5. Programming Weekly Tracker Sheet – Enabling Works for Al Jadaf Development
Statistics
Data Date: 4-July-13 Previous Update On: 27-Jun-13
Baseline Finish 21-Aug-13 Last update forecast finish 10-Nov-13
Rev. Contract Finish N/A This update forecast finish 16-Nov-13
Delay This Period (In Days): - Cumu. Delay (Contract): 77 days
Planned % Complete 71.3 % Last update Actual % Complete 20.08 %
This update Actual % Complete 23.6 %
Key Activity / Milestones Comparison (This Reporting Period)
Sr. No. Activity
Baseline This Update
Delay/Ahead Comments
Start Finish Start Finish*
1 Installation of fence and sign boards (S3) 2-March-13 20-March-13 14-March-13 On going
2
Obtain Approval from DEWA for shop drawing & material
submittal ( 11 Kv cable ) ( PLOT R1 & H3 ) 14-March-13 28-March-13 26-March-13 On going
3
Obtain Approval from DEWA for shop drawing &
material submittal (132 Kv ) 14-March-13 28-March-13 26-March-13 On going
4 Construction of secant pile wall in plot R1 7-May-13 4-Jun-13 11-May-13 22-Jun-13 Completed
5 Construction of guide wall in plot H3 30-Apr-13 22-May-13 22-Jun-13 30-July-13 Completed
6 Construction of secant pile wall in plot H3 8-May-13 28-May-13 27-Jun-13 On going
7 Construction of guide wall in plot S2 16-May-13 3-Jun-13 1-July-13 2-July-13 Completed
8 Construction of secant pile wall in plot S2 25-May-13 15-Jun-13 2-July-13 On going
9 Construction of secant pile wall in plot S3 8-May-13 25-May-13 25-May-13 On going
ENGINEERING
RTA Construction NOC for Plot S2 15-May-13 6-Jun-13 Completed
Obtaining shoring permitfor Plot S2 13-May-13 27-Jun-13 Completed
Obtaining shoring permitfor Plot S1 14-May-13 23-Jun-13 Completed
RTA Construction NOC for Plot H1 12-May-13 23-Jun-13 Completed
* - Dates are derived from the updated program
Project Milestones
Sr. No. Milestone
Baseline Last Update This Update
Comments
Finish Start Finish Start Finish
1 Contract Commencement Date 22-Jan-13 22-Jan-13 22-Jan-13 completed
2 Start of Mobilization Works 4-Feb-13 22-Jan-13 22-Jan-13 completed
8 Project Completion 21-Aug-13 16-Nov-13 Forecast Date
Narrative
This Week:
- Plot S3: Secant Pile Wall in Progress.
- Obtaining shoring permits for plot H2
- Start of Guide wall and secant pile wall in Plot H3
- Start of Guide wall in Plot S1 and H1.
Next week:
- Obtaining Permit for Plot H2 By APG and start construction of guide wall.
- Continue the Construction of Secant Pile Wall in Plots H3 and S2
- Start construction of secant pile wall in plot S1
- Completion of Shoring Works in Plot S3
Modifications to Logic, Links, Durations and Relationships
1 A Baseline Program was submitted and under review
External Dependency Factors
- Authorities Approvals
7. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
270 71.3% 23.6% 25-Dec-12 21-Aug-13 25-Dec-12 A 16-Nov-13 -70
Milestones
Milestones 270 0% 0% 25-Dec-12 21-Aug-13 25-Dec-12 A 16-Nov-13 -70
A1000 Award of contract 0 100% 100% 100% 25-Dec-12 25-Dec-12 A
A1020 Start of Mobilization 0 100% 100% 100% 04-Feb-13 22-Jan-13 A
A1010 Contract commencement date 0 100% 100% 100% 22-Jan-13 22-Jan-13 A
A1030 Project Completion 0 0% 0% 0% 21-Aug-13 16-Nov-13 -70
Plots
Plots 246 73.35% 24.28% 22-Jan-13 21-Aug-13 12-Jan-13 A 14-Nov-13 -69
Plot S3
Plot S3 220 98.82% 60.89% 30-Jan-13 21-Aug-13 22-Jan-13 A 21-Oct-13 -49
Engineering
Engineering 77 100% 100% 30-Jan-13 29-Apr-13 23-Jan-13 A 22-May-13 A
A1040 Receive IFC drawings 0 100% 100% 100% 30-Jan-13 23-Jan-13 A
A1060 Submittal of Method Statement 5 100% 100% 100% 06-Feb-13 11-Feb-13 30-Jan-13 A 07-Feb-13 A
A1050 Submittal of Design and shop drawings 5 100% 100% 100% 06-Feb-13 11-Feb-13 31-Jan-13 A 31-Jan-13 A
A1090 Approval of method statement ( ByAPG ) 2 100% 100% 100% 12-Feb-13 13-Feb-13 02-Feb-13 A 07-Feb-13 A
A1070 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 10-Apr-13 11-Apr-13 03-Feb-13 A 13-Apr-13 A
A1080 Approval of Design and shop drawings ( by DM ) 14 100% 100% 100% 10-Apr-13 25-Apr-13 14-Apr-13 A 28-Apr-13 A
A1230 Design NOC from APG 0 100% 100% 100% 11-Apr-13 15-Apr-13 A
A1270 RTA Construction NOC 0 100% 100% 100% 27-Apr-13 08-May-13 A
A1100 Obtaining shoring permit 0 100% 100% 100% 29-Apr-13 22-May-13 A
Authorities Approvals
Authorities Approvals 154 100% 94.27% 30-Jan-13 05-May-13 22-Jan-13 A 29-Jul-13 -5
Fencing /Hoarding and sign board
Fencing /Hoarding and sign board 34 100% 92.5% 10-Feb-13 20-Mar-13 29-Jan-13 A 08-Jul-13 13
A1110 Submittal of fence and sign board drawings 3 100% 100% 100% 10-Feb-13 12-Feb-13 29-Jan-13 A 31-Jan-13 A
A1120 Approval of drawings ( APG) 2 100% 100% 100% 13-Feb-13 14-Feb-13 02-Feb-13 A 11-Feb-13 A
A1140 Obtaining fencing and Hoarding permit 0 100% 100% 100% 28-Feb-13 06-Feb-13 A
A1130 Approval of drawings ( by DM ) 14 100% 100% 100% 13-Feb-13 28-Feb-13 12-Feb-13 A 04-Mar-13 A
A1150 Installation of fence and sign boards 17 85% 100% 85% 02-Mar-13 20-Mar-13 14-Mar-13 A 08-Jul-13 13
Temporary site office
Temporary site office 77 0% 0% 30-Jan-13 29-Apr-13 29-Jan-13 A 12-May-13 A
A1160 Submittal of site offices drawings 6 100% 100% 100% 30-Jan-13 05-Feb-13 29-Jan-13 A 29-Jan-13 A
A1170 Approval of site offices drawings 10 100% 100% 100% 10-Apr-13 21-Apr-13 01-Apr-13 A 30-Apr-13 A
A1180 Obtaining permit 0 100% 100% 100% 21-Apr-13 07-May-13 A
A1190 Installation of temporary site offices 7 100% 100% 100% 22-Apr-13 29-Apr-13 08-May-13 A 12-May-13 A
Permanent office
Permanent office 145 0% 0% 10-Feb-13 05-May-13 11-Feb-13 A 29-Jul-13 -12
A1200 Submit a proposal of permanent offices 2 100% 100% 100% 10-Feb-13 11-Feb-13 11-Feb-13 A 11-Feb-13 A
A1210 Approval of proposal ( APG ) 2 100% 100% 100% 12-Feb-13 13-Feb-13 12-Feb-13 A 04-Jul-13 -12
A1360 Approval of proposal ( DM ) 12 0% 100% 0% 10-Apr-13 23-Apr-13 04-Jul-13 17-Jul-13 -12
A1370 Obtaining permit 0 0% 100% 0% 23-Apr-13 17-Jul-13 -12
A1380 Installation of permanent offices 10 0% 100% 0% 24-Apr-13 05-May-13 18-Jul-13 29-Jul-13 -12
Site visit demarcation
Site visit demarcation 0 0% 0% 03-Feb-13 03-Feb-13 22-Jan-13 A 22-Jan-13 A
A1220 Obtaining site visit demarcation 0 100% 100% 100% 03-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 03-Feb-13 17-Feb-13 22-Jan-13 A 04-Feb-13 A
A1250 Obtaining NOC for trial trenching 0 100% 100% 100% 03-Feb-13 22-Jan-13 A
A1260 starting trial trenches at site for water , ettisalat and sewerage 12 100% 100% 100% 04-Feb-13 17-Feb-13 02-Feb-13 A 04-Feb-13 A
Mobilization permit
Mobilization permit 0 0% 0% 28-Feb-13 28-Feb-13 25-Feb-13 A 25-Feb-13 A
F M A M J J A S O N D
16-Nov-13,...
16-Nov-13,...
Award of c...
Start of M...
Contract c...
Project Co...
14-Nov-13,...
21-Oct-13,...
22-May-13 ...
Receive IF...
Submittal ...
Submittal ...
Approval o...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
29-Jul-13,...
08-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Approval o...
Installati...
12-May-13 ...
Submittal ...
Approval o...
Obtaining ...
Installati...
29-Jul-13,...
Submit a p...
Approval o...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
04-Feb-13 ...
Obtaining ...
starting t...
25-Feb-13 ...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 10
8. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A1350 Obtaining mobilization permit 0 100% 100% 100% 28-Feb-13 25-Feb-13 A
Construction Demarcation
Construction Demarcation 0 0% 0% 25-Apr-13 25-Apr-13 08-May-13 A 08-May-13 A
A1340 Obtaining Construction demarcation 0 100% 100% 100% 25-Apr-13 08-May-13 A
Mobilization
Mobilization 15 100% 100% 02-Mar-13 18-Mar-13 26-Feb-13 A 28-May-13 A
A1390 Mobilization of tools and equipments 15 100% 100% 100% 02-Mar-13 18-Mar-13 26-Feb-13 A 28-May-13 A
Construction
Construction 143 98.28% 43.13% 30-Apr-13 21-Aug-13 14-May-13 A 21-Oct-13 -49
A1400 Construction of guide wall 14 100% 100% 100% 30-Apr-13 15-May-13 14-May-13 A 27-May-13 A
A1410 Construction of secant pile wall 15 91% 100% 91% 08-May-13 25-May-13 25-May-13 A 06-Jul-13 2
A1420 Installation of dewatering system 6 0% 100% 0% 08-May-13 14-May-13 04-Jul-13 10-Jul-13 -49
A1430 Construction of capping beam 17 0% 100% 0% 14-May-13 02-Jun-13 04-Jul-13 23-Jul-13 -4
A1500 Instruction to Excavate 0 0% 100% 0% 25-May-13 06-Jul-13 2
A1450 Running of dewatering system 82 0% 51.22% 0% 15-May-13 21-Aug-13 11-Jul-13 21-Oct-13 -49
A1440 Excavation up to anchors level 20 0% 100% 0% 25-May-13 17-Jun-13 13-Jul-13 04-Aug-13 -4
A1460 Installation of anchors 19 0% 100% 0% 02-Jun-13 24-Jun-13 30-Jul-13 22-Aug-13 -12
A1470 Excavation up to final level 18 0% 100% 0% 11-Jun-13 01-Jul-13 07-Aug-13 29-Aug-13 -12
Plot R1
Plot R1 245 59.74% 38.92% 22-Jan-13 20-Aug-13 12-Jan-13 A 13-Nov-13 -68
Engineering
Engineering 206 100% 100% 22-Jan-13 02-Jul-13 12-Jan-13 A 23-Sep-13 -70
A1480 Receive IFC drawings 0 100% 100% 100% 22-Jan-13 12-Jan-13 A
A1490 Submittal of Design and shop drawings 5 100% 100% 100% 22-Jan-13 28-Jan-13 16-Jan-13 A 16-Jan-13 A
A1510 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 29-Jan-13 30-Jan-13 17-Jan-13 A 13-Apr-13 A
A7050 Design NOC from APG 0 100% 100% 100% 10-Apr-13 10-Apr-13 A
A1520 Approval of Design and shop drawings ( by DM ) 14 100% 100% 100% 11-Apr-13 27-Apr-13 14-Apr-13 A 21-Apr-13 A
A1550 Obtaining Partial shoring permit 0 100% 100% 100% 27-Apr-13 22-Apr-13 A
A7060 RTA Construction NOC 0 100% 100% 100% 30-Apr-13 08-May-13 A
A1540 Obtaining shoring permit 0 0% 100% 0% 02-Jul-13 23-Sep-13 -70
Authorities Approvals
Authorities Approvals 192 100% 57.16% 07-Feb-13 30-Jun-13 16-Jan-13 A 23-Sep-13 -55
Fencing / Hoarding and sign board
Fencing / Hoarding and sign board 35 100% 100% 13-Feb-13 25-Mar-13 16-Jan-13 A 25-Feb-13 A
A3650 Submittal of fencing and sign board drawings 4 100% 100% 100% 13-Feb-13 17-Feb-13 16-Jan-13 A 29-Jan-13 A
A3660 Approval of drawings ( APG) 2 100% 100% 100% 18-Feb-13 19-Feb-13 30-Jan-13 A 31-Jan-13 A
A3670 Approval of drawings ( by DM ) 14 100% 100% 100% 18-Feb-13 05-Mar-13 02-Feb-13 A 14-Feb-13 A
A3680 Obtaining fencing and Hoarding permit 0 100% 100% 100% 05-Mar-13 19-Feb-13 A
A3690 Installation of fence and sign boards 17 100% 100% 100% 06-Mar-13 25-Mar-13 23-Feb-13 A 25-Feb-13 A
Temporary site office
Temporary site office 58 0% 0% 18-Feb-13 25-Apr-13 29-Jan-13 A 29-Apr-13 A
A3700 Submittal of site offices drawings 5 100% 100% 100% 18-Feb-13 23-Feb-13 29-Jan-13 A 29-Jan-13 A
A3710 Approval of site offices drawings 14 100% 100% 100% 24-Feb-13 11-Mar-13 30-Jan-13 A 27-Apr-13 A
A3720 Obtaining permit 0 100% 100% 100% 17-Apr-13 28-Apr-13 A
A3730 Installation of temporary site offices 7 100% 100% 100% 18-Apr-13 25-Apr-13 28-Apr-13 A 29-Apr-13 A
Site visit demarcation
Site visit demarcation 0 0% 0% 07-Feb-13 07-Feb-13 22-Jan-13 A 22-Jan-13 A
A3760 Obtaining site visit demarcation 0 100% 100% 100% 07-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 07-Feb-13 21-Feb-13 22-Jan-13 A 23-Jan-13 A
A3780 Obtaining NOC for trial trenching 0 100% 100% 100% 07-Feb-13 22-Jan-13 A
A3790 starting trial trenches at site for water , Ettisalat and sewerage 12 100% 100% 100% 09-Feb-13 21-Feb-13 22-Jan-13 A 23-Jan-13 A
Utilities Relocation
Utilities Relocation 192 100% 17.39% 09-Feb-13 30-Jun-13 10-Feb-13 A 23-Sep-13 -70
F M A M J J A S O N D
Obtaining ...
08-May-13 ...
Obtaining ...
28-May-13 ...
