SlideShare a Scribd company logo
1 of 85
Download to read offline
© 2014 : Prof JJ Smallwood
1
PROF JOHN SMALLWOOD
DEPT. OF CONSTRUCTION MANAGEMENT
NELSON MANDELA METROPOLITAN UNIVERSITY
SOUTH AFRICA
COUNCIL FOR THE BUILT ENVIRONMENT
INCORPORATION OF CONSTRUCTION HEALTH AND SAFETY (H&S)
INTO TERTIARY BUILT ENVIRONMENT EDUCATION
WORKSHOP, PORT ELIZABETH, 19 SEPTEMBER 2014
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
2
Introduction (1)
 According to the Construction Industry Development (cidb)
(2009), during visits to 1 415 construction sites by Department
of Labour (DoL) inspectors:
 1 388 notices were issued:
 86 (6%) improvement notices
 1 015 (73%) contravention notices
 287 (21%) prohibition notices
 Furthermore, 52.5% of contractors were non-compliant
 The disabling injury frequency rate (DIIR) is a rate, per
200 000 hours worked, of disabling injuries due to all causes
i.e. per 100 workers x 2 000 hrs / yr:
 0.98 (cidb, 2009)
 Fatality rate per 100 000 workers: 25.5 (cidb, 2009)
© 2014 : Prof JJ Smallwood
3
Introduction (2)
Construction H&S occurs in a macro environment:
Figure 1: Construction H&S – the macro environment (Smallwood, 1995)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
4
Introduction (3)
 151 / 450 (33.6%) cases of death and disabling of construction
workers in the USA, the hazard that contributed to the incident
could have been eliminated or reduced if design-for-H&S
measures had been implemented (Behm, 2006)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
5
Injaka Bridge collapse (1)
Injaka Bridge collapse, Mpumalanga, July, 1998 (Travers, 1998)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
Injaka Bridge collapse (2)
Department of Labour (2002):
 Causes:
 The slide path was not under the webs
 The placing of the sliding pads between the deck and temporary
bearings was not as specified
 Insufficient reinforcement in the deck section, especially the bottom
slab
 The failure to fully appreciate the implications of the early cracks
 The acceptance and approval of a launching nose which was
substantially less stiff than that prescribed in the project specification
 The deviation from the project specification regarding the automatic
pier deflection monitoring at pier 2
 The deviation from the project specification regarding the height
tolerances of the temporary bearings on pier 3
 The use of design and construction personnel, at decision-making
level, without appropriate qualification and experience in incremental
launched bridges
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
Injaka Bridge collapse (3)
 No independent design reviews were conducted of either the
temporary or permanent works
 Contributory causes:
 The lack of experience on the part of design personnel in
incremental launching techniques resulted in poor
communications between the parties to clarify understandings
and interpretations regarding the slide path position
 The lack of clear instructions in the project specification and
clear indications on the consulting engineers design drawings
as to the position of the sliding path, resulted in incorrect
interpretations being made
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
H&S is a profit centre not a ‘cost’
 Based upon the value of construction work completed in the
year 2002, namely R 56 343m (South African Reserve Bank,
2003) the total COA could have been between 4.3%
(R 2 401.2m / R 56 343m), and 5.4% (R 3 041.5m / R 56 343m)
(Smallwood, 2004a; cidb, 2009)
 Cost of prevention is:
 Between 0.5% and 3% of project costs (Smallwood, 2004a)
 1.6% of tender cost estimate and 1% of project cost (Smallwood,
2011a)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
9
Importance of the project parameters
Parameter
Architects Arch. Tech’s Mean
Mean
Score
Rank Mean
Score
Rank Mean
Score
Rank
Project quality 4.74 1 4.59 1 4.67 1
End-user ergonomics 4.29 3 4.46 3 4.38 2
Environment 4.25 4 4.49 2 4.37 3=
Project cost 4.38 2 4.35 5 4.37 3=
Project time 4.20 5 4.38 4 4.29 5
Project health and safety (H&S) 3.94 6 4.19 6 4.07 6
Construction ergonomics 3.58 4 3.92 7 3.75 7
Table 1: Importance of project parameters to Architectural practices and Architectural Technologists
(MS: 1.00 – 5.00) (Smallwood, 2009a).
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
10
Designing and safety (1)
Natural-light openings, Port Elizabeth (Smallwood)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
11
Designing and safety (2)
‘Open’ precast concrete cladding, Port Elizabeth (Smallwood)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
12
Designing for safety
‘Balustrade’ precast concrete cladding, Cape Town (Smallwood)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
13
Designing for ergonomics and H&S (1)
Precast concrete stair flights, Port Elizabeth (Smallwood)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
14
Designing for ergonomics and H&S (2)
Precast concrete stair flights, Port Elizabeth (Smallwood)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
15
Designing and ergonomics and OH
‘Bush-hammered’ concrete, Port Elizabeth (Smallwood)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
16
Designing for ergonomics and OH
Thermal Lance, Mount Road Police Station, Port Elizabeth (Smallwood, 1987)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
17
Designing and ergonomics
Face brick lining to semi-circular RC soffit, Sandton (Smallwood)
© 2014 : Prof JJ Smallwood
18
Integration of design and construction (1)
 Two issues - influence of design on construction H&S, and
the type of procurement system
 Design influences construction directly and indirectly:
 Directly, through design, choice of structural frame, details, method
of fixing, constructability, and specification of materials and finishes
 Indirectly, through choice of procurement system and conditions of
contract, procurement, decision regarding project duration, and
reference to H&S on various occasions
 Certain procurement systems such as design-build promote
the integration of design and construction
 Optimum integration engenders and enhances H&S as it
facilitates contractor contributions to the design process
 Designing for H&S is one of sixteen design for
constructability principles – contractors can contribute
© 2014 : Prof JJ Smallwood
19
Integration of design and construction (2)
Figure 2: Elevation of masonry Bridge over the Tweed at Coldstream, 1866 (Irwin and Sibbald, 1983)
© 2014 : Prof JJ Smallwood
20
Integration of design and construction (3)
Figure 3: Centering for masonry Bridge over the Tweed at Coldstream, 1866 (Irwin and Sibbald, 1983)
© 2014 : Prof JJ Smallwood
21
Integration of design and construction (4)
Bloukrans Bridge (p. 11, Concrete Beton, 1983)
© 2014 : Prof JJ Smallwood
22
Integration of design and construction (5)
Bloukrans Bridge (Inside Front, Concrete Beton, 1983)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
23
Integration of design and construction (6)
Bloukrans bridge project (Steele, 1983):
 “…notable for the close cooperation and team effort which
were achieved by the consultant and contractor, and
encouragement given by the client.”
 “… consulting engineers had clearly indicated in their
design how the task should be tackled and worked closely
with the contractors in converting the drawings they had
supplied to reality…”
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
24
Construction Regulations (1)
 Definition of ‘designer’ – a competent person who:
 prepares a design
 checks and approves a design
 arranges for a person at work under his / her control to prepare a
design including an employee of that person
 designs temporary work including its components
 An architect or engineer contributing to, or having overall
responsibility for a design
 Building services engineer designing details for fixed plant
 Surveyor specifying articles or drawing up specifications
 Contractor carrying out design work as part of a design and
build project
 Interior designer, shop-fitter, or landscape architect
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
25
Construction Regulations (2)
Relative to Structures 6 (1) designers of a structure must:
 (a) ensure that the H&S standards incorporated into the
regulations are complied with in the design
 (b) take the H&S specification into consideration
 (c) include in a report to the client before tender stage:
 all relevant H&S information about the design that may affect the
pricing of the work
 the geotechnical-science aspects
 the loading that the structure is designed to withstand
 (d) inform the client of any known or anticipated dangers or
hazards relating to the construction work, and make available
all relevant information required for the safe execution of the
work upon being designed or when the design is changed
 (e) modify the design or make use of substitute materials
where the design necessitates the use of dangerous
procedures or materials hazardous to H&S
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
26
Construction Regulations (3)
 (f) consider hazards relating to subsequent maintenance of
the structure and make provision in the design for that work
to be performed to minimize the risk
 (g) when mandated by the client conduct inspections to
ensure conformance of construction to design. If not
mandated then the client’s agent is responsible
 (h) when mandated by the client stop construction work not in
accordance with the design’s H&S aspects. If not mandated
then the client’s agent is responsible
 (i) when mandated by the client, during his / her final
inspection of the structure include the H&S aspects of the
structure, declare the structure safe for use and issue a
completion certificate
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
27
Construction Regulations (4)
Clients required to, among other:
 5 (1) (a) Prepare a baseline risk assessment (BRA)
 5 (1) (b) Prepare an H&S specification based on the BRA
 5 (1) (c) Provide the designer with the H&S specification
 5 (1) (d) Ensure that the designer takes the H&S specification
into account during design
 5 (1) (e) Ensure that the designer carries out the duties in
Regulation 6 ‘Duties of designers’
 5 (1) (f) Include the H&S specification (revised after the
designers’ reports?) in the tender documents
 5 (1) (g) Ensure that potential PCs have made provision for the
cost of H&S in their tenders
 5 (1) (h) Ensure that the PC to be appointed has the necessary
competencies and resources
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
28
Influence of designers (1)
 Directly:
 Concept design
 General design
 Choice of structural frame
 Details
 Provision for services (construction ergonomics)
 Specification of materials, finishes and processes
 Consideration of H&S:
 During design coordination
 During constructability reviews
 Reference to H&S:
 During pre-tender site visit
 Upon site handover
 During site visits / inspections
 During site visits / meetings
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
29
 Indirectly:
 Selection of / advice regarding type of procurement system
 Selection of / advice regarding preparation of contract
documentation
 Decision regarding / advice with respect to project duration
 Status of design upon commencement of construction (contractor
pre-planning)
 H&S prequalification of contractors
 Site location e.g. exposure to elements, power lines etc.
 Site coverage e.g. availability for storage
Influence of designers (2)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
30
General design (1)
 Shape of structure i.e. irregular plan shape
 Pitch of roof i.e. high pitch
 Over sailing sections (access to soffit / working overhead)
 External work and finishes (elevated work to facades)
 Position of ablutions relative to municipal services (depth of
excavations)
 Pre-fabrication, pre-assembly and pre-casting:
 Reduces elevated in-situ work
 Reduces manual handling
 Engenders mechanisation
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
31
General design (2)
Bahia Temple, Delhi, India (Smallwood, 2005)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
General design (3)
Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
General design (4)
Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
General design (5)
Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
General design (6)
Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
General design (7)
Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
General design (8)
Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
General design (9)
Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
39
General design (10)
Investec Office Complex scaffolding collapse, Sandton, August, 1997 (Prinsloo, 1997)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
40
General design (11)
Precast wall panels, Dublin (Smallwood, 2004)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
41
General design (12)
Precast floor panels, Dublin (Smallwood, 2004)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
42
Choice of structural frame (1)
 Load bearing masonry:
 Mass of materials
 Manual handling / Bending and twisting
 On-site storage (housekeeping!)
 Timber frame:
 Pre-fabrication
 Light weight
 Less on-site storage = enhanced housekeeping
 Less manual handling
 Engenders mechanisation
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
43
 Structural steel:
 Less on-site storage = enhanced housekeeping
 Pre-assembly
 Less manual handling
 Very challenging elevated work
 Reinforced concrete:
 On-site storage (housekeeping!)
 Manual handling / Bending and twisting / Use of body force
 Challenging elevated work
Choice of structural frame (2)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
44
Details (1)
