Submit Search
Upload
Chapter12b.pdf
•
0 likes
•
4 views
W
WasiqAhmed4
Follow
underground methods for tunneling
Read less
Read more
Engineering
Report
Share
Report
Share
1 of 32
Download now
Download to read offline
Recommended
Detection of Abnormal Formation Pressures using Drilling Parameters
Detection of Abnormal Formation Pressures using Drilling Parameters
IRJET Journal
Ijciet 10 01_049
Ijciet 10 01_049
IAEME Publication
NACE_2009_MBX_Bristle_Blaster_-_Surface_Preparation
NACE_2009_MBX_Bristle_Blaster_-_Surface_Preparation
Tjiptadi Soerjono
"Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles"
Remedy Geotechnics Ltd
Di 00028
Di 00028
Dr. (Eng.) Nabil GHANNAY
Das b. m._,soil_mechanics_laboratory_manual,_6th_ed,_2002
Das b. m._,soil_mechanics_laboratory_manual,_6th_ed,_2002
Lawrence Omai
poster-Ash
poster-Ash
Ash Kumar
Field Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer Bit
IRJET Journal
Recommended
Detection of Abnormal Formation Pressures using Drilling Parameters
Detection of Abnormal Formation Pressures using Drilling Parameters
IRJET Journal
Ijciet 10 01_049
Ijciet 10 01_049
IAEME Publication
NACE_2009_MBX_Bristle_Blaster_-_Surface_Preparation
NACE_2009_MBX_Bristle_Blaster_-_Surface_Preparation
Tjiptadi Soerjono
"Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles"
Remedy Geotechnics Ltd
Di 00028
Di 00028
Dr. (Eng.) Nabil GHANNAY
Das b. m._,soil_mechanics_laboratory_manual,_6th_ed,_2002
Das b. m._,soil_mechanics_laboratory_manual,_6th_ed,_2002
Lawrence Omai
poster-Ash
poster-Ash
Ash Kumar
Field Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer Bit
IRJET Journal
Ijmet 10 02_028
Ijmet 10 02_028
IAEME Publication
Civil engineering lab tests pdf
Civil engineering lab tests pdf
Saqib Imran
BEND-TWIST COUPLING AND ITS EFFECT ON CAVITATION INCEPTION OF COMPOSITE MARIN...
BEND-TWIST COUPLING AND ITS EFFECT ON CAVITATION INCEPTION OF COMPOSITE MARIN...
IAEME Publication
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
IRJET Journal
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
ALI KIFAH KADHUM
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
IAEME Publication
Core plugging test
Core plugging test
Kamal Abdurahman
CFD analysis of bio-inspired corrugated airfoils
CFD analysis of bio-inspired corrugated airfoils
Pradeep Kannah Purushothaman
The Evaluation of Soil Liquefaction Potential using Shear Wave Velocity based...
The Evaluation of Soil Liquefaction Potential using Shear Wave Velocity based...
CSCJournals
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Audubon Engineering Company
Effects of shale volume distribution on the elastic properties of reserviors ...
Effects of shale volume distribution on the elastic properties of reserviors ...
DR. RICHMOND IDEOZU
1.0 Flyover 0+620.pdf
1.0 Flyover 0+620.pdf
ssuser471126
Numerical Investigation of Turbulent Flow over a Rotating Circular Cylinder u...
Numerical Investigation of Turbulent Flow over a Rotating Circular Cylinder u...
IJERA Editor
Comparison of Water Injection, Gas Injection, and Water Alternating Gas Injec...
Comparison of Water Injection, Gas Injection, and Water Alternating Gas Injec...