Mobilizati...
21-Oct-13,...
Constructi...
Constructi...
Installati...
Constructi...
Instructio...
Running of...
Excavation...
Installati...
Excavation...
13-Nov-13,...
23-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Design NOC...
Approval o...
Obtaining ...
RTA Constr...
Obtaining ...
23-Sep-13,...
25-Feb-13 ...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
29-Apr-13 ...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
23-Jan-13 ...
Obtaining ...
starting t...
23-Sep-13,...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 10
9. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Electricity network relocation ( 11 KV relocation works )
Electricity network relocation ( 11 KV relocation works ) 164 100% 20% 26-Feb-13 25-Jun-13 27-Feb-13 A 08-Sep-13 -63
A3920 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 27-Feb-13 A 04-Mar-13 A
A3930 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 09-Mar-13 14-Mar-13 23-Mar-13 A 24-Mar-13 A
A3940 Obtain Approval from DEWA for shop drawing & material submittal 13 46.15% 100% 46.15% 14-Mar-13 28-Mar-13 26-Mar-13 A 11-Jul-13 -63
A3950 11kv cable exstock delivery at site 7 0% 100% 0% 29-Apr-13 06-May-13 11-Jul-13 18-Jul-13 -63
A3990 11KV Cable Joint production & DEWA FAT Inspection and all tests 13 0% 100% 0% 30-Apr-13 14-May-13 13-Jul-13 27-Jul-13 -63
A3970 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 30-Apr-13 27-May-13 13-Jul-13 11-Aug-13 -51
A3960 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 15-May-13 11-Jun-13 28-Jul-13 25-Aug-13 -63
A3980 Shut down and jointing 12 0% 100% 0% 12-Jun-13 25-Jun-13 26-Aug-13 08-Sep-13 -63
Telephone Network Relocation
Telephone Network Relocation 192 100% 0% 09-Feb-13 30-Jun-13 10-Feb-13 A 23-Sep-13 -70
A6320 Trial pit NOC 16 100% 100% 100% 09-Feb-13 26-Feb-13 10-Feb-13 A 20-Feb-13 A
A6330 Trial pit and shop drawing preparation 7 28.57% 100% 28.57% 10-Apr-13 17-Apr-13 01-Apr-13 A 09-Jul-13 -70
A6350 Placement of order and recipt of material at site 18 0% 100% 0% 10-Apr-13 30-Apr-13 04-Jul-13 24-Jul-13 -70
A6340 Approval from Etisalat 12 0% 100% 0% 18-Apr-13 01-May-13 10-Jul-13 23-Jul-13 -69
A6360 Installation of new cable 40 0% 100% 0% 02-May-13 18-Jun-13 25-Jul-13 11-Sep-13 -70
A6370 Shutdown of existing system 5 0% 100% 0% 19-Jun-13 24-Jun-13 12-Sep-13 17-Sep-13 -70
A6380 Re-connection 5 0% 100% 0% 25-Jun-13 30-Jun-13 18-Sep-13 23-Sep-13 -70
Construction Demarcation
Construction Demarcation 0 0% 0% 29-Apr-13 29-Apr-13 25-Apr-13 A 25-Apr-13 A
A3870 Obtaining Construction demarcation 0 100% 100% 100% 29-Apr-13 25-Apr-13 A
Construction
Construction 161 51.72% 32.25% 01-May-13 20-Aug-13 08-May-13 A 13-Nov-13 -68
A1840 Construction of guide wall 23 100% 100% 100% 01-May-13 27-May-13 08-May-13 A 08-Jun-13 A
A1850 Construction of secant pile wall 25 100% 100% 100% 09-May-13 08-Jun-13 11-May-13 A 22-Jun-13 A
A1860 Installation of dewatering system 6 0% 100% 0% 09-May-13 15-May-13 04-Jul-13 10-Jul-13 -47
A1870 Construction of capping beam 23 0% 100% 0% 20-May-13 16-Jun-13 04-Jul-13 30-Jul-13 -2
A1890 Running of dewatering system 80 0% 51.25% 0% 16-May-13 20-Aug-13 11-Jul-13 19-Oct-13 -47
A6990 Instruction to Excavate 0 0% 0% 0% 15-Jul-13 06-Oct-13 -70
A1880 Excavation up to anchors level 20 0% 0% 0% 15-Jul-13 06-Aug-13 06-Oct-13 02-Nov-13 -70
A1900 Installation of anchors 20 0% 0% 0% 21-Jul-13 14-Aug-13 12-Oct-13 09-Nov-13 -70
A1910 Excavation up to final level 19 0% 0% 0% 27-Jul-13 19-Aug-13 22-Oct-13 13-Nov-13 -70
Area with Utilities
Area with Utilities 20 2.41% 0% 03-Jul-13 25-Jul-13 24-Sep-13 21-Oct-13 -66
A1930 Construction of guide wall 7 0% 14.29% 0% 03-Jul-13 10-Jul-13 24-Sep-13 01-Oct-13 -70
A1920 Construction of secant pile wall ( services area ) 10 0% 0% 0% 07-Jul-13 17-Jul-13 28-Sep-13 08-Oct-13 -70
A1940 Construction of capping beam 7 0% 0% 0% 18-Jul-13 25-Jul-13 09-Oct-13 21-Oct-13 -66
Plot H3
Plot H3 222 65.47% 32.1% 10-Feb-13 21-Aug-13 22-Jan-13 A 05-Nov-13 -61
Engineering
Engineering 181 100% 100% 10-Feb-13 01-Jul-13 06-Feb-13 A 12-Sep-13 -61
A4000 Receive IFC drawings 0 100% 100% 100% 10-Feb-13 06-Feb-13 A
A4010 Submittal of Design and shop drawings 5 100% 100% 100% 11-Feb-13 16-Feb-13 26-Feb-13 A 26-Feb-13 A
A4020 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 17-Feb-13 18-Feb-13 28-Feb-13 A 13-Apr-13 A
A4030 Approval of Design and shop drawings ( by DM ) 7 100% 100% 100% 10-Apr-13 25-Apr-13 15-Apr-13 A 16-Jun-13 A
A7070 Design NOC from APG 0 100% 100% 100% 11-Apr-13 18-Apr-13 A
A7080 RTA Construction NOC 0 100% 100% 100% 29-Apr-13 23-May-13 A
A6790 Obtaining Partial shoring permit 0 100% 100% 100% 25-Apr-13 17-Jun-13 A
A4040 Obtaining shoring permit 0 0% 100% 0% 01-Jul-13 12-Sep-13 -61
F M A M J J A S O N D
08-Sep-13,...
Trial pit ...
Investegat...
Obtain App...
11kv cable...
11KV Cable...
Civil Work...
Dispatch c...
Shut down ...
23-Sep-13,...
Trial pit ...
Trial pit ...
Placement ...
Approval f...
Installati...
Shutdown o...
Re-connect...
25-Apr-13 ...
Obtaining ...
13-Nov-13,...
Constructi...
Constructi...
Installati...
Constructi...
Running of...
Instructio...
Excavation...
Installati...
Excavation...
21-Oct-13,...
Constructi...
Constructi...
Constructi...
05-Nov-13,...
12-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 3 of 10
10. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Authorities Approvals
Authorities Approvals 172 100% 59.85% 16-Feb-13 26-Jun-13 22-Jan-13 A 08-Sep-13 -43
Fencing / Hoarding and sign board
Fencing / Hoarding and sign board 35 100% 100% 18-Feb-13 30-Mar-13 29-Jan-13 A 13-Mar-13 A
A4130 Submittal of fence and sign board drawings 4 100% 100% 100% 18-Feb-13 21-Feb-13 29-Jan-13 A 05-Feb-13 A
A4140 Approval of drawings ( APG) 2 100% 100% 100% 23-Feb-13 24-Feb-13 06-Feb-13 A 11-Feb-13 A
A4150 Approval of drawings ( by DM ) 14 100% 100% 100% 23-Feb-13 10-Mar-13 12-Feb-13 A 04-Mar-13 A
A4160 Obtaining fencing and Hoarding permit 0 100% 100% 100% 10-Mar-13 06-Mar-13 A
A4170 Installation of fence and sign boards 17 100% 100% 100% 11-Mar-13 30-Mar-13 10-Mar-13 A 13-Mar-13 A
Temporary site office
Temporary site office 122 0% 0% 23-Feb-13 29-Apr-13 29-Jan-13 A 15-Jul-13 2
A4180 Submittal of site offices drawings 6 100% 100% 100% 23-Feb-13 28-Feb-13 29-Jan-13 A 29-Jan-13 A
A4190 Approval of site offices drawings 10 100% 100% 100% 02-Mar-13 12-Mar-13 27-Feb-13 A 04-Jun-13 A
A4200 Obtaining permit 0 0% 100% 0% 17-Apr-13 04-Jul-13 2
A4210 Installation of temporary site offices 10 0% 100% 0% 18-Apr-13 29-Apr-13 04-Jul-13 15-Jul-13 2
Site visit demarcation
Site visit demarcation 0 0% 0% 16-Feb-13 16-Feb-13 22-Jan-13 A 22-Jan-13 A
A4240 Obtaining site visit demarcation 0 100% 100% 100% 16-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 16-Feb-13 02-Mar-13 23-Jan-13 A 24-Feb-13 A
A4250 Obtaining NOC for trial trenching 0 100% 100% 100% 16-Feb-13 23-Jan-13 A
A4260 starting trial trenches at site for water, Ettisalat and sewerage 12 100% 100% 100% 17-Feb-13 02-Mar-13 12-Feb-13 A 24-Feb-13 A
Utilities Relocation
Utilities Relocation 164 100% 20% 26-Feb-13 26-Jun-13 27-Feb-13 A 08-Sep-13 -61
Electricity network relocation ( 11 KV relocation works )
Electricity network relocation ( 11 KV relocation works ) 164 100% 20% 26-Feb-13 26-Jun-13 27-Feb-13 A 08-Sep-13 -61
A6450 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 27-Feb-13 A 04-Mar-13 A
A6390 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 09-Mar-13 14-Mar-13 23-Mar-13 A 24-Mar-13 A
A6400 Obtain Approval from DEWA for shop drawing & material submittal 13 46.15% 100% 46.15% 14-Mar-13 28-Mar-13 26-Mar-13 A 11-Jul-13 -61
A6410 11kv cable exstock delivery at site 7 0% 100% 0% 30-Apr-13 07-May-13 11-Jul-13 18-Jul-13 -61
A6430 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 01-May-13 28-May-13 13-Jul-13 11-Aug-13 -49
A6460 11KV Cable Joint production & DEWA FAT Inspection and all tests 13 0% 100% 0% 01-May-13 15-May-13 13-Jul-13 27-Jul-13 -61
A6420 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 16-May-13 12-Jun-13 28-Jul-13 25-Aug-13 -61
A6440 Shut down and jointing 12 0% 100% 0% 13-Jun-13 26-Jun-13 26-Aug-13 08-Sep-13 -61
Construction Demarcation
Construction Demarcation 0 0% 0% 28-Apr-13 28-Apr-13 22-Jun-13 A 22-Jun-13 A
A4340 Obtaining Construction demarcation 0 100% 100% 100% 28-Apr-13 22-Jun-13 A
Construction
Construction 110 58.79% 23.85% 30-Apr-13 21-Aug-13 22-Jun-13 A 05-Nov-13 -61
A4050 Construction of guide wall 20 100% 100% 100% 30-Apr-13 22-May-13 22-Jun-13 A 30-Jun-13 A
A4060 Construction of secant pile wall 18 50.8% 100% 50.8% 08-May-13 28-May-13 27-Jun-13 A 13-Jul-13 -49
A4070 Installation of dewatering system 6 0% 100% 0% 08-May-13 14-May-13 04-Jul-13 10-Jul-13 -49
A4080 Construction of capping beam 25 0% 100% 0% 08-May-13 05-Jun-13 04-Jul-13 01-Aug-13 -6
A4100 Running of dewatering system 82 0% 51.22% 0% 15-May-13 21-Aug-13 11-Jul-13 21-Oct-13 -49
A7000 Instruction to Excavate 0 0% 0% 0% 17-Jul-13 29-Sep-13 -61
A4220 Excavation up to anchors level 15 0% 0% 0% 17-Jul-13 03-Aug-13 29-Sep-13 20-Oct-13 -61
A4110 Installation of anchors 20 0% 0% 0% 18-Jul-13 12-Aug-13 30-Sep-13 27-Oct-13 -61
A4120 Excavation up to final level 20 0% 0% 0% 27-Jul-13 20-Aug-13 08-Oct-13 05-Nov-13 -61
Area with Utilities
Area with Utilities 20 4.82% 0% 02-Jul-13 24-Jul-13 14-Sep-13 06-Oct-13 -60
A6850 Construction of guide wall 7 0% 28.57% 0% 02-Jul-13 09-Jul-13 14-Sep-13 21-Sep-13 -61
A6840 Construction of secant pile wall ( services area ) 10 0% 0% 0% 06-Jul-13 16-Jul-13 17-Sep-13 28-Sep-13 -61
A6860 Construction of capping beam 7 0% 0% 0% 17-Jul-13 24-Jul-13 29-Sep-13 06-Oct-13 -60
F M A M J J A S O N D
08-Sep-13,...
13-Mar-13 ...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
15-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
24-Feb-13 ...
Obtaining ...
starting t...
08-Sep-13,...
08-Sep-13,...
Trial pit ...
Investegat...
Obtain App...
11kv cable...
Civil Work...
11KV Cable...
Dispatch c...
Shut down ...
22-Jun-13 ...
Obtaining ...
05-Nov-13,...
Constructi...
Constructi...
Installati...
Constructi...
Running of...
Instructio...
Excavation...
Installati...
Excavation...
06-Oct-13,...
Constructi...
Constructi...