 Affect constructability
 Affect work method
 Affect work postures
 Affect required plant and equipment
 May require access
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
45
Details (2)
Externally installed full fenestration, Dublin (Smallwood, 2004)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
46
Details (3)
Externally installed full fenestration, Dublin (Smallwood, 2004)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
47
Provision for services (1)
 Affects construction ergonomics:
 No. of services e.g. in ceiling
 Layering (horizontal plane)
 Space for working and fixing e.g. in vertical ducts
 Method of fixing
 Therefore, optimum:
 Coordination
 Layering
 Sectional area (vertical ducts)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
48
Provision for services (2)
Congested ceiling space, Cape Town (Smallwood, 2004)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
49
Provision for services (3)
Congested ceiling space, Cape Town (Smallwood, 2004)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
50
Position of fittings (1)
Porte Cochere, Nelspruit Airport (Smallwood, 2004)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
51
Position of fittings (2)
Light fittings, Porte Cochere, Nelspruit Airport (Smallwood, 2004)
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
52
Materials (1)
May be / have:
 Heavy - mass per unit / m / m2 / m3
 Rough surface
 Sharp edges
 Toxic
 Large e.g. ceiling / drywall panels and glass shop fronts
© 2003 : Prof JJ Smallwood
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
53
Materials (2)
‘Melting’ mastic asphalt, Canal Walk, Cape Town (Smallwood, 2000)
© 2014 : Prof JJ Smallwood
54
Impact of design(ers) (1)
Occasion
Response (%)
II RankDon’t
know
Never Rarely
Some-
times
Often Always
Site inspections/ discussions 0.0 28.3 28.3 28.3 28.3 28.3 2.64 1
Site meetings 0.0 28.3 28.3 28.3 28.3 28.3 2.56 2
Site handover 1.0 28.3 28.3 28.3 28.3 28.3 2.50 3
Preparing project documentation 1.0 28.3 28.3 28.3 28.3 28.3 2.24 4
Pre-tender meeting 1.0 28.3 28.3 28.3 28.3 28.3 2.19 5
Working drawings 1.0 28.3 28.3 28.3 28.3 28.3 2.18 6
Evaluating tenders 2.0 28.3 28.3 28.3 28.3 28.3 2.13 7
Detailed design 1.0 28.3 28.3 28.3 28.3 28.3 2.12 8
Pre-qualifying contractors 1.0 28.3 28.3 28.3 28.3 28.3 2.08 9
Constructability reviews 4.1 28.3 28.3 28.3 28.3 28.3 2.05 10
Design coordination meetings 1.0 28.3 28.3 28.3 28.3 28.3 1.90 11
Client meetings 2.0 28.3 28.3 28.3 28.3 28.3 1.88 12
Concept (design) 1.0 28.3 28.3 28.3 28.3 28.3 1.82 13
Deliberating project duration 4.2 28.3 28.3 28.3 28.3 28.3 1.77 14
Table 2: Frequency at which Architectural practices consider / refer to H&S on various occasions (II: 0 - 4)
(Smallwood, 2000).
© 2014 : Prof JJ Smallwood
55
Impact of design(ers) (2)
Occasion
Response (%)
II RankDon’t
know
Never Rarely
Some-
times
Often Always
Site meetings 0.0 0.0 2.1 12.4 35.1 50.5 3.34 1
Site inspections / discussions 0.0 1.0 1.0 13.4 41.2 43.3 3.25 2
Site handover 1.0 1.0 6.3 12.5 28.1 51.0 3.20 3
Preparing project documentation 0.0 1.0 4.1 18.6 33.0 43.3 3.13 4
Detailed design 0.0 2.1 13.5 24.0 31.3 29.2 2.72 5
Working drawings 1.0 1.0 18.6 22.7 33.0 23.7 2.58 6
Pre-tender meeting 1.0 4.2 20.8 18.8 30.2 25.0 2.49 7
Constructability reviews 2.1 2.1 17.5 24.7 37.1 16.5 2.44 8
Concept (design) 0.0 4.1 14.4 35.1 28.9 17.5 2.41 9
Client meetings 0.0 4.1 12.4 41.2 32.0 10.3 2.32 10
Design coordination meetings 0.0 3.1 17.5 41.2 25.8 12.4 2.27 11
Evaluating tenders 0.0 9.4 29.2 22.9 25.0 13.5 2.04 12
Deliberating project duration 4.1 9.3 25.8 29.9 26.8 4.1 1.82 13
Pre-qualifying contractors 3.2 13.7 28.4 20.0 26.3 8.4 1.81 14
Table 3: Frequency at which Engineering practices consider / refer to H&S on various occasions (II: 0 - 4)
(Smallwood, 2004b).
© 2014 : Prof JJ Smallwood
56
Impact of design(ers) (3)
Aspect
Response (%)
II RankDon’t
know
Never Rarely
Some-
times
Often Always
Specification 2.0 26.3 26.3 26.3 26.3 26.3 2.54 1
Method of fixing 1.0 26.3 26.3 26.3 26.3 26.3 2.53 2
Position of components 4.0 26.3 26.3 26.3 26.3 26.3 2.40 3
Edge of materials 4.0 26.3 26.3 26.3 26.3 26.3 2.36 4
Content of materials 2.0 26.3 26.3 26.3 26.3 26.3 2.34 5
Details 3.1 26.3 26.3 26.3 26.3 26.3 2.31 6
Finishes 4.1 26.3 26.3 26.3 26.3 26.3 2.28 7
Type of structural frame 4.0 26.3 26.3 26.3 26.3 26.3 2.26 8
Plan layout 5.1 26.3 26.3 26.3 26.3 26.3 2.22 9
Texture of materials 3.0 26.3 26.3 26.3 26.3 26.3 2.15 10
Design (general) 1.0 26.3 26.3 26.3 26.3 26.3 2.07 11
Schedule 6.2 26.3 26.3 26.3 26.3 26.3 2.03 12
Surface area of materials 6.1 26.3 26.3 26.3 26.3 26.3 2.03 13
Elevations 5.1 26.3 26.3 26.3 26.3 26.3 1.98 14
Site location 3.0 26.3 26.3 26.3 26.3 26.3 1.90 15
Mass of materials 5.1 26.3 26.3 26.3 26.3 26.3 1.87 16
Table 4: Frequency of which Architectural practices consider / refer to H&S relative to various design related
aspects (II: 0 - 4) (Smallwood, 2000).
© 2014 : Prof JJ Smallwood
57
Impact of design(ers) (4)
Aspect
Response (%)
II RankDon’t
know
Never Rarely
Some-
times
Often Always
Specification 1.0 3.1 8.2 8.2 35.1 44.3 3.07 1
Method of fixing 3.1 3.1 6.2 14.4 34.0 39.2 2.94 2
Design (general) 1.0 0.0 10.4 21.9 38.5 28.1 2.82 3
Details 1.0 4.2 14.6 19.8 33.3 27.1 2.63 4
Type of structural frame 10.4 8.3 8.3 15.6 19.8 37.5 2.49 5
Position of components 5.2 7.2 13.4 18.6 36.1 19.6 2.37 6
Content of material 5.2 7.2 9.3 32.0 25.8 20.6 2.33 7
Plan layout 6.2 7.2 11.3 22.7 35.1 17.5 2.32 8
Site location 4.1 9.3 17.5 18.6 27.8 22.7 2.29 9
Schedule 4.1 10.3 13.4 28.9 28.9 14.4 2.15 10
Elevations 7.2 9.3 18.6 19.6 28.9 16.5 2.10 11
Mass of materials 8.3 7.3 18.8 24.0 24.0 17.7 2.09 12
Edge of materials 8.2 8.2 15.5 32.0 22.7 13.4 2.01 13
Finishes 4.1 11.3 18.6 33.0 23.7 9.3 1.93 14
Surface area of materials 8.3 12.5 22.9 29.2 16.7 10.4 1.73 15
Texture of materials 9.3 11.3 25.8 29.9 14.4 9.3 1.66 16
Table 5: Frequency of which Engineering practices consider / refer to H&S relative to various design related
aspects (II: 0 - 4) (Smallwood, 2004b).
© 2014 : Prof JJ Smallwood
58
Impact of design(ers) (5)
Table 6: Frequency at which Architectural practices and Architectural Technologists consider / refer to
construction ergonomics on various occasions (MS: 1.00 – 5.00) (Smallwood, 2009a).
Occasion (Stream)
Architects Arch. Tech’s Mean
Mean
Score
Rank
Mean
Score
Rank
Mean
Score
Rank
Detailed design (Upstream) 3.83 1 3.30 2= 3.57 1
Working drawings (Upstream) 3.65 2 3.32 1 3.49 2
Concept (design) (Upstream) 3.61 3 3.30 2= 3.46 3
Preparing project documentation 3.46 4 2.81 5 3.14 4
Site inspections/discussions 3.38 5 2.84 4 3.11 5
Site meetings 3.35 6 2.73 6 3.04 6
Design coordination meetings 3.32 7 2.65 7 2.99 7
Client meetings 2.97 9 2.54 8 2.76 8
Constructability reviews 3.06 8 2.41 9 2.74 9
Site handover 2.80 10 2.16 10 2.48 10
Deliberating project duration 2.76 11 1.86 12= 2.31 11
Pre-qualifying contractors 2.51 13 1.97 11 2.24 12
Pre-tender meeting 2.57 12 1.78 14 2.18 13=
Evaluating tenders 2.50 14 1.86 12= 2.18 13=
© 2014 : Prof JJ Smallwood
59
Impact of design(ers) (6)
Table 7: Frequency at which Architectural practices and Architectural Technologists consider / refer to
construction ergonomics relative to various design related aspects (MS: 1.00 – 5.00)
(Smallwood, 2009a).
Aspect
Architects Arch. Tech’s Mean
Mean
Score
Rank
Mean
Score
Rank
Mean
Score
Rank
Plan layout 3.81 1 3.38 1= 3.60 1
Design (general) 3.75 3 3.38 1= 3.57 2
Details 3.78 2 2.97 6 3.38 3
Method of fixing 3.67 4 3.03 4 3.35 4
Specification 3.63 5 3.00 5 3.32 5
Position of components 3.38 7 2.97 7 3.18 6
Elevations 3.18 10 3.16 3 3.17 7
Finishes 3.50 6 2.65 11 3.08 8
Type of structural frame 3.17 11 2.92 9 3.05 9
Site location 2.96 14 2.95 8 2.96 10
Schedule 3.04 12 2.81 10 2.93 11=
Edge of materials 3.24 8 2.62 12 2.93 11=
Texture of materials 3.21 9 2.38 15 2.80 13
Content of material 3.01 13 2.54 13 2.78 14
Surface area of materials 2.79 15 2.41 14 2.60 15
Mass of materials 2.54 16 2.35 16 2.45 16
© 2014 : Prof JJ Smallwood
60
Impact of design(ers) (7)
Table 8: Extent to which various design related aspects impact on construction ergonomics according to
Architectural practices and Architectural Technologists (MS: 1.00 – 5.00) (Smallwood, 2009a).
Aspect
Architects Arch. Tech’s Mean
Mean
Score
Rank
Mean
Score
Rank
Mean
Score
Rank
Design (general) 3.83 1 4.08 2 3.96 1
Details 3.72 2 4.05 4 3.89 2
Plan layout 3.57 4 4.08 3 3.83 3
Position of components 3.50 5 4.03 5 3.77 4
Method of fixing 3.58 3 3.83 9 3.71 5
Site location 3.23 9 4.11 1 3.67 6=
Finishes 3.47 6= 3.86 8 3.67 6=
Edge of materials 3.26 8 3.94 6 3.60 8
Specification 3.47 6= 3.70 11 3.59 9
Type of structural frame 3.15 10 3.89 7 3.52 10
Elevations 3.06 13 3.81 10 3.44 11
Texture of materials 3.11 11 3.56 14 3.34 12
Schedule 3.02 14 3.60 13 3.31 13=
Mass of materials 2.97 15 3.65 12 3.31 13=
Content of material 3.08 12 3.44 16 3.26 15
Surface area of materials 2.73 16 3.46 15 3.10 16
© 2014 : Prof JJ Smallwood
Knowledge of mass and density of materials
Table 9: Summary of architectural designers’ and architectural technologists’ response and
responses within a 10% range of the actual mass or density (Smallwood, 2011b)
Material Response (%) No response (%) Within 10% range (%)
Solid clay brick 82.1 17.9 23.4
Two-cell concrete block 83.3 16.7 1.5
Precast concrete kerb 83.3 16.7 9.2
Double Roman concrete roof tile 83.3 16.7 10.8
m2 glass 5 mm thick 76.9 23.1 3.4
Concrete 73.1 26.9 19.6
Marble 66.7 33.3 17.3
Sandstone 66.7 33.3 5.8
Steel 64.1 35.9 8.2
Mean 75.5 24.5 11.0
© 2014 : Prof JJ Smallwood
Role and knowledge of mass and density of materials
Table 10: Frequency at which practices consider the mass and density of materials when designing
and specifying (MS: 1.00 – 5.00) (Smallwood, 2011b)
Response (%)
MS
Unsure
Never……………...…………………..…Always
1 2 3 4 5
4.0 24.0 32.0 22.7 9.3 8.0 2.43
Response (%)
MS
Unsure
Limited……………………..…………Extensive
1 2 3 4 5
4.1 44.6 29.7 14.9 4.1 2.7 1.86
Table 12: Respondents’ rating of their knowledge of the mass and density of materials
(MS: 1.00 – 5.00) (Smallwood, 2011b)
.
Response (%)
MS
Unsure
Minor….. ……………………………..…Major
1 2 3 4 5
13.5 8.1 4.1 18.9 32.4 23.0 3.67
Table 11: Potential of the consideration of the mass and density of materials to contribute to an
improvement in construction ergonomics (MS: 1.00 – 5.00) (Smallwood, 2011b)
© 2014 : Prof JJ Smallwood
Landscape architecture and landscape construction
H&S (1)
Table 14: Extent to which landscape construction H&S should be addressed in landscape
architecture programmes according to landscape architects (Smallwood, 2010a)
.
Response (%)
MS
Unsure
Minor….. ……………………………..…Major
1 2 3 4 5
27.8 22.2 27.8 11.1 11.1 0.0 2.15
Table 13: Extent to which tertiary landscape architecture education addresses landscape
construction H&S according to landscape architects (MS: 1.00 – 5.00) (Smallwood, 2010a)
Addressing of construction H&S Yes (%)
Unsure 9.5
Not at all 0.0
Included in a range of subjects 23.8
Included in the subject ‘design’ 23.8
A subject ‘construction H&S’ 42.9
© 2014 : Prof JJ Smallwood
Landscape architecture and landscape construction
H&S (2)
Table 15: Landscape architects’ sources of knowledge of landscape construction H&S (Smallwood,
2010a)
Source Yes (%)
Experience 95.2
Magazine articles 38.1
Tertiary education 23.8
Workshops 19.0
Postgraduate qualifications 14.3
Practice notes 14.3
CPD Seminars 9.5
Conference papers 4.8
Journal papers 4.8
Other: OH&S Act 4.8
© 2014 : Prof JJ Smallwood
Interior design and construction H&S (1)
Table 17: Extent to which construction H&S should be addressed in interior design
programmes according to interior designers (Smallwood, 2009b)
.
Response (%)
MS
Unsure
Minor….. ……………………………..…………..Major
1 2 3 4 5
50.0 10.0 30.0 10.0 0.0 0.0 2.00
Table 16: Extent to which tertiary interior design education addresses construction H&S according
to interior designers (MS: 1.00 – 5.00) (Smallwood, 2009b)
Addressing of construction H&S Yes (%)
Unsure 18.2
Not at all 0.0
Included in a range of subjects 18.2
Included in the subject ‘design’ 0.0
A subject ‘construction H&S’ 63.6
© 2014 : Prof JJ Smallwood
Interior design and construction H&S (2)
Table 18: Interior designers’ sources of knowledge of construction H&S (Smallwood, 2009b)
Means Yes (%)
Experience 45.5
Magazine articles 27.3
Other: OH&S Act 27.3
Journal papers 18.2
Workshops 9.1
Conference papers 0.0
CPD Seminars 0.0
Postgraduate qualifications 0.0
Practice notes 0.0
Tertiary education 0.0
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
67
Built environment construction H&S education
Table 19 : The importance of the inclusion of construction H&S in the tertiary education
programmes of built environment disciplines according to architectural academics
(MS: 1.00 – 5.00) (Smallwood, 2014)
Discipline
Response (%)
MS Rank
Unsure
Hardly…………….………………….……. Very
1 2 3 4 5
Construction management 0.0 0.0 0.0 0.0 0.0 100.0 5.00 1
Civil engineering 0.0 0.0 0.0 0.0 25.0 75.0 4.75 2
Electrical engineering 0.0 0.0 0.0 0.0 50.0 50.0 4.50 3
Mechanical engineering 0.0 0.0 0.0 25.0 25.0 50.0 4.25 4
Project management 0.0 0.0 25.0 0.0 0.0 75.0 4.25 5
Landscape architecture 0.0 0.0 20.0 40.0 20.0 20.0 3.40 6
Architecture 0.0 16.7 16.7 16.7 16.7 33.3 3.33 7
Quantity surveying 0.0 0.0 25.0 50.0 0.0 25.0 3.25 8
Interior design 0.0 20.0 20.0 40.0 20.0 0.0 2.60 9
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
68
Architectural construction H&S education (1)
Table 20: Extent to which construction H&S is addressed / included in architectural programmes /
curricula (Smallwood, 2014).
Response (%)
Unsure Yes No
0.0 66.7 33.3
Form
Response (%)
Unsure Yes No
Separate subject 0.0 0.0 100.0
Issue in design project briefs 0.0 66.7 33.3
Criterion for assessment in design project