IRJET Journal
Report work on retaining wall
Report work on retaining wall
vikas Meena
Evaluation of Safe Bearing Capacity by Using Statical Analysis
Evaluation of Safe Bearing Capacity by Using Statical Analysis
ijtsrd
Thesis Powerpoint
Thesis Powerpoint
neha47
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
Leo Youngman
Numerical Analysis of Lift & Drag Performance of NACA0012 Wind Turbine Aerofoil
Numerical Analysis of Lift & Drag Performance of NACA0012 Wind Turbine Aerofoil
IRJET Journal
Geological site investigation for Civil Engineering Foundations
Geological site investigation for Civil Engineering Foundations
Dr.Anil Deshpande
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
Karpagam Institute of Teechnology
Online book store management system project.pdf
Online book store management system project.pdf
Kamal Acharya
More Related Content
Similar to Chapter12b.pdf
Ijmet 10 02_028
Ijmet 10 02_028
IAEME Publication
Civil engineering lab tests pdf
Civil engineering lab tests pdf
Saqib Imran
BEND-TWIST COUPLING AND ITS EFFECT ON CAVITATION INCEPTION OF COMPOSITE MARIN...
BEND-TWIST COUPLING AND ITS EFFECT ON CAVITATION INCEPTION OF COMPOSITE MARIN...
IAEME Publication
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
IRJET Journal
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
ALI KIFAH KADHUM
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
IAEME Publication
Core plugging test
Core plugging test
Kamal Abdurahman
CFD analysis of bio-inspired corrugated airfoils
CFD analysis of bio-inspired corrugated airfoils
Pradeep Kannah Purushothaman
The Evaluation of Soil Liquefaction Potential using Shear Wave Velocity based...
The Evaluation of Soil Liquefaction Potential using Shear Wave Velocity based...
CSCJournals
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Audubon Engineering Company
Effects of shale volume distribution on the elastic properties of reserviors ...
Effects of shale volume distribution on the elastic properties of reserviors ...
DR. RICHMOND IDEOZU
1.0 Flyover 0+620.pdf
1.0 Flyover 0+620.pdf
ssuser471126
Numerical Investigation of Turbulent Flow over a Rotating Circular Cylinder u...
Numerical Investigation of Turbulent Flow over a Rotating Circular Cylinder u...
IJERA Editor
Comparison of Water Injection, Gas Injection, and Water Alternating Gas Injec...
Comparison of Water Injection, Gas Injection, and Water Alternating Gas Injec...
IRJET Journal
Report work on retaining wall
Report work on retaining wall
vikas Meena
Evaluation of Safe Bearing Capacity by Using Statical Analysis
Evaluation of Safe Bearing Capacity by Using Statical Analysis
ijtsrd
Thesis Powerpoint
Thesis Powerpoint
neha47
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
Leo Youngman
Numerical Analysis of Lift & Drag Performance of NACA0012 Wind Turbine Aerofoil
Numerical Analysis of Lift & Drag Performance of NACA0012 Wind Turbine Aerofoil
IRJET Journal
Geological site investigation for Civil Engineering Foundations
Geological site investigation for Civil Engineering Foundations
Dr.Anil Deshpande
Similar to Chapter12b.pdf
(20)
Ijmet 10 02_028
Ijmet 10 02_028
Civil engineering lab tests pdf
Civil engineering lab tests pdf
BEND-TWIST COUPLING AND ITS EFFECT ON CAVITATION INCEPTION OF COMPOSITE MARIN...
BEND-TWIST COUPLING AND ITS EFFECT ON CAVITATION INCEPTION OF COMPOSITE MARIN...
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
STRENGTH OF REINFORCED CONCRETE CORBELS – A PARAMETRIC STUDY
Core plugging test
Core plugging test
CFD analysis of bio-inspired corrugated airfoils
CFD analysis of bio-inspired corrugated airfoils
The Evaluation of Soil Liquefaction Potential using Shear Wave Velocity based...
The Evaluation of Soil Liquefaction Potential using Shear Wave Velocity based...
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Effects of shale volume distribution on the elastic properties of reserviors ...
Effects of shale volume distribution on the elastic properties of reserviors ...
1.0 Flyover 0+620.pdf
1.0 Flyover 0+620.pdf
Numerical Investigation of Turbulent Flow over a Rotating Circular Cylinder u...
Numerical Investigation of Turbulent Flow over a Rotating Circular Cylinder u...
Comparison of Water Injection, Gas Injection, and Water Alternating Gas Injec...