Constructi...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 4 of 10
11. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Plot H1
Plot H1 224 53.4% 8.96% 17-Feb-13 21-Aug-13 22-Jan-13 A 14-Nov-13 -69
Engineering
Engineering 180 100% 87.1% 17-Feb-13 30-Jun-13 11-Feb-13 A 18-Sep-13 -65
A4450 Receive IFC drawings 0 100% 100% 100% 17-Feb-13 11-Feb-13 A
A4460 Submittal of Design and shop drawings 5 100% 100% 100% 18-Feb-13 23-Feb-13 12-Mar-13 A 14-Mar-13 A
A4470 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 24-Feb-13 25-Feb-13 16-Mar-13 A 14-Apr-13 A
A4480 Approval of Design and shop drawings ( by DM ) 14 28.57% 100% 28.57% 10-Apr-13 25-Apr-13 18-Apr-13 A 15-Jul-13 -69
A7090 Design NOC from APG 0 100% 100% 100% 25-Apr-13 06-May-13 A
A7100 RTA Construction NOC 0 100% 100% 100% 12-May-13 23-Jun-13 A
A6800 Obtaining Partial shoring permit 0 0% 100% 0% 09-May-13 29-Jul-13 -69
A4490 Obtaining shoring permit 0 0% 100% 0% 30-Jun-13 18-Sep-13 -65
Authorities Approvals
Authorities Approvals 177 100% 61.31% 18-Feb-13 26-Jun-13 22-Jan-13 A 15-Sep-13 -48
Fencing / Hoarding and sign board
Fencing / Hoarding and sign board 38 100% 100% 23-Feb-13 07-Apr-13 29-Jan-13 A 09-Mar-13 A
A4580 Submittal of fence and sign board drawings 4 100% 100% 100% 23-Feb-13 26-Feb-13 29-Jan-13 A 05-Feb-13 A
A4590 Approval of drawings ( APG) 2 100% 100% 100% 27-Feb-13 28-Feb-13 06-Feb-13 A 11-Feb-13 A
A4600 Approval of drawings ( by DM ) 14 100% 100% 100% 27-Feb-13 14-Mar-13 12-Feb-13 A 04-Mar-13 A
A4610 Obtaining fencing and hoarding permit 0 100% 100% 100% 14-Mar-13 06-Mar-13 A
A4620 Installation of fence and sign boards 20 100% 100% 100% 16-Mar-13 07-Apr-13 06-Mar-13 A 09-Mar-13 A
Temporary site office
Temporary site office 63 0% 0% 27-Feb-13 11-May-13 29-Jan-13 A 02-May-13 A
A4630 Submittal of site offices drawings 6 100% 100% 100% 27-Feb-13 05-Mar-13 29-Jan-13 A 05-Mar-13 A
A4640 Approval of site offices drawings 10 100% 100% 100% 06-Mar-13 17-Mar-13 27-Feb-13 A 30-Apr-13 A
A4650 Obtaining permit 0 100% 100% 100% 17-Apr-13 30-Apr-13 A
A4660 Installation of temporary site offices 20 100% 100% 100% 18-Apr-13 11-May-13 01-May-13 A 02-May-13 A
Site visit demarcation
Site visit demarcation 0 0% 0% 18-Feb-13 18-Feb-13 22-Jan-13 A 22-Jan-13 A
A4690 Obtaining site visit demarcation 0 100% 100% 100% 18-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 18-Feb-13 03-Mar-13 23-Jan-13 A 28-Feb-13 A
A4700 Obtaining NOC for trial trenching 0 100% 100% 100% 18-Feb-13 23-Jan-13 A
A4710 starting trial trenches at site for water , Ettisalat and sewerage 12 100% 100% 100% 18-Feb-13 03-Mar-13 20-Feb-13 A 28-Feb-13 A
Utilities Relocation
Utilities Relocation 170 100% 20% 26-Feb-13 26-Jun-13 27-Feb-13 A 15-Sep-13 -65
Electricity network relocation ( 11 KV relocation works )
Electricity network relocation ( 11 KV relocation works ) 170 100% 20% 26-Feb-13 26-Jun-13 27-Feb-13 A 15-Sep-13 -65
A6770 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 27-Feb-13 A 04-Mar-13 A
A6710 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 10-Apr-13 16-Apr-13 23-Mar-13 A 24-Mar-13 A
A6720 Obtain Approval from DEWA for shop drawing & material submittal 13 0% 100% 0% 16-Apr-13 30-Apr-13 04-Jul-13 18-Jul-13 -65
A6730 11kv cable exstock delivery at site 7 0% 100% 0% 30-Apr-13 07-May-13 18-Jul-13 25-Jul-13 -65
A6750 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 01-May-13 28-May-13 20-Jul-13 18-Aug-13 -53
A6780 11KV Cable Joint production & DEWA FAT Inspection and all tests 13 0% 100% 0% 01-May-13 15-May-13 20-Jul-13 03-Aug-13 -65
A6740 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 16-May-13 12-Jun-13 04-Aug-13 01-Sep-13 -65
A6760 Shut down and jointing 12 0% 100% 0% 13-Jun-13 26-Jun-13 02-Sep-13 15-Sep-13 -65
Construction Demarcation
Construction Demarcation 0 0% 0% 12-May-13 12-May-13 25-Jun-13 A 25-Jun-13 A
A4790 Obtaining Construction demarcation 0 100% 100% 100% 12-May-13 25-Jun-13 A
Construction
Construction 84 46.86% 0% 13-May-13 21-Aug-13 01-Aug-13 14-Nov-13 -69
A4500 Construction of guide wall 20 0% 100% 0% 13-May-13 04-Jun-13 01-Aug-13 26-Aug-13 -69
A4510 Construction of secant pile wall 21 0% 100% 0% 21-May-13 15-Jun-13 12-Aug-13 04-Sep-13 -69
A4520 Installation of dewatering system 6 0% 100% 0% 21-May-13 27-May-13 12-Aug-13 18-Aug-13 -69
F M A M J J A S O N D
14-Nov-13,...
18-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
15-Sep-13,...
09-Mar-13 ...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
02-May-13 ...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
28-Feb-13 ...
Obtaining ...
starting t...
15-Sep-13,...
15-Sep-13,...
Trial pit ...
Investegat...
Obtain App...
11kv cable...
Civil Work...
11KV Cable...
Dispatch c...
Shut down ...
25-Jun-13 ...
Obtaining ...
14-Nov-13,...
Constructi...
Constructi...
Installati...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 5 of 10
12. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A4550 Running of dewatering system 71 0% 43.66% 0% 28-May-13 21-Aug-13 19-Aug-13 14-Nov-13 -69
A4530 Construction of capping beam 20 0% 100% 0% 30-May-13 23-Jun-13 21-Aug-13 12-Sep-13 -43
A7010 Instruction to Excavate 0 0% 100% 0% 16-Jun-13 05-Sep-13 -49
A4540 Excavation up to anchors level 22 0% 0% 0% 06-Jul-13 30-Jul-13 24-Sep-13 23-Oct-13 -65
A4560 Installation of anchors 19 0% 0% 0% 17-Jul-13 07-Aug-13 06-Oct-13 31-Oct-13 -65
A4570 Excavation up to final level 20 0% 0% 0% 24-Jul-13 18-Aug-13 13-Oct-13 10-Nov-13 -65
Area with Utilities
Area with Utilities 20 7.24% 0% 01-Jul-13 23-Jul-13 19-Sep-13 12-Oct-13 -65
A6880 Construction of guide wall 7 0% 42.86% 0% 01-Jul-13 08-Jul-13 19-Sep-13 26-Sep-13 -65
A6870 Construction of secant pile wall ( services area ) 10 0% 0% 0% 04-Jul-13 15-Jul-13 23-Sep-13 03-Oct-13 -65
A6890 Construction of capping beam 7 0% 0% 0% 16-Jul-13 23-Jul-13 05-Oct-13 12-Oct-13 -65
Plot S2
Plot S2 197 85.1% 20.6% 24-Feb-13 20-Aug-13 22-Jan-13 A 20-Oct-13 -48
Engineering
Engineering 160 100% 100% 24-Feb-13 08-Jun-13 11-Feb-13 A 02-Sep-13 -48
A4900 Receive IFC drawings 0 100% 100% 100% 24-Feb-13 11-Feb-13 A
A4910 Submittal of Design and shop drawings 5 100% 100% 100% 10-Apr-13 15-Apr-13 24-Apr-13 A 24-Apr-13 A
A4920 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 16-Apr-13 17-Apr-13 25-Apr-13 A 05-Jun-13 A
A4930 Approval of Design and shop drawings ( by DM ) 14 100% 100% 100% 16-Apr-13 01-May-13 19-May-13 A 06-Jun-13 A
A7110 Design NOC from APG 0 100% 100% 100% 17-Apr-13 23-May-13 A
A7120 RTA Construction NOC 0 100% 100% 100% 15-May-13 06-Jun-13 A
A6810 Obtaining Partial shoring permit 0 100% 100% 100% 13-May-13 27-Jun-13 A
A4940 Obtaining shoring permit 0 0% 100% 0% 08-Jun-13 02-Sep-13 -48
Authorities Approvals
Authorities Approvals 154 100% 57.91% 25-Feb-13 30-May-13 22-Jan-13 A 26-Aug-13 -25
Fencing / Hoarding and sign board
Fencing / Hoarding and sign board 34 100% 92.5% 03-Mar-13 10-Apr-13 29-Jan-13 A 07-Jul-13 -41
A5030 Submittal of fence and sign board drawings 4 100% 100% 100% 03-Mar-13 06-Mar-13 29-Jan-13 A 05-Feb-13 A
A5040 Approval of drawings ( APG) 2 100% 100% 100% 07-Mar-13 09-Mar-13 06-Feb-13 A 11-Feb-13 A
A5050 Approval of drawings ( by DM ) 10 100% 100% 100% 07-Mar-13 18-Mar-13 12-Feb-13 A 04-Mar-13 A
A5060 Obtaining fencing and hoarding permit 0 100% 100% 100% 18-Mar-13 06-Mar-13 A
A5070 Installation of fence and sign boards 20 85% 100% 85% 19-Mar-13 10-Apr-13 14-Mar-13 A 07-Jul-13 -41
Temporary site office
Temporary site office 121 0% 0% 07-Mar-13 20-May-13 29-Jan-13 A 27-Jul-13 -1
A5080 Submittal of site offices drawings 6 100% 100% 100% 07-Mar-13 13-Mar-13 29-Jan-13 A 29-Jan-13 A
A5090 Approval of site offices drawings 10 100% 100% 100% 14-Mar-13 25-Mar-13 05-Mar-13 A 04-Jun-13 A
A5100 Obtaining permit 0 0% 100% 0% 27-Apr-13 04-Jul-13 -1
A5110 Installation of temporary site offices 20 0% 100% 0% 28-Apr-13 20-May-13 04-Jul-13 27-Jul-13 -1
Site visit demarcation
Site visit demarcation 0 0% 0% 25-Feb-13 25-Feb-13 22-Jan-13 A 22-Jan-13 A
A5140 Obtaining site visit demarcation 0 100% 100% 100% 25-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 25-Feb-13 10-Mar-13 23-Jan-13 A 04-Feb-13 A
A5150 Obtaining NOC for trial trenching 0 100% 100% 100% 25-Feb-13 23-Jan-13 A
A5160 starting trial trenches at site for water , Ettisalat and sewerage 12 100% 100% 100% 25-Feb-13 10-Mar-13 02-Feb-13 A 04-Feb-13 A
Utilities Relocation
Utilities Relocation 153 100% 20% 26-Feb-13 30-May-13 23-Jan-13 A 26-Aug-13 -48
Electricity network relocation ( 132 KV relocation works )
Electricity network relocation ( 132 KV relocation works ) 153 100% 20% 26-Feb-13 30-May-13 23-Jan-13 A 26-Aug-13 -48
A6530 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 23-Jan-13 A 29-Jan-13 A
A6470 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 09-Mar-13 14-Mar-13 10-Mar-13 A 01-Apr-13 A
A6480 Obtain Approval from DEWA for shop drawing & material submittal 0 0% 100% 0% 10-Apr-13 10-Apr-13 27-Jun-13 A 04-Jul-13 -47
A6490 132kv cable exstock delivery at site 7 0% 100% 0% 10-Apr-13 17-Apr-13 04-Jul-13 11-Jul-13 -48
F M A M J J A S O N D
Running of...
Constructi...
Instructio...
Excavation...
Installati...
Excavation...
12-Oct-13,...
Constructi...
Constructi...
Constructi...
20-Oct-13,...
02-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
26-Aug-13,...
07-Jul-13,...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
27-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
04-Feb-13 ...
Obtaining ...
starting t...
26-Aug-13,...
26-Aug-13,...
Trial pit ...
Investegat...
Obtain App...
132kv cabl...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 6 of 10
13. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A6510 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 11-Apr-13 08-May-13 06-Jul-13 01-Aug-13 -36
A6540 132KV Cable Joint production & DEWAFAT Inspection and all tests 13 0% 100% 0% 11-Apr-13 25-Apr-13 06-Jul-13 20-Jul-13 -48
A6500 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 27-Apr-13 22-May-13 21-Jul-13 18-Aug-13 -48
A6520 Shut down and jointing 7 0% 100% 0% 23-May-13 30-May-13 19-Aug-13 26-Aug-13 -48
Construction Demarcation
Construction Demarcation 0 0% 0% 14-May-13 14-May-13 23-Jun-13 A 23-Jun-13 A
A5240 Obtaining Construction demarcation 0 100% 100% 100% 14-May-13 23-Jun-13 A
Construction
Construction 80 82.32% 10.5% 16-May-13 20-Aug-13 01-Jul-13 A 20-Oct-13 -48
A4950 Construction of guide wall 16 100% 100% 100% 16-May-13 03-Jun-13 01-Jul-13 A 02-Jul-13 A
A4960 Construction of secant pile wall 18 3.4% 100% 3.4% 25-May-13 15-Jun-13 02-Jul-13 A 31-Jul-13 -41
A4970 Installation of dewatering system 6 0% 100% 0% 25-May-13 30-May-13 13-Jul-13 18-Jul-13 -41
A5000 Running of dewatering system 67 0% 41.79% 0% 01-Jun-13 20-Aug-13 20-Jul-13 07-Oct-13 -41
A4980 Construction of capping beam 17 0% 100% 0% 03-Jun-13 23-Jun-13 21-Jul-13 11-Aug-13 -8
A7020 Instruction to Excavate 0 0% 100% 0% 22-Jun-13 16-Sep-13 -48
A4990 Excavation up to anchors level 17 0% 64.71% 0% 22-Jun-13 10-Jul-13 16-Sep-13 05-Oct-13 -48
A5010 Installation of anchors 14 0% 35.71% 0% 29-Jun-13 14-Jul-13 23-Sep-13 08-Oct-13 -48
A5020 Excavation up to final level 15 0% 0% 0% 04-Jul-13 21-Jul-13 29-Sep-13 20-Oct-13 -48
Area with Utilities
Area with Utilities 18 100% 0% 09-Jun-13 29-Jun-13 03-Sep-13 23-Sep-13 -44
A6910 Construction of guide wall 7 0% 100% 0% 09-Jun-13 16-Jun-13 03-Sep-13 10-Sep-13 -48
A6900 Construction of secant pile wall ( services area ) 8 0% 100% 0% 12-Jun-13 20-Jun-13 07-Sep-13 15-Sep-13 -48
A6920 Construction of capping beam 7 0% 100% 0% 22-Jun-13 29-Jun-13 16-Sep-13 23-Sep-13 -44
Plot S1
Plot S1 201 81.44% 12.69% 25-Feb-13 19-Aug-13 22-Jan-13 A 24-Oct-13 -52
Engineering
Engineering 155 100% 100% 03-Mar-13 09-Jun-13 11-Feb-13 A 03-Sep-13 -52
A5360 Receive IFC drawings 0 100% 100% 100% 03-Mar-13 11-Feb-13 A
A5370 Submittal of Design and shop drawings 4 100% 100% 100% 10-Apr-13 14-Apr-13 30-Apr-13 A 30-Apr-13 A
A5380 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 15-Apr-13 16-Apr-13 30-Apr-13 A 02-May-13 A
A5390 Approval of Design and shop drawings ( by DM ) 14 100% 100% 100% 15-Apr-13 30-Apr-13 19-May-13 A 23-Jun-13 A
A7130 Design NOC from APG 0 100% 100% 100% 02-May-13 23-May-13 A
A7140 RTA Construction NOC 0 100% 100% 100% 16-May-13 12-Jun-13 A
A6820 Obtaining Partial shoring permit 0 100% 100% 100% 14-May-13 23-Jun-13 A
A5400 Obtaining shoring permits 0 0% 100% 0% 09-Jun-13 03-Sep-13 -52
Authorities Approvals
Authorities Approvals 154 100% 57.71% 25-Feb-13 30-May-13 22-Jan-13 A 26-Aug-13 -28
Hoarding and sign board
Hoarding and sign board 32 100% 92.5% 10-Mar-13 15-Apr-13 29-Jan-13 A 07-Jul-13 -39
A5490 Submittal of fence and sign board drawings 4 100% 100% 100% 10-Mar-13 13-Mar-13 29-Jan-13 A 05-Feb-13 A
A5500 Approval of drawings ( APG) 2 100% 100% 100% 14-Mar-13 16-Mar-13 06-Feb-13 A 11-Feb-13 A
A5510 Approval of drawings ( DM ) 6 100% 100% 100% 17-Mar-13 23-Mar-13 12-Feb-13 A 04-Mar-13 A
A5520 Obtaining Fencing and Hoarding permit 0 100% 100% 100% 23-Mar-13 06-Mar-13 A
A5530 Installation of fence and sign boards 20 85% 100% 85% 24-Mar-13 15-Apr-13 14-Mar-13 A 07-Jul-13 -39
Temporary site office
Temporary site office 115 0% 0% 14-Mar-13 19-May-13 29-Jan-13 A 27-Jul-13 -4
A5540 Submittal of site offices drawings 6 100% 100% 100% 14-Mar-13 20-Mar-13 29-Jan-13 A 29-Jan-13 A
A5550 Approval of site offices drawings 7 100% 100% 100% 15-Apr-13 25-Apr-13 01-May-13 A 04-Jun-13 A
A5560 Obtaining Permit 0 0% 100% 0% 25-Apr-13 04-Jul-13 -4
A5570 Installation of temporary site offices 20 0% 100% 0% 27-Apr-13 19-May-13 04-Jul-13 27-Jul-13 -4
Site visit demarcation
Site visit demarcation 0 0% 0% 25-Feb-13 25-Feb-13 22-Jan-13 A 22-Jan-13 A
F M A M J J A S O N D
Civil Work...