assessments
0.0 33.3 66.7
Component of a subject 0.0 33.3 66.7
Module in various subjects 0.0 33.3 66.7
On an ad-hoc basis 0.0 33.3 66.7
Table 21: Form in which construction H&S is addressed / included in architectural programmes /
curricula (Smallwood, 2014).
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
69
Architectural construction H&S education (3)
Table 22: The importance of the inclusion of subject areas relative to construction H&S in an architectural
programme according to architectural academics (MS: 1.00 – 5.00) (Smallwood, 2014)
Subject area
Response (%)
MS Rank
Unsure
Hardly………….…………….……………Very
1 2 3 4 5
Occupational health 0.0 0.0 0.0 16.7 50.0 33.3 4.17 1
Occupational safety 0.0 0.0 0.0 16.7 50.0 33.3 4.17 2
OH&S Act & Regulations 0.0 0.0 0.0 33.3 33.3 33.3 4.00 3
H&S plans 0.0 0.0 0.0 33.3 33.3 33.3 4.00 4
H&S specifications 0.0 0.0 0.0 50.0 16.7 33.3 3.83 5
Role of project managers in construction H&S 0.0 0.0 16.7 16.7 33.3 33.3 3.83 6
Role of construction H&S in project
performance
0.0 0.0 16.7 0.0 83.3 0.0 3.67 7
Role of designers in construction H&S 0.0 0.0 0.0 66.7 0.0 33.3 3.67 8
Specifying for construction H&S 0.0 0.0 16.7 33.3 33.3 16.7 3.50 9
Need for construction H&S 16.7 0.0 16.7 16.7 50.0 0.0 3.40 10
Designing for construction H&S 0.0 20.0 0.0 20.0 40.0 20.0 3.40 11
Hazard identification and risk assessment 0.0 16.7 16.7 16.7 16.7 33.3 3.33 12
Designing for construction ergonomics 0.0 16.7 16.7 0.0 66.7 0.0 3.17 13
Role of quantity surveyors in construction H&S 0.0 0.0 50.0 0.0 50.0 0.0 3.00 14
Detailing for construction H&S 0.0 16.7 16.7 33.3 33.3 0.0 2.83 15
Role of clients in construction H&S 0.0 0.0 50.0 33.3 16.7 0.0 2.67 16
Environment and construction H&S 0.0 16.7 33.3 16.7 33.3 0.0 2.67 17
Economics of construction H&S 0.0 33.3 33.3 0.0 16.7 16.7 2.50 18
Influence of procurement on construction H&S 16.7 33.3 16.7 16.7 16.7 0.0 2.20 19
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
70
Architectural construction H&S education (4)
Table 23: The extent to which actions / activities / aspects impact on construction H&S according
to architectural academics (MS: 0.00 – 5.00 i.e. midpoint is 2.50) (Smallwood, 2014)
Action / Activity / Aspect
Response (%)
MS RankUnsure Does
not
Minor …………………………………Major
1 2 3 4 5
H&S pre-qualification of
contractors
0.0 0.0 0.0 0.0 0.0 66.7 33.3 4.33 1
Site handover 0.0 0.0 0.0 0.0 33.3 33.3 33.3 4.00 2
Site inspections / discussions 0.0 0.0 0.0 0.0 33.3 50.0 16.7 3.83 3
Detailed design 0.0 0.0 0.0 0.0 50.0 33.3 16.7 3.67 4
Constructability reviews 16.7 0.0 0.0 0.0 33.3 50.0 0.0 3.60 5
Design 0.0 0.0 0.0 0.0 66.7 16.7 16.7 3.50 6
Project duration 0.0 0.0 0.0 16.7 50.0 16.7 16.7 3.33 7
Pre-tender meeting 16.7 0.0 0.0 16.7 33.3 33.3 0.0 3.20 8
Evaluation of tenders 16.7 0.0 0.0 16.7 33.3 33.3 0.0 3.20 9
Site meetings 0.0 16.7 0.0 0.0 60.0 20.0 20.0 3.00 10
Design coordination meetings 0.0 16.7 0.0 0.0 50.0 33.3 0.0 2.83 11
Working drawings 16.7 0.0 0.0 33.3 33.3 16.7 0.0 2.80 12
Project documentation 16.7 0.0 16.7 16.7 50.0 0.0 0.0 2.40 13
Client brief 0.0 16.7 16.7 16.7 33.3 0.0 16.7 2.33 14
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
71
Architectural construction H&S education (5)
Table 24: The extent to which design related aspects impact on construction H&S according to
architectural academics (MS: 0.00 – 5.00 i.e. midpoint is 2.50) (Smallwood, 2014)
Aspect
Response (%)
MS RankUnsure Does
not
Minor …………………………………Major
1 2 3 4 5
Method of fixing 0.0 0.0 0.0 0.0 16.7 50.0 33.3 4.17 1
Mass of materials 16.7 0.0 0.0 0.0 16.7 50.0 16.7 4.00 2
Edge of materials 0.0 0.0 0.0 0.0 66.7 16.7 16.7 3.50 3
Type of structural frame 0.0 0.0 0.0 16.7 33.3 33.3 16.7 3.50 4
Specification 0.0 0.0 0.0 16.7 33.3 33.3 16.7 3.50 5
Site location 0.0 0.0 16.7 0.0 33.3 33.3 16.7 3.33 6
Content of material 0.0 16.7 0.0 0.0 16.7 50.0 16.7 3.33 7
Design (general) 0.0 0.0 16.7 0.0 33.3 50.0 0.0 3.17 8
Surface area of materials 0.0 16.7 0.0 16.7 16.7 16.7 33.3 3.17 9
Texture of materials 0.0 0.0 16.7 16.7 16.7 50.0 0.0 3.00 10
Position of components 0.0 20.0 0.0 0.0 40.0 20.0 20.0 3.00 11
Details 0.0 0.0 0.0 33.3 50.0 16.7 0.0 2.83 12
Plan layout 0.0 0.0 16.7 33.3 16.7 33.3 0.0 2.67 13
Finishes 0.0 16.7 0.0 33.3 16.7 16.7 16.7 2.67 14
Elevations 0.0 0.0 16.7 33.3 33.3 16.7 0.0 2.50 15
Schedule 0.0 0.0 16.7 50.0 16.7 16.7 0.0 2.33 16
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
72
A model for designers
SACAP architectural
work stages (1 – 6)
ApplicationoftheNBR(PartsA–X)
Design opportunity window:
Design options
Design selection
H&S reviews
Sign-off or revisit 1
H&S checklists
H&S data records
Sign-off or revisit 2
Variation orders (VOs)
Sign-off or revisit 3
The Goldswain
Core Model
Core ModelDesign knowledge window:
Construction processes
Construction programming
Contextual H&S
Causes of Accidents
Hazard Identification and
Risk Assessments (HIRAs)
Project type and complexity
Design recommendations
Lifecycles of buildings
Figure 4: The Goldswain Core Model (Goldswain, 2014).
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
73
Construction management H&S education (1)
Table 4A: The importance of the inclusion of subject areas relative to construction H&S in a construction
management programme according to GC National H&S Competition winners (MS: 1.00 – 5.00)
(Smallwood, 2010b)
Subject area
Response (%)
MS Rank
Unsure
Hardly………….…………….……………Very
1 2 3 4 5
Management of subcontractors 0.0 0.0 0.0 0.0 11.1 88.9 4.89 1
Role of construction management 0.0 0.0 0.0 0.0 11.1 88.9 4.89 2
Worker participation 0.0 0.0 0.0 0.0 11.1 88.9 4.89 3
OH&S Act & Regulations 0.0 0.0 0.0 0.0 11.1 88.9 4.89 4
H&S / Productivity / Quality 0.0 0.0 0.0 0.0 22.2 77.8 4.78 5
H&S pre-planning 0.0 0.0 0.0 0.0 22.2 77.8 4.78 6
H&S programs 0.0 0.0 0.0 0.0 22.2 77.8 4.78 7
Safety 0.0 0.0 0.0 0.0 22.2 77.8 4.78 8
H&S education & training 0.0 0.0 0.0 0.0 33.3 66.7 4.67 9
Role of project managers 0.0 0.0 0.0 0.0 33.3 66.7 4.67 10
H&S plans 0.0 0.0 0.0 11.1 11.1 77.8 4.67 11
Health & hygiene 0.0 0.0 0.0 0.0 44.4 55.6 4.56 12
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
74
Construction management H&S education (1)
Table 4B: The importance of the inclusion of subject areas relative to construction H&S in a construction
management programme according to GC National H&S Competition winners (MS: 1.00 – 5.00)
(Smallwood, 2010b)
Subject area
Response (%)
MS Rank
Unsure
Hardly………….…………….……………Very
1 2 3 4 5
Role of clients 0.0 0.0 0.0 11.1 22.2 66.7 4.56 13
Role of designers 0.0 0.0 0.0 11.1 22.2 66.7 4.56 14
H&S culture e.g. values, vision, goals, &
mission
0.0 0.0 0.0 12.5 25.0 62.5 4.50 15
Economics of H&S 0.0 0.0 0.0 22.2 22.2 55.6 4.33 16
Role of the media & awareness 0.0 0.0 0.0 22.2 22.2 55.6 4.33 17
Environment 0.0 0.0 0.0 33.3 0.0 66.7 4.33 18
Measurement & statistics 0.0 0.0 0.0 33.3 0.0 66.7 4.33 19
Role of the unions 0.0 0.0 11.1 11.1 22.2 55.6 4.22 20
COID Act (workers’ compensation) 0.0 11.1 0.0 11.1 11.1 66.7 4.22 21
Ergonomics 0.0 0.0 0.0 33.3 22.2 44.4 4.11 22
Influence of procurement 0.0 0.0 11.1 22.2 33.3 33.3 3.89 23
Role of quantity surveyors 11.1 0.0 11.1 33.3 11.1 33.3 3.33 24
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
75
The role of cost engineers / quantity surveyors
 Cost Engineers / Quantity Surveyors:
 May practice as project managers (if registered as Pr CPMs)
 Prepare project estimates
 May advise regarding the type of procurement system
 May advise regarding project duration
 Often prepare contract documentation
 Often compile bills of quantities / schedule of rates
 Assess pre-qualification and tender submissions
 The cost of accidents contributes to the cost of construction
 Construction Regulations include “surveyor specifying
articles or drawing up specifications” under definition of
designer
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
76
A holistic perspective cost engineers / QSs
 A client needs to be able to make a scientific assessment of
the PC’s provision for H&S
 The client’s H&S specification and designer report should
provide a reference
 The H&S plan should provide a reference:
 However, H&S plan to be applied from date of commencement
[Regulation 7(1) (a) i.e. not necessarily available at tender / bid stage
 The requirement on the client to ensure that the PC has made
adequate provision for H&S amplifies the need for a pre-tender H&S
plan (not required by the Regulations)
 Each project is unique despite many common activities
 A provisional sum would not do justice
 PCs and contractors have varying levels of expertise
 Emerging contractors should be guided
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
77
H&S Preliminaries items (1)
Can facilitate adequate provision for H&S by PCs in terms
of Regulation 5 (1) (g) through inclusion of, among other, an
‘H&S’ section in the Preliminaries:
 H&S plan
 H&S file
 Risk assessment
 SWPs and method statements
 Design of temporary works
 Design of permanent structures
 Engineering design and / or certification
 Medicals
 Biological monitoring
 Environmental measurement
 Education and training
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
78
H&S Preliminaries items (2)
 Full-time or part-time Construction H&S Officer
[Regulation 8 (5)], or management of H&S as a whole
(preferably not)
 H&S Representatives
 Meetings
 General administration
 Hoarding and / or public walkways
 Catch platforms
 Facilities related requirements – Regulation 30:
 WCs – for each gender, and 1 for every 30 workers
 WHBs (not required)
 Showers – 1 for every 15
 Changing facilities – for each gender
 Sheltered eating areas
 Living accommodation – for workers far removed from their homes
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
79
H&S Preliminaries items (3)
 Guarding and barricading
 Storage
 Storage for flammable goods – Regulation 25 (a)
 Temporary electrical installations
 Scaffolding
 Special scaffolding
 Suspended scaffolding
 Access
 Signage
 Housekeeping
 Personal protective equipment
 Fire precautions
 First aid
 Transport of workers
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
80
H&S Preliminaries items (4)
 Inspections
 Maintenance
 Emergency plan
Other provisions such as material and personnel hoists, and
mobile and tower cranes can be addressed in the traditional
manner
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
81
References (1)
 Behm, M. 2006. An Analysis of Construction Accidents from a
Design Perspective. Silver Spring: The Center to Protect
Workers’ Rights.
 Construction Industry Development Board (cidb). 2009.
Construction Health & Safety Status & Recommendations.
Pretoria: cidb.
 Department of Labour. 2002. Section 32 Investigation Report
into the Injaka Bridge Collapse of 6 July 1998. Pretoria.
 Goldswain, C. 2014. Architectural Design Interventions
Toward Improvement of Construction Health, Safety, and
Ergonomics in South Africa. Unpublished PhD (Construction
Management) Thesis. Port Elizabeth: NMMU.
 Irwin, A.W. and Sibbald, W.I. 1983. Falsework A Handbook of
Design and Practice. London: Granada Technical Books.
 Prinsloo, K. 1997. Beeld, 27 August, p.3.
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
82
References (2)
 Republic of South Africa. 2014. No. R. 84 Occupational Health
and Safety Act, 1993 Construction Regulations 2014.
Government Gazette No. 37305. Pretoria.
 Smallwood, J.J. 1995. The Influence of management on the
occurrence of loss causative incidents in the South African
construction industry. Unpublished MSc (Constr Man)
Dissertation, University of Port Elizabeth, Port Elizabeth.
 Smallwood, J.J. 2000. A study of the relationship between
occupational health and safety, labour productivity and
quality in the South African construction industry.
Unpublished PhD Thesis. University of Port Elizabeth, Port
Elizabeth.
 Smallwood, J.J. 2004a. Optimum cost: The role of health and
safety (H&S). In: Verster JJP, ed. Proceedings International
Cost Engineering Council 4th World Congress, Cape Town,
April 2004. International Cost Engineering Council, 2004: CD-
Rom Smallwood-J- Optimum Cost-Health & Safety.pdf
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
83
References (3)
 Smallwood, J.J. 2004b. The influence of engineering designers
on health and safety during construction. Journal of the South
African Institution of Civil Engineering, 46 (1), 2–8.
 Smallwood, J.J. 2009a. Architects and Architectural
Technologists: Their Influence on Construction Ergonomics,
ergonomicsSA, 21(2), 41-64.
 Smallwood, J.J. 2009b. Interior Designers and Construction
Health and Safety. Unpublished research findings.
 Smallwood, J.J. 2010a. Landscape Architects and Landscape
Construction Health and Safety (H&S). Unpublished research
findings.
 Smallwood, J.J. 2010b. Construction Management Health and
Safety (H&S) Course Content: Towards the Optimum. In:
Proceedings of the CIB World Building Congress, Salford
Quays, 14-17 May, 2010.
© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
84
References (4)
 Smallwood, J.J. 2011a. Financial Provision for Health and
Safety (H&S) in Construction. In: Proceedings of the CIB W099
Conference, Washington D.C., 24-26 August,
F:datapapers45.pdf.
 Smallwood, J.J. 2011b. Mass and density of construction
materials: designers’ knowledge, perceptions, and practices,
ergonomicsSA, 23(1), 28-41.
 Smallwood, J.J. 2014. The need for the inclusion of
Construction health and safety (H&S) in architectural
education. Unpublished paper presented at the: architecture
Otherware XXV International Union of Architects Congress,
Durban, 4-9 August.
 South African Reserve Bank. 2003. Quarterly Bulletin.
Pretoria: South African Reserve Bank.
 Steele, D. 1983. Bloukrans Bridge. Concrete Beton, Nr 30 1983
06, 10-11.

