total quantity =10.28 m3 e. 1st class brick work in cement mortar superstructure Net Centre Line (30 cm Layer) =26.1-1 /2 (2 x 0.3 ) =25.8m Total quantity of 1st class brick work work = L x B x H m3 = 25.8 x 0.3 x 3.5 Total quantity =27.09m3
  • 7. Sr. No. Description No . Leng th M. Brea dth M. Height M. Qty. Total Unit 1 Earthwork in excavation 1 25.2 0.9 0.9 21.141 20.412 Cu. m 2 Lime Concrete in Foundation 1 25.2 0.9 0.3 7.047 6.804 Cu. m. 3 Brickwork in foundation and Plinth (a) 60 cm layer 1 25.5 0.6 0.3 4.59 (b) 50 cm layer 1 25.6 0.5 0.3 3.84 (c) 40 cm layer 1 25.7 0.4 0.57 5.911 14.341 Cu. m Measurement Sheet
  • 8. Sr. No. Description No. Lengt h M. Bread th M. Height M. Qty. Total Unit 3 D.P.C 1 25.7 0.4 -- 10.44 10.28 Sq.m 4 1st class brick work in cement mortar superstructure 1 25.8 0.3 3.5 27.405 27.09 Cu. m. Deduction for Doors and Windows D1 2 1.2 0.3 2.1 1.512 W1 2 1.2 0.3 1.2 0.864 -2.376 Cu.m Deduction for Lintels above doors and windows with 15 cm bearing at each end (20 cm thick) D1 2 1.5 0.3 0.2 0.18 W1 2 1.5 0.3 0.2 0.18 -0.36 Cu.m Net Quantity of 1st class brick work in cement mortar superstructure 24.354 Cu.m
  • 9. (b) Long wall short wall method Using the above image, we can first find the length of long wall and short wall. Centre to Centre length of long wall = 5+ (1/2ร—0.30) + (1/2 x 0.30) = 6.60 m Centre to Centre length of short wall = 4+ (1/2 x 0.30) + (1/2ร—0.30) = 4.30 m After finding out the length of the long wall and short wall, now find the quantity of the various items which are used in construction. Room-1 3 x 4 m Room-2 3 x 4 m D1 D1 W1 W1
  • 10. a. Earthwork in excavation in foundation trench Length of long wall = c/c length + width of earthwork = 6.6+ 0.9= 7.5m Length of short wall = c/c length -width of earthwork = 4.3 - 0.9= 3.4m Total quantity of earth work = L x B x H m3 Long wall = 2 x 7.5 x 0.9 x 0.9 =12.15m3 Short wall = 3 x 3.4 x 0.9 x 0.9 =8.262m3 Total =12.15 + 8.262=20.412 m3 Sr. No. Description No. Length M. Breadth M. Height M. Qty. Total 1 Earthwork in excavation Long Wall 2 7.5 0.9 0.9 12.15 Short Wall 3 3.4 0.9 0.9 8.262 20.412
  • 11. b. Lime concrete in foundation: Length of long wall = c/c length + width of concrete in foundation = 6.6 + 0.9= 7.5m Length of short wall = c/c length - width of concrete in foundation = 4.3 - 0.9= 3.4m Total quantity of earth work = L x B x H m3 Long wall = 2 x 7.5 x 0.9 x 0.3 = 4.05m3 Short wall = 3 x 3.4 x 0.9 x 0.3 = 2.754m3 Total =4.05 + 2.754=6.804m3 Sr. No. Description No. Length M. Breadth M. Height M. Qty. Total 2 Lime Concrete in Foundation Long Wall 2 7.5 0.9 0.3 4.05 Short Wall 3 3.4 0.9 0.3 2.754 6.804
  • 12. c. First class brick work in 1:6 cement mortar in foundation and plinth Length of long wall (60 cm Layer)= c/c length + width of First class brick work = 6.6+ 0.6= 7.2m Length of short wall (60 cm Layer) = c/c length - width of First class brick work = 4.3 - 0.6= 3.7m Length of long wall (50 cm Layer)= c/c length + width of First class brick work = 6.6+ 0.5= 7.1m Length of short wall (50 cm Layer) = c/c length - width of First class brick work = 4.3 - 0.5= 3.8m Length of long wall (40 cm Layer)= c/c length + width of First class brick work = 6.6+ 0.4= 7.0m Length of short wall (40 cm Layer) = c/c length - width of First class brick work = 4.3 - 0.4= 3.9m Sr. No. Description No. Length M. Breadth M. Height M. Qty. Total Unit 3 Brickwork in foundation and plinth Long Wall 1st footing 60 cm 2 7.2 0.6 0.3 2.592 2nd footing 50 cm 2 7.1 0.5 0.3 2.13 2nd footing 40 cm 2 7 0.4 0.575 3.22 Short Wall 1st footing 60 cm 3 3.7 0.6 0.3 1.998 2nd footing 50 cm 3 3.8 0.5 0.3 1.71 2nd footing 40 cm 3 3.9 0.4 0.575 2.691 14.341 Cu.m.