132KV Cabl...
Dispatch c...
Shut down ...
23-Jun-13 ...
Obtaining ...
20-Oct-13,...
Constructi...
Constructi...
Installati...
Running of...
Constructi...
Instructio...
Excavation...
Installati...
Excavation...
23-Sep-13,...
Constructi...
Constructi...
Constructi...
24-Oct-13,...
03-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
26-Aug-13,...
07-Jul-13,...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
27-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 7 of 10
14. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A5600 Obtaining site visit demarcation 0 100% 100% 100% 25-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 25-Feb-13 10-Mar-13 23-Jan-13 A 10-Feb-13 A
A5610 Obtaining NOC for trial trenching 0 100% 100% 100% 25-Feb-13 23-Jan-13 A
A5620 starting trial trenches at site for water , Ettisalat and sewerage 12 100% 100% 100% 25-Feb-13 10-Mar-13 05-Feb-13 A 10-Feb-13 A
Utilities Relocation
Utilities Relocation 153 100% 20% 26-Feb-13 30-May-13 04-Mar-13 A 26-Aug-13 -52
Electricity network relocation ( 132 KV relocation works )
Electricity network relocation ( 132 KV relocation works ) 153 100% 20% 26-Feb-13 30-May-13 04-Mar-13 A 26-Aug-13 -52
A6610 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 04-Mar-13 A 04-Mar-13 A
A6550 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 09-Mar-13 14-Mar-13 10-Mar-13 A 01-Apr-13 A
A6560 Obtain Approval from DEWA for shop drawing & material submittal 13 100% 100% 100% 14-Mar-13 28-Mar-13 26-Mar-13 A 04-Jul-13 -51
A6570 132kv cable exstock delivery at site 7 0% 100% 0% 10-Apr-13 17-Apr-13 04-Jul-13 11-Jul-13 -52
A6590 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 11-Apr-13 08-May-13 06-Jul-13 01-Aug-13 -40
A6620 132KV Cable Joint production & DEWAFAT Inspection and all tests 13 0% 100% 0% 11-Apr-13 25-Apr-13 06-Jul-13 20-Jul-13 -52
A6580 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 27-Apr-13 22-May-13 21-Jul-13 18-Aug-13 -52
A6600 Shut down and jointing 7 0% 100% 0% 23-May-13 30-May-13 19-Aug-13 26-Aug-13 -52
Construction Demarcation
Construction Demarcation 0 0% 0% 16-May-13 16-May-13 23-Jun-13 A 23-Jun-13 A
A5700 Obtaining Construction demarcation 0 100% 100% 100% 16-May-13 23-Jun-13 A
Construction
Construction 84 78.18% 1.84% 18-May-13 19-Aug-13 01-Jul-13 A 24-Oct-13 -52
A5410 Construction of guide wall 14 16% 100% 16% 18-May-13 02-Jun-13 01-Jul-13 A 23-Jul-13 -39
A5420 Construction of secant pile wall 19 0% 100% 0% 26-May-13 17-Jun-13 13-Jul-13 03-Aug-13 -39
A5430 Installation of dewatering system 6 0% 100% 0% 26-May-13 01-Jun-13 13-Jul-13 18-Jul-13 -39
A5440 Construction of capping beam 24 0% 100% 0% 28-May-13 25-Jun-13 15-Jul-13 13-Aug-13 -11
A5460 Running of dewatering system 65 0% 41.54% 0% 02-Jun-13 19-Aug-13 20-Jul-13 05-Oct-13 -39
A7030 Instruction to Excavate 0 0% 100% 0% 20-Jun-13 15-Sep-13 -52
A5450 Excavation up to anchors level 20 0% 60% 0% 20-Jun-13 13-Jul-13 15-Sep-13 07-Oct-13 -52
A5470 Installation of anchors 16 0% 25% 0% 30-Jun-13 17-Jul-13 24-Sep-13 12-Oct-13 -52
A5480 Excavation up to final level 17 0% 0% 0% 07-Jul-13 25-Jul-13 01-Oct-13 24-Oct-13 -52
Area with Utilities
Area with Utilities 16 100% 0% 10-Jun-13 27-Jun-13 04-Sep-13 22-Sep-13 -45
A6940 Construction of guide wall 7 0% 100% 0% 10-Jun-13 17-Jun-13 04-Sep-13 11-Sep-13 -52
A6930 Construction of secant pile wall ( services area ) 6 0% 100% 0% 13-Jun-13 19-Jun-13 08-Sep-13 14-Sep-13 -52
A6950 Construction of capping beam 7 0% 100% 0% 20-Jun-13 27-Jun-13 15-Sep-13 22-Sep-13 -45
Plot H2
Plot H2 201 78.42% 9.69% 25-Feb-13 20-Aug-13 22-Jan-13 A 24-Oct-13 -52
Engineering
Engineering 122 100% 89.94% 10-Apr-13 08-Jun-13 08-May-13 A 02-Sep-13 -54
A5820 Receive IFC drawings 0 100% 100% 100% 10-Apr-13 08-May-13 A
A5830 Submittal of Design and shop drawings 5 100% 100% 100% 10-Apr-13 15-Apr-13 21-May-13 A 21-May-13 A
A5840 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 16-Apr-13 17-Apr-13 22-May-13 A 12-Jun-13 A
A5850 Approval of Design and shop drawings ( by DM ) 14 50% 100% 50% 16-Apr-13 01-May-13 12-Jun-13 A 11-Jul-13 -17
A7150 Design NOC from APG 0 100% 100% 100% 08-May-13 13-Jun-13 A
A7160 RTA Construction NOC 0 100% 100% 100% 27-May-13 24-Jun-13 A
A6830 Obtaining Partial shoring permit 0 0% 100% 0% 23-May-13 04-Jul-13 -34
A5860 Obtaining shoring permit 0 0% 100% 0% 08-Jun-13 02-Sep-13 -54
Authorities Approvals
Authorities Approvals 154 100% 52.62% 25-Feb-13 30-May-13 22-Jan-13 A 26-Aug-13 -30
Fencing/ Hoarding and sign board
Fencing/ Hoarding and sign board 38 100% 100% 17-Mar-13 29-Apr-13 29-Jan-13 A 13-Mar-13 A
A5950 Submittal of fence and sign board drawings 4 100% 100% 100% 17-Mar-13 20-Mar-13 29-Jan-13 A 05-Feb-13 A
F M A M J J A S O N D
Obtaining ...
10-Feb-13 ...
Obtaining ...
starting t...
26-Aug-13,...
26-Aug-13,...
Trial pit ...
Investegat...
Obtain App...
132kv cabl...
Civil Work...
132KV Cabl...
Dispatch c...
Shut down ...
23-Jun-13 ...
Obtaining ...
24-Oct-13,...
Constructi...
Constructi...
Installati...
Constructi...
Running of...
Instructio...
Excavation...
Installati...
Excavation...
22-Sep-13,...
Constructi...
Constructi...
Constructi...
24-Oct-13,...
02-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
26-Aug-13,...
13-Mar-13 ...
Submittal ...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 8 of 10
15. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A5960 Approval of drawings ( APG) 2 100% 100% 100% 21-Mar-13 23-Mar-13 06-Feb-13 A 27-Feb-13 A
A5970 Approval of drawings ( by DM ) 14 100% 100% 100% 21-Mar-13 06-Apr-13 27-Feb-13 A 03-Mar-13 A
A5980 Obtaining fencing and hoarding permit 0 100% 100% 100% 06-Apr-13 06-Mar-13 A
A5990 Installation of fence and sign boards 20 100% 100% 100% 07-Apr-13 29-Apr-13 12-Mar-13 A 13-Mar-13 A
Temporary site office
Temporary site office 109 0% 0% 21-Mar-13 20-May-13 29-Jan-13 A 27-Jul-13 -6
A6000 Submittal of site offices drawings 6 100% 100% 100% 21-Mar-13 27-Mar-13 29-Jan-13 A 29-Jan-13 A
A6010 Approval of site offices drawings 10 100% 100% 100% 16-Apr-13 27-Apr-13 01-May-13 A 04-Jun-13 A
A6020 Obtaining permit 0 0% 100% 0% 27-Apr-13 04-Jul-13 -6
A6030 Installation of temporary site offices 20 0% 100% 0% 28-Apr-13 20-May-13 04-Jul-13 27-Jul-13 -6
Site visit demarcation
Site visit demarcation 0 0% 0% 25-Feb-13 25-Feb-13 22-Jan-13 A 22-Jan-13 A
A6060 Obtaining site visit demarcation 0 100% 100% 100% 25-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 25-Feb-13 10-Mar-13 23-Jan-13 A 12-Mar-13 A
A6070 Obtaining NOC for trial trenching 0 100% 100% 100% 25-Feb-13 23-Jan-13 A
A6080 starting trial trenches at site for water , ettisalat and sewerage 12 100% 100% 100% 25-Feb-13 10-Mar-13 10-Feb-13 A 12-Mar-13 A
Utilities Relocation
Utilities Relocation 153 100% 15% 26-Feb-13 30-May-13 04-Mar-13 A 26-Aug-13 -54
Electricity network relocation ( 132 KV relocation works )
Electricity network relocation ( 132 KV relocation works ) 153 100% 15% 26-Feb-13 30-May-13 04-Mar-13 A 26-Aug-13 -54
A6690 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 04-Mar-13 A 04-Mar-13 A
A6630 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 50% 100% 50% 09-Mar-13 14-Mar-13 10-Mar-13 A 07-Jul-13 -54
A6640 Obtain Approval from DEWA for shop drawing & material submittal 13 100% 100% 100% 14-Mar-13 28-Mar-13 26-Mar-13 A 07-Jul-13 -54
A6650 132kv cable exstock delivery at site 7 0% 100% 0% 11-Apr-13 18-Apr-13 06-Jul-13 13-Jul-13 -54
A6670 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 13-Apr-13 09-May-13 07-Jul-13 03-Aug-13 -42
A6700 132KV Cable Joint production & DEWAFAT Inspection and all tests 13 0% 100% 0% 13-Apr-13 27-Apr-13 07-Jul-13 21-Jul-13 -54
A6660 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 28-Apr-13 23-May-13 22-Jul-13 19-Aug-13 -54
A6680 Shut down and jointing 6 0% 100% 0% 25-May-13 30-May-13 20-Aug-13 26-Aug-13 -54
Construction Demarcation
Construction Demarcation 0 0% 0% 26-May-13 26-May-13 06-Jul-13 06-Jul-13 -34
A6160 Obtaining Construction demarcation 0 0% 100% 0% 26-May-13 06-Jul-13 -34
Construction
Construction 88 74.81% 0% 28-May-13 20-Aug-13 08-Jul-13 24-Oct-13 -52
A5870 Construction of guide wall 15 0% 100% 0% 28-May-13 15-Jun-13 08-Jul-13 24-Jul-13 -34
A5880 Construction of secant pile wall 21 0% 100% 0% 05-Jun-13 22-Jun-13 16-Jul-13 11-Aug-13 -34
A5890 Installation of dewatering system 6 0% 100% 0% 05-Jun-13 12-Jun-13 16-Jul-13 22-Jul-13 -34
A5920 Running of dewatering system 57 0% 31.58% 0% 13-Jun-13 20-Aug-13 23-Jul-13 29-Sep-13 -34
A5900 Construction of capping beam 20 0% 100% 0% 08-Jun-13 30-Jun-13 25-Jul-13 19-Aug-13 -19
A7040 Instruction to Excavate 0 0% 100% 0% 23-Jun-13 15-Sep-13 -54
A5910 Excavation up to anchors level 18 0% 55.56% 0% 23-Jun-13 13-Jul-13 15-Sep-13 05-Oct-13 -54
A5930 Installation of anchors 16 0% 12.5% 0% 02-Jul-13 20-Jul-13 24-Sep-13 12-Oct-13 -54
A5940 Excavation up to final level 16 0% 0% 0% 10-Jul-13 28-Jul-13 02-Oct-13 24-Oct-13 -52
Area with Utilities
Area with Utilities 17 100% 0% 09-Jun-13 27-Jun-13 03-Sep-13 22-Sep-13 -49
A6970 Construction of guide wall 7 0% 100% 0% 09-Jun-13 16-Jun-13 03-Sep-13 10-Sep-13 -54
A6960 Construction of secant pile wall ( services area ) 7 0% 100% 0% 12-Jun-13 19-Jun-13 07-Sep-13 14-Sep-13 -54
A6980 Construction of capping beam 7 0% 100% 0% 20-Jun-13 27-Jun-13 15-Sep-13 22-Sep-13 -49
Project Close-out
Project Close-out 26 0% 0% 21-Jul-13 21-Aug-13 12-Oct-13 16-Nov-13 -70
A6280 Submittal of As-built drawings 10 0% 0% 0% 21-Jul-13 31-Jul-13 12-Oct-13 27-Oct-13 -62
A6290 Approval of As-built drawings 12 0% 0% 0% 28-Jul-13 12-Aug-13 23-Oct-13 06-Nov-13 -62
F M A M J J A S O N D
Approval o...
Approval o...
Obtaining ...
Installati...
27-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
12-Mar-13 ...
Obtaining ...
starting t...
26-Aug-13,...
26-Aug-13,...
Trial pit ...
Investegat...
Obtain App...
132kv cabl...
Civil Work...
132KV Cabl...
Dispatch c...