© 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood
85
References (5)
 The National Spiritual Assembly of the Bahia’is of India. 2002.
The Dawning Place of the Remembrance of God. New Delhi:
Thomson Press.
 Travers, R. 1998. Lowvelder, 10 July, p. 1.

More Related Content

What's hot

Chee Wong - CV DEC2016
Chee Wong - CV DEC2016Chee Wong - CV DEC2016
Chee Wong - CV DEC2016Chee Wong
 
Academic paper and supporting document on fast track construction (1)
Academic paper and supporting document on fast track construction (1)Academic paper and supporting document on fast track construction (1)
Academic paper and supporting document on fast track construction (1)Ahmed Rushdhie
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...HIMADRI BANERJI
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Building Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participantsBuilding Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participantsHamdija Velagic
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh PrasadRajesh Prasad
 
Wael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp LettersWael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp LettersWaell Azmy
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...HIMADRI BANERJI
 
Zeonn Koh 4 page CV
Zeonn Koh 4 page CVZeonn Koh 4 page CV
Zeonn Koh 4 page CVZeonn Koh
 
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...Adeoye Charles
 
Mohamed Tarek Amin-Senior Mech Engineer-Qatar
Mohamed Tarek Amin-Senior Mech Engineer-QatarMohamed Tarek Amin-Senior Mech Engineer-Qatar
Mohamed Tarek Amin-Senior Mech Engineer-QatarMohamed Amin
 
Integrated project
Integrated projectIntegrated project
Integrated projectLee Fong Yen
 
Integrated project
Integrated projectIntegrated project
Integrated projectisyroc
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 

What's hot (20)

Chee Wong - CV DEC2016
Chee Wong - CV DEC2016Chee Wong - CV DEC2016
Chee Wong - CV DEC2016
 
Academic paper and supporting document on fast track construction (1)
Academic paper and supporting document on fast track construction (1)Academic paper and supporting document on fast track construction (1)
Academic paper and supporting document on fast track construction (1)
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Building Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participantsBuilding Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participants
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh Prasad
 
Wael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp LettersWael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp Letters
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
ASCE T&DI Abstract 40 - Final Paper
ASCE T&DI Abstract 40 - Final PaperASCE T&DI Abstract 40 - Final Paper
ASCE T&DI Abstract 40 - Final Paper
 
Zeonn Koh 4 page CV
Zeonn Koh 4 page CVZeonn Koh 4 page CV
Zeonn Koh 4 page CV
 
Engr ilyas cv new
Engr ilyas cv newEngr ilyas cv new
Engr ilyas cv new
 
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
 
Mohamed Tarek Amin-Senior Mech Engineer-Qatar
Mohamed Tarek Amin-Senior Mech Engineer-QatarMohamed Tarek Amin-Senior Mech Engineer-Qatar
Mohamed Tarek Amin-Senior Mech Engineer-Qatar
 
Ahmed Abdallah Resume
Ahmed Abdallah ResumeAhmed Abdallah Resume
Ahmed Abdallah Resume
 
Integrated project
Integrated projectIntegrated project
Integrated project
 
Integrated project
Integrated projectIntegrated project
Integrated project
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
MARTIN Daniel CV
MARTIN Daniel CVMARTIN Daniel CV
MARTIN Daniel CV
 
Khaled Naguib
Khaled NaguibKhaled Naguib
Khaled Naguib
 

Viewers also liked

Sebring Revolution
Sebring RevolutionSebring Revolution
Sebring RevolutionLeana Jones
 
Ubv modulo 5 presentacion.docx 1
Ubv modulo 5 presentacion.docx 1Ubv modulo 5 presentacion.docx 1
Ubv modulo 5 presentacion.docx 1Estefania Naranjo
 
Los 7 hábitos de la gente altamente efectiva
Los 7 hábitos de la gente altamente efectivaLos 7 hábitos de la gente altamente efectiva
Los 7 hábitos de la gente altamente efectivasonibermora
 
Estructura organizacional (jerarquías y organigramas)
Estructura organizacional (jerarquías y organigramas)Estructura organizacional (jerarquías y organigramas)
Estructura organizacional (jerarquías y organigramas)sonibermora
 
Social Psychology Field Interviews - Equallyokedtarians - Liberal arts and H...
Social Psychology Field Interviews  - Equallyokedtarians - Liberal arts and H...Social Psychology Field Interviews  - Equallyokedtarians - Liberal arts and H...
Social Psychology Field Interviews - Equallyokedtarians - Liberal arts and H...AlbionSmall1892
 

Viewers also liked (7)

Sebring Revolution
Sebring RevolutionSebring Revolution
Sebring Revolution
 
Resume2016
Resume2016Resume2016
Resume2016
 
Ubv modulo 5 presentacion.docx 1
Ubv modulo 5 presentacion.docx 1Ubv modulo 5 presentacion.docx 1
Ubv modulo 5 presentacion.docx 1
 
Los 7 hábitos de la gente altamente efectiva
Los 7 hábitos de la gente altamente efectivaLos 7 hábitos de la gente altamente efectiva
Los 7 hábitos de la gente altamente efectiva
 
Estructura organizacional (jerarquías y organigramas)
Estructura organizacional (jerarquías y organigramas)Estructura organizacional (jerarquías y organigramas)
Estructura organizacional (jerarquías y organigramas)
 
RESUME 10 4-15
RESUME 10 4-15RESUME 10 4-15
RESUME 10 4-15
 
Social Psychology Field Interviews - Equallyokedtarians - Liberal arts and H...
Social Psychology Field Interviews  - Equallyokedtarians - Liberal arts and H...Social Psychology Field Interviews  - Equallyokedtarians - Liberal arts and H...
Social Psychology Field Interviews - Equallyokedtarians - Liberal arts and H...
 