  • 13. d. 2.5 cm thick DPC (1:2:4) with water proofing compound Length of long wall = c/c length + width of DPC = 6.6+ 0.4=7.0 m Length of short wall = c/c length + width of DPC = 4.3 โ€“ 0.4= 3.9m Total quantity of earth work = L x B m2 Long wall = 2 x7.0 x 0.4 =5.6m2 Short wall = 3 x 3.9 x 0.4 =4.68m2 Total =5.6 +4.68=10.28 m2 Sr. No. Description No . Leng th M. Brea dth M. Height M. Qty. Total Unit 4 2.5 cm thick DPC (1:2:4) with water proofing compound Long Wall 2 7.0 0.4 - 5.6 Short Wall 3 3.9 0.4 - 4.68 10.28 Sq.m
  • 14. e. 1st class brick work in cement mortar superstructure Length of long wall = c/c length + width of 1st class brick work = 6.6+ 0.3= 6.9m Length of short wall = c/c length - width of 1st class brick work = 4.3 โ€“ 0.3= 4.0m Total quantity of earth work = L x B x H m3 Long wall = 2 x6.9 x 0.3 x3.5=14.59m3 Short wall = 3 x 4.0 x 0.3 x 3.5=12.6m3 Total =14.59+12.6=27.09 m3 Sr. No. Description No. Lengt h M. Bread th M. Height M. Qty. Total Unit 5 1st class brick work in cement mortar superstructure Long Wall 2 6.9 0.3 3.5 14.59 Short Wall 3 4.0 0.3 3.5 12.6 . 27.09 Cu.m
  • 15. Sr. No. Description No . Len gth M. Bre adth M. Height M. Qty. Total Unit 1 Earthwork in excavation Long Wall 2 7.5 0.9 0.9 12.15 Short Wall 3 3.4 0.9 0.9 8.262 20.412 Cu.m 2 Lime Concrete in Foundation Long Wall 2 7.5 0.9 0.3 4.05 Short Wall 3 3.4 0.9 0.3 2.754 6.804 Cu.m. (b) Long wall short wall method
  • 16. Sr. No. Description No . Leng th M. Brea dth M. Heigh t M. Qty. Total Unit 3 Brickwork in foundation and plinth Long Wall 1st footing 60 cm 2 7.2 0.6 0.3 2.592 2nd footing 50 cm 2 7.1 0.5 0.3 2.13 2nd footing 40 cm 2 7 0.4 0.575 3.22 Short Wall 1st footing 60 cm 3 3.7 0.6 0.3 1.998 2nd footing 50 cm 3 3.8 0.5 0.3 1.71 2nd footing 40 cm 3 3.9 0.4 0.575 2.691 14.341 Cu. m.
  • 17. Sr. No. Description No . Leng th M. Brea dth M. Height M. Qty. Total Unit 4 2.5 cm thick DPC (1:2:4) with water proofing compound Long Wall 2 7 0.4 - 5.6 Short Wall 3 3.9 0.4 - 4.68 10.28 Sq.m
  • 18. 5 1st class brick work in cement mortar superstructure Long Wall 2 6.9 0.3 3.5 14.49 Short Wall 3 4.0 0.3 3.5 12.6 . 27.09 Cu.m Deduction for Doors and Windows D1 2 1.2 0.3 2.1 1.512 W1 2 1.2 0.3 1.2 0.864 -2.376 Cu.m Deduction for Lintels above doors and windows with 15 cm bearing at each end (20 cm thick) D1 2 1.5 0.3 0.2 0.18 W1 2 1.5 0.3 0.2 0.18 -0.36 Cu.m Net Quantity of 1st class brick work in cement mortar superstructure 24.354 Cu.m
  • 20. Exercise-3: Estimate the quantities of following items of a two roomed building given in Fig. a. Earthwork in excavation in foundation trench b. Lime concrete in foundation c. First class brick work in 1:6 cement mortar in foundation and plinth d. 2.5 cm thick DPC (1:2:4) with water proofing compound e. 1st class brick work in cement mortar superstructure The dimensions of doors, windows and selves are Door D = 1.20 m ร— 2.10 m. Windows W = 1.00 m ร— 1.50 m Shelves S = 1.00 m ร— 1.50 m 4.20 0.6 0.2 0.2 0.2 0.2 0.2 0.3 30 40 50 60 70 80 L.c.c 1.10 P.L G.L 1.1 m