Comparison of Water Injection, Gas Injection, and Water Alternating Gas Injec...
Report work on retaining wall
Report work on retaining wall
Evaluation of Safe Bearing Capacity by Using Statical Analysis
Evaluation of Safe Bearing Capacity by Using Statical Analysis
Thesis Powerpoint
Thesis Powerpoint
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
Numerical Analysis of Lift & Drag Performance of NACA0012 Wind Turbine Aerofoil
Numerical Analysis of Lift & Drag Performance of NACA0012 Wind Turbine Aerofoil
Geological site investigation for Civil Engineering Foundations
Geological site investigation for Civil Engineering Foundations
Recently uploaded
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
Karpagam Institute of Teechnology
Online book store management system project.pdf
Online book store management system project.pdf
Kamal Acharya
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
RashidFaridChishti
Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptx
alijaker017
Electrical shop management system project report.pdf
Electrical shop management system project report.pdf
Kamal Acharya
Insurance management system project report.pdf
Insurance management system project report.pdf
Kamal Acharya
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
archanaece3
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Dr.Costas Sachpazis
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
T.D. Shashikala
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
Morshed Ahmed Rahath
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Prakhyath Rai
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
EMMANUELLEFRANCEHELI
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Er.Sonali Nasikkar
Geometric constructions Engineering Drawing.pdf
Geometric constructions Engineering Drawing.pdf
JNTUA
Supermarket billing system project report..pdf
Supermarket billing system project report..pdf
Kamal Acharya
Circuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineering
KanchhaTamang
BURGER ORDERING SYSYTEM PROJECT REPORT..pdf
BURGER ORDERING SYSYTEM PROJECT REPORT..pdf
Kamal Acharya
Piping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdf
AshrafRagab14
Intelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent Acts
Sheetal Jain
"United Nations Park" Site Visit Report.
"United Nations Park" Site Visit Report.
MdManikurRahman
Recently uploaded
(20)
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
Online book store management system project.pdf
Online book store management system project.pdf
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptx
Electrical shop management system project report.pdf
Electrical shop management system project report.pdf
Insurance management system project report.pdf
Insurance management system project report.pdf
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Geometric constructions Engineering Drawing.pdf
Geometric constructions Engineering Drawing.pdf
Supermarket billing system project report..pdf
Supermarket billing system project report..pdf
Circuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineering
BURGER ORDERING SYSYTEM PROJECT REPORT..pdf
BURGER ORDERING SYSYTEM PROJECT REPORT..pdf
Piping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdf
Intelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent Acts
"United Nations Park" Site Visit Report.
"United Nations Park" Site Visit Report.
Chapter12b.pdf
1.
1 • A. J.
Clark School of Engineering •Department of Civil and Environmental Engineering Sixth Edition CHAPTER 12b Construction Planning, Equipment, and Methods DRILLING ROCK AND EARTH DRILLING ROCK AND EARTH By By Dr. Ibrahim Assakkaf Dr. Ibrahim Assakkaf ENCE ENCE 420 420 – – Construction Equipment and Methods Construction Equipment and Methods Spring 2003 Spring 2003 Department of Civil and Environmental Engineering Department of Civil and Environmental Engineering University of Maryland, College Park University of Maryland, College Park CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 73 SELECTING THE DRILLING SELECTING THE DRILLING METHOD AND EQUIPMENT METHOD AND EQUIPMENT The drilling pattern should be The drilling pattern should be planned to produce rock sizes that planned to produce rock sizes that are small enough to permit most of are small enough to permit most of them to be handled by the them to be handled by the excavator, such as a loader or excavator, such as a loader or shovel, or to pass into the crusher shovel, or to pass into the crusher opening without secondary opening without secondary blasting. blasting.
2.