Similar to Construction H & S in Tertiary Education_Professor Smallwood Presentation at SAIOSH CPD Workshop 21 July 2016

1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziriOyeniyi Samuel
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
Construction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformConstruction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformProfessor Kabir Sadeghi
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...
IRJET-  	  Analysis, Design and Estimation of Multi- Storied Residential Buil...IRJET-  	  Analysis, Design and Estimation of Multi- Storied Residential Buil...
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...IRJET Journal
 
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdfARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdfFaruq42
 
Development Proposal
Development ProposalDevelopment Proposal
Development Proposaldtan97
 
Assessment of risk on road projects in nigeria construction industry
Assessment of risk on road projects in nigeria construction industryAssessment of risk on road projects in nigeria construction industry
Assessment of risk on road projects in nigeria construction industryResearchWap
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Khalid Abdel Naser Abdel Rahim
 
CV-Gabriel Koncal-LinkedIn
CV-Gabriel Koncal-LinkedInCV-Gabriel Koncal-LinkedIn
CV-Gabriel Koncal-LinkedInGabriel Koncal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 

Similar to Construction H & S in Tertiary Education_Professor Smallwood Presentation at SAIOSH CPD Workshop 21 July 2016 (20)

Analysis Of Concreting Process’s Productivity In The Distrito Federal: Charac...
Analysis Of Concreting Process’s Productivity In The Distrito Federal: Charac...Analysis Of Concreting Process’s Productivity In The Distrito Federal: Charac...
Analysis Of Concreting Process’s Productivity In The Distrito Federal: Charac...
 
1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Construction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformConstruction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum Platform
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
B012140812
B012140812B012140812
B012140812
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...
IRJET-  	  Analysis, Design and Estimation of Multi- Storied Residential Buil...IRJET-  	  Analysis, Design and Estimation of Multi- Storied Residential Buil...
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...
 
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdfARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
 
Development Proposal
Development ProposalDevelopment Proposal
Development Proposal
 
cv for Project Engineer
cv for Project Engineercv for Project Engineer
cv for Project Engineer
 
Assessment of risk on road projects in nigeria construction industry
Assessment of risk on road projects in nigeria construction industryAssessment of risk on road projects in nigeria construction industry
Assessment of risk on road projects in nigeria construction industry
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
CV-Gabriel Koncal-LinkedIn
CV-Gabriel Koncal-LinkedInCV-Gabriel Koncal-LinkedIn
CV-Gabriel Koncal-LinkedIn
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 

Construction H & S in Tertiary Education_Professor Smallwood Presentation at SAIOSH CPD Workshop 21 July 2016