Shut down ...
06-Jul-13,...
Obtaining ...
24-Oct-13,...
Constructi...
Constructi...
Installati...
Running of...
Constructi...
Instructio...
Excavation...
Installati...
Excavation...
22-Sep-13,...
Constructi...
Constructi...
Constructi...
16-Nov-13,...
Submittal ...
Approval o...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 9 of 10
16. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A6300 Demobilization of all plant , equipments and facilities 4 0% 0% 0% 18-Aug-13 21-Aug-13 12-Nov-13 16-Nov-13 -70
A6310 Site handing over 0 0% 0% 0% 21-Aug-13 16-Nov-13 -70
F M A M J J A S O N D
Demobiliza...
Site handi...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Weekly Update
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 10 of 10
17. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
224 53.4% 8.96% 17-Feb-13 21-Aug-13 22-Jan-13 A 14-Nov-13 -69
Plots
Plots 224 53.4% 8.96% 17-Feb-13 21-Aug-13 22-Jan-13 A 14-Nov-13 -69
Plot H1
Plot H1 224 53.4% 8.96% 17-Feb-13 21-Aug-13 22-Jan-13 A 14-Nov-13 -69
Engineering
Engineering 180 100% 87.1% 17-Feb-13 30-Jun-13 11-Feb-13 A 18-Sep-13 -65
A4450 Receive IFC drawings 0 100% 100% 100% 17-Feb-13 11-Feb-13 A
A4460 Submittal of Design and shop drawings 5 100% 100% 100% 18-Feb-13 23-Feb-13 12-Mar-13 A 14-Mar-13 A
A4470 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 24-Feb-13 25-Feb-13 16-Mar-13 A 14-Apr-13 A
A4480 Approval of Design and shop drawings ( by DM ) 14 28.57% 100% 28.57% 10-Apr-13 25-Apr-13 18-Apr-13 A 15-Jul-13 -69
A7090 Design NOC from APG 0 100% 100% 100% 25-Apr-13 06-May-13 A
A7100 RTA Construction NOC 0 100% 100% 100% 12-May-13 23-Jun-13 A
A6800 Obtaining Partial shoring permit 0 0% 100% 0% 09-May-13 29-Jul-13 -69
A4490 Obtaining shoring permit 0 0% 100% 0% 30-Jun-13 18-Sep-13 -65
Authorities Approvals
Authorities Approvals 177 100% 61.31% 18-Feb-13 26-Jun-13 22-Jan-13 A 15-Sep-13 -48
Fencing / Hoarding and sign board
Fencing / Hoarding and sign board 38 100% 100% 23-Feb-13 07-Apr-13 29-Jan-13 A 09-Mar-13 A
A4580 Submittal of fence and sign board drawings 4 100% 100% 100% 23-Feb-13 26-Feb-13 29-Jan-13 A 05-Feb-13 A
A4590 Approval of drawings ( APG) 2 100% 100% 100% 27-Feb-13 28-Feb-13 06-Feb-13 A 11-Feb-13 A
A4600 Approval of drawings ( by DM ) 14 100% 100% 100% 27-Feb-13 14-Mar-13 12-Feb-13 A 04-Mar-13 A
A4610 Obtaining fencing and hoarding permit 0 100% 100% 100% 14-Mar-13 06-Mar-13 A
A4620 Installation of fence and sign boards 20 100% 100% 100% 16-Mar-13 07-Apr-13 06-Mar-13 A 09-Mar-13 A
Temporary site office
Temporary site office 63 0% 0% 27-Feb-13 11-May-13 29-Jan-13 A 02-May-13 A
A4630 Submittal of site offices drawings 6 100% 100% 100% 27-Feb-13 05-Mar-13 29-Jan-13 A 05-Mar-13 A
A4640 Approval of site offices drawings 10 100% 100% 100% 06-Mar-13 17-Mar-13 27-Feb-13 A 30-Apr-13 A
A4650 Obtaining permit 0 100% 100% 100% 17-Apr-13 30-Apr-13 A
A4660 Installation of temporary site offices 20 100% 100% 100% 18-Apr-13 11-May-13 01-May-13 A 02-May-13 A
Site visit demarcation
Site visit demarcation 0 0% 0% 18-Feb-13 18-Feb-13 22-Jan-13 A 22-Jan-13 A
A4690 Obtaining site visit demarcation 0 100% 100% 100% 18-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 18-Feb-13 03-Mar-13 23-Jan-13 A 28-Feb-13 A
A4700 Obtaining NOC for trial trenching 0 100% 100% 100% 18-Feb-13 23-Jan-13 A
A4710 starting trial trenches at site for water , Ettisalat and sewerage 12 100% 100% 100% 18-Feb-13 03-Mar-13 20-Feb-13 A 28-Feb-13 A
Utilities Relocation
Utilities Relocation 170 100% 20% 26-Feb-13 26-Jun-13 27-Feb-13 A 15-Sep-13 -65
Electricity network relocation ( 11 KV relocation works )
Electricity network relocation ( 11 KV relocation works ) 170 100% 20% 26-Feb-13 26-Jun-13 27-Feb-13 A 15-Sep-13 -65
A6770 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 27-Feb-13 A 04-Mar-13 A
A6710 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 10-Apr-13 16-Apr-13 23-Mar-13 A 24-Mar-13 A
A6720 Obtain Approval from DEWA for shop drawing & material submittal 13 0% 100% 0% 16-Apr-13 30-Apr-13 04-Jul-13 18-Jul-13 -65
A6730 11kv cable exstock delivery at site 7 0% 100% 0% 30-Apr-13 07-May-13 18-Jul-13 25-Jul-13 -65
A6750 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 01-May-13 28-May-13 20-Jul-13 18-Aug-13 -53
A6780 11KV Cable Joint production & DEWA FAT Inspection and all tests 13 0% 100% 0% 01-May-13 15-May-13 20-Jul-13 03-Aug-13 -65
A6740 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 16-May-13 12-Jun-13 04-Aug-13 01-Sep-13 -65
A6760 Shut down and jointing 12 0% 100% 0% 13-Jun-13 26-Jun-13 02-Sep-13 15-Sep-13 -65
Construction Demarcation
Construction Demarcation 0 0% 0% 12-May-13 12-May-13 25-Jun-13 A 25-Jun-13 A
A4790 Obtaining Construction demarcation 0 100% 100% 100% 12-May-13 25-Jun-13 A
Construction
Construction 84 46.86% 0% 13-May-13 21-Aug-13 01-Aug-13 14-Nov-13 -69
J F M A M J J A S O N
18-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
15-Sep-13,...
09-Mar-13 ...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
02-May-13 ...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
28-Feb-13 ...
Obtaining ...
starting t...
15-Sep-13,...
15-Sep-13,...
Trial pit ...
Investegat...
Obtain App...
11kv cable...
Civil Work...
11KV Cable...
Dispatch c...
Shut down ...
25-Jun-13 ...
Obtaining ...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot H1
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 2
18. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A4500 Construction of guide wall 20 0% 100% 0% 13-May-13 04-Jun-13 01-Aug-13 26-Aug-13 -69
A4510 Construction of secant pile wall 21 0% 100% 0% 21-May-13 15-Jun-13 12-Aug-13 04-Sep-13 -69
A4520 Installation of dewatering system 6 0% 100% 0% 21-May-13 27-May-13 12-Aug-13 18-Aug-13 -69
A4550 Running of dewatering system 71 0% 43.66% 0% 28-May-13 21-Aug-13 19-Aug-13 14-Nov-13 -69
A4530 Construction of capping beam 20 0% 100% 0% 30-May-13 23-Jun-13 21-Aug-13 12-Sep-13 -43
A7010 Instruction to Excavate 0 0% 100% 0% 16-Jun-13 05-Sep-13 -49
A4540 Excavation up to anchors level 22 0% 0% 0% 06-Jul-13 30-Jul-13 24-Sep-13 23-Oct-13 -65
A4560 Installation of anchors 19 0% 0% 0% 17-Jul-13 07-Aug-13 06-Oct-13 31-Oct-13 -65
A4570 Excavation up to final level 20 0% 0% 0% 24-Jul-13 18-Aug-13 13-Oct-13 10-Nov-13 -65
Area with Utilities
Area with Utilities 20 7.24% 0% 01-Jul-13 23-Jul-13 19-Sep-13 12-Oct-13 -65
A6880 Construction of guide wall 7 0% 42.86% 0% 01-Jul-13 08-Jul-13 19-Sep-13 26-Sep-13 -65
A6870 Construction of secant pile wall ( services area ) 10 0% 0% 0% 04-Jul-13 15-Jul-13 23-Sep-13 03-Oct-13 -65
A6890 Construction of capping beam 7 0% 0% 0% 16-Jul-13 23-Jul-13 05-Oct-13 12-Oct-13 -65
J F M A M J J A S O N
Constructi...
Constructi...
Installati...
Constructi...
Instructio...
Excavation...
Installati...
12-Oct-13,...
Constructi...
Constructi...
Constructi...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot H1
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 2
19. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
201 78.42% 9.69% 25-Feb-13 20-Aug-13 22-Jan-13 A 24-Oct-13 -52
Plots
Plots 201 78.42% 9.69% 25-Feb-13 20-Aug-13 22-Jan-13 A 24-Oct-13 -52
Plot H2
Plot H2 201 78.42% 9.69% 25-Feb-13 20-Aug-13 22-Jan-13 A 24-Oct-13 -52
Engineering
Engineering 122 100% 89.94% 10-Apr-13 08-Jun-13 08-May-13 A 02-Sep-13 -54
A5820 Receive IFC drawings 0 100% 100% 100% 10-Apr-13 08-May-13 A
A5830 Submittal of Design and shop drawings 5 100% 100% 100% 10-Apr-13 15-Apr-13 21-May-13 A 21-May-13 A
A5840 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 16-Apr-13 17-Apr-13 22-May-13 A 12-Jun-13 A
A5850 Approval of Design and shop drawings ( by DM ) 14 50% 100% 50% 16-Apr-13 01-May-13 12-Jun-13 A 11-Jul-13 -17
A7150 Design NOC from APG 0 100% 100% 100% 08-May-13 13-Jun-13 A
A7160 RTA Construction NOC 0 100% 100% 100% 27-May-13 24-Jun-13 A
A6830 Obtaining Partial shoring permit 0 0% 100% 0% 23-May-13 04-Jul-13 -34
A5860 Obtaining shoring permit 0 0% 100% 0% 08-Jun-13 02-Sep-13 -54
Authorities Approvals
Authorities Approvals 154 100% 52.62% 25-Feb-13 30-May-13 22-Jan-13 A 26-Aug-13 -30
Fencing/ Hoarding and sign board
Fencing/ Hoarding and sign board 38 100% 100% 17-Mar-13 29-Apr-13 29-Jan-13 A 13-Mar-13 A
A5950 Submittal of fence and sign board drawings 4 100% 100% 100% 17-Mar-13 20-Mar-13 29-Jan-13 A 05-Feb-13 A
A5960 Approval of drawings ( APG) 2 100% 100% 100% 21-Mar-13 23-Mar-13 06-Feb-13 A 27-Feb-13 A
A5970 Approval of drawings ( by DM ) 14 100% 100% 100% 21-Mar-13 06-Apr-13 27-Feb-13 A 03-Mar-13 A
A5980 Obtaining fencing and hoarding permit 0 100% 100% 100% 06-Apr-13 06-Mar-13 A
A5990 Installation of fence and sign boards 20 100% 100% 100% 07-Apr-13 29-Apr-13 12-Mar-13 A 13-Mar-13 A
Temporary site office
Temporary site office 109 0% 0% 21-Mar-13 20-May-13 29-Jan-13 A 27-Jul-13 -6
A6000 Submittal of site offices drawings 6 100% 100% 100% 21-Mar-13 27-Mar-13 29-Jan-13 A 29-Jan-13 A
A6010 Approval of site offices drawings 10 100% 100% 100% 16-Apr-13 27-Apr-13 01-May-13 A 04-Jun-13 A
A6020 Obtaining permit 0 0% 100% 0% 27-Apr-13 04-Jul-13 -6
A6030 Installation of temporary site offices 20 0% 100% 0% 28-Apr-13 20-May-13 04-Jul-13 27-Jul-13 -6
Site visit demarcation
Site visit demarcation 0 0% 0% 25-Feb-13 25-Feb-13 22-Jan-13 A 22-Jan-13 A
A6060 Obtaining site visit demarcation 0 100% 100% 100% 25-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 25-Feb-13 10-Mar-13 23-Jan-13 A 12-Mar-13 A
A6070 Obtaining NOC for trial trenching 0 100% 100% 100% 25-Feb-13 23-Jan-13 A
A6080 starting trial trenches at site for water , ettisalat and sewerage 12 100% 100% 100% 25-Feb-13 10-Mar-13 10-Feb-13 A 12-Mar-13 A
Utilities Relocation
Utilities Relocation 153 100% 15% 26-Feb-13 30-May-13 04-Mar-13 A 26-Aug-13 -54
Electricity network relocation ( 132 KV relocation works )
Electricity network relocation ( 132 KV relocation works ) 153 100% 15% 26-Feb-13 30-May-13 04-Mar-13 A 26-Aug-13 -54
A6690 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 04-Mar-13 A 04-Mar-13 A
A6630 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 50% 100% 50% 09-Mar-13 14-Mar-13 10-Mar-13 A 07-Jul-13 -54
A6640 Obtain Approval from DEWA for shop drawing & material submittal 13 100% 100% 100% 14-Mar-13 28-Mar-13 26-Mar-13 A 07-Jul-13 -54
A6650 132kv cable exstock delivery at site 7 0% 100% 0% 11-Apr-13 18-Apr-13 06-Jul-13 13-Jul-13 -54
A6670 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 13-Apr-13 09-May-13 07-Jul-13 03-Aug-13 -42
A6700 132KV Cable Joint production & DEWAFAT Inspection and all tests 13 0% 100% 0% 13-Apr-13 27-Apr-13 07-Jul-13 21-Jul-13 -54
A6660 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 28-Apr-13 23-May-13 22-Jul-13 19-Aug-13 -54
A6680 Shut down and jointing 6 0% 100% 0% 25-May-13 30-May-13 20-Aug-13 26-Aug-13 -54
Construction Demarcation
Construction Demarcation 0 0% 0% 26-May-13 26-May-13 06-Jul-13 06-Jul-13 -34
A6160 Obtaining Construction demarcation 0 0% 100% 0% 26-May-13 06-Jul-13 -34
Construction
Construction 88 74.81% 0% 28-May-13 20-Aug-13 08-Jul-13 24-Oct-13 -52
J F M A M J J A S O N
24-Oct-13,...
24-Oct-13,...
24-Oct-13,...
02-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
26-Aug-13,...
13-Mar-13 ...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
27-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
12-Mar-13 ...
Obtaining ...
starting t...
26-Aug-13,...
26-Aug-13,...
Trial pit ...
Investegat...
Obtain App...
132kv cabl...
Civil Work...
132KV Cabl...
Dispatch c...
Shut down ...
06-Jul-13,...
Obtaining ...