2 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 74 DRILLING JOB ANALYSIS DRILLING JOB ANALYSIS In analyzing a job for drilling and In analyzing a job for drilling and blasting operations, there are four blasting operations, there are four factors factors to be considered: to be considered: 1.The cubic yards of rock per linear foot of hole. 2.The number of pounds of explosive per cubic yard of rock. 3.The number of pounds of explosive per linear foot of hole. 4.Will the resulting breakage meet the job requirements? CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 75 DRILLING JOB ANALYSIS DRILLING JOB ANALYSIS Note Note:The value of each of the :The value of each of the first three factors first three factors may be estimated in advance of drilling may be estimated in advance of drilling and blasting operations and blasting operations, but after , but after experimental drilling operations are experimental drilling operations are conducted, it probably will be desirable to conducted, it probably will be desirable to modify the values to give better results. modify the values to give better results. The The fourth factor is more subjective, but the fourth factor is more subjective, but the relationship between hole size and spacing relationship between hole size and spacing gives some indication of expected results. gives some indication of expected results.
3.
3 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 76 The relationships between the first The relationships between the first three factors are illustrated in Table 1. three factors are illustrated in Table 1. The volumes of rock per linear foot of The volumes of rock per linear foot of hole are based on the net depth of hole are based on the net depth of holes and do not include sub holes and do not include sub- -drilling, drilling, which usually will be necessary. which usually will be necessary. The pounds of explosive per linear foot The pounds of explosive per linear foot of hole are based on filling the holes of hole are based on filling the holes completely with 60% dynamite. completely with 60% dynamite. DRILLING JOB ANALYSIS DRILLING JOB ANALYSIS CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 77 Table 1 (Table 12-4, Text) Drilling and Blasting Data
4.
4 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 78 The pounds of explosive per cubic The pounds of explosive per cubic yard of rock are based on filling yard of rock are based on filling each hole to 100, 75, and 50% of each hole to 100, 75, and 50% of its total capacity with dynamite. its total capacity with dynamite. When a hole is not filled When a hole is not filled completely with dynamite, the completely with dynamite, the surplus volume is filled with surplus volume is filled with stemming. stemming. DRILLING JOB ANALYSIS DRILLING JOB ANALYSIS CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 79 RATES OF DRILLING ROCK RATES OF DRILLING ROCK The rates of drilling rock will vary with The rates of drilling rock will vary with a number of a number of factors factors such as: such as: 9The type of drill and bit size, 9Hardness of the rock, 9Depth of holes, 9Drilling pattern, 9Terrain, and 9Time lost waiting for other operations.
5.
5 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 80 RATES OF DRILLING ROCK RATES OF DRILLING ROCK If pneumatic drills are used, the If pneumatic drills are used, the rate of rate of drilling will vary with the pressure of drilling will vary with the pressure of the air. the air. The portion of time that a drill is The portion of time that a drill is operative is defined as the operative is defined as the availability availability factor factor, , which is usually expressed as which is usually expressed as a percent of the total time that the drill a percent of the total time that the drill is expected to be working. is expected to be working. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 81 Historical drill penetration rates based Historical drill penetration rates based on very general rock on very general rock- -type type classification is shown in Table 2 classification is shown in Table 2 (Table 12 (Table 12- -5, Text) 5, Text) These rates should be used as a These rates should be used as a guide guide Actual project estimates need to be Actual project estimates need to be based on drilling tests of specified based on drilling tests of specified rock which will be encountered. rock which will be encountered. RATES OF DRILLING ROCK RATES OF DRILLING ROCK
6.
6 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 82 Table 2. Drilling Production Rates (Table 12-5, Text) RATES OF DRILLING ROCK RATES OF DRILLING ROCK CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 83 RATES OF DRILLING ROCK RATES OF DRILLING ROCK Drill bits, rods, and couplings are Drill bits, rods, and couplings are high wear items, and the time high wear items, and the time required to replace or change each required to replace or change each affects the drilling production. affects the drilling production. Table 3 (Table12 Table 3 (Table12- -6, Text) gives the 6, Text) gives the average life of these high wear items average life of these high wear items based on the drill footage and the based on the drill footage and the type of rock. type of rock.
7.