  • 1. © 2014 : Prof JJ Smallwood 1 PROF JOHN SMALLWOOD DEPT. OF CONSTRUCTION MANAGEMENT NELSON MANDELA METROPOLITAN UNIVERSITY SOUTH AFRICA COUNCIL FOR THE BUILT ENVIRONMENT INCORPORATION OF CONSTRUCTION HEALTH AND SAFETY (H&S) INTO TERTIARY BUILT ENVIRONMENT EDUCATION WORKSHOP, PORT ELIZABETH, 19 SEPTEMBER 2014
  • 2. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 2 Introduction (1)  According to the Construction Industry Development (cidb) (2009), during visits to 1 415 construction sites by Department of Labour (DoL) inspectors:  1 388 notices were issued:  86 (6%) improvement notices  1 015 (73%) contravention notices  287 (21%) prohibition notices  Furthermore, 52.5% of contractors were non-compliant  The disabling injury frequency rate (DIIR) is a rate, per 200 000 hours worked, of disabling injuries due to all causes i.e. per 100 workers x 2 000 hrs / yr:  0.98 (cidb, 2009)  Fatality rate per 100 000 workers: 25.5 (cidb, 2009)
  • 3. © 2014 : Prof JJ Smallwood 3 Introduction (2) Construction H&S occurs in a macro environment: Figure 1: Construction H&S – the macro environment (Smallwood, 1995)
  • 4. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 4 Introduction (3)  151 / 450 (33.6%) cases of death and disabling of construction workers in the USA, the hazard that contributed to the incident could have been eliminated or reduced if design-for-H&S measures had been implemented (Behm, 2006)
  • 5. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 5 Injaka Bridge collapse (1) Injaka Bridge collapse, Mpumalanga, July, 1998 (Travers, 1998)
  • 6. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood Injaka Bridge collapse (2) Department of Labour (2002):  Causes:  The slide path was not under the webs  The placing of the sliding pads between the deck and temporary bearings was not as specified  Insufficient reinforcement in the deck section, especially the bottom slab  The failure to fully appreciate the implications of the early cracks  The acceptance and approval of a launching nose which was substantially less stiff than that prescribed in the project specification  The deviation from the project specification regarding the automatic pier deflection monitoring at pier 2  The deviation from the project specification regarding the height tolerances of the temporary bearings on pier 3  The use of design and construction personnel, at decision-making level, without appropriate qualification and experience in incremental launched bridges
  • 7. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood Injaka Bridge collapse (3)  No independent design reviews were conducted of either the temporary or permanent works  Contributory causes:  The lack of experience on the part of design personnel in incremental launching techniques resulted in poor communications between the parties to clarify understandings and interpretations regarding the slide path position  The lack of clear instructions in the project specification and clear indications on the consulting engineers design drawings as to the position of the sliding path, resulted in incorrect interpretations being made
  • 8. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood H&S is a profit centre not a ‘cost’  Based upon the value of construction work completed in the year 2002, namely R 56 343m (South African Reserve Bank, 2003) the total COA could have been between 4.3% (R 2 401.2m / R 56 343m), and 5.4% (R 3 041.5m / R 56 343m) (Smallwood, 2004a; cidb, 2009)  Cost of prevention is:  Between 0.5% and 3% of project costs (Smallwood, 2004a)  1.6% of tender cost estimate and 1% of project cost (Smallwood, 2011a)
  • 9. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 9 Importance of the project parameters Parameter Architects Arch. Tech’s Mean Mean Score Rank Mean Score Rank Mean Score Rank Project quality 4.74 1 4.59 1 4.67 1 End-user ergonomics 4.29 3 4.46 3 4.38 2 Environment 4.25 4 4.49 2 4.37 3= Project cost 4.38 2 4.35 5 4.37 3= Project time 4.20 5 4.38 4 4.29 5 Project health and safety (H&S) 3.94 6 4.19 6 4.07 6 Construction ergonomics 3.58 4 3.92 7 3.75 7 Table 1: Importance of project parameters to Architectural practices and Architectural Technologists (MS: 1.00 – 5.00) (Smallwood, 2009a).
  • 10. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 10 Designing and safety (1) Natural-light openings, Port Elizabeth (Smallwood)
  • 11. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 11 Designing and safety (2) ‘Open’ precast concrete cladding, Port Elizabeth (Smallwood)
  • 12. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 12 Designing for safety ‘Balustrade’ precast concrete cladding, Cape Town (Smallwood)
  • 13. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 13 Designing for ergonomics and H&S (1) Precast concrete stair flights, Port Elizabeth (Smallwood)
  • 14. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 14 Designing for ergonomics and H&S (2) Precast concrete stair flights, Port Elizabeth (Smallwood)
  • 15. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 15 Designing and ergonomics and OH ‘Bush-hammered’ concrete, Port Elizabeth (Smallwood)
  • 16. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 16 Designing for ergonomics and OH Thermal Lance, Mount Road Police Station, Port Elizabeth (Smallwood, 1987)
  • 17. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 17 Designing and ergonomics Face brick lining to semi-circular RC soffit, Sandton (Smallwood)
  • 18. © 2014 : Prof JJ Smallwood 18 Integration of design and construction (1)  Two issues - influence of design on construction H&S, and the type of procurement system  Design influences construction directly and indirectly:  Directly, through design, choice of structural frame, details, method of fixing, constructability, and specification of materials and finishes  Indirectly, through choice of procurement system and conditions of contract, procurement, decision regarding project duration, and reference to H&S on various occasions  Certain procurement systems such as design-build promote the integration of design and construction  Optimum integration engenders and enhances H&S as it facilitates contractor contributions to the design process  Designing for H&S is one of sixteen design for constructability principles – contractors can contribute
  • 19. © 2014 : Prof JJ Smallwood 19 Integration of design and construction (2) Figure 2: Elevation of masonry Bridge over the Tweed at Coldstream, 1866 (Irwin and Sibbald, 1983)
  • 20. © 2014 : Prof JJ Smallwood 20 Integration of design and construction (3) Figure 3: Centering for masonry Bridge over the Tweed at Coldstream, 1866 (Irwin and Sibbald, 1983)
  • 21. © 2014 : Prof JJ Smallwood 21 Integration of design and construction (4) Bloukrans Bridge (p. 11, Concrete Beton, 1983)
  • 22. © 2014 : Prof JJ Smallwood 22 Integration of design and construction (5) Bloukrans Bridge (Inside Front, Concrete Beton, 1983)
  • 23. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 23 Integration of design and construction (6) Bloukrans bridge project (Steele, 1983):  “…notable for the close cooperation and team effort which were achieved by the consultant and contractor, and encouragement given by the client.”  “… consulting engineers had clearly indicated in their design how the task should be tackled and worked closely with the contractors in converting the drawings they had supplied to reality…”
  • 24. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 24 Construction Regulations (1)  Definition of ‘designer’ – a competent person who:  prepares a design  checks and approves a design  arranges for a person at work under his / her control to prepare a design including an employee of that person  designs temporary work including its components  An architect or engineer contributing to, or having overall responsibility for a design  Building services engineer designing details for fixed plant  Surveyor specifying articles or drawing up specifications  Contractor carrying out design work as part of a design and build project  Interior designer, shop-fitter, or landscape architect
  • 25. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 25 Construction Regulations (2) Relative to Structures 6 (1) designers of a structure must:  (a) ensure that the H&S standards incorporated into the regulations are complied with in the design  (b) take the H&S specification into consideration  (c) include in a report to the client before tender stage:  all relevant H&S information about the design that may affect the pricing of the work  the geotechnical-science aspects  the loading that the structure is designed to withstand  (d) inform the client of any known or anticipated dangers or hazards relating to the construction work, and make available all relevant information required for the safe execution of the work upon being designed or when the design is changed  (e) modify the design or make use of substitute materials where the design necessitates the use of dangerous procedures or materials hazardous to H&S
  • 26. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 26 Construction Regulations (3)  (f) consider hazards relating to subsequent maintenance of the structure and make provision in the design for that work to be performed to minimize the risk  (g) when mandated by the client conduct inspections to ensure conformance of construction to design. If not mandated then the client’s agent is responsible  (h) when mandated by the client stop construction work not in accordance with the design’s H&S aspects. If not mandated then the client’s agent is responsible  (i) when mandated by the client, during his / her final inspection of the structure include the H&S aspects of the structure, declare the structure safe for use and issue a completion certificate
  • 27. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 27 Construction Regulations (4) Clients required to, among other:  5 (1) (a) Prepare a baseline risk assessment (BRA)  5 (1) (b) Prepare an H&S specification based on the BRA  5 (1) (c) Provide the designer with the H&S specification  5 (1) (d) Ensure that the designer takes the H&S specification into account during design  5 (1) (e) Ensure that the designer carries out the duties in Regulation 6 ‘Duties of designers’  5 (1) (f) Include the H&S specification (revised after the designers’ reports?) in the tender documents  5 (1) (g) Ensure that potential PCs have made provision for the cost of H&S in their tenders  5 (1) (h) Ensure that the PC to be appointed has the necessary competencies and resources
  • 28. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 28 Influence of designers (1)  Directly:  Concept design  General design  Choice of structural frame  Details  Provision for services (construction ergonomics)  Specification of materials, finishes and processes  Consideration of H&S:  During design coordination  During constructability reviews  Reference to H&S:  During pre-tender site visit  Upon site handover  During site visits / inspections  During site visits / meetings
  • 29. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 29  Indirectly:  Selection of / advice regarding type of procurement system  Selection of / advice regarding preparation of contract documentation  Decision regarding / advice with respect to project duration  Status of design upon commencement of construction (contractor pre-planning)  H&S prequalification of contractors  Site location e.g. exposure to elements, power lines etc.  Site coverage e.g. availability for storage Influence of designers (2)
  • 30. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 30 General design (1)  Shape of structure i.e. irregular plan shape  Pitch of roof i.e. high pitch  Over sailing sections (access to soffit / working overhead)  External work and finishes (elevated work to facades)  Position of ablutions relative to municipal services (depth of excavations)  Pre-fabrication, pre-assembly and pre-casting:  Reduces elevated in-situ work  Reduces manual handling  Engenders mechanisation
  • 31. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 31 General design (2) Bahia Temple, Delhi, India (Smallwood, 2005)
  • 32. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood General design (3) Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
  • 33. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood General design (4) Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
  • 34. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood General design (5) Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
  • 35. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood General design (6) Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
  • 36. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood General design (7) Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
  • 37. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood General design (8) Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
  • 38. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood General design (9) Bahia Temple, Delhi, India (The National Spiritual Assembly of the Bahia’is of India, 2002)
  • 39. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 39 General design (10) Investec Office Complex scaffolding collapse, Sandton, August, 1997 (Prinsloo, 1997)
  • 40. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 40 General design (11) Precast wall panels, Dublin (Smallwood, 2004)
  • 41. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 41 General design (12) Precast floor panels, Dublin (Smallwood, 2004)
  • 42. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 42 Choice of structural frame (1)  Load bearing masonry:  Mass of materials  Manual handling / Bending and twisting  On-site storage (housekeeping!)  Timber frame:  Pre-fabrication  Light weight  Less on-site storage = enhanced housekeeping  Less manual handling  Engenders mechanisation