24-Oct-13,...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot H2
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 2
20. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A5870 Construction of guide wall 15 0% 100% 0% 28-May-13 15-Jun-13 08-Jul-13 24-Jul-13 -34
A5880 Construction of secant pile wall 21 0% 100% 0% 05-Jun-13 22-Jun-13 16-Jul-13 11-Aug-13 -34
A5890 Installation of dewatering system 6 0% 100% 0% 05-Jun-13 12-Jun-13 16-Jul-13 22-Jul-13 -34
A5920 Running of dewatering system 57 0% 31.58% 0% 13-Jun-13 20-Aug-13 23-Jul-13 29-Sep-13 -34
A5900 Construction of capping beam 20 0% 100% 0% 08-Jun-13 30-Jun-13 25-Jul-13 19-Aug-13 -19
A7040 Instruction to Excavate 0 0% 100% 0% 23-Jun-13 15-Sep-13 -54
A5910 Excavation up to anchors level 18 0% 55.56% 0% 23-Jun-13 13-Jul-13 15-Sep-13 05-Oct-13 -54
A5930 Installation of anchors 16 0% 12.5% 0% 02-Jul-13 20-Jul-13 24-Sep-13 12-Oct-13 -54
A5940 Excavation up to final level 16 0% 0% 0% 10-Jul-13 28-Jul-13 02-Oct-13 24-Oct-13 -52
Area with Utilities
Area with Utilities 17 100% 0% 09-Jun-13 27-Jun-13 03-Sep-13 22-Sep-13 -49
A6970 Construction of guide wall 7 0% 100% 0% 09-Jun-13 16-Jun-13 03-Sep-13 10-Sep-13 -54
A6960 Construction of secant pile wall ( services area ) 7 0% 100% 0% 12-Jun-13 19-Jun-13 07-Sep-13 14-Sep-13 -54
A6980 Construction of capping beam 7 0% 100% 0% 20-Jun-13 27-Jun-13 15-Sep-13 22-Sep-13 -49
J F M A M J J A S O N
Constructi...
Constructi...
Installati...
Running of...
Constructi...
Instructio...
Excavation...
Installati...
Excavation...
22-Sep-13,...
Constructi...
Constructi...
Constructi...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot H2
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 2
21. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
222 65.47% 32.1% 10-Feb-13 21-Aug-13 22-Jan-13 A 05-Nov-13 -61
Plots
Plots 222 65.47% 32.1% 10-Feb-13 21-Aug-13 22-Jan-13 A 05-Nov-13 -61
Plot H3
Plot H3 222 65.47% 32.1% 10-Feb-13 21-Aug-13 22-Jan-13 A 05-Nov-13 -61
Engineering
Engineering 181 100% 100% 10-Feb-13 01-Jul-13 06-Feb-13 A 12-Sep-13 -61
A4000 Receive IFC drawings 0 100% 100% 100% 10-Feb-13 06-Feb-13 A
A4010 Submittal of Design and shop drawings 5 100% 100% 100% 11-Feb-13 16-Feb-13 26-Feb-13 A 26-Feb-13 A
A4020 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 17-Feb-13 18-Feb-13 28-Feb-13 A 13-Apr-13 A
A4030 Approval of Design and shop drawings ( by DM ) 7 100% 100% 100% 10-Apr-13 25-Apr-13 15-Apr-13 A 16-Jun-13 A
A7070 Design NOC from APG 0 100% 100% 100% 11-Apr-13 18-Apr-13 A
A7080 RTA Construction NOC 0 100% 100% 100% 29-Apr-13 23-May-13 A
A6790 Obtaining Partial shoring permit 0 100% 100% 100% 25-Apr-13 17-Jun-13 A
A4040 Obtaining shoring permit 0 0% 100% 0% 01-Jul-13 12-Sep-13 -61
Authorities Approvals
Authorities Approvals 172 100% 59.85% 16-Feb-13 26-Jun-13 22-Jan-13 A 08-Sep-13 -43
Fencing / Hoarding and sign board
Fencing / Hoarding and sign board 35 100% 100% 18-Feb-13 30-Mar-13 29-Jan-13 A 13-Mar-13 A
A4130 Submittal of fence and sign board drawings 4 100% 100% 100% 18-Feb-13 21-Feb-13 29-Jan-13 A 05-Feb-13 A
A4140 Approval of drawings ( APG) 2 100% 100% 100% 23-Feb-13 24-Feb-13 06-Feb-13 A 11-Feb-13 A
A4150 Approval of drawings ( by DM ) 14 100% 100% 100% 23-Feb-13 10-Mar-13 12-Feb-13 A 04-Mar-13 A
A4160 Obtaining fencing and Hoarding permit 0 100% 100% 100% 10-Mar-13 06-Mar-13 A
A4170 Installation of fence and sign boards 17 100% 100% 100% 11-Mar-13 30-Mar-13 10-Mar-13 A 13-Mar-13 A
Temporary site office
Temporary site office 122 0% 0% 23-Feb-13 29-Apr-13 29-Jan-13 A 15-Jul-13 2
A4180 Submittal of site offices drawings 6 100% 100% 100% 23-Feb-13 28-Feb-13 29-Jan-13 A 29-Jan-13 A
A4190 Approval of site offices drawings 10 100% 100% 100% 02-Mar-13 12-Mar-13 27-Feb-13 A 04-Jun-13 A
A4200 Obtaining permit 0 0% 100% 0% 17-Apr-13 04-Jul-13 2
A4210 Installation of temporary site offices 10 0% 100% 0% 18-Apr-13 29-Apr-13 04-Jul-13 15-Jul-13 2
Site visit demarcation
Site visit demarcation 0 0% 0% 16-Feb-13 16-Feb-13 22-Jan-13 A 22-Jan-13 A
A4240 Obtaining site visit demarcation 0 100% 100% 100% 16-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 16-Feb-13 02-Mar-13 23-Jan-13 A 24-Feb-13 A
A4250 Obtaining NOC for trial trenching 0 100% 100% 100% 16-Feb-13 23-Jan-13 A
A4260 starting trial trenches at site for water, Ettisalat and sewerage 12 100% 100% 100% 17-Feb-13 02-Mar-13 12-Feb-13 A 24-Feb-13 A
Utilities Relocation
Utilities Relocation 164 100% 20% 26-Feb-13 26-Jun-13 27-Feb-13 A 08-Sep-13 -61
Electricity network relocation ( 11 KV relocation works )
Electricity network relocation ( 11 KV relocation works ) 164 100% 20% 26-Feb-13 26-Jun-13 27-Feb-13 A 08-Sep-13 -61
A6450 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 27-Feb-13 A 04-Mar-13 A
A6390 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 09-Mar-13 14-Mar-13 23-Mar-13 A 24-Mar-13 A
A6400 Obtain Approval from DEWA for shop drawing & material submittal 13 46.15% 100% 46.15% 14-Mar-13 28-Mar-13 26-Mar-13 A 11-Jul-13 -61
A6410 11kv cable exstock delivery at site 7 0% 100% 0% 30-Apr-13 07-May-13 11-Jul-13 18-Jul-13 -61
A6430 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 01-May-13 28-May-13 13-Jul-13 11-Aug-13 -49
A6460 11KV Cable Joint production & DEWA FAT Inspection and all tests 13 0% 100% 0% 01-May-13 15-May-13 13-Jul-13 27-Jul-13 -61
A6420 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 16-May-13 12-Jun-13 28-Jul-13 25-Aug-13 -61
A6440 Shut down and jointing 12 0% 100% 0% 13-Jun-13 26-Jun-13 26-Aug-13 08-Sep-13 -61
Construction Demarcation
Construction Demarcation 0 0% 0% 28-Apr-13 28-Apr-13 22-Jun-13 A 22-Jun-13 A
A4340 Obtaining Construction demarcation 0 100% 100% 100% 28-Apr-13 22-Jun-13 A
Construction
Construction 110 58.79% 23.85% 30-Apr-13 21-Aug-13 22-Jun-13 A 05-Nov-13 -61
J F M A M J J A S O N
12-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
08-Sep-13,...
13-Mar-13 ...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
15-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
24-Feb-13 ...
Obtaining ...
starting t...
08-Sep-13,...
08-Sep-13,...
Trial pit ...
Investegat...
Obtain App...
11kv cable...
Civil Work...
11KV Cable...
Dispatch c...
Shut down ...
22-Jun-13 ...
Obtaining ...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot H3
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 2
22. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A4050 Construction of guide wall 20 100% 100% 100% 30-Apr-13 22-May-13 22-Jun-13 A 30-Jun-13 A
A4060 Construction of secant pile wall 18 50.8% 100% 50.8% 08-May-13 28-May-13 27-Jun-13 A 13-Jul-13 -49
A4070 Installation of dewatering system 6 0% 100% 0% 08-May-13 14-May-13 04-Jul-13 10-Jul-13 -49
A4080 Construction of capping beam 25 0% 100% 0% 08-May-13 05-Jun-13 04-Jul-13 01-Aug-13 -6
A4100 Running of dewatering system 82 0% 51.22% 0% 15-May-13 21-Aug-13 11-Jul-13 21-Oct-13 -49
A7000 Instruction to Excavate 0 0% 0% 0% 17-Jul-13 29-Sep-13 -61
A4220 Excavation up to anchors level 15 0% 0% 0% 17-Jul-13 03-Aug-13 29-Sep-13 20-Oct-13 -61
A4110 Installation of anchors 20 0% 0% 0% 18-Jul-13 12-Aug-13 30-Sep-13 27-Oct-13 -61
A4120 Excavation up to final level 20 0% 0% 0% 27-Jul-13 20-Aug-13 08-Oct-13 05-Nov-13 -61
Area with Utilities
Area with Utilities 20 4.82% 0% 02-Jul-13 24-Jul-13 14-Sep-13 06-Oct-13 -60
A6850 Construction of guide wall 7 0% 28.57% 0% 02-Jul-13 09-Jul-13 14-Sep-13 21-Sep-13 -61
A6840 Construction of secant pile wall ( services area ) 10 0% 0% 0% 06-Jul-13 16-Jul-13 17-Sep-13 28-Sep-13 -61
A6860 Construction of capping beam 7 0% 0% 0% 17-Jul-13 24-Jul-13 29-Sep-13 06-Oct-13 -60
J F M A M J J A S O N
Constructi...
Constructi...
Installati...
Constructi...
Running of...
Instructio...
Excavation...
Installati...
06-Oct-13,...
Constructi...
Constructi...
Constructi...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot H3
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 2
23. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
245 59.74% 38.92% 22-Jan-13 20-Aug-13 12-Jan-13 A 13-Nov-13 -68
Plots
Plots 245 59.74% 38.92% 22-Jan-13 20-Aug-13 12-Jan-13 A 13-Nov-13 -68
Plot R1
Plot R1 245 59.74% 38.92% 22-Jan-13 20-Aug-13 12-Jan-13 A 13-Nov-13 -68
Engineering
Engineering 206 100% 100% 22-Jan-13 02-Jul-13 12-Jan-13 A 23-Sep-13 -70
A1480 Receive IFC drawings 0 100% 100% 100% 22-Jan-13 12-Jan-13 A
A1490 Submittal of Design and shop drawings 5 100% 100% 100% 22-Jan-13 28-Jan-13 16-Jan-13 A 16-Jan-13 A
A1510 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 29-Jan-13 30-Jan-13 17-Jan-13 A 13-Apr-13 A
A7050 Design NOC from APG 0 100% 100% 100% 10-Apr-13 10-Apr-13 A
A1520 Approval of Design and shop drawings ( by DM ) 14 100% 100% 100% 11-Apr-13 27-Apr-13 14-Apr-13 A 21-Apr-13 A
A1550 Obtaining Partial shoring permit 0 100% 100% 100% 27-Apr-13 22-Apr-13 A
A7060 RTA Construction NOC 0 100% 100% 100% 30-Apr-13 08-May-13 A
A1540 Obtaining shoring permit 0 0% 100% 0% 02-Jul-13 23-Sep-13 -70
Authorities Approvals
Authorities Approvals 192 100% 57.16% 07-Feb-13 30-Jun-13 16-Jan-13 A 23-Sep-13 -55
Fencing / Hoarding and sign board
Fencing / Hoarding and sign board 35 100% 100% 13-Feb-13 25-Mar-13 16-Jan-13 A 25-Feb-13 A
A3650 Submittal of fencing and sign board drawings 4 100% 100% 100% 13-Feb-13 17-Feb-13 16-Jan-13 A 29-Jan-13 A
A3660 Approval of drawings ( APG) 2 100% 100% 100% 18-Feb-13 19-Feb-13 30-Jan-13 A 31-Jan-13 A
A3670 Approval of drawings ( by DM ) 14 100% 100% 100% 18-Feb-13 05-Mar-13 02-Feb-13 A 14-Feb-13 A
A3680 Obtaining fencing and Hoarding permit 0 100% 100% 100% 05-Mar-13 19-Feb-13 A
A3690 Installation of fence and sign boards 17 100% 100% 100% 06-Mar-13 25-Mar-13 23-Feb-13 A 25-Feb-13 A
Temporary site office
Temporary site office 58 0% 0% 18-Feb-13 25-Apr-13 29-Jan-13 A 29-Apr-13 A
A3700 Submittal of site offices drawings 5 100% 100% 100% 18-Feb-13 23-Feb-13 29-Jan-13 A 29-Jan-13 A
A3710 Approval of site offices drawings 14 100% 100% 100% 24-Feb-13 11-Mar-13 30-Jan-13 A 27-Apr-13 A
A3720 Obtaining permit 0 100% 100% 100% 17-Apr-13 28-Apr-13 A
A3730 Installation of temporary site offices 7 100% 100% 100% 18-Apr-13 25-Apr-13 28-Apr-13 A 29-Apr-13 A
Site visit demarcation
Site visit demarcation 0 0% 0% 07-Feb-13 07-Feb-13 22-Jan-13 A 22-Jan-13 A
A3760 Obtaining site visit demarcation 0 100% 100% 100% 07-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 07-Feb-13 21-Feb-13 22-Jan-13 A 23-Jan-13 A
A3780 Obtaining NOC for trial trenching 0 100% 100% 100% 07-Feb-13 22-Jan-13 A
A3790 starting trial trenches at site for water , Ettisalat and sewerage 12 100% 100% 100% 09-Feb-13 21-Feb-13 22-Jan-13 A 23-Jan-13 A
Utilities Relocation
Utilities Relocation 192 100% 17.39% 09-Feb-13 30-Jun-13 10-Feb-13 A 23-Sep-13 -70
Electricity network relocation ( 11 KV relocation works )
Electricity network relocation ( 11 KV relocation works ) 164 100% 20% 26-Feb-13 25-Jun-13 27-Feb-13 A 08-Sep-13 -63
A3920 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 27-Feb-13 A 04-Mar-13 A
A3930 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 09-Mar-13 14-Mar-13 23-Mar-13 A 24-Mar-13 A
A3940 Obtain Approval from DEWA for shop drawing & material submittal 13 46.15% 100% 46.15% 14-Mar-13 28-Mar-13 26-Mar-13 A 11-Jul-13 -63
A3950 11kv cable exstock delivery at site 7 0% 100% 0% 29-Apr-13 06-May-13 11-Jul-13 18-Jul-13 -63
A3990 11KV Cable Joint production & DEWA FAT Inspection and all tests 13 0% 100% 0% 30-Apr-13 14-May-13 13-Jul-13 27-Jul-13 -63
A3970 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 30-Apr-13 27-May-13 13-Jul-13 11-Aug-13 -51
A3960 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 15-May-13 11-Jun-13 28-Jul-13 25-Aug-13 -63
A3980 Shut down and jointing 12 0% 100% 0% 12-Jun-13 25-Jun-13 26-Aug-13 08-Sep-13 -63
Telephone Network Relocation
Telephone Network Relocation 192 100% 0% 09-Feb-13 30-Jun-13 10-Feb-13 A 23-Sep-13 -70
A6320 Trial pit NOC 16 100% 100% 100% 09-Feb-13 26-Feb-13 10-Feb-13 A 20-Feb-13 A
A6330 Trial pit and shop drawing preparation 7 28.57% 100% 28.57% 10-Apr-13 17-Apr-13 01-Apr-13 A 09-Jul-13 -70
J F M A M J J A S O N
23-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Design NOC...