7 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 84 RATES OF DRILLING ROCK RATES OF DRILLING ROCK Table 3 (Table 12-6b, Text) CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 85 OPTIMUM AIR PRESSURE OPTIMUM AIR PRESSURE FOR DRILLING FOR DRILLING Figure 1 (Fig 11 Figure 1 (Fig 11- -15 Text) shows 15 Text) shows the relationship between the the relationship between the average rate of penetration and average rate of penetration and the operating pressure for each the operating pressure for each group of drills. group of drills. Figure 2 (Fig 11 Figure 2 (Fig 11- -16, Text) is a 16, Text) is a nomogram nomogram based on the based on the information appearing in Fig. 13 information appearing in Fig. 13- - 15 which indicates the percent 15 which indicates the percent increase in penetration resulting increase in penetration resulting from an increase in air pressure. from an increase in air pressure. Example: Example: If the pressure is increased from If the pressure is increased from 90 to 100 psi, the increase in 90 to 100 psi, the increase in penetration will be 38%. penetration will be 38%.
8.
8 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 86 ECONOMY OF INCREASING ECONOMY OF INCREASING AIR PRESSURE AIR PRESSURE The decision to increase the air pressure at the The decision to increase the air pressure at the drills should not be determined solely on the basis drills should not be determined solely on the basis of the anticipated increase in production and the of the anticipated increase in production and the increase in the cost of compressed air and drilling increase in the cost of compressed air and drilling equipment. equipment. Drilling is only one item in a chain of operations, Drilling is only one item in a chain of operations, which includes drilling, blasting, loading, and which includes drilling, blasting, loading, and hauling. hauling. Figure 3 presents a curve that establishes the Figure 3 presents a curve that establishes the lowest total cost of producing the end product of a lowest total cost of producing the end product of a drilling operation. The curve is plotted to indicate drilling operation. The curve is plotted to indicate this cost for varying air pressures. this cost for varying air pressures. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 87 ECONOMY OF INCREASING ECONOMY OF INCREASING AIR PRESSURE AIR PRESSURE
9.
9 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 88 DRILLING PRODUCTION DRILLING PRODUCTION ESTIMATE ESTIMATE To begin a drilling production estimate it is first necessary to make an assumption about the type of equipment that will be used. Tables 12-5 & 12-6 provide information to guide that first decision. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 89 The final equipment decision should only be made after test drilling the formation. Test drilling should help to quantify: • Penetration rate • Drilling method • Bit size / Bit type PRODUCTION ESTIMATE PRODUCTION ESTIMATE
10.
10 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 90 Penetration Rate is a function of: • The rock • The drilling method • The size & type of bit PENETRATION RATE PENETRATION RATE CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 91 The rock properties which effect penetration rate are: • Hardness • Texture • Breaking characteristic • Formation THE ROCK THE ROCK
11.
11 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 92 HARDNESS HARDNESS Hardness is the resistance of a smooth surface to abrasion. It is measured by the MOH scale (Friedrich Mohs). CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 93 Hardness is measured by the MOH scale. The scale is from 1 to 10, with • Diamond rated as 10 • Talc rated as 1 HARDNESS HARDNESS
12.
12 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 94 HARDNESS HARDNESS Scratch Test Diamond 10.0 Schist 5.0 Knife Granite 4.0 Knife Limestone 3.0 Copper coin Potash 2.0 Fingernail Gypsum 1.5 Fingernail CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 95 HARDNESS HARDNESS Hardness affects drilling speed. HARDNESS DRILLING SPEED 1-2 FAST 3-4 FAST - MEDIUM 5 MEDIUM 6-7 SLOW - MEDIUM 8-9 SLOW
13.
13 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 96 TEXTURE TEXTURE Texture is the grain structure of the rock. • A loose grained structure (porous, cavities) drills fast. • Grains large enough to be seen individually (granite) will drill medium. • Fine-grained rocks drill slow. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 97 BREAKING BREAKING CHARACTERISTIC CHARACTERISTIC Describes how the rock breaks when struck.
14.