  • 43. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 43  Structural steel:  Less on-site storage = enhanced housekeeping  Pre-assembly  Less manual handling  Very challenging elevated work  Reinforced concrete:  On-site storage (housekeeping!)  Manual handling / Bending and twisting / Use of body force  Challenging elevated work Choice of structural frame (2)
  • 44. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 44 Details (1)  Affect constructability  Affect work method  Affect work postures  Affect required plant and equipment  May require access
  • 45. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 45 Details (2) Externally installed full fenestration, Dublin (Smallwood, 2004)
  • 46. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 46 Details (3) Externally installed full fenestration, Dublin (Smallwood, 2004)
  • 47. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 47 Provision for services (1)  Affects construction ergonomics:  No. of services e.g. in ceiling  Layering (horizontal plane)  Space for working and fixing e.g. in vertical ducts  Method of fixing  Therefore, optimum:  Coordination  Layering  Sectional area (vertical ducts)
  • 48. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 48 Provision for services (2) Congested ceiling space, Cape Town (Smallwood, 2004)
  • 49. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 49 Provision for services (3) Congested ceiling space, Cape Town (Smallwood, 2004)
  • 50. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 50 Position of fittings (1) Porte Cochere, Nelspruit Airport (Smallwood, 2004)
  • 51. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 51 Position of fittings (2) Light fittings, Porte Cochere, Nelspruit Airport (Smallwood, 2004)
  • 52. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 52 Materials (1) May be / have:  Heavy - mass per unit / m / m2 / m3  Rough surface  Sharp edges  Toxic  Large e.g. ceiling / drywall panels and glass shop fronts © 2003 : Prof JJ Smallwood
  • 53. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 53 Materials (2) ‘Melting’ mastic asphalt, Canal Walk, Cape Town (Smallwood, 2000)
  • 54. © 2014 : Prof JJ Smallwood 54 Impact of design(ers) (1) Occasion Response (%) II RankDon’t know Never Rarely Some- times Often Always Site inspections/ discussions 0.0 28.3 28.3 28.3 28.3 28.3 2.64 1 Site meetings 0.0 28.3 28.3 28.3 28.3 28.3 2.56 2 Site handover 1.0 28.3 28.3 28.3 28.3 28.3 2.50 3 Preparing project documentation 1.0 28.3 28.3 28.3 28.3 28.3 2.24 4 Pre-tender meeting 1.0 28.3 28.3 28.3 28.3 28.3 2.19 5 Working drawings 1.0 28.3 28.3 28.3 28.3 28.3 2.18 6 Evaluating tenders 2.0 28.3 28.3 28.3 28.3 28.3 2.13 7 Detailed design 1.0 28.3 28.3 28.3 28.3 28.3 2.12 8 Pre-qualifying contractors 1.0 28.3 28.3 28.3 28.3 28.3 2.08 9 Constructability reviews 4.1 28.3 28.3 28.3 28.3 28.3 2.05 10 Design coordination meetings 1.0 28.3 28.3 28.3 28.3 28.3 1.90 11 Client meetings 2.0 28.3 28.3 28.3 28.3 28.3 1.88 12 Concept (design) 1.0 28.3 28.3 28.3 28.3 28.3 1.82 13 Deliberating project duration 4.2 28.3 28.3 28.3 28.3 28.3 1.77 14 Table 2: Frequency at which Architectural practices consider / refer to H&S on various occasions (II: 0 - 4) (Smallwood, 2000).
  • 55. © 2014 : Prof JJ Smallwood 55 Impact of design(ers) (2) Occasion Response (%) II RankDon’t know Never Rarely Some- times Often Always Site meetings 0.0 0.0 2.1 12.4 35.1 50.5 3.34 1 Site inspections / discussions 0.0 1.0 1.0 13.4 41.2 43.3 3.25 2 Site handover 1.0 1.0 6.3 12.5 28.1 51.0 3.20 3 Preparing project documentation 0.0 1.0 4.1 18.6 33.0 43.3 3.13 4 Detailed design 0.0 2.1 13.5 24.0 31.3 29.2 2.72 5 Working drawings 1.0 1.0 18.6 22.7 33.0 23.7 2.58 6 Pre-tender meeting 1.0 4.2 20.8 18.8 30.2 25.0 2.49 7 Constructability reviews 2.1 2.1 17.5 24.7 37.1 16.5 2.44 8 Concept (design) 0.0 4.1 14.4 35.1 28.9 17.5 2.41 9 Client meetings 0.0 4.1 12.4 41.2 32.0 10.3 2.32 10 Design coordination meetings 0.0 3.1 17.5 41.2 25.8 12.4 2.27 11 Evaluating tenders 0.0 9.4 29.2 22.9 25.0 13.5 2.04 12 Deliberating project duration 4.1 9.3 25.8 29.9 26.8 4.1 1.82 13 Pre-qualifying contractors 3.2 13.7 28.4 20.0 26.3 8.4 1.81 14 Table 3: Frequency at which Engineering practices consider / refer to H&S on various occasions (II: 0 - 4) (Smallwood, 2004b).
  • 56. © 2014 : Prof JJ Smallwood 56 Impact of design(ers) (3) Aspect Response (%) II RankDon’t know Never Rarely Some- times Often Always Specification 2.0 26.3 26.3 26.3 26.3 26.3 2.54 1 Method of fixing 1.0 26.3 26.3 26.3 26.3 26.3 2.53 2 Position of components 4.0 26.3 26.3 26.3 26.3 26.3 2.40 3 Edge of materials 4.0 26.3 26.3 26.3 26.3 26.3 2.36 4 Content of materials 2.0 26.3 26.3 26.3 26.3 26.3 2.34 5 Details 3.1 26.3 26.3 26.3 26.3 26.3 2.31 6 Finishes 4.1 26.3 26.3 26.3 26.3 26.3 2.28 7 Type of structural frame 4.0 26.3 26.3 26.3 26.3 26.3 2.26 8 Plan layout 5.1 26.3 26.3 26.3 26.3 26.3 2.22 9 Texture of materials 3.0 26.3 26.3 26.3 26.3 26.3 2.15 10 Design (general) 1.0 26.3 26.3 26.3 26.3 26.3 2.07 11 Schedule 6.2 26.3 26.3 26.3 26.3 26.3 2.03 12 Surface area of materials 6.1 26.3 26.3 26.3 26.3 26.3 2.03 13 Elevations 5.1 26.3 26.3 26.3 26.3 26.3 1.98 14 Site location 3.0 26.3 26.3 26.3 26.3 26.3 1.90 15 Mass of materials 5.1 26.3 26.3 26.3 26.3 26.3 1.87 16 Table 4: Frequency of which Architectural practices consider / refer to H&S relative to various design related aspects (II: 0 - 4) (Smallwood, 2000).
  • 57. © 2014 : Prof JJ Smallwood 57 Impact of design(ers) (4) Aspect Response (%) II RankDon’t know Never Rarely Some- times Often Always Specification 1.0 3.1 8.2 8.2 35.1 44.3 3.07 1 Method of fixing 3.1 3.1 6.2 14.4 34.0 39.2 2.94 2 Design (general) 1.0 0.0 10.4 21.9 38.5 28.1 2.82 3 Details 1.0 4.2 14.6 19.8 33.3 27.1 2.63 4 Type of structural frame 10.4 8.3 8.3 15.6 19.8 37.5 2.49 5 Position of components 5.2 7.2 13.4 18.6 36.1 19.6 2.37 6 Content of material 5.2 7.2 9.3 32.0 25.8 20.6 2.33 7 Plan layout 6.2 7.2 11.3 22.7 35.1 17.5 2.32 8 Site location 4.1 9.3 17.5 18.6 27.8 22.7 2.29 9 Schedule 4.1 10.3 13.4 28.9 28.9 14.4 2.15 10 Elevations 7.2 9.3 18.6 19.6 28.9 16.5 2.10 11 Mass of materials 8.3 7.3 18.8 24.0 24.0 17.7 2.09 12 Edge of materials 8.2 8.2 15.5 32.0 22.7 13.4 2.01 13 Finishes 4.1 11.3 18.6 33.0 23.7 9.3 1.93 14 Surface area of materials 8.3 12.5 22.9 29.2 16.7 10.4 1.73 15 Texture of materials 9.3 11.3 25.8 29.9 14.4 9.3 1.66 16 Table 5: Frequency of which Engineering practices consider / refer to H&S relative to various design related aspects (II: 0 - 4) (Smallwood, 2004b).
  • 58. © 2014 : Prof JJ Smallwood 58 Impact of design(ers) (5) Table 6: Frequency at which Architectural practices and Architectural Technologists consider / refer to construction ergonomics on various occasions (MS: 1.00 – 5.00) (Smallwood, 2009a). Occasion (Stream) Architects Arch. Tech’s Mean Mean Score Rank Mean Score Rank Mean Score Rank Detailed design (Upstream) 3.83 1 3.30 2= 3.57 1 Working drawings (Upstream) 3.65 2 3.32 1 3.49 2 Concept (design) (Upstream) 3.61 3 3.30 2= 3.46 3 Preparing project documentation 3.46 4 2.81 5 3.14 4 Site inspections/discussions 3.38 5 2.84 4 3.11 5 Site meetings 3.35 6 2.73 6 3.04 6 Design coordination meetings 3.32 7 2.65 7 2.99 7 Client meetings 2.97 9 2.54 8 2.76 8 Constructability reviews 3.06 8 2.41 9 2.74 9 Site handover 2.80 10 2.16 10 2.48 10 Deliberating project duration 2.76 11 1.86 12= 2.31 11 Pre-qualifying contractors 2.51 13 1.97 11 2.24 12 Pre-tender meeting 2.57 12 1.78 14 2.18 13= Evaluating tenders 2.50 14 1.86 12= 2.18 13=
  • 59. © 2014 : Prof JJ Smallwood 59 Impact of design(ers) (6) Table 7: Frequency at which Architectural practices and Architectural Technologists consider / refer to construction ergonomics relative to various design related aspects (MS: 1.00 – 5.00) (Smallwood, 2009a). Aspect Architects Arch. Tech’s Mean Mean Score Rank Mean Score Rank Mean Score Rank Plan layout 3.81 1 3.38 1= 3.60 1 Design (general) 3.75 3 3.38 1= 3.57 2 Details 3.78 2 2.97 6 3.38 3 Method of fixing 3.67 4 3.03 4 3.35 4 Specification 3.63 5 3.00 5 3.32 5 Position of components 3.38 7 2.97 7 3.18 6 Elevations 3.18 10 3.16 3 3.17 7 Finishes 3.50 6 2.65 11 3.08 8 Type of structural frame 3.17 11 2.92 9 3.05 9 Site location 2.96 14 2.95 8 2.96 10 Schedule 3.04 12 2.81 10 2.93 11= Edge of materials 3.24 8 2.62 12 2.93 11= Texture of materials 3.21 9 2.38 15 2.80 13 Content of material 3.01 13 2.54 13 2.78 14 Surface area of materials 2.79 15 2.41 14 2.60 15 Mass of materials 2.54 16 2.35 16 2.45 16
  • 60. © 2014 : Prof JJ Smallwood 60 Impact of design(ers) (7) Table 8: Extent to which various design related aspects impact on construction ergonomics according to Architectural practices and Architectural Technologists (MS: 1.00 – 5.00) (Smallwood, 2009a). Aspect Architects Arch. Tech’s Mean Mean Score Rank Mean Score Rank Mean Score Rank Design (general) 3.83 1 4.08 2 3.96 1 Details 3.72 2 4.05 4 3.89 2 Plan layout 3.57 4 4.08 3 3.83 3 Position of components 3.50 5 4.03 5 3.77 4 Method of fixing 3.58 3 3.83 9 3.71 5 Site location 3.23 9 4.11 1 3.67 6= Finishes 3.47 6= 3.86 8 3.67 6= Edge of materials 3.26 8 3.94 6 3.60 8 Specification 3.47 6= 3.70 11 3.59 9 Type of structural frame 3.15 10 3.89 7 3.52 10 Elevations 3.06 13 3.81 10 3.44 11 Texture of materials 3.11 11 3.56 14 3.34 12 Schedule 3.02 14 3.60 13 3.31 13= Mass of materials 2.97 15 3.65 12 3.31 13= Content of material 3.08 12 3.44 16 3.26 15 Surface area of materials 2.73 16 3.46 15 3.10 16
  • 61. © 2014 : Prof JJ Smallwood Knowledge of mass and density of materials Table 9: Summary of architectural designers’ and architectural technologists’ response and responses within a 10% range of the actual mass or density (Smallwood, 2011b) Material Response (%) No response (%) Within 10% range (%) Solid clay brick 82.1 17.9 23.4 Two-cell concrete block 83.3 16.7 1.5 Precast concrete kerb 83.3 16.7 9.2 Double Roman concrete roof tile 83.3 16.7 10.8 m2 glass 5 mm thick 76.9 23.1 3.4 Concrete 73.1 26.9 19.6 Marble 66.7 33.3 17.3 Sandstone 66.7 33.3 5.8 Steel 64.1 35.9 8.2 Mean 75.5 24.5 11.0
  • 62. © 2014 : Prof JJ Smallwood Role and knowledge of mass and density of materials Table 10: Frequency at which practices consider the mass and density of materials when designing and specifying (MS: 1.00 – 5.00) (Smallwood, 2011b) Response (%) MS Unsure Never……………...…………………..…Always 1 2 3 4 5 4.0 24.0 32.0 22.7 9.3 8.0 2.43 Response (%) MS Unsure Limited……………………..…………Extensive 1 2 3 4 5 4.1 44.6 29.7 14.9 4.1 2.7 1.86 Table 12: Respondents’ rating of their knowledge of the mass and density of materials (MS: 1.00 – 5.00) (Smallwood, 2011b) . Response (%) MS Unsure Minor….. ……………………………..…Major 1 2 3 4 5 13.5 8.1 4.1 18.9 32.4 23.0 3.67 Table 11: Potential of the consideration of the mass and density of materials to contribute to an improvement in construction ergonomics (MS: 1.00 – 5.00) (Smallwood, 2011b)
  • 63. © 2014 : Prof JJ Smallwood Landscape architecture and landscape construction H&S (1) Table 14: Extent to which landscape construction H&S should be addressed in landscape architecture programmes according to landscape architects (Smallwood, 2010a) . Response (%) MS Unsure Minor….. ……………………………..…Major 1 2 3 4 5 27.8 22.2 27.8 11.1 11.1 0.0 2.15 Table 13: Extent to which tertiary landscape architecture education addresses landscape construction H&S according to landscape architects (MS: 1.00 – 5.00) (Smallwood, 2010a) Addressing of construction H&S Yes (%) Unsure 9.5 Not at all 0.0 Included in a range of subjects 23.8 Included in the subject ‘design’ 23.8 A subject ‘construction H&S’ 42.9
  • 64. © 2014 : Prof JJ Smallwood Landscape architecture and landscape construction H&S (2) Table 15: Landscape architects’ sources of knowledge of landscape construction H&S (Smallwood, 2010a) Source Yes (%) Experience 95.2 Magazine articles 38.1 Tertiary education 23.8 Workshops 19.0 Postgraduate qualifications 14.3 Practice notes 14.3 CPD Seminars 9.5 Conference papers 4.8 Journal papers 4.8 Other: OH&S Act 4.8
  • 65. © 2014 : Prof JJ Smallwood Interior design and construction H&S (1) Table 17: Extent to which construction H&S should be addressed in interior design programmes according to interior designers (Smallwood, 2009b) . Response (%) MS Unsure Minor….. ……………………………..…………..Major 1 2 3 4 5 50.0 10.0 30.0 10.0 0.0 0.0 2.00 Table 16: Extent to which tertiary interior design education addresses construction H&S according to interior designers (MS: 1.00 – 5.00) (Smallwood, 2009b) Addressing of construction H&S Yes (%) Unsure 18.2 Not at all 0.0 Included in a range of subjects 18.2 Included in the subject ‘design’ 0.0 A subject ‘construction H&S’ 63.6
  • 66. © 2014 : Prof JJ Smallwood Interior design and construction H&S (2) Table 18: Interior designers’ sources of knowledge of construction H&S (Smallwood, 2009b) Means Yes (%) Experience 45.5 Magazine articles 27.3 Other: OH&S Act 27.3 Journal papers 18.2 Workshops 9.1 Conference papers 0.0 CPD Seminars 0.0 Postgraduate qualifications 0.0 Practice notes 0.0 Tertiary education 0.0
  • 67. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 67 Built environment construction H&S education Table 19 : The importance of the inclusion of construction H&S in the tertiary education programmes of built environment disciplines according to architectural academics (MS: 1.00 – 5.00) (Smallwood, 2014) Discipline Response (%) MS Rank Unsure Hardly…………….………………….……. Very 1 2 3 4 5 Construction management 0.0 0.0 0.0 0.0 0.0 100.0 5.00 1 Civil engineering 0.0 0.0 0.0 0.0 25.0 75.0 4.75 2 Electrical engineering 0.0 0.0 0.0 0.0 50.0 50.0 4.50 3 Mechanical engineering 0.0 0.0 0.0 25.0 25.0 50.0 4.25 4 Project management 0.0 0.0 25.0 0.0 0.0 75.0 4.25 5 Landscape architecture 0.0 0.0 20.0 40.0 20.0 20.0 3.40 6 Architecture 0.0 16.7 16.7 16.7 16.7 33.3 3.33 7 Quantity surveying 0.0 0.0 25.0 50.0 0.0 25.0 3.25 8 Interior design 0.0 20.0 20.0 40.0 20.0 0.0 2.60 9
  • 68. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 68 Architectural construction H&S education (1) Table 20: Extent to which construction H&S is addressed / included in architectural programmes / curricula (Smallwood, 2014). Response (%) Unsure Yes No 0.0 66.7 33.3 Form Response (%) Unsure Yes No Separate subject 0.0 0.0 100.0 Issue in design project briefs 0.0 66.7 33.3 Criterion for assessment in design project assessments 0.0 33.3 66.7 Component of a subject 0.0 33.3 66.7 Module in various subjects 0.0 33.3 66.7 On an ad-hoc basis 0.0 33.3 66.7 Table 21: Form in which construction H&S is addressed / included in architectural programmes / curricula (Smallwood, 2014).
