Gas CCS in China - Jia Li at the UKCCSRC Gas CCS Meeting, University of Sussex, 25 June 2014
1. 1
Gas CCS in China
Dr Jia Li
Lecturer in Carbon Capture and Storage
2014 Jun 25, University of Sussex
Gas CCS meeting
2. Content
• Update on CCS in China
• Background on Chinese Natural Gas Industry
• Post-combustion Capture Studies in CCGT Power Plant
- Datang Study
- Huaneng Pilot
• SNG
3. CCS R&D Activities and Scoping Projects
• National 973 Projects (two led by Petro China)
• National 863 Projects (incl. IGCC, Algae, Oxyfuel, EOR)
• National Key Technology Program (CO2 storage, capture from blast furnace
iron making)
• EU-UK-China NZEC / COACH /STRACO2
• UK-China Chinese Advanced Power Plants Carbon Capture Options
• US-China Clean Energy Research Centre
• Australia – China CO2 Geologic Storage Cooperation Project
• Italy – China CCS Cooperation
• Guangdong CCS Readiness Project
• A number of studies by Asian Development Bank and the World Bank
• Participation in ISO standard design
4. CCS Pilot Projects in China
• Petro China Jilin Oilfield, EOR, 100,000 t/a (2007- )
• CAS – Jinlong CO2 Chemical Utilization, 10,000 t/a (2007- )
• Huaneng Gaobeidian post-combustion capture, 3000 t/a (2008 -)
• CNOOC biodegradable plastic CO2 utilisation, 2100 t/a (2009- )
• Huaneng Shidongkou post-combustion capture, 120,000 t/a (2009- )
• Chongqing Shuanghuai post-combustion capture, 10,000 t/a (2010- )
• SINOPEC Shengli Oil Field post-combustion and EOR, 40,000 t/a (2010 - )
• Lianyuan Gang Clean Coal Energy System pre-combustion, 30,000t/a (2011- )
• Shenhua CTL capture and saline aquifer storage, 100,000 t/a (2011 - )
• ENN Microalgae Bio-fuel Demonstration, 20,000 t/a (TBC)
• Huaneng Green-gen IGCC CCS Pilot, up to 100,000t/a capture (TBC)
• Hubei Yingcheng Oxy-combustion R&D, 50,000 t/a capture (TBC)
• Guangdong 1 million ton post-combustion (Pre-M) (2014- )
5.
6.
7. Gas Production and Consumption in China
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
160.0
billioncubicmetre(bcm)
Year
Total Consumption Total Production
Source: BP, 2012; NDRC, 2013
Compounded growth rate (2003-2012):
Consumption: 15.8%
Production: 11.9%
8. Gas Net Import Ratio in China
0%
5%
10%
15%
20%
25%
30%
2007 2008 2009 2010 2011 2012
GsaNetImportRatio
Year
Source: BP, 2012; NDRC, 2013
The dependency ratio of
crude oil is 56% in 2012
9. Conventional
Gas
51%
Coal SNG
6%
CBM
6%Shale Gas
2%
Import Gas
35%
Estimated Gas Sources in 2015
• Total domestic production:
176 bcm
• Conventional gas: 138.5 bcm
• Coal Synthetic Natural Gas:
15 to 18 bcm
• Coal bed methane: 16 bcm
• Shale Gas: 6.5 bcm (with 200
bcm potential)
• Import LNG and pipeline
gas: 93.5 bcm
Source: NEA, 2012
http://zfxxgk.nea.gov.cn/auto86/201212/W0
20121203312244945303.pdf
10. Natural Gas in China
• The share of natural gas in the energy mix will increase from 4%
in 2010 to 10% in 2020
• The government is reforming the gas market, current regulated
“city-gate gas prices” are around 3 to 3.3 per cm in the east of
China
• Natural gas will be applied for generating electricity in major
cities with tight “environment capacity”, such as Beijing,
Shenzhen, Shanghai, Guangzhou
• The CCGT capacity is estimated to increase from 20GW in 2010
to 60GW in 2015 and 110GW in 2020
• Some pioneer projects are studying CCS in gas-fired power plants
in China
11. Datang Gas CCS Study
ADB TA‐8001 (PRC): Study on Carbon Capture and Storage in Natural Gas-Based
Power Plants
Information provided by Dr Andrew Minchener (Project Lead)
12. Project Objectives
• Develop a CCS roadmap for natural gas-based CHP
plants;
• Carry out a techno-economic feasibility analysis for a CCS
pilot scale demonstration on the Gaojing CHP plant;
• Formulate a CCS-readiness plan for natural gas-based
CHP plants;
• Establish a capacity strengthening programme for
various stakeholder groups concerned with the
application of CCS for gas fired CHP systems.