14 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 98 • • Shatters - into small pieces from a light blow • Brittle - breaks easily with a light blow • Shaving - when shaved off in pieces they break easily • Strong - resists breaking when hit hard • Malleable - flattens instead of breaking BREAKING BREAKING CHARACTERISTIC CHARACTERISTIC CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 99 BREAKING BREAKING CHARACTERISTIC CHARACTERISTIC • Shatters - drills fast • Brittle - drills fast to medium • Shaving - drills medium • Strong - drills slow to medium • Malleable - drills slow
15.
15 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 100 DRILLING METHOD DRILLING METHOD ROTARY- PERCUSSION The piston provides striking energy to the rock through the drill steel. There is rotation so the bit strikes fresh rock with each blow. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 101 Text, FIG. 12-10, 11 & 12 Drill steel ROTARY ROTARY PERCUSSION PERCUSSION
16.
16 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 102 PERCUSSION DRILLING PERCUSSION DRILLING Hardness Quartzite 7.0 Trap Rock 6.0 Schist 5.0 Granite 4.0 Dolomite 3.5 Limestone 3.0 Galena 2.5 CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 103 ESTIMATING DRILLING ESTIMATING DRILLING PRODUCTION PRODUCTION The first step in estimating The first step in estimating drilling production is to make an drilling production is to make an assumption about the type of assumption about the type of equipment which will be used. equipment which will be used. That first assumption will be That first assumption will be guided by the type of rock to be guided by the type of rock to be drilled. drilled.
17.
17 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 104 ESTIMATING DRILLING ESTIMATING DRILLING PRODUCTION PRODUCTION Both Tables 2 and 3 give Both Tables 2 and 3 give information that is useful in making information that is useful in making such a decision. such a decision. Once a drill type and bit is selected, Once a drill type and bit is selected, the format given in the following the format given in the following figure (Figure 4) can be used to figure (Figure 4) can be used to estimate the hourly production. estimate the hourly production. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 105 ESTIMATING DRILLING ESTIMATING DRILLING PRODUCTION PRODUCTION It must again be emphasized, the It must again be emphasized, the final decision on the type of final decision on the type of equipment should only be made equipment should only be made after test drilling the specific after test drilling the specific formation. formation. The drilling test should yield data The drilling test should yield data on the penetration rate based on bit on the penetration rate based on bit size and type. size and type.
18.
18 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 106 ESTIMATING DRILLING ESTIMATING DRILLING PRODUCTION PRODUCTION Figure 4. Format for Estimating Drilling Production CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 107 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (1) Depth of Hole: (1) Depth of Hole: Usually, when drilling for loading explosives and blasting, it is necessary to subdrill below the desired final bottom or floor elevation. This extra depth is dependent on the blasting design. Normally, 2 or 3 ft of extra depth is required. Therefore, if the depth to the finish grade is 25 ft (pull depth), it may be necessary to actually drill 28 ft ft 3 or 2 Pull (ft) Drill + =
19.
19 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 108 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (2) Penetration Rate: (2) Penetration Rate: The penetration rate will be an average rate developed from test drilling program based on specific bit size and type If no information given for a particular drill, Table 2 (Table 13 - 5 ) can be used for estimating the penetration rate Example: If a 41/2 - d rill is used @ 250 psi to penetrate dolomite, the penetration rate in minutes will be min ft 83 . 1 60 110 Rate n Penetratio = = CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 109 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION Table 2. Drilling Production Rates (Table 12-5, Text)
20.
20 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 110 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (3) Drilling Time: (3) Drilling Time: The drilling time shall be calculated from (4) Change Steel: (4) Change Steel: If drilling depth is greater than the steel length, it will be necessary to add steel during the drilling and to remove steel when coming out of the hole. For track-mounted rotary-percussion drills, standard steel lengths are 10 or 12 ft. They require about 0.5 min or less to add or remove a length. Rate n Penetratio Drill Time Drilling = CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 111 Text p. 359 STEP 4 STEP 4 CHANGE CHANGE STEEL STEEL Steel
21.