  • 69. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 69 Architectural construction H&S education (3) Table 22: The importance of the inclusion of subject areas relative to construction H&S in an architectural programme according to architectural academics (MS: 1.00 – 5.00) (Smallwood, 2014) Subject area Response (%) MS Rank Unsure Hardly………….…………….……………Very 1 2 3 4 5 Occupational health 0.0 0.0 0.0 16.7 50.0 33.3 4.17 1 Occupational safety 0.0 0.0 0.0 16.7 50.0 33.3 4.17 2 OH&S Act & Regulations 0.0 0.0 0.0 33.3 33.3 33.3 4.00 3 H&S plans 0.0 0.0 0.0 33.3 33.3 33.3 4.00 4 H&S specifications 0.0 0.0 0.0 50.0 16.7 33.3 3.83 5 Role of project managers in construction H&S 0.0 0.0 16.7 16.7 33.3 33.3 3.83 6 Role of construction H&S in project performance 0.0 0.0 16.7 0.0 83.3 0.0 3.67 7 Role of designers in construction H&S 0.0 0.0 0.0 66.7 0.0 33.3 3.67 8 Specifying for construction H&S 0.0 0.0 16.7 33.3 33.3 16.7 3.50 9 Need for construction H&S 16.7 0.0 16.7 16.7 50.0 0.0 3.40 10 Designing for construction H&S 0.0 20.0 0.0 20.0 40.0 20.0 3.40 11 Hazard identification and risk assessment 0.0 16.7 16.7 16.7 16.7 33.3 3.33 12 Designing for construction ergonomics 0.0 16.7 16.7 0.0 66.7 0.0 3.17 13 Role of quantity surveyors in construction H&S 0.0 0.0 50.0 0.0 50.0 0.0 3.00 14 Detailing for construction H&S 0.0 16.7 16.7 33.3 33.3 0.0 2.83 15 Role of clients in construction H&S 0.0 0.0 50.0 33.3 16.7 0.0 2.67 16 Environment and construction H&S 0.0 16.7 33.3 16.7 33.3 0.0 2.67 17 Economics of construction H&S 0.0 33.3 33.3 0.0 16.7 16.7 2.50 18 Influence of procurement on construction H&S 16.7 33.3 16.7 16.7 16.7 0.0 2.20 19
  • 70. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 70 Architectural construction H&S education (4) Table 23: The extent to which actions / activities / aspects impact on construction H&S according to architectural academics (MS: 0.00 – 5.00 i.e. midpoint is 2.50) (Smallwood, 2014) Action / Activity / Aspect Response (%) MS RankUnsure Does not Minor …………………………………Major 1 2 3 4 5 H&S pre-qualification of contractors 0.0 0.0 0.0 0.0 0.0 66.7 33.3 4.33 1 Site handover 0.0 0.0 0.0 0.0 33.3 33.3 33.3 4.00 2 Site inspections / discussions 0.0 0.0 0.0 0.0 33.3 50.0 16.7 3.83 3 Detailed design 0.0 0.0 0.0 0.0 50.0 33.3 16.7 3.67 4 Constructability reviews 16.7 0.0 0.0 0.0 33.3 50.0 0.0 3.60 5 Design 0.0 0.0 0.0 0.0 66.7 16.7 16.7 3.50 6 Project duration 0.0 0.0 0.0 16.7 50.0 16.7 16.7 3.33 7 Pre-tender meeting 16.7 0.0 0.0 16.7 33.3 33.3 0.0 3.20 8 Evaluation of tenders 16.7 0.0 0.0 16.7 33.3 33.3 0.0 3.20 9 Site meetings 0.0 16.7 0.0 0.0 60.0 20.0 20.0 3.00 10 Design coordination meetings 0.0 16.7 0.0 0.0 50.0 33.3 0.0 2.83 11 Working drawings 16.7 0.0 0.0 33.3 33.3 16.7 0.0 2.80 12 Project documentation 16.7 0.0 16.7 16.7 50.0 0.0 0.0 2.40 13 Client brief 0.0 16.7 16.7 16.7 33.3 0.0 16.7 2.33 14
  • 71. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 71 Architectural construction H&S education (5) Table 24: The extent to which design related aspects impact on construction H&S according to architectural academics (MS: 0.00 – 5.00 i.e. midpoint is 2.50) (Smallwood, 2014) Aspect Response (%) MS RankUnsure Does not Minor …………………………………Major 1 2 3 4 5 Method of fixing 0.0 0.0 0.0 0.0 16.7 50.0 33.3 4.17 1 Mass of materials 16.7 0.0 0.0 0.0 16.7 50.0 16.7 4.00 2 Edge of materials 0.0 0.0 0.0 0.0 66.7 16.7 16.7 3.50 3 Type of structural frame 0.0 0.0 0.0 16.7 33.3 33.3 16.7 3.50 4 Specification 0.0 0.0 0.0 16.7 33.3 33.3 16.7 3.50 5 Site location 0.0 0.0 16.7 0.0 33.3 33.3 16.7 3.33 6 Content of material 0.0 16.7 0.0 0.0 16.7 50.0 16.7 3.33 7 Design (general) 0.0 0.0 16.7 0.0 33.3 50.0 0.0 3.17 8 Surface area of materials 0.0 16.7 0.0 16.7 16.7 16.7 33.3 3.17 9 Texture of materials 0.0 0.0 16.7 16.7 16.7 50.0 0.0 3.00 10 Position of components 0.0 20.0 0.0 0.0 40.0 20.0 20.0 3.00 11 Details 0.0 0.0 0.0 33.3 50.0 16.7 0.0 2.83 12 Plan layout 0.0 0.0 16.7 33.3 16.7 33.3 0.0 2.67 13 Finishes 0.0 16.7 0.0 33.3 16.7 16.7 16.7 2.67 14 Elevations 0.0 0.0 16.7 33.3 33.3 16.7 0.0 2.50 15 Schedule 0.0 0.0 16.7 50.0 16.7 16.7 0.0 2.33 16
  • 72. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 72 A model for designers SACAP architectural work stages (1 – 6) ApplicationoftheNBR(PartsA–X) Design opportunity window: Design options Design selection H&S reviews Sign-off or revisit 1 H&S checklists H&S data records Sign-off or revisit 2 Variation orders (VOs) Sign-off or revisit 3 The Goldswain Core Model Core ModelDesign knowledge window: Construction processes Construction programming Contextual H&S Causes of Accidents Hazard Identification and Risk Assessments (HIRAs) Project type and complexity Design recommendations Lifecycles of buildings Figure 4: The Goldswain Core Model (Goldswain, 2014).
  • 73. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 73 Construction management H&S education (1) Table 4A: The importance of the inclusion of subject areas relative to construction H&S in a construction management programme according to GC National H&S Competition winners (MS: 1.00 – 5.00) (Smallwood, 2010b) Subject area Response (%) MS Rank Unsure Hardly………….…………….……………Very 1 2 3 4 5 Management of subcontractors 0.0 0.0 0.0 0.0 11.1 88.9 4.89 1 Role of construction management 0.0 0.0 0.0 0.0 11.1 88.9 4.89 2 Worker participation 0.0 0.0 0.0 0.0 11.1 88.9 4.89 3 OH&S Act & Regulations 0.0 0.0 0.0 0.0 11.1 88.9 4.89 4 H&S / Productivity / Quality 0.0 0.0 0.0 0.0 22.2 77.8 4.78 5 H&S pre-planning 0.0 0.0 0.0 0.0 22.2 77.8 4.78 6 H&S programs 0.0 0.0 0.0 0.0 22.2 77.8 4.78 7 Safety 0.0 0.0 0.0 0.0 22.2 77.8 4.78 8 H&S education & training 0.0 0.0 0.0 0.0 33.3 66.7 4.67 9 Role of project managers 0.0 0.0 0.0 0.0 33.3 66.7 4.67 10 H&S plans 0.0 0.0 0.0 11.1 11.1 77.8 4.67 11 Health & hygiene 0.0 0.0 0.0 0.0 44.4 55.6 4.56 12
  • 74. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 74 Construction management H&S education (1) Table 4B: The importance of the inclusion of subject areas relative to construction H&S in a construction management programme according to GC National H&S Competition winners (MS: 1.00 – 5.00) (Smallwood, 2010b) Subject area Response (%) MS Rank Unsure Hardly………….…………….……………Very 1 2 3 4 5 Role of clients 0.0 0.0 0.0 11.1 22.2 66.7 4.56 13 Role of designers 0.0 0.0 0.0 11.1 22.2 66.7 4.56 14 H&S culture e.g. values, vision, goals, & mission 0.0 0.0 0.0 12.5 25.0 62.5 4.50 15 Economics of H&S 0.0 0.0 0.0 22.2 22.2 55.6 4.33 16 Role of the media & awareness 0.0 0.0 0.0 22.2 22.2 55.6 4.33 17 Environment 0.0 0.0 0.0 33.3 0.0 66.7 4.33 18 Measurement & statistics 0.0 0.0 0.0 33.3 0.0 66.7 4.33 19 Role of the unions 0.0 0.0 11.1 11.1 22.2 55.6 4.22 20 COID Act (workers’ compensation) 0.0 11.1 0.0 11.1 11.1 66.7 4.22 21 Ergonomics 0.0 0.0 0.0 33.3 22.2 44.4 4.11 22 Influence of procurement 0.0 0.0 11.1 22.2 33.3 33.3 3.89 23 Role of quantity surveyors 11.1 0.0 11.1 33.3 11.1 33.3 3.33 24
  • 75. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 75 The role of cost engineers / quantity surveyors  Cost Engineers / Quantity Surveyors:  May practice as project managers (if registered as Pr CPMs)  Prepare project estimates  May advise regarding the type of procurement system  May advise regarding project duration  Often prepare contract documentation  Often compile bills of quantities / schedule of rates  Assess pre-qualification and tender submissions  The cost of accidents contributes to the cost of construction  Construction Regulations include “surveyor specifying articles or drawing up specifications” under definition of designer
  • 76. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 76 A holistic perspective cost engineers / QSs  A client needs to be able to make a scientific assessment of the PC’s provision for H&S  The client’s H&S specification and designer report should provide a reference  The H&S plan should provide a reference:  However, H&S plan to be applied from date of commencement [Regulation 7(1) (a) i.e. not necessarily available at tender / bid stage  The requirement on the client to ensure that the PC has made adequate provision for H&S amplifies the need for a pre-tender H&S plan (not required by the Regulations)  Each project is unique despite many common activities  A provisional sum would not do justice  PCs and contractors have varying levels of expertise  Emerging contractors should be guided
  • 77. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 77 H&S Preliminaries items (1) Can facilitate adequate provision for H&S by PCs in terms of Regulation 5 (1) (g) through inclusion of, among other, an ‘H&S’ section in the Preliminaries:  H&S plan  H&S file  Risk assessment  SWPs and method statements  Design of temporary works  Design of permanent structures  Engineering design and / or certification  Medicals  Biological monitoring  Environmental measurement  Education and training
  • 78. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 78 H&S Preliminaries items (2)  Full-time or part-time Construction H&S Officer [Regulation 8 (5)], or management of H&S as a whole (preferably not)  H&S Representatives  Meetings  General administration  Hoarding and / or public walkways  Catch platforms  Facilities related requirements – Regulation 30:  WCs – for each gender, and 1 for every 30 workers  WHBs (not required)  Showers – 1 for every 15  Changing facilities – for each gender  Sheltered eating areas  Living accommodation – for workers far removed from their homes
  • 79. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 79 H&S Preliminaries items (3)  Guarding and barricading  Storage  Storage for flammable goods – Regulation 25 (a)  Temporary electrical installations  Scaffolding  Special scaffolding  Suspended scaffolding  Access  Signage  Housekeeping  Personal protective equipment  Fire precautions  First aid  Transport of workers
  • 80. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 80 H&S Preliminaries items (4)  Inspections  Maintenance  Emergency plan Other provisions such as material and personnel hoists, and mobile and tower cranes can be addressed in the traditional manner
  • 81. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 81 References (1)  Behm, M. 2006. An Analysis of Construction Accidents from a Design Perspective. Silver Spring: The Center to Protect Workers’ Rights.  Construction Industry Development Board (cidb). 2009. Construction Health & Safety Status & Recommendations. Pretoria: cidb.  Department of Labour. 2002. Section 32 Investigation Report into the Injaka Bridge Collapse of 6 July 1998. Pretoria.  Goldswain, C. 2014. Architectural Design Interventions Toward Improvement of Construction Health, Safety, and Ergonomics in South Africa. Unpublished PhD (Construction Management) Thesis. Port Elizabeth: NMMU.  Irwin, A.W. and Sibbald, W.I. 1983. Falsework A Handbook of Design and Practice. London: Granada Technical Books.  Prinsloo, K. 1997. Beeld, 27 August, p.3.
  • 82. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 82 References (2)  Republic of South Africa. 2014. No. R. 84 Occupational Health and Safety Act, 1993 Construction Regulations 2014. Government Gazette No. 37305. Pretoria.  Smallwood, J.J. 1995. The Influence of management on the occurrence of loss causative incidents in the South African construction industry. Unpublished MSc (Constr Man) Dissertation, University of Port Elizabeth, Port Elizabeth.  Smallwood, J.J. 2000. A study of the relationship between occupational health and safety, labour productivity and quality in the South African construction industry. Unpublished PhD Thesis. University of Port Elizabeth, Port Elizabeth.  Smallwood, J.J. 2004a. Optimum cost: The role of health and safety (H&S). In: Verster JJP, ed. Proceedings International Cost Engineering Council 4th World Congress, Cape Town, April 2004. International Cost Engineering Council, 2004: CD- Rom Smallwood-J- Optimum Cost-Health & Safety.pdf
  • 83. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 83 References (3)  Smallwood, J.J. 2004b. The influence of engineering designers on health and safety during construction. Journal of the South African Institution of Civil Engineering, 46 (1), 2–8.  Smallwood, J.J. 2009a. Architects and Architectural Technologists: Their Influence on Construction Ergonomics, ergonomicsSA, 21(2), 41-64.  Smallwood, J.J. 2009b. Interior Designers and Construction Health and Safety. Unpublished research findings.  Smallwood, J.J. 2010a. Landscape Architects and Landscape Construction Health and Safety (H&S). Unpublished research findings.  Smallwood, J.J. 2010b. Construction Management Health and Safety (H&S) Course Content: Towards the Optimum. In: Proceedings of the CIB World Building Congress, Salford Quays, 14-17 May, 2010.
  • 84. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 84 References (4)  Smallwood, J.J. 2011a. Financial Provision for Health and Safety (H&S) in Construction. In: Proceedings of the CIB W099 Conference, Washington D.C., 24-26 August, F:datapapers45.pdf.  Smallwood, J.J. 2011b. Mass and density of construction materials: designers’ knowledge, perceptions, and practices, ergonomicsSA, 23(1), 28-41.  Smallwood, J.J. 2014. The need for the inclusion of Construction health and safety (H&S) in architectural education. Unpublished paper presented at the: architecture Otherware XXV International Union of Architects Congress, Durban, 4-9 August.  South African Reserve Bank. 2003. Quarterly Bulletin. Pretoria: South African Reserve Bank.  Steele, D. 1983. Bloukrans Bridge. Concrete Beton, Nr 30 1983 06, 10-11. 
  • 85. © 2014 : Prof JJ Smallwood© 2014 : Prof JJ Smallwood 85 References (5)  The National Spiritual Assembly of the Bahia’is of India. 2002. The Dawning Place of the Remembrance of God. New Delhi: Thomson Press.  Travers, R. 1998. Lowvelder, 10 July, p. 1.