Source: Minchener, 2013
15. Datang Gas CCS Plan
• A CCS pilot scale demonstration for Gaojing natural gas
power plant through post-combustion chemical
scrubbing (3 tonne per day)
• Establish CCS-readiness guidelines to meet new and
future CCS retrofitting requirements for applications to
all natural gas power plants within PRC
• ADB TA provides an important assessment of strategic
and technical options and impact on economic
competitiveness (draft report by July 2013; followed by
stakeholder workshops in Sep and Oct)
Source: Minchener, 2013
16. Huaneng Gas CCS Pilot
Information provided by Mr Lianbo Liu (Project Manager)
17. CCM Verification Project
CCM燃气碳捕集验证项目
First CO2 capture pilot plant for natural gas based
power station in China, built by CERI in 2012 (1000
tons CO2 per year)
CERI建造的中国首套燃气电厂二氧化碳捕集测试
系统(规模1000吨CO2/年)
This plant (named CCM Verification Plant here) is
also served as a verification plant for Norway CO2
Capture Mongstad (CCM) project
挪威CCM碳捕集工程的验证项目,第一阶段
CCM Project is executed by Statoil to build a full-
scale post combustion capture of CO2 from a
combined heat and power station at Mongstad
CCM项目将对Mongstad热电厂烟道气进行CO2全
捕集,工程建设由挪威国家石油公司负责
CCM Verification plant has been running stably for
3000 hours with capture efficiency >85%
(85%~92%)
在保证84%捕集率的条件下,CCM验证项目已连
续稳定运行2000小时(捕集率84%~92%)
18. Features of CCM Verification Plant
CCM工程项目特征
Absorber with Intercooling System
吸收塔伴中间冷却
Novel Regeneration System, Reducing 20% Energy Cost
Compared with Traditional Stripper
新型再生系统,相对传统再生方式可减少20%能耗
Natural Gas Boiler to Provide Flue Gas and Steam
天然气锅炉提供烟道气和再生用蒸汽、烟气循环
Solvent Reclaim System
溶液回收再生装置
Two Independent Online Lab Analysis Systems to Ensure
Accurate Experimental Data
两套独立的实验室在线分析系统,确保数据相符和准确
PLC with UPS for Pilot Plant
PLC自动控制,备有UPS不间歇电源
Data Collection and Online Share with Norway
数据采集和在线共享
19. 19
Online Database Files
在线数据文件
Automatic Data Collection Every 5 Seconds, and Generating Performance Curves
现场数据采集,每5秒存储形成数据库文件,通过数据分析,形成小时统计数据及性能曲线
烟气成分实时数据 Daily Analyzer CalibrationFlue gas content analysis
real-time data
Solvent ph level
and density
20. Clean coal and CCS in China and the developing economies of Asia, Dr Andrew J Minchener,
http://www.ukccsrc.ac.uk/7-february-future-uk-coal-ccs-options-workshop
Approved SNG projects by government in China
25. Final Remark
• Gas fired power plants will increase rapidly though it is
still a small proportion of total generation capacity
• CCGT power plants are likely first deployed in large cities
and developed regions, with limit land resource and high
population density, therefore CCS Ready is very
important to avoid the carbon lock-in effect
• Datang and Huaneng are developing pilot CO2 capture
projects in gas-fired power plants
• SNG and gas processing will provide low-cost
opportunities for CCS in the gas industry