21 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 112 STEP 4 STEP 4 CHANGE STEEL CHANGE STEEL Shank (Striking Bar) Bit Coupling Steel CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 113 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (4) Change Steel (Cont’d): (4) Change Steel (Cont’d): It is recommended by the author to use 1.1 min to add 20-ft length of steel, and 1.5 min to remove the same length of steel NOTE: if the steel length is less than 20 ft, the time required to change steel can be taken as 0 min, unless otherwise specified.
22.
22 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 114 STEP 4 CHANGE STEEL STEP 4 CHANGE STEEL Steel, approximate weights: SIZE INCHES LENGTH FEET WEIGHT POUNDS 1.5 10 53 1.5 12 64 1.75 10 60 1.75 12 71 CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 115 STEP 4 STEP 4 CHANGE CHANGE STEEL STEEL Steel
23.
23 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 116 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (5) Blow Hole: (5) Blow Hole: After the actual drilling is completed, it is good practice to blow out the hole to ensure that all cuttings are removed. Some drillers prefer to drill an extra foot and to pull the drill out without blowing the hole clean NOTE: It is customary to use 0.1 min for the blow hole time, unless otherwise specified for a particular site conditions and drill type. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 117 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (6) Move to Next Hole: (6) Move to Next Hole: The time required to move between drill hole locations is a function of the distance (blasting pattern) and the terrain. Track-mounted rotary-percussion drills have travel speeds of from 1 to 3 mph. However, because the hole spacing is often less than 20 ft and the operator is maneuvering to place the drill over an exact spot, the travel speed is so low A speed of 0.25 mph can be used.
24.
24 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 118 STEP 6 STEP 6 MOVE MOVE May have to lower the mast CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 119 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (6) Move to Next Hole (cont’d): (6) Move to Next Hole (cont’d): Example: If the blasting pattern is a 6 X 8 - ftgrid, then the time required (in minutes) to the next hole will be (7) Align Steel: (7) Align Steel: Once over the drilling location, the mast or steel must be aligned. In the case of rotary drills the entire machine is leveled by the use of hydraulic jacks. This usually takes about 0.5 to 1.0 min. min 36 . 0 5280 60 25 . 0 8 speed distance (min) required Time = = =
25.
25 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 120 STEP 6 STEP 6 MOVE TO NEXT HOLE MOVE TO NEXT HOLE If drilling for blasting operations distance will be set by the blasting pattern. An 8 X 10 pattern means 8 ft between rows and a 10 ft spacing between holes. Therefore, the travel distance moving along the row is 10 ft. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 121 STEP 7 ALIGN STEP 7 ALIGN STEEL STEEL Time to align is discussed on page 360. Outrigger for leveling
26.
26 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 122 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (8) Change Bit: (8) Change Bit: A time allowance must be considered for changing bits, shanks, couplings, and steel. Table 3 (Table 13 - 6, Text) provides information for determining the frequency of such changes On the average, the normal time is about 4 min Unless otherwise specified. Example: A 6 1/2 - B downhole drill @ 350 psi to be used for drilling medium silica granite. What is the time required to change bit? Assume 23’ drill length. min 05 . 0 1800 23 4 (ft) life (ft) drill time normal (min) Time = × = × = CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 123 STEP 8 CHANGE BIT STEP 8 CHANGE BIT Bits, shanks, couplings and steel are all high wear items that must be replaced frequently.
27.
27 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 124 STEP 8 CHANGE BIT STEP 8 CHANGE BIT The time allowance for replacement is a factor of both the actual time to remove and replace, and the frequency of such changes. Table 12- 6 provides frequency information. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 125 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION Table 4 (Table 12-6a, Text)
28.
28 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 126 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (9) Total Time: (9) Total Time: (10) Operating Rate: (10) Operating Rate: (8) (7) (6) (5) (4) (3) TotalTime + + + + + = (min) Time Total (ft) Drill (ft/min) Rate Operating = CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 127 GUIDELINES FOR ESTIMATING GUIDELINES FOR ESTIMATING DRILLING PRODUCTION DRILLING PRODUCTION (11) Production Efficiency: (11) Production Efficiency: With experienced drillers working on a large project, a 50-min production hour should be achievable. Sometimes, a 40- min production hour might be more appropriate. (12) Hourly Production (12) Hourly Production Rate Operating Efficiency Production (ft/hr) Production Hourly × =
29.