Approval o...
Obtaining ...
RTA Constr...
Obtaining ...
23-Sep-13,...
25-Feb-13 ...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
29-Apr-13 ...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
23-Jan-13 ...
Obtaining ...
starting t...
23-Sep-13,...
08-Sep-13,...
Trial pit ...
Investegat...
Obtain App...
11kv cable...
11KV Cable...
Civil Work...
Dispatch c...
Shut down ...
23-Sep-13,...
Trial pit ...
Trial pit ...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot R1
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 2
24. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A6350 Placement of order and recipt of material at site 18 0% 100% 0% 10-Apr-13 30-Apr-13 04-Jul-13 24-Jul-13 -70
A6340 Approval from Etisalat 12 0% 100% 0% 18-Apr-13 01-May-13 10-Jul-13 23-Jul-13 -69
A6360 Installation of new cable 40 0% 100% 0% 02-May-13 18-Jun-13 25-Jul-13 11-Sep-13 -70
A6370 Shutdown of existing system 5 0% 100% 0% 19-Jun-13 24-Jun-13 12-Sep-13 17-Sep-13 -70
A6380 Re-connection 5 0% 100% 0% 25-Jun-13 30-Jun-13 18-Sep-13 23-Sep-13 -70
Construction Demarcation
Construction Demarcation 0 0% 0% 29-Apr-13 29-Apr-13 25-Apr-13 A 25-Apr-13 A
A3870 Obtaining Construction demarcation 0 100% 100% 100% 29-Apr-13 25-Apr-13 A
Construction
Construction 161 51.72% 32.25% 01-May-13 20-Aug-13 08-May-13 A 13-Nov-13 -68
A1840 Construction of guide wall 23 100% 100% 100% 01-May-13 27-May-13 08-May-13 A 08-Jun-13 A
A1850 Construction of secant pile wall 25 100% 100% 100% 09-May-13 08-Jun-13 11-May-13 A 22-Jun-13 A
A1860 Installation of dewatering system 6 0% 100% 0% 09-May-13 15-May-13 04-Jul-13 10-Jul-13 -47
A1870 Construction of capping beam 23 0% 100% 0% 20-May-13 16-Jun-13 04-Jul-13 30-Jul-13 -2
A1890 Running of dewatering system 80 0% 51.25% 0% 16-May-13 20-Aug-13 11-Jul-13 19-Oct-13 -47
A6990 Instruction to Excavate 0 0% 0% 0% 15-Jul-13 06-Oct-13 -70
A1880 Excavation up to anchors level 20 0% 0% 0% 15-Jul-13 06-Aug-13 06-Oct-13 02-Nov-13 -70
A1900 Installation of anchors 20 0% 0% 0% 21-Jul-13 14-Aug-13 12-Oct-13 09-Nov-13 -70
A1910 Excavation up to final level 19 0% 0% 0% 27-Jul-13 19-Aug-13 22-Oct-13 13-Nov-13 -70
Area with Utilities
Area with Utilities 20 2.41% 0% 03-Jul-13 25-Jul-13 24-Sep-13 21-Oct-13 -66
A1930 Construction of guide wall 7 0% 14.29% 0% 03-Jul-13 10-Jul-13 24-Sep-13 01-Oct-13 -70
A1920 Construction of secant pile wall ( services area ) 10 0% 0% 0% 07-Jul-13 17-Jul-13 28-Sep-13 08-Oct-13 -70
A1940 Construction of capping beam 7 0% 0% 0% 18-Jul-13 25-Jul-13 09-Oct-13 21-Oct-13 -66
J F M A M J J A S O N
Placement ...
Approval f...
Installati...
Shutdown o...
Re-connect...
25-Apr-13 ...
Obtaining ...
Constructi...
Constructi...
Installati...
Constructi...
Running of...
Instructio...
21-Oct-13,...
Constructi...
Constructi...
Constructi...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot R1
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 2
25. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
201 81.44% 12.69% 25-Feb-13 19-Aug-13 22-Jan-13 A 24-Oct-13 -52
Plots
Plots 201 81.44% 12.69% 25-Feb-13 19-Aug-13 22-Jan-13 A 24-Oct-13 -52
Plot S1
Plot S1 201 81.44% 12.69% 25-Feb-13 19-Aug-13 22-Jan-13 A 24-Oct-13 -52
Engineering
Engineering 155 100% 100% 03-Mar-13 09-Jun-13 11-Feb-13 A 03-Sep-13 -52
A5360 Receive IFC drawings 0 100% 100% 100% 03-Mar-13 11-Feb-13 A
A5370 Submittal of Design and shop drawings 4 100% 100% 100% 10-Apr-13 14-Apr-13 30-Apr-13 A 30-Apr-13 A
A5380 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 15-Apr-13 16-Apr-13 30-Apr-13 A 02-May-13 A
A5390 Approval of Design and shop drawings ( by DM ) 14 100% 100% 100% 15-Apr-13 30-Apr-13 19-May-13 A 23-Jun-13 A
A7130 Design NOC from APG 0 100% 100% 100% 02-May-13 23-May-13 A
A7140 RTA Construction NOC 0 100% 100% 100% 16-May-13 12-Jun-13 A
A6820 Obtaining Partial shoring permit 0 100% 100% 100% 14-May-13 23-Jun-13 A
A5400 Obtaining shoring permits 0 0% 100% 0% 09-Jun-13 03-Sep-13 -52
Authorities Approvals
Authorities Approvals 154 100% 57.71% 25-Feb-13 30-May-13 22-Jan-13 A 26-Aug-13 -28
Hoarding and sign board
Hoarding and sign board 32 100% 92.5% 10-Mar-13 15-Apr-13 29-Jan-13 A 07-Jul-13 -39
A5490 Submittal of fence and sign board drawings 4 100% 100% 100% 10-Mar-13 13-Mar-13 29-Jan-13 A 05-Feb-13 A
A5500 Approval of drawings ( APG) 2 100% 100% 100% 14-Mar-13 16-Mar-13 06-Feb-13 A 11-Feb-13 A
A5510 Approval of drawings ( DM ) 6 100% 100% 100% 17-Mar-13 23-Mar-13 12-Feb-13 A 04-Mar-13 A
A5520 Obtaining Fencing and Hoarding permit 0 100% 100% 100% 23-Mar-13 06-Mar-13 A
A5530 Installation of fence and sign boards 20 85% 100% 85% 24-Mar-13 15-Apr-13 14-Mar-13 A 07-Jul-13 -39
Temporary site office
Temporary site office 115 0% 0% 14-Mar-13 19-May-13 29-Jan-13 A 27-Jul-13 -4
A5540 Submittal of site offices drawings 6 100% 100% 100% 14-Mar-13 20-Mar-13 29-Jan-13 A 29-Jan-13 A
A5550 Approval of site offices drawings 7 100% 100% 100% 15-Apr-13 25-Apr-13 01-May-13 A 04-Jun-13 A
A5560 Obtaining Permit 0 0% 100% 0% 25-Apr-13 04-Jul-13 -4
A5570 Installation of temporary site offices 20 0% 100% 0% 27-Apr-13 19-May-13 04-Jul-13 27-Jul-13 -4
Site visit demarcation
Site visit demarcation 0 0% 0% 25-Feb-13 25-Feb-13 22-Jan-13 A 22-Jan-13 A
A5600 Obtaining site visit demarcation 0 100% 100% 100% 25-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 25-Feb-13 10-Mar-13 23-Jan-13 A 10-Feb-13 A
A5610 Obtaining NOC for trial trenching 0 100% 100% 100% 25-Feb-13 23-Jan-13 A
A5620 starting trial trenches at site for water , Ettisalat and sewerage 12 100% 100% 100% 25-Feb-13 10-Mar-13 05-Feb-13 A 10-Feb-13 A
Utilities Relocation
Utilities Relocation 153 100% 20% 26-Feb-13 30-May-13 04-Mar-13 A 26-Aug-13 -52
Electricity network relocation ( 132 KV relocation works )
Electricity network relocation ( 132 KV relocation works ) 153 100% 20% 26-Feb-13 30-May-13 04-Mar-13 A 26-Aug-13 -52
A6610 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 04-Mar-13 A 04-Mar-13 A
A6550 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 09-Mar-13 14-Mar-13 10-Mar-13 A 01-Apr-13 A
A6560 Obtain Approval from DEWA for shop drawing & material submittal 13 100% 100% 100% 14-Mar-13 28-Mar-13 26-Mar-13 A 04-Jul-13 -51
A6570 132kv cable exstock delivery at site 7 0% 100% 0% 10-Apr-13 17-Apr-13 04-Jul-13 11-Jul-13 -52
A6590 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 11-Apr-13 08-May-13 06-Jul-13 01-Aug-13 -40
A6620 132KV Cable Joint production & DEWAFAT Inspection and all tests 13 0% 100% 0% 11-Apr-13 25-Apr-13 06-Jul-13 20-Jul-13 -52
A6580 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 27-Apr-13 22-May-13 21-Jul-13 18-Aug-13 -52
A6600 Shut down and jointing 7 0% 100% 0% 23-May-13 30-May-13 19-Aug-13 26-Aug-13 -52
Construction Demarcation
Construction Demarcation 0 0% 0% 16-May-13 16-May-13 23-Jun-13 A 23-Jun-13 A
A5700 Obtaining Construction demarcation 0 100% 100% 100% 16-May-13 23-Jun-13 A
Construction
Construction 84 78.18% 1.84% 18-May-13 19-Aug-13 01-Jul-13 A 24-Oct-13 -52
J F M A M J J A S O N
24-Oct-13,...
24-Oct-13,...
24-Oct-13,...
03-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
26-Aug-13,...
07-Jul-13,...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
27-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
10-Feb-13 ...
Obtaining ...
starting t...
26-Aug-13,...
26-Aug-13,...
Trial pit ...
Investegat...
Obtain App...
132kv cabl...
Civil Work...
132KV Cabl...
Dispatch c...
Shut down ...
23-Jun-13 ...
Obtaining ...
24-Oct-13,...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot S1
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 2
26. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
A5410 Construction of guide wall 14 16% 100% 16% 18-May-13 02-Jun-13 01-Jul-13 A 23-Jul-13 -39
A5420 Construction of secant pile wall 19 0% 100% 0% 26-May-13 17-Jun-13 13-Jul-13 03-Aug-13 -39
A5430 Installation of dewatering system 6 0% 100% 0% 26-May-13 01-Jun-13 13-Jul-13 18-Jul-13 -39
A5440 Construction of capping beam 24 0% 100% 0% 28-May-13 25-Jun-13 15-Jul-13 13-Aug-13 -11
A5460 Running of dewatering system 65 0% 41.54% 0% 02-Jun-13 19-Aug-13 20-Jul-13 05-Oct-13 -39
A7030 Instruction to Excavate 0 0% 100% 0% 20-Jun-13 15-Sep-13 -52
A5450 Excavation up to anchors level 20 0% 60% 0% 20-Jun-13 13-Jul-13 15-Sep-13 07-Oct-13 -52
A5470 Installation of anchors 16 0% 25% 0% 30-Jun-13 17-Jul-13 24-Sep-13 12-Oct-13 -52
A5480 Excavation up to final level 17 0% 0% 0% 07-Jul-13 25-Jul-13 01-Oct-13 24-Oct-13 -52
Area with Utilities
Area with Utilities 16 100% 0% 10-Jun-13 27-Jun-13 04-Sep-13 22-Sep-13 -45
A6940 Construction of guide wall 7 0% 100% 0% 10-Jun-13 17-Jun-13 04-Sep-13 11-Sep-13 -52
A6930 Construction of secant pile wall ( services area ) 6 0% 100% 0% 13-Jun-13 19-Jun-13 08-Sep-13 14-Sep-13 -52
A6950 Construction of capping beam 7 0% 100% 0% 20-Jun-13 27-Jun-13 15-Sep-13 22-Sep-13 -45
J F M A M J J A S O N
Constructi...
Constructi...
Installati...
Constructi...
Running of...
Instructio...
Excavation...
Installati...
Excavation...
22-Sep-13,...
Constructi...
Constructi...