29 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 128 Example 1 Example 1 A project utilizing experienced drillers will A project utilizing experienced drillers will require the drilling and blasting of high silica, require the drilling and blasting of high silica, fine fine- -grained sandstone rock. From field drilling grained sandstone rock. From field drilling tests it was determined that a direct drilling tests it was determined that a direct drilling rate of 120 ft per hour could be achieved with a rate of 120 ft per hour could be achieved with a 3 1/2 HD bit on a rotary percussion drill @ 100 3 1/2 HD bit on a rotary percussion drill @ 100 psi psi. The drills to be used take 10 . The drills to be used take 10- -ft steel. The ft steel. The blasting pattern will be a 10 X 10 blasting pattern will be a 10 X 10- -ft grid with 2 ft grid with 2 ft of sub ft of sub- -drilling required. On the average the drilling required. On the average the specified finish grade is 16 ft below the existing specified finish grade is 16 ft below the existing ground surface. Determine the drilling ground surface. Determine the drilling production. production. CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 129 Example 1 (cont’d) Example 1 (cont’d) Using the format of Figure 4: (1) Depth of hole (a) 16-ft pull (b) 18-ft drill (16 + 2) (2) Penetration 2.00 ft/min (120 ft ÷ 60) (3) Drilling Time: 9.00 min (18 ft ÷ 2 ft/min) (4) Change Steel: 0.00 min (d<20 ft) (5) Blow Hole: 0.10 min (6) Move to Next Hole 0.45 min (10 ft ÷ 0.25 mph) (7) Align Steel: 1.00 min (8) Change Bit: 0.08 min (4 X 18/850 ) (9) Total Time 10.63 min Note: 850 was obtained from Table 5
30.
30 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 130 Example 1 (cont’d) Example 1 (cont’d) Table 5 (Table 12-6c, Text) CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 131 Example 1 (cont’d) Example 1 (cont’d) (10) Operating Rate: 1.69 ft/min (18 ÷ 10.63) (11) Production Efficiency.: 50 min/hr (12) Hourly Production 84.5 ft/hr (50 × 1.55)
31.
31 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 132 Example 2 Example 2 The drilling production of Example 1 must The drilling production of Example 1 must match that of hauling and loading for the match that of hauling and loading for the project, which is 500 cu yd per hour. How project, which is 500 cu yd per hour. How many drill units will be required? many drill units will be required? required be will drills Two yd cu 500 yd cu 556 278 2 yd cu 278 hole / yd cu 59.26 drill per hr hole 4.69 drill per hr hole 69 . 4 ft/hole 18 ft/hr 5 . 84 yd/hole cu 26 . 59 27 16 10 10 Production Hole ∴ > = × = × = = × × = CHAPTER 12b. DRILLING ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 133 DRILLING EARTH DRILLING EARTH Purposes for drilling holes in earth Purposes for drilling holes in earth. . In the construction and mining industries In the construction and mining industries holes are drilled into the earth for many holes are drilled into the earth for many purposes, including, but not limited to: purposes, including, but not limited to: 1.Obtaining samples of soil for test purposes. 2.Locating and evaluating deposits of aggregate suitable for mining. 3.Locating and evaluating deposits of minerals. 4.Permitting the installation of cast- in - p lace piles or shafts to support structures.
32.
32 CHAPTER 12b. DRILLING
ROCK AND EARTH ENCE 420 ©Assakkaf Slide No. 134 DRILLING EARTH DRILLING EARTH 5. Enabling the driving of load-bearing piles into hard and tough formations. 6. Providing wells for supplies of water or for deep drainage purposes. 7. Providing shafts for ventilating mines, tunnels, and other underground facilities. 8. Providing horizontal holes through embankments, such as those for the installation of utility conduits.
Download now