Constructi...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot S1
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 2
27. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
211 85.1% 20.6% 07-Feb-13 20-Aug-13 22-Jan-13 A 20-Oct-13 -48
Plots
Plots 211 85.1% 20.6% 07-Feb-13 20-Aug-13 22-Jan-13 A 20-Oct-13 -48
Plot R1
Plot R1 0 0% 0% 07-Feb-13 07-Feb-13 22-Jan-13 A 22-Jan-13 A
Plot S2
Plot S2 197 85.1% 20.6% 24-Feb-13 20-Aug-13 22-Jan-13 A 20-Oct-13 -48
Engineering
Engineering 160 100% 100% 24-Feb-13 08-Jun-13 11-Feb-13 A 02-Sep-13 -48
A4900 Receive IFC drawings 0 100% 100% 100% 24-Feb-13 11-Feb-13 A
A4910 Submittal of Design and shop drawings 5 100% 100% 100% 10-Apr-13 15-Apr-13 24-Apr-13 A 24-Apr-13 A
A4920 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 16-Apr-13 17-Apr-13 25-Apr-13 A 05-Jun-13 A
A4930 Approval of Design and shop drawings ( by DM ) 14 100% 100% 100% 16-Apr-13 01-May-13 19-May-13 A 06-Jun-13 A
A7110 Design NOC from APG 0 100% 100% 100% 17-Apr-13 23-May-13 A
A7120 RTA Construction NOC 0 100% 100% 100% 15-May-13 06-Jun-13 A
A6810 Obtaining Partial shoring permit 0 100% 100% 100% 13-May-13 27-Jun-13 A
A4940 Obtaining shoring permit 0 0% 100% 0% 08-Jun-13 02-Sep-13 -48
Authorities Approvals
Authorities Approvals 154 100% 57.91% 25-Feb-13 30-May-13 22-Jan-13 A 26-Aug-13 -25
Fencing / Hoarding and sign board
Fencing / Hoarding and sign board 34 100% 92.5% 03-Mar-13 10-Apr-13 29-Jan-13 A 07-Jul-13 -41
A5030 Submittal of fence and sign board drawings 4 100% 100% 100% 03-Mar-13 06-Mar-13 29-Jan-13 A 05-Feb-13 A
A5040 Approval of drawings ( APG) 2 100% 100% 100% 07-Mar-13 09-Mar-13 06-Feb-13 A 11-Feb-13 A
A5050 Approval of drawings ( by DM ) 10 100% 100% 100% 07-Mar-13 18-Mar-13 12-Feb-13 A 04-Mar-13 A
A5060 Obtaining fencing and hoarding permit 0 100% 100% 100% 18-Mar-13 06-Mar-13 A
A5070 Installation of fence and sign boards 20 85% 100% 85% 19-Mar-13 10-Apr-13 14-Mar-13 A 07-Jul-13 -41
Temporary site office
Temporary site office 121 0% 0% 07-Mar-13 20-May-13 29-Jan-13 A 27-Jul-13 -1
A5080 Submittal of site offices drawings 6 100% 100% 100% 07-Mar-13 13-Mar-13 29-Jan-13 A 29-Jan-13 A
A5090 Approval of site offices drawings 10 100% 100% 100% 14-Mar-13 25-Mar-13 05-Mar-13 A 04-Jun-13 A
A5100 Obtaining permit 0 0% 100% 0% 27-Apr-13 04-Jul-13 -1
A5110 Installation of temporary site offices 20 0% 100% 0% 28-Apr-13 20-May-13 04-Jul-13 27-Jul-13 -1
Site visit demarcation
Site visit demarcation 0 0% 0% 25-Feb-13 25-Feb-13 22-Jan-13 A 22-Jan-13 A
A5140 Obtaining site visit demarcation 0 100% 100% 100% 25-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 25-Feb-13 10-Mar-13 23-Jan-13 A 04-Feb-13 A
A5150 Obtaining NOC for trial trenching 0 100% 100% 100% 25-Feb-13 23-Jan-13 A
A5160 starting trial trenches at site for water , Ettisalat and sewerage 12 100% 100% 100% 25-Feb-13 10-Mar-13 02-Feb-13 A 04-Feb-13 A
Utilities Relocation
Utilities Relocation 153 100% 20% 26-Feb-13 30-May-13 23-Jan-13 A 26-Aug-13 -48
Electricity network relocation ( 132 KV relocation works )
Electricity network relocation ( 132 KV relocation works ) 153 100% 20% 26-Feb-13 30-May-13 23-Jan-13 A 26-Aug-13 -48
A6530 Trial pit NOC 9 100% 100% 100% 26-Feb-13 07-Mar-13 23-Jan-13 A 29-Jan-13 A
A6470 Investegation , finding services ,Trial pit verification and shop drawing preparation
6 100% 100% 100% 09-Mar-13 14-Mar-13 10-Mar-13 A 01-Apr-13 A
A6480 Obtain Approval from DEWA for shop drawing & material submittal 0 0% 100% 0% 10-Apr-13 10-Apr-13 27-Jun-13 A 04-Jul-13 -47
A6490 132kv cable exstock delivery at site 7 0% 100% 0% 10-Apr-13 17-Apr-13 04-Jul-13 11-Jul-13 -48
A6510 Civil Works - Excavation, Concrete trough installation, Cable laying, cover placing, backfilling and HV Tests
24 0% 100% 0% 11-Apr-13 08-May-13 06-Jul-13 01-Aug-13 -36
A6540 132KV Cable Joint production & DEWAFAT Inspection and all tests 13 0% 100% 0% 11-Apr-13 25-Apr-13 06-Jul-13 20-Jul-13 -48
A6500 Dispatch clearance, Documentation & Transportation of metrial to reach in hand
23 0% 100% 0% 27-Apr-13 22-May-13 21-Jul-13 18-Aug-13 -48
A6520 Shut down and jointing 7 0% 100% 0% 23-May-13 30-May-13 19-Aug-13 26-Aug-13 -48
Construction Demarcation
Construction Demarcation 0 0% 0% 14-May-13 14-May-13 23-Jun-13 A 23-Jun-13 A
A5240 Obtaining Construction demarcation 0 100% 100% 100% 14-May-13 23-Jun-13 A
J F M A M J J A S O N
20-Oct-13,...
20-Oct-13,...
22-Jan-13 ...
20-Oct-13,...
02-Sep-13,...
Receive IF...
Submittal ...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
Obtaining ...
26-Aug-13,...
07-Jul-13,...
Submittal ...
Approval o...
Approval o...
Obtaining ...
Installati...
27-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
04-Feb-13 ...
Obtaining ...
starting t...
26-Aug-13,...
26-Aug-13,...
Trial pit ...
Investegat...
Obtain App...
132kv cabl...
Civil Work...
132KV Cabl...
Dispatch c...
Shut down ...
23-Jun-13 ...
Obtaining ...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot S2
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 2
28. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Construction
Construction 80 82.32% 10.5% 16-May-13 20-Aug-13 01-Jul-13 A 20-Oct-13 -48
A4950 Construction of guide wall 16 100% 100% 100% 16-May-13 03-Jun-13 01-Jul-13 A 02-Jul-13 A
A4960 Construction of secant pile wall 18 3.4% 100% 3.4% 25-May-13 15-Jun-13 02-Jul-13 A 31-Jul-13 -41
A4970 Installation of dewatering system 6 0% 100% 0% 25-May-13 30-May-13 13-Jul-13 18-Jul-13 -41
A5000 Running of dewatering system 67 0% 41.79% 0% 01-Jun-13 20-Aug-13 20-Jul-13 07-Oct-13 -41
A4980 Construction of capping beam 17 0% 100% 0% 03-Jun-13 23-Jun-13 21-Jul-13 11-Aug-13 -8
A7020 Instruction to Excavate 0 0% 100% 0% 22-Jun-13 16-Sep-13 -48
A4990 Excavation up to anchors level 17 0% 64.71% 0% 22-Jun-13 10-Jul-13 16-Sep-13 05-Oct-13 -48
A5010 Installation of anchors 14 0% 35.71% 0% 29-Jun-13 14-Jul-13 23-Sep-13 08-Oct-13 -48
A5020 Excavation up to final level 15 0% 0% 0% 04-Jul-13 21-Jul-13 29-Sep-13 20-Oct-13 -48
Area with Utilities
Area with Utilities 18 100% 0% 09-Jun-13 29-Jun-13 03-Sep-13 23-Sep-13 -44
A6910 Construction of guide wall 7 0% 100% 0% 09-Jun-13 16-Jun-13 03-Sep-13 10-Sep-13 -48
A6900 Construction of secant pile wall ( services area ) 8 0% 100% 0% 12-Jun-13 20-Jun-13 07-Sep-13 15-Sep-13 -48
A6920 Construction of capping beam 7 0% 100% 0% 22-Jun-13 29-Jun-13 16-Sep-13 23-Sep-13 -44
J F M A M J J A S O N
20-Oct-13,...
Constructi...
Constructi...
Installati...
Running of...
Constructi...
Instructio...
Excavation...
Installati...
Excavation...
23-Sep-13,...
Constructi...
Constructi...
Constructi...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot S2
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 2
29. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013)
220 98.82% 60.89% 30-Jan-13 21-Aug-13 22-Jan-13 A 21-Oct-13 -49
Plots
Plots 220 98.82% 60.89% 30-Jan-13 21-Aug-13 22-Jan-13 A 21-Oct-13 -49
Plot S3
Plot S3 220 98.82% 60.89% 30-Jan-13 21-Aug-13 22-Jan-13 A 21-Oct-13 -49
Engineering
Engineering 77 100% 100% 30-Jan-13 29-Apr-13 23-Jan-13 A 22-May-13 A
A1040 Receive IFC drawings 0 100% 100% 100% 30-Jan-13 23-Jan-13 A
A1060 Submittal of Method Statement 5 100% 100% 100% 06-Feb-13 11-Feb-13 30-Jan-13 A 07-Feb-13 A
A1050 Submittal of Design and shop drawings 5 100% 100% 100% 06-Feb-13 11-Feb-13 31-Jan-13 A 31-Jan-13 A
A1090 Approval of method statement ( ByAPG ) 2 100% 100% 100% 12-Feb-13 13-Feb-13 02-Feb-13 A 07-Feb-13 A
A1070 Approval of Design and shop drawings ( byAPG ) 2 100% 100% 100% 10-Apr-13 11-Apr-13 03-Feb-13 A 13-Apr-13 A
A1080 Approval of Design and shop drawings ( by DM ) 14 100% 100% 100% 10-Apr-13 25-Apr-13 14-Apr-13 A 28-Apr-13 A
A1230 Design NOC from APG 0 100% 100% 100% 11-Apr-13 15-Apr-13 A
A1270 RTA Construction NOC 0 100% 100% 100% 27-Apr-13 08-May-13 A
A1100 Obtaining shoring permit 0 100% 100% 100% 29-Apr-13 22-May-13 A
Authorities Approvals
Authorities Approvals 154 100% 94.27% 30-Jan-13 05-May-13 22-Jan-13 A 29-Jul-13 -5
Fencing /Hoarding and sign board
Fencing /Hoarding and sign board 34 100% 92.5% 10-Feb-13 20-Mar-13 29-Jan-13 A 08-Jul-13 13
A1110 Submittal of fence and sign board drawings 3 100% 100% 100% 10-Feb-13 12-Feb-13 29-Jan-13 A 31-Jan-13 A
A1120 Approval of drawings ( APG) 2 100% 100% 100% 13-Feb-13 14-Feb-13 02-Feb-13 A 11-Feb-13 A
A1140 Obtaining fencing and Hoarding permit 0 100% 100% 100% 28-Feb-13 06-Feb-13 A
A1130 Approval of drawings ( by DM ) 14 100% 100% 100% 13-Feb-13 28-Feb-13 12-Feb-13 A 04-Mar-13 A
A1150 Installation of fence and sign boards 17 85% 100% 85% 02-Mar-13 20-Mar-13 14-Mar-13 A 08-Jul-13 13
Temporary site office
Temporary site office 77 0% 0% 30-Jan-13 29-Apr-13 29-Jan-13 A 12-May-13 A
A1160 Submittal of site offices drawings 6 100% 100% 100% 30-Jan-13 05-Feb-13 29-Jan-13 A 29-Jan-13 A
A1170 Approval of site offices drawings 10 100% 100% 100% 10-Apr-13 21-Apr-13 01-Apr-13 A 30-Apr-13 A
A1180 Obtaining permit 0 100% 100% 100% 21-Apr-13 07-May-13 A
A1190 Installation of temporary site offices 7 100% 100% 100% 22-Apr-13 29-Apr-13 08-May-13 A 12-May-13 A
Permanent office
Permanent office 145 0% 0% 10-Feb-13 05-May-13 11-Feb-13 A 29-Jul-13 -12
A1200 Submit a proposal of permanent offices 2 100% 100% 100% 10-Feb-13 11-Feb-13 11-Feb-13 A 11-Feb-13 A
A1210 Approval of proposal ( APG ) 2 100% 100% 100% 12-Feb-13 13-Feb-13 12-Feb-13 A 04-Jul-13 -12
A1360 Approval of proposal ( DM ) 12 0% 100% 0% 10-Apr-13 23-Apr-13 04-Jul-13 17-Jul-13 -12
A1370 Obtaining permit 0 0% 100% 0% 23-Apr-13 17-Jul-13 -12
A1380 Installation of permanent offices 10 0% 100% 0% 24-Apr-13 05-May-13 18-Jul-13 29-Jul-13 -12
Site visit demarcation
Site visit demarcation 0 0% 0% 03-Feb-13 03-Feb-13 22-Jan-13 A 22-Jan-13 A
A1220 Obtaining site visit demarcation 0 100% 100% 100% 03-Feb-13 22-Jan-13 A
NOC for trial trenches
NOC for trial trenches 12 100% 100% 03-Feb-13 17-Feb-13 22-Jan-13 A 04-Feb-13 A
A1250 Obtaining NOC for trial trenching 0 100% 100% 100% 03-Feb-13 22-Jan-13 A
A1260 starting trial trenches at site for water , ettisalat and sewerage 12 100% 100% 100% 04-Feb-13 17-Feb-13 02-Feb-13 A 04-Feb-13 A
Mobilization permit
Mobilization permit 0 0% 0% 28-Feb-13 28-Feb-13 25-Feb-13 A 25-Feb-13 A
A1350 Obtaining mobilization permit 0 100% 100% 100% 28-Feb-13 25-Feb-13 A
Construction Demarcation
Construction Demarcation 0 0% 0% 25-Apr-13 25-Apr-13 08-May-13 A 08-May-13 A
A1340 Obtaining Construction demarcation 0 100% 100% 100% 25-Apr-13 08-May-13 A
Mobilization
Mobilization 15 100% 100% 02-Mar-13 18-Mar-13 26-Feb-13 A 28-May-13 A
A1390 Mobilization of tools and equipments 15 100% 100% 100% 02-Mar-13 18-Mar-13 26-Feb-13 A 28-May-13 A
J F M A M J J A S O N
21-Oct-13,...
21-Oct-13,...
21-Oct-13,...
22-May-13 ...
Receive IF...
Submittal ...
Submittal ...
Approval o...
Approval o...
Approval o...
Design NOC...
RTA Constr...
Obtaining ...
29-Jul-13,...
08-Jul-13,...
Submittal ...
Approval o...
Obtaining ...
Approval o...
Installati...
12-May-13 ...
Submittal ...
Approval o...
Obtaining ...
Installati...
29-Jul-13,...
Submit a p...
Approval o...
Approval o...
Obtaining ...
Installati...
22-Jan-13 ...
Obtaining ...
04-Feb-13 ...
Obtaining ...
starting t...
25-Feb-13 ...
Obtaining ...
08-May-13 ...
Obtaining ...
28-May-13 ...
Mobilizati...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot S3
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 2
30. Activity ID Activity Name Original
Duration
Activity
%
Complete
Schedule
%
Complete
Performance
%
Complete
BL Project
Start
BL Project
Finish
Start Finish Total
Float
Construction
Construction 143 98.28% 43.13% 30-Apr-13 21-Aug-13 14-May-13 A 21-Oct-13 -49
A1400 Construction of guide wall 14 100% 100% 100% 30-Apr-13 15-May-13 14-May-13 A 27-May-13 A
A1410 Construction of secant pile wall 15 91% 100% 91% 08-May-13 25-May-13 25-May-13 A 06-Jul-13 2
A1420 Installation of dewatering system 6 0% 100% 0% 08-May-13 14-May-13 04-Jul-13 10-Jul-13 -49
A1430 Construction of capping beam 17 0% 100% 0% 14-May-13 02-Jun-13 04-Jul-13 23-Jul-13 -4
A1500 Instruction to Excavate 0 0% 100% 0% 25-May-13 06-Jul-13 2
A1450 Running of dewatering system 82 0% 51.22% 0% 15-May-13 21-Aug-13 11-Jul-13 21-Oct-13 -49
A1440 Excavation up to anchors level 20 0% 100% 0% 25-May-13 17-Jun-13 13-Jul-13 04-Aug-13 -4
A1460 Installation of anchors 19 0% 100% 0% 02-Jun-13 24-Jun-13 30-Jul-13 22-Aug-13 -12
A1470 Excavation up to final level 18 0% 100% 0% 11-Jun-13 01-Jul-13 07-Aug-13 29-Aug-13 -12
J F M A M J J A S O N
21-Oct-13,...
Constructi...
Constructi...
Installati...
Constructi...
Instructio...
Running of...
Excavation...
Installati...
Excavation...
Al Jaddaf Hotels and Apartments- Dubai - Shoring Works- (4.7.2013) Plot S